CN104632122A - Block profile control well selection method used in low-permeability fractured reservoir - Google Patents

Block profile control well selection method used in low-permeability fractured reservoir Download PDF

Info

Publication number
CN104632122A
CN104632122A CN201310551942.4A CN201310551942A CN104632122A CN 104632122 A CN104632122 A CN 104632122A CN 201310551942 A CN201310551942 A CN 201310551942A CN 104632122 A CN104632122 A CN 104632122A
Authority
CN
China
Prior art keywords
well
block
profile control
ipi
value
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310551942.4A
Other languages
Chinese (zh)
Inventor
张�荣
李宪文
王兴宏
徐春梅
陈荣环
刘保彻
吴天江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CN201310551942.4A priority Critical patent/CN104632122A/en
Publication of CN104632122A publication Critical patent/CN104632122A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/13Methods or devices for cementing, for plugging holes, crevices or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

A block profile control well selection method used in a low-permeability fractured reservoir belongs to the technical field of petroleum industry. Introducing original thickness and original permeability, providing an IPI well selection method, performing well selection according to an IPI calculation result, and then performing profile control by adopting a profile control process; the well selection method for block profile control is to select a well meeting the following conditions: testing the wellhead pressure drop curve of each water well in the profile control block; working systems of adjacent wells are not changed in the testing time period, the testing time of the 1 st well of each block is 24 hours, the stage that the pressure drop tends to be gentle is found out, and the testing time of the block is determined; sequentially testing other water injection wells in the block; after the test is finished, drawing a pressure drop curve of the wellhead of the water injection well; the wells below the block average IPI value were selected as profile control wells, and the wells around the block average dimensionless IPI value and above the block average IPI value were not treated.

Description

A kind of low permeability fractured type oil reservoir use for Block Profile Control well choosing method
Technical field
The present invention relates to a kind of low permeability fractured type oil reservoir use for Block Profile Control well choosing method, belong to oil work technical field.
Background technology
Current domestic representative decision-making technic mainly contains: PI decision-making technic, RE decision-making technic, the tracer decision-making technic of China University Of Petroleum Beijing's research, and the RS decision-making technic of Oil Exploration in China developmental research institute development.Wherein PI decision-making technic is that Petroleum Univ. (East China) professor Zhao Fulin equals to propose and utilizes well head falloff curve to select well decision-making technic the nineties.Generally apply at tens, middle and high infiltration oil field blocks such as triumph, grand celebration, Central Plains, effect is better, but for Fracture with low permeability oil reservoir, there is erroneous judgement profile control well, these methods also have certain limitation.
Summary of the invention
In order to overcome the deficiencies in the prior art, the invention provides a kind of low permeability fractured type oil reservoir use for Block Profile Control well choosing method.
Low permeability fractured type oil reservoir use for a Block Profile Control well choosing method, containing following steps;
Introducing original thickness, original permeability proposes IPI well choosing method, carry out selecting well according to IPI result of calculation, carrying out profile control according to then adopting profile control technology;
The well choosing method of Block Profile Control chooses the well met the following conditions:
(1) the well head pressure depression curve of well each in profile control block is tested; In testing time section, the working system of contiguous each well does not change, and the 1st mouthful of 24 hours well testing time of each block, finds out the stage that drop of pressure tends towards stability, determines the testing time of block;
(2) successively other water injection well in block is tested;
(3) after test completes, the falloff curve of wellhead of water injection well is drawn;
(4) calculate the PI value of each well, then calculate the zero dimension IPI value of each well;
PI = ∫ 0 t p ( t ) dt t
IPI = k i h 1.842 × 10 - 3 qμ · PI
(5) select the well lower than the average IPI value of block to be profile control well, the well near block average zero dimension IPI value and higher than the average IPI value of block is disregarded.
Advantage of the present invention is:
(1) zero dimension IPI value considers the original permeability of reservoir, eliminates the pressure relief capability of reservoir own to the impact of falloff curve.And the size of zero dimension PI value and reservoir permeability increase multiple (k/ki) and are inversely proportional to.Namely the predominant pathway growth rank formed in current reservoir is higher, and it is larger that permeability increases multiple, and zero dimension PI value is less;
(2) zero dimension IPI value is tolerance Reservoir Seepage ability being strengthened to degree, working system before its size and water injection well closing well, as irrelevant in injection pressure, injection rate etc., therefore in same block different Injection Well zero dimension PI value between can mutually compare;
(3) IPI value calculates simple, and result is only relevant with choosing of computing time.The principle chosen computing time is: in closed-in time t, and testing well will complete main drop of pressure amplitude, and calibration curve information can reflect pit shaft, the formation information of wellbore region in the certain limit of near wellbore zone.
Detailed description of the invention
Obviously, the many modifications and variations that those skilled in the art do based on aim of the present invention belong to protection scope of the present invention.
Embodiment 1: a kind of low-permeability oilfield Block Profile Control well choosing method
For being that main block profile control well selection accuracy rate is not high with dynamic-analysis method, the problems such as the cycle is long, the invention provides a kind of effective well choosing method adapting to block integral profile control, and then improve measure specific aim and efficient, improve block waterflooding development effect.
Select the region that comprehensive water cut is high, water injection well cementing quality is good, leaks phenomenon without channelling and interlayer string.Test the water injection well falloff curve of region or block in flakes, calculate IPI value and the average IPI value of block of corresponding well, select the well lower than the average IPI value of block to be profile control well, sorted by IPI value is ascending by profile control well, the well that prioritizing selection IPI value is little carries out profile control.
Below in conjunction with detailed description of the invention, the present invention is further illustrated:
(1) the well head pressure depression curve of well each in block is tested.In testing time section, the working system of contiguous each well does not change, and the 1st mouthful of 24 hours well testing time of each block, finds out the stage that drop of pressure tends towards stability, determines the testing time of block.
(2) successively other water injection well of block is tested.
(3) after test completes, the falloff curve of wellhead of water injection well is drawn.
(4) calculate the PI value of each well, then calculate the zero dimension IPI value of each well.
PI = ∫ 0 t p ( t ) dt t
IPI = k i h 1.842 × 10 - 3 qμ · PI
(5) select the well lower than the average IPI value of block to be profile control well, the well near block average zero dimension IPI value and higher than the average IPI value of block is disregarded.
As mentioned above, embodiments of the invention are explained, but as long as do not depart from inventive point of the present invention in fact and effect can have a lot of distortion, this will be readily apparent to persons skilled in the art.Therefore, such variation is also all included within protection scope of the present invention.

