CN104533520A - 一种监控隧道拱顶沉降和周边收敛的方法 - Google Patents
一种监控隧道拱顶沉降和周边收敛的方法 Download PDFInfo
- Publication number
- CN104533520A CN104533520A CN201410717505.XA CN201410717505A CN104533520A CN 104533520 A CN104533520 A CN 104533520A CN 201410717505 A CN201410717505 A CN 201410717505A CN 104533520 A CN104533520 A CN 104533520A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- rope
- monitoring
- spring scale
- reading
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01C—MEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
- G01C5/00—Measuring height; Measuring distances transverse to line of sight; Levelling between separated points; Surveyors' levels
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01C—MEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
- G01C7/00—Tracing profiles
- G01C7/06—Tracing profiles of cavities, e.g. tunnels
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Radar, Positioning & Navigation (AREA)
- Remote Sensing (AREA)
- Multimedia (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本发明提供了一种监控隧道拱顶沉降和周边收敛的方法,通过安装无弹性变形的绳索,一端固定于隧道断面一端拱脚、另一端系于标定后的电子弹簧秤上,该弹簧秤位于隧道断面另一端拱脚上,中间部分绳索穿过隧道圆拱;在监控开始时,首先预加一个初始力、使得电子弹簧秤上的读书有一个初始读数,拉动绳索,使得弹簧秤上的初始读数趋于稳定,并做记录,重复上述步骤,在多个断面布设相同方式监控措施,在隧道施工时,持续观测电子弹簧秤的读书,如有读数发生变化,暂停施工,再利用全钻仪或者3D激光扫描仪对隧道截面进行复测,发现问题及时处理。本发明装置简单、免模型预测、计算量小、无技术难度、便于工人及时发现危险状况。
Description
技术领域
本发明属于监控量测领域,尤其涉及一种监控隧道拱顶沉降和周边收敛的方法。
背景技术
隧道等地下工程施工由于其隐蔽性、不确定性和多变化性等特点,施工难度大,易造成各种各样的工程质量事故,严重地影响了工程施工进度和工程质量,施工监控量测目的是及时监测掌握工程结构的应力应变情况,进行信息化处理,指导工程施工,确保施工安全及结构的长期稳定性,验证支护结构效果,积累量测数据,为信息化设计与施工提供依据。
在隧道施工中,监控量测最重要的任务就是及时、准确地监测围岩的变形财情况,进行监控量测数据分析,提早做出预警预报,尽早采取必要措施,避免事故的发生。
尽管隧道施工监控量测工作在我国开展有一些年了,但是总体而言,在具体施工中其实施与应用都还很不完善。监控量测工作的发展主要表现在监测仪器与监测方法的不断更新进步。当前应用于监控量测的主要仪器包括:水准仪、全站仪、钢挂尺、收敛计和适应于不同材料的压力盒、应变应力计等等。这些仪器的应用在硬件条件上就保证了监控量测工作的准确性,提高了监控量测的可操作性、适应性、稳定性和精度。但是水准仪、钢挂尺、收敛计都由于测量精度不高,受隧道施工影响较大,涉及器材较多,易对隧道造成施工阻碍,且数据存储、传输、处理、分析等工作量大,工程应用不便。
目前在大多数的隧道施工监控量测中技术人员都采用全站仪进行。相比其他三种仪器,全站仪具有精度高、施测方便、数据传输方便等优点。并且全站仪可以直接与计算机连接,在友好的计算机操作***中,可以实现监测数据的自动传输、处理、分析。全站仪的应用使得隧道监控量测工作迈上了一个新台阶,另外国内率先应用了3D激光扫描仪进行监控量测工作,在监控量测仪器的更新发展上做出了新的探索。但无论是采用全钻仪还是3D激光扫描仪都存在仪器设备昂贵、监控速度慢,监控滞后等缺点。
发明内容
针对现有技术的不足,本发明提出了一种监控隧道拱顶沉降和周边收敛的方法,目的是找到一种简便、经济、有效、能够及时监控隧道拱顶和周边瞬间变换的监控方法。
本发明是这样实现的,一种监控隧道拱顶沉降和周边收敛的方法,包括以下步骤:
(1)将无弹性变形的绳索一端固定于隧道断面一端拱脚、另一端系于标定后的电子弹簧秤上,该弹簧秤位于隧道断面另一端拱脚上;所述绳索中间部分穿过悬挂钉于隧道圆拱的圆环上;
(2)在监控开始时,首先对绳索预加一个初始力使得电子弹簧秤上的读数有一个初始读数,然后拉动绳索,使得弹簧秤上的初始读数趋于稳定,并做记录;
(3)在隧道纵向的多个断面上分别重复实施上述步骤(1)和(2);
(4)在隧道施工时,持续观测电子弹簧秤的读书,如有读数发生变化,暂停施工,再利用全钻仪或者3D激光扫描仪对隧道截面进行复测,及时发现问题并处理。
优选地,所述隧道圆拱包括拱顶、隧道周围围堰以及衬砌。
优选地,在步骤(4)中,所述施工包括隧道开挖、拱顶注浆、衬砌修补。
相比于现有技术的缺点和不足,本发明具有以下有益效果:本发明装置简单、免模型预测、计算量小、无技术难度、便于工人及时发现危险状况。
附图说明
图1是本发明监控隧道拱顶沉降和周边收敛的方法的原理结构示意图。
具体实施方式
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
一种监控隧道拱顶沉降和周边收敛的方法,如图1所示,包括以下步骤:
