CN104532985B - Shear wall cast with tenon-and-mortise precast concrete blocks replacing formworks and construction method thereof - Google Patents

Shear wall cast with tenon-and-mortise precast concrete blocks replacing formworks and construction method thereof Download PDF

Info

Publication number
CN104532985B
CN104532985B CN201410774744.9A CN201410774744A CN104532985B CN 104532985 B CN104532985 B CN 104532985B CN 201410774744 A CN201410774744 A CN 201410774744A CN 104532985 B CN104532985 B CN 104532985B
Authority
CN
China
Prior art keywords
building block
shear wall
fagging
wall
mortise
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410774744.9A
Other languages
Chinese (zh)
Other versions
CN104532985A (en
Inventor
韩忠民
李红建
李秋海
李保平
管玉民
于洪耀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENAN ZHONGDING ZHITUO ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Original Assignee
HENAN ZHONGDING ZHITUO ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN ZHONGDING ZHITUO ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd filed Critical HENAN ZHONGDING ZHITUO ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Priority to CN201410774744.9A priority Critical patent/CN104532985B/en
Publication of CN104532985A publication Critical patent/CN104532985A/en
Application granted granted Critical
Publication of CN104532985B publication Critical patent/CN104532985B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A shear wall cast with tenon-and-mortise precast concrete blocks replacing formworks is characterized in that two blocks with vertically and bilaterally corresponding fastened tenon-and-mortise structures are spliced to form a masonry with a structure, internal cavities of the structure are vertically and completely communicated and horizontally locally communicated, the structure is provided with external level crevices and vertical staggered joints, vertical and horizontal reinforcing steel bars are placed in the internal cavities in the masonry respectively, and concrete is cast. When the shear wall is constructed, a '_' wall, a 'T'-shaped wall or an 'L'-shaped wall can be built only by two types of blocks are needed, a formwork system is no longer set up, waiting for maintenance of the concrete is no longer needed, and continuous operation can be performed. When the used blocks are self-locked in a tenon-and-mortise manner in a horizontal layer, and the vertical reinforcing steel bars can be conveniently fastened in the internal cavities of the shear wall by fastening from two sides to the center.

