CN104924451A - Reinforcing mesh dropping device - Google Patents

Reinforcing mesh dropping device Download PDF

Info

Publication number
CN104924451A
CN104924451A CN201510288328.2A CN201510288328A CN104924451A CN 104924451 A CN104924451 A CN 104924451A CN 201510288328 A CN201510288328 A CN 201510288328A CN 104924451 A CN104924451 A CN 104924451A
Authority
CN
China
Prior art keywords
rotating shaft
mat reinforcement
upper frame
bar
bottom framework
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510288328.2A
Other languages
Chinese (zh)
Other versions
CN104924451B (en
Inventor
范文捷
张忠美
刘芳
邓清闯
郭红战
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongyuan University of Technology
Original Assignee
Zhongyuan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongyuan University of Technology filed Critical Zhongyuan University of Technology
Priority to CN201510288328.2A priority Critical patent/CN104924451B/en
Publication of CN104924451A publication Critical patent/CN104924451A/en
Application granted granted Critical
Publication of CN104924451B publication Critical patent/CN104924451B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/022Means for inserting reinforcing members into the mould or for supporting them in the mould

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a reinforcing mesh dropping device which comprises a bottom frame and an upper frame. The bottom frame and the upper frame are connected through stand columns. At least two supports are welded to the interior of the bottom frame. Each support is provided with a rotating shaft. A clamping device is arranged at the lower portion of each rotating shaft. A rotating device is installed at the upper end of each rotating shaft. Hoist pans are installed on the upper frame. According to the reinforcing mesh dropping device, multiple reinforcing meshes are clamped through multiple layers of clamping jaws on sleeves, the whole device is hoisted to the position where the reinforcing meshes need to be placed through the hoist pans on the upper frame, the rotating shafts are driven to rotate positively and negatively by rotating gears, and therefore the reinforcing meshes are lifted and dropped. The reinforcing meshes do not need to be laid into a die one by one through manual work, the labor intensity of workers is lowered, the production efficiency is improved, the production cost is reduced, very good economic benefits and social benefit are achieved, and automatic production of cement prefabricated slabs is facilitated.