Claims (1)

1. low permeability fractured type oil reservoir use for a Block Profile Control well choosing method, it is characterized in that containing following steps;
Introducing original thickness, original permeability proposes IPI well choosing method, carry out selecting well according to IPI result of calculation, carrying out profile control according to then adopting profile control technology;
The well choosing method of Block Profile Control chooses the well met the following conditions:
(1) the well head pressure depression curve of well each in profile control block is tested; In testing time section, the working system of contiguous each well does not change, and the 1st mouthful of 24 hours well testing time of each block, finds out the stage that drop of pressure tends towards stability, determines the testing time of block;
(2) successively other water injection well in block is tested;
(3) after test completes, the falloff curve of wellhead of water injection well is drawn;
(4) calculate the PI value of each well, then calculate the zero dimension IPI value of each well;
PI = ∫ 0 t p ( t ) dt t
IPI = k i h 1.842 × 10 - 3 qμ · PI
(5) select the well lower than the average IPI value of block to be profile control well, the well near block average zero dimension IPI value and higher than the average IPI value of block is disregarded.
CN201310551942.4A 2013-11-08 2013-11-08 Block profile control well selection method used in low-permeability fractured reservoir Pending CN104632122A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310551942.4A CN104632122A (en) 2013-11-08 2013-11-08 Block profile control well selection method used in low-permeability fractured reservoir

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310551942.4A CN104632122A (en) 2013-11-08 2013-11-08 Block profile control well selection method used in low-permeability fractured reservoir

Publications (1)

Publication Number Publication Date
CN104632122A true CN104632122A (en) 2015-05-20

Family

ID=53211301

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310551942.4A Pending CN104632122A (en) 2013-11-08 2013-11-08 Block profile control well selection method used in low-permeability fractured reservoir

Country Status (1)