(1)将无弹性变形的绳索一端固定于隧道断面一端拱脚监控点A,另一端系于标定后的电子弹簧秤上,该弹簧秤位于隧道断面另一端拱脚监控点E;所述绳索中间部分穿过悬挂钉于拱顶监控点C和隧道周围围堰监控点B、D(或衬砌)上的圆环上,上述中间部分监控点可以根据现场情况进行加密布设;
(2)在监控开始时,首先对绳索预加一个初始力使得电子弹簧秤上的读数有一个初始读数,然后拉动绳索,使得弹簧秤上的初始读数趋于稳定,并记录初始读数;
(3)在隧道纵向的多个断面上分别重复实施上述步骤(1)和(2),布设多道监控装置,间隔间距可以根据现场情况设置为2~4米;
(4)在隧道进行开挖、拱顶注浆、衬砌修补等施工时,持续观测电子弹簧秤的读数,如有读数发生变化,暂停施工,再利用全钻仪或者3D激光扫描仪对隧道截面进行复测,及时发现问题并处理。
本发明利用隧道拱顶沉降和周边收敛时隧道截面的几何形状会发生改变这一事实为基础,通过将简单几何原理应用到隧道施工过程中进行监控隧道拱顶沉降和周边收敛中来,设计巧妙、装置简单、免模型预测、计算量小、无技术难度、便于工人及时发现危险状况。
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。
Claims (3)
1.一种监控隧道拱顶沉降和周边收敛的方法,其特征在于,包括以下步骤:
(1)将无弹性变形的绳索一端固定于隧道断面一端拱脚、另一端系于标定后的电子弹簧秤上,该弹簧秤位于隧道断面另一端拱脚上;所述绳索中间部分穿过悬挂钉于隧道圆拱的圆环上;
(2)在监控开始时,首先对绳索预加一个初始力使得电子弹簧秤上的读数有一个初始读数,然后拉动绳索,使得弹簧秤上的初始读数趋于稳定,并做记录;
(3)在隧道的纵向多个断面上分别重复实施上述步骤(1)和(2);
(4)在隧道施工时,持续观测电子弹簧秤的读书,如有读数发生变化,暂停施工,再利用全钻仪或者3D激光扫描仪对隧道截面进行复测,及时发现问题并处理。
2.如权利要求1所述的监控隧道拱顶沉降和周边收敛的方法,其特征在于,所述隧道圆拱包括拱顶、隧道周围围堰以及衬砌。
3.如权利要求2所述的监控隧道拱顶沉降和周边收敛的方法,其特征在于,在步骤(4)中,所述施工包括隧道开挖、拱顶注浆。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410717505.XA CN104533520A (zh) | 2014-12-01 | 2014-12-01 | 一种监控隧道拱顶沉降和周边收敛的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410717505.XA CN104533520A (zh) | 2014-12-01 | 2014-12-01 | 一种监控隧道拱顶沉降和周边收敛的方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104533520A true CN104533520A (zh) | 2015-04-22 |
Family
ID=52849120
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410717505.XA Pending CN104533520A (zh) | 2014-12-01 | 2014-12-01 | 一种监控隧道拱顶沉降和周边收敛的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104533520A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109489623A (zh) * | 2018-11-24 | 2019-03-19 | 上海勘察设计研究院(集团)有限公司 | 一种采用三维激光扫描仪测量桥头引道不均匀沉降的方法 |
CN109505658A (zh) * | 2018-12-11 | 2019-03-22 | 云南航天工程物探检测股份有限公司 | 基于拱顶下沉和周边收敛的隧道监测预警***及方法 |
CN109882242A (zh) * | 2019-03-15 | 2019-06-14 | 青岛理工大学 | 一种交通隧道拱顶坍塌快速识别方法 |
CN112539733A (zh) * | 2020-11-20 | 2021-03-23 | 沈阳达能电安全高新产业技术研究院有限公司 | 一种隧道沉降监测装置及隧道沉降监测方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3147471A1 (de) * | 1981-12-01 | 1983-07-14 | Maschinenfabrik Korfmann Gmbh, 5810 Witten | Verfahren und vorrichtung zum aufhaengen einer luttenleitung |
DE3619527A1 (de) * | 1986-06-10 | 1987-12-17 | Pohle & Rehling Gmbh | Lagerraum fuer dieselkraftstoffe |
CN202348345U (zh) * | 2011-12-17 | 2012-07-25 | 中铁十二局集团有限公司 | 隧道围岩监测自动报警*** |
CN103335596A (zh) * | 2013-06-26 | 2013-10-02 | 同济大学 | 隧道收敛位移和拱顶沉降的测量装置及测量方法 |
CN203443579U (zh) * | 2013-09-05 | 2014-02-19 | 中铁上海工程局有限公司 | 一种基于单侧壁导坑法的隧道收敛监测*** |
CN103791802A (zh) * | 2014-01-27 | 2014-05-14 | 北京工业大学 | 一种地下隧道两帮收敛变形电子测量装置与方法 |
-
2014
- 2014-12-01 CN CN201410717505.XA patent/CN104533520A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3147471A1 (de) * | 1981-12-01 | 1983-07-14 | Maschinenfabrik Korfmann Gmbh, 5810 Witten | Verfahren und vorrichtung zum aufhaengen einer luttenleitung |