Description

Fall bar-mat reinforcement device
Technical field
The invention belongs to mechanical equipment technical field, be specifically related to a kind of for the bar-mat reinforcement device that falls in the production line of building material industry cement pre-fabricated panel.
Background technology
Superposed box mesh-beam floor system is the new technology of building structure scientific and technical innovation, and superposed box mesh-beam floor system adopts bar-mat reinforcement and concreting to form large-scale cement pre-fabricated panel.
Cement pre-fabricated panel, in compressing process, needs bar-mat reinforcement to be placed in mould, is then pressed toward casting concrete in mould.
At present, existing production technology adopts artificial method to be placed in a mold by bar-mat reinforcement, manually bar-mat reinforcement is placed in mould the realization being unfavorable for automated production cement pre-fabricated panel, and artificial inefficiency bar-mat reinforcement is placed in mould, the labour intensity of workman is large, therefore, imperative to the existing technological transformation manually bar-mat reinforcement is placed in mould.
Summary of the invention
The present invention is to solve the placement of bar-mat reinforcement adopts manual method in the prior art of cement pre-fabricated panel, inefficiency, working strength is large, and be unfavorable for the technical problems such as the realization of automated production cement pre-fabricated panel, thus provide the bar-mat reinforcement device that falls that a kind of operating efficiency is high, labour intensity is little.
For solving the problems of the technologies described above, the technical solution used in the present invention is as follows:
One falls bar-mat reinforcement device, comprise bottom framework and upper frame, bottom framework is connected by column with upper frame, the internal welding of bottom framework is connected at least two bearings, each bearing is all provided with rotating shaft, rotating shaft bottom is provided with clamping device, and the upper end of rotating shaft is provided with tumbler, and upper frame is provided with hanging scaffold.
Be welded with gripper shoe respectively in the corner of bottom framework inside, the lower end of column is installed on the supporting plate, and the upper end of column is connected with upper frame.
The area of described bottom framework is greater than the area of upper frame.
Described clamping device comprises sleeve, and jacket casing is located at the lower end of rotating shaft, and with rotating shaft tight fit; Sleeve is provided with at least two-layer claw.
Described claw is crisscross arranged on the half side-view of sleeve.
Described tumbler comprises gear, and gear is arranged on the upper end of rotating shaft.
Between rotating shaft and gear, be provided with bearing block, gear is installed through after bearing block in the upper end of rotating shaft.
The inside of two relative sides of bottom framework is welded with two bearings respectively.
The gear be positioned on the bearing of the same side of bottom framework is meshed.
The present invention establishes multiple bar-mat reinforcement by the multilayer claw card on sleeve, and by the hanging scaffold on upper frame, whole device is hung the position needing to place bar-mat reinforcement, drives rotating and reverse of rotating shaft, thus realize the picking-up of bar-mat reinforcement and drop by transmitting gear.No longer need artificial one by one bar-mat reinforcement is routed in mould, reduce the labour intensity of workman, improve production efficiency, reduce production cost, have good economic benefit and social benefit, be conducive to the automated production realizing cement pre-fabricated panel.
Accompanying drawing explanation
Fig. 1 is the structural representation of embodiment 1.
Fig. 2 is the top view of embodiment 1.
Fig. 3 is the upward view of embodiment 1.
Fig. 4 is the left view of embodiment 1.
Fig. 5 is the assembling schematic diagram of embodiment 1 middle sleeve and rotating shaft.
Fig. 6 is the A-A view of Fig. 5.
Detailed description of the invention
Embodiment 1: as shown in figures 1 to 6, one falls bar-mat reinforcement device, comprises bottom framework 1 and upper frame 6, upper frame 6 is provided with hanging scaffold 7, the whole device of hanging scaffold Liftable.
Be welded with gripper shoe 2 respectively in the corner of bottom framework 1 inside, the lower end of column 3 is arranged in gripper shoe 2, and the upper end of column 3 is connected with upper frame 6.
Two bearings 4 are welded with respectively in the inside of two relative sides of bottom framework 1, each bearing 4 is all provided with rotating shaft 5, rotating shaft 5 bottom is provided with clamping device, described clamping device comprises sleeve 11, sleeve 11 is set in the lower end of rotating shaft 5, and can synchronous axial system with rotating shaft 5 tight fit, and on sleeve 11, be provided with four layers of claw 12, these four layers of claws 12 are crisscross arranged on the half side-view of sleeve 11, and claw 12 is all in sickleshaped.
The upper end of rotating shaft 5 is provided with tumbler, described tumbler comprises gear 9, and gear 9 is arranged on the upper end of rotating shaft 5, and is provided with bearing block 8 between rotating shaft 5 and gear 9, gear 9 is installed through after bearing block 8 in the upper end of rotating shaft 5, and rotating shaft 5 can be rotated around bearing block 8.The gear 9 be positioned on the bearing 4 of the same side of bottom framework 1 is meshed.
Wherein, the area of described bottom framework 1 is greater than the area of upper frame 6.
Operation principle: rotating shaft 5 just turn 90 degrees by hand rotation gear, now, sleeve 11 does not arrange the inside of half side-view towards bottom framework 1 of claw 12, and multiple bar-mat reinforcement is put into bottom framework 1 of the present invention inner, bar-mat reinforcement is now free to move up and down because not having stop.
Rotating shaft 5 is rotated backward 90 degree, in rotary course after putting into bottom framework 1 inside by bar-mat reinforcement, and each claw 12 holds up several bar-mat reinforcements respectively.Bar-mat reinforcement is fallen, and need rotating shaft 5 to rotate forward 90 degree again, now, the bar-mat reinforcement on the claw of ground floor falls, and the bar-mat reinforcement on the claw of third layer drops on the claw of the second layer, and the claw of the 4th layer stops that bar-mat reinforcement falls above.Then rotating shaft 5 is rotated backward 90 degree again, now, bar-mat reinforcement on the claw of the second layer drops on the claw of ground floor, bar-mat reinforcement on the claw of the 4th layer drops on the claw of third layer, then, rotating shaft 5 is just turn 90 degrees, now, bar-mat reinforcement on the claw of ground floor falls, and the bar-mat reinforcement on the claw of third layer drops on the claw of the second layer, and the claw of the 4th layer stops that bar-mat reinforcement falls above.Repeat above-mentioned action, the interruption that can complete bar-mat reinforcement falls.
Embodiment 2: one falls bar-mat reinforcement device, comprise bottom framework and upper frame, bottom framework is connected by column with upper frame, the internal welding of bottom framework is connected at least two bearings, each bearing is all provided with rotating shaft, rotating shaft bottom is provided with clamping device, and the upper end of rotating shaft is provided with tumbler, and upper frame is provided with hanging scaffold.
Embodiment 3: one falls bar-mat reinforcement device, comprises bottom framework and upper frame, is welded with gripper shoe respectively in the corner of bottom framework inside, the lower end of column is installed on the supporting plate, and the upper end of column is connected with upper frame.The internal welding of bottom framework is connected at least two bearings, and each bearing is all provided with rotating shaft, and rotating shaft bottom is provided with clamping device, and the upper end of rotating shaft is provided with tumbler, and upper frame is provided with hanging scaffold.
Wherein, the area of described bottom framework is greater than the area of upper frame.
Embodiment 4: one falls bar-mat reinforcement device, and comprise bottom framework and upper frame, bottom framework is connected by column with upper frame, and upper frame is provided with hanging scaffold.
The inside of two relative sides of bottom framework is welded with two bearings respectively, and each bearing is all provided with rotating shaft.
Rotating shaft bottom is provided with clamping device, and described clamping device comprises sleeve, and jacket casing is located at the lower end of rotating shaft, and with rotating shaft tight fit, sleeve is provided with at least two-layer claw.
The upper end of rotating shaft is provided with tumbler, and described tumbler comprises gear, and gear is arranged on the upper end of rotating shaft.
Between rotating shaft and gear, be provided with bearing block, gear is installed through after bearing block in the upper end of rotating shaft.The gear be positioned on the bearing of the same side of bottom framework is meshed.