Country Link
CN (1) CN104632122A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105715238A (en) * 2015-12-01 2016-06-29 山东石大油田技术服务股份有限公司 Real time monitoring and controlling method for displacement pressure gradient of waterflooding development oil reservoir
CN107035348A (en) * 2017-05-08 2017-08-11 中国石油天然气股份有限公司 Multi-factor analysis well selection method and device for oil field profile control
CN108590571A (en) * 2018-03-27 2018-09-28 中国石油天然气股份有限公司 Method for determining dosage of profile control agent of low-permeability fractured water-breakthrough reservoir for water injection well

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6836731B1 (en) * 2001-02-05 2004-12-28 Schlumberger Technology Corporation Method and system of determining well performance
CN103244087A (en) * 2013-05-21 2013-08-14 中国石油大学(北京) Profile control and water plugging well selection decision-making method for low-permeability reservoirs

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6836731B1 (en) * 2001-02-05 2004-12-28 Schlumberger Technology Corporation Method and system of determining well performance
CN103244087A (en) * 2013-05-21 2013-08-14 中国石油大学(北京) Profile control and water plugging well selection decision-making method for low-permeability reservoirs

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
冯其红等: "低渗透裂缝性油藏调剖选井无因次压力指数决策方法", 《石油学报》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105715238A (en) * 2015-12-01 2016-06-29 山东石大油田技术服务股份有限公司 Real time monitoring and controlling method for displacement pressure gradient of waterflooding development oil reservoir
CN107035348A (en) * 2017-05-08 2017-08-11 中国石油天然气股份有限公司 Multi-factor analysis well selection method and device for oil field profile control
CN107035348B (en) * 2017-05-08 2019-05-07 中国石油天然气股份有限公司 Multi-factor analysis well selection method and device for oil field profile control
CN108590571A (en) * 2018-03-27 2018-09-28 中国石油天然气股份有限公司 Method for determining dosage of profile control agent of low-permeability fractured water-breakthrough reservoir for water injection well

Similar Documents

Publication Publication Date Title
WO2018121035A1 (en) Customized method for determining coal mining face floor water inrush risk level
RU2671502C2 (en) Structural discrimination indexes of ordovician limestone top filling zones and determination method
CN103924966B (en) Grouping of Sand Members And Well based on reservoir properties time-varying model construction method again
CN104695950A (en) Prediction method for volcanic rock oil reservoir productivity
MY146703A (en) Method of drilling and producing hydrocarbons from subsurface formations
CN106909758A (en) A kind of new method of fine and close oil reservoir-level well multistage sub-clustering perforating site optimization design
CN106639995A (en) Water-drive reservoir crude oil recovery rate prediction method
CN107387051A (en) The method that low permeable and heterogeneity reservoir multistage pressure break horizontal well refracturing selects well
CN103912248A (en) Method for predicting water content of water-flooding oil field
CN104100263A (en) Method for determining residual oil saturation of non-uniform water flooded layer
CN105930932A (en) Gas index-based shale-gas-layer standardized open-flow capacity obtaining method
RU2014144308A (en) SYSTEM AND METHOD FOR ANALYSIS OF PRESSURE DATA IN A COLLECTOR
CN104632122A (en) Block profile control well selection method used in low-permeability fractured reservoir
CN104408541A (en) Method for evaluating uniform steam injection effect of steam huff and puff horizontal well
CN107035348B (en) Multi-factor analysis well selection method and device for oil field profile control
CN106503284B (en) Shale gas horizontal well horizontal segment gas-bearing formation produces gas evaluation method
CN103995297A (en) Method for correcting resistivity of crack carbonatite stratum
CN104632150B (en) The method that the offshore oilfield difference reasonable Liquid output of well group determines
CN106761718A (en) Determine that mid-deep strata oil reservoir employs the new method of thickness limit
CN104712301A (en) Method for determining fracturing size of volcanic reservoir
CN105089597A (en) Crack complexity evaluation method
CN106468170A (en) Lacustrine shale oil dessert Dominated Factors evaluation methodology
CN108999608A (en) Low-permeability conglomerate reservoir dominant channel identification method and system
CN106150454B (en) Offshore oilfield vector quantization production and injection proration method
CN106845685B (en) Parameter optimization method for reducing horizontal well oil testing fracturing operation cost

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150520