DE3619527A1 (de) * | 1986-06-10 | 1987-12-17 | Pohle & Rehling Gmbh | Lagerraum fuer dieselkraftstoffe |
CN202348345U (zh) * | 2011-12-17 | 2012-07-25 | 中铁十二局集团有限公司 | 隧道围岩监测自动报警*** |
CN103335596A (zh) * | 2013-06-26 | 2013-10-02 | 同济大学 | 隧道收敛位移和拱顶沉降的测量装置及测量方法 |
CN203443579U (zh) * | 2013-09-05 | 2014-02-19 | 中铁上海工程局有限公司 | 一种基于单侧壁导坑法的隧道收敛监测*** |
CN103791802A (zh) * | 2014-01-27 | 2014-05-14 | 北京工业大学 | 一种地下隧道两帮收敛变形电子测量装置与方法 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109489623A (zh) * | 2018-11-24 | 2019-03-19 | 上海勘察设计研究院(集团)有限公司 | 一种采用三维激光扫描仪测量桥头引道不均匀沉降的方法 |
CN109489623B (zh) * | 2018-11-24 | 2021-05-11 | 上海勘察设计研究院(集团)有限公司 | 一种采用三维激光扫描仪测量桥头引道不均匀沉降的方法 |
CN109505658A (zh) * | 2018-12-11 | 2019-03-22 | 云南航天工程物探检测股份有限公司 | 基于拱顶下沉和周边收敛的隧道监测预警***及方法 |
CN109882242A (zh) * | 2019-03-15 | 2019-06-14 | 青岛理工大学 | 一种交通隧道拱顶坍塌快速识别方法 |
CN112539733A (zh) * | 2020-11-20 | 2021-03-23 | 沈阳达能电安全高新产业技术研究院有限公司 | 一种隧道沉降监测装置及隧道沉降监测方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103410516B (zh) | 小直径隧洞全断面开挖围岩变形预警工法 | |
CN111335186A (zh) | 转体桥梁安全监测预警方法、***、存储介质、预警平台 | |
CN110608054B (zh) | 一种全断面法开挖隧道支护结构变形预测方法及装置 | |
CN104533520A (zh) | 一种监控隧道拱顶沉降和周边收敛的方法 | |
CN108960621A (zh) | 一种盾构隧道施工下穿高铁桥梁的桥梁监测与评价方法 | |
CN105332739A (zh) | 一种隧道支护结构受力监测装置及方法 | |
CN112857988A (zh) | 一种管片足尺试验非对称荷载加载试验***及其试验方法 | |
CN104318004A (zh) | 基于变形数据的隧道二次衬砌结构的弯矩内力分析方法 | |
CN103901180A (zh) | 一种间接得到地下巷道围岩受力和变形状态的方法 | |
CN103471647A (zh) | 一种盾构隧道远程自动化监测方法 | |
Ma et al. | Distance effects of the fault on the surrounding rock mass stability of the main powerhouse at the Huanggou pumped-storage power station | |
CN112924061A (zh) | 一种天然气管道非均匀沉降应力无线实时监测***及方法 | |
Li et al. | Deformation behavior monitoring of a tunnel in its temporary shoring demolishing process using optical fiber sensing technology | |
CN113062773B (zh) | 深部隧道装配式通风竖井的自动化监测预警***及施工方法 | |
CN113591347A (zh) | 一种高边坡施工过程中动态监测方法及预警*** | |
CN202548622U (zh) | 一种隧道施工用远程测控*** | |
CN205644892U (zh) | 一种基于bim的地下工程施工安全风险感知装置 | |
CN104298856B (zh) | 基于围岩变形监控与数值模拟的隧道超前地质预报方法 | |
CN202548621U (zh) | 一种电网隧道用自动化远程监控*** | |
CN205484212U (zh) | 一种围岩损伤时间效应测试结构 | |
Yao | Research on invert monitoring system of expansive rock tunnel based on distributed optical fiber | |
Lunardi et al. | Tunnel monitoring system—a contribution for the preparation of guidelines | |
Zhao et al. | Information monitoring technology for support structure of railway tunnel during operation | |
Gama | A method for continuous monitoring of tunnel deformations during construction and service phases | |
CN215338205U (zh) | 一种用于监测破除地下连续墙施工变形的结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20150422 |