Claims (9)

1. the bar-mat reinforcement device that falls, it is characterized in that: comprise bottom framework (1) and upper frame (6), bottom framework (1) is connected by column (3) with upper frame (6), the internal welding of bottom framework (1) is connected at least two bearings (4), each bearing (4) is all provided with rotating shaft (5), rotating shaft (5) bottom is provided with clamping device, and the upper end of rotating shaft (5) is provided with tumbler, and upper frame (6) is provided with hanging scaffold (7).
2. according to claim 1 fall bar-mat reinforcement device, it is characterized in that: the corner inner at bottom framework (1) is welded with gripper shoe (2) respectively, the lower end of column (3) is arranged in gripper shoe (2), and the upper end of column (3) is connected with upper frame (6).
3. according to claim 2 fall bar-mat reinforcement device, it is characterized in that: the area of described bottom framework (1) is greater than the area of upper frame (6).
4. according to claim 1 fall bar-mat reinforcement device, it is characterized in that: described clamping device comprises sleeve (11), sleeve (11) is set in the lower end of rotating shaft (5), and with rotating shaft (5) tight fit; Sleeve (11) is provided with at least two-layer claw (12).
5. according to claim 4 fall bar-mat reinforcement device, it is characterized in that: described claw (12) is crisscross arranged on the half side-view of sleeve (11).
6. require the bar-mat reinforcement device that falls described in 1 or 4 or 5 according to circle, it is characterized in that: described tumbler comprises gear (9), gear (9) is arranged on the upper end of rotating shaft (5).
7. according to claim 6 fall bar-mat reinforcement device, it is characterized in that: between rotating shaft (5) and gear (9), be provided with bearing block (8), gear (9) is installed afterwards through bearing block (8) in the upper end of rotating shaft (5).
8. the bar-mat reinforcement device that falls according to claim 1 or 7, is characterized in that: the inside of two relative sides of bottom framework (1) is welded with two bearings (4) respectively.
9. according to claim 8 fall bar-mat reinforcement device, it is characterized in that: the gear (9) be positioned on the bearing (4) of bottom framework (1) same side is meshed.
CN201510288328.2A 2015-06-01 2015-06-01 Fall bar-mat reinforcement device Expired - Fee Related CN104924451B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510288328.2A CN104924451B (en) 2015-06-01 2015-06-01 Fall bar-mat reinforcement device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510288328.2A CN104924451B (en) 2015-06-01 2015-06-01 Fall bar-mat reinforcement device

Publications (2)

Publication Number Publication Date
CN104924451A true CN104924451A (en) 2015-09-23
CN104924451B CN104924451B (en) 2017-07-14

Family

ID=54112024

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510288328.2A Expired - Fee Related CN104924451B (en) 2015-06-01 2015-06-01 Fall bar-mat reinforcement device

Country Status (1)

Country Link
CN (1) CN104924451B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110253751A (en) * 2019-07-19 2019-09-20 中原工学院 A kind of four-bar mechanism cloth steel mesh machine and its application method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0644143A1 (en) * 1993-09-17 1995-03-22 MAN Roland Druckmaschinen AG Transport device for sheet material stacked on pallets
CN203919341U (en) * 2014-06-22 2014-11-05 任丘市永基建筑安装工程有限公司 Steel reinforcement cage delivery device
CN104555470A (en) * 2014-12-10 2015-04-29 中原工学院 Automatic board chopping device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0644143A1 (en) * 1993-09-17 1995-03-22 MAN Roland Druckmaschinen AG Transport device for sheet material stacked on pallets
CN203919341U (en) * 2014-06-22 2014-11-05 任丘市永基建筑安装工程有限公司 Steel reinforcement cage delivery device
CN104555470A (en) * 2014-12-10 2015-04-29 中原工学院 Automatic board chopping device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110253751A (en) * 2019-07-19 2019-09-20 中原工学院 A kind of four-bar mechanism cloth steel mesh machine and its application method

Also Published As

Publication number Publication date
CN104924451B (en) 2017-07-14

Similar Documents

Publication Publication Date Title
CN103741955B (en) automatic wall building machine
CN107650258A (en) A kind of bidirectional circulating structure prefabricated components production line and control method
CN204475841U (en) Self lift type shaft template device
CN109129837B (en) Cement brick preparation and shedder
CN112454643A (en) Modularized disassembly-free wall formwork automatic production system
CN103510717A (en) Method for constructing building wall
CN106142335B (en) A kind of production method and particular manufacturing craft of rectangular gas flue
CN203714840U (en) Bridge type setting machine
CN104924451A (en) Reinforcing mesh dropping device
CN103896075A (en) Bridge type setting machine
CN202062499U (en) Twin-span rotary-type concrete tubular pile manufacturing device
CN204418692U (en) Novel frame structure constructional column concrete casting machine
CN209780253U (en) Mould shell turning device
CN203640248U (en) Fast construction device for external wall of light well
CN104139451A (en) Concrete core slab prefabricated internal mold, assembling frame and assembling method
CN104555470B (en) Automatically sheet piling device
CN206105343U (en) Whole form removal machine of putting of prestressing force
CN212983915U (en) Waterproof wall of leading of assembled soleplate
CN105000399A (en) Precast slab device for automatic cement unloading
CN202689278U (en) Superimposed hollow slab
CN202924388U (en) Ceramic tile temporary storage device
CN104609237B (en) Multi-connecting-rod mechanism loader
CN208729979U (en) A kind of precast facade thermal-insulation connecting piece placement manipulator
CN109050376B (en) Building assembly transmission device
CN104563505A (en) External wall and heat insulation layer integrated construction method and external wall decoration lifting platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170714

Termination date: 20200601