Description

A kind of shear wall replacing template to pour with mortise and tenon type precast concrete segment and its apply Work method
Technical field
The present invention relates to building field is and in particular to a kind of mortise and tenon type precast concrete segment replaces what template poured to cut Power wall and its construction method.
Background technology
At present, because China's skyscraper market is huge, especially high residential building project, all using cast in place reinforced bar coagulation Native shear wall structure system, and the construction of cast-in-situ steel reinforced concrete shear wall structure not only needs substantial amounts of formwork system, especially It is to need a large amount of common templates in addition it is also necessary to poured in place concrete, and scene carries out maintenance.In this process, mould bases work Journey will expend a large amount of common templates and scaffold in addition it is also necessary to a large amount of skilled worker;And cast-in-place concrete only has process The maintenance of certain time, can be only achieved certain intensity, just can carry out lower one working procedure, when consuming valuable in a large number Between.The material cost of whole process consuming, cost of labor, time cost are very large.At present, some joinery and its constructions are occurred in that Body of wall, changes and traditional pours pattern.But, the building block species pattern being used more it is difficult to produce, building process hold Splicing mistake easily occurs, and is unfavorable for that the stock of building block sorts out, occupied fund is more.
Content of the invention
The present invention provides a kind of shear wall replacing template to pour with mortise and tenon type precast concrete segment and its construction method, Solve the problems, such as that the block styles that the body of wall of existing joinery and its construction uses are more.
For achieving the above object, employ the following technical solutions:
A kind of shear wall replacing template to pour with mortise and tenon type precast concrete segment, described shear wall by two kinds have on The mutually corresponding building block fastening joinery and its construction in lower left and right is spliced into masonry, and described masonry has internal cavities whole phases up and down Logical, level local communicates, outer horizontal straight joint, the structure of the upper and lower fissure of displacement, be mounted with respectively in cavity masonry within vertical with Horizontal reinforcement, and casting concrete.
Described building block includes the first building block and second building block of edge mutual Tenon self-locking;First building block is " Qian " shape, tool Have positioned at middle fagging and two flanks, the top of fagging and bottom are respectively provided with projection and groove, the top of left side flank End and bottom are respectively provided with projection and groove, and the top of right side flank and bottom are respectively provided with projection and groove;The Two building blocks are " h " shape, have positioned at middle fagging and two fins, perforate in the middle part of fagging, fagging top both sides have and support The equidirectional projection of plate, flap apex both sides have projection and projection, and fin two bottom sides have groove and groove , raised, the raised, groove of fin is different with groove location in front and back.
Between the flank top of described first building block and fagging, there is reinforced hole, the second building block flap apex both sides have puts Put the hole used by reinforcing bar.
The flank of described first building block has the symmetrical gusset vertical with flank;The fagging two of described second building block Side has the gusset vertical with fagging.
Described shear wall is " one " shape wall, " l " shape wall or " t " shape wall.
A kind of construction method of the shear wall replacing template to pour with mortise and tenon type precast concrete segment it is characterised in that: During construction, the vertical reinforcement of the first good shear wall of colligation, mutual for building block self-locking is spliced into first level layer, then by vertical reinforcement It is placed in the cavity of shear wall, afterwards in one layer of horizontal reinforcement of horizontal level colligation of building block cavity, then splice one layer again Building block, colligation horizontal reinforcement, repeats to splice level course and colligation horizontal reinforcement, when body of wall is close to beam bottom position, will push up After the good common templates in layer masonry local, integrated poured concrete is carried out to whole shear wall.
The present invention changes this construction method at present, it is only necessary to use two kinds of forms in the construction of shear wall structure Building block it is possible to build " one " shape wall, " t " shape wall or " l " shape wall by laying bricks or stones, and be no longer necessary to build formwork system it is not required that Wait the maintenance of concrete, you can worked continuously;Furthermore because building block adopts industrialized standard to produce, its specification, size Can be guaranteed, consisting of the precision of masonry size be greatly improved, thus improving the construction quality of shear wall.More need To be proposed: building block used in the present invention, in level course Tenon self-locking, is by the way of both sides are to center engaging, can Easily vertical reinforcement to be fastened in the inner chamber of shear wall.So this invention had both improve the construction quality of shear wall, and Save material, artificial, time, purified job site simultaneously, saved building cost, improve work efficiency.
Further, reinforced hole is arranged on building block, can more specification reinforcing bar tie up construction, without building by laying bricks or stones Temporary punching during body of wall.
Further, building block arranges gusset, insulation material can be placed in the space that gusset isolates, make to build by laying bricks or stones Body of wall there is heat insulation function, meet the standard of modern architecture heat preservation energy-saving.
Brief description
Fig. 1 is the front view of the first building block.
Fig. 2 is the rearview of Fig. 1.
Fig. 3 is the left view of Fig. 1.
Fig. 4 is the right view of Fig. 1.
Fig. 5 is the top view of Fig. 1.
Fig. 6 is the upward view of Fig. 1.
Fig. 7 is the a-a sectional view of Fig. 5.
Fig. 8 is the b-b sectional view of Fig. 5.
Fig. 9 is the front view of the second building block.
Figure 10 is the left view of Fig. 9.
Figure 11 is the plan view of Fig. 9.
Figure 12 is the bottom view of Fig. 9.
Figure 13 is the a-a sectional view of Fig. 9.
Figure 14 is the b-b sectional view of Fig. 9.
Figure 15 is the c-c sectional view of Fig. 9.
Figure 16 is the schematic diagram of first building block with gusset.
Figure 17 is the schematic diagram of second building block with gusset.
Figure 18 is the schematic diagram of level course a.
Figure 19 is the schematic diagram of level course a.
Figure 20 is the schematic diagram of level course b.
Figure 21 is the schematic diagram of level course b.
Figure 22 is the schematic diagram of " l " shape wall level course a.
Figure 23 is the schematic diagram of " l " shape wall level course b.
Figure 24 is the schematic diagram of " t " shape wall level course a.
Figure 25 is the schematic diagram of " t " shape wall level course b.
Figure 26 is the schematic diagram of " one " shape wall level course a of sheet with rib.
Figure 27 is the schematic diagram of " one " shape wall level course a of sheet with rib.
Figure 28 is the schematic diagram of " one " shape wall level course b of sheet with rib.
Figure 29 is the schematic diagram of " one " shape wall level course b of sheet with rib.
Figure 30 is the schematic diagram of " l " shape wall level course a of sheet with rib.
Figure 31 is the schematic diagram of " l " shape wall level course b of sheet with rib.
Figure 32 is the schematic diagram of " t " shape wall level course a of sheet with rib.
Figure 33 is the schematic diagram of " t " shape wall level course b of sheet with rib.
Wherein, 1 is the fagging of the first building block, and 2 is flank, and 3 is raised, and 4 is groove, and 5 is raised, and 6 is groove, 7 is raised, and 8 is groove, and 9 is the fagging of the second building block, and 10 is fin, and 11 is perforate, and 12 is raised, and 13 is raised, 14 is raised, and 15 is groove, and 16 is groove, and 17 is hole, and 18 is gusset.
Specific embodiment
As shown in accompanying drawing 1-15, described shear wall is formed by the first concrete prefabricated building block and the second building block Tenon self-locking Body of wall, fixation binding horizontally and vertically reinforcing bar in cavity inner chamber, and casting concrete.
First building block is " Qian " shape, has positioned at middle fagging 1 and two flanks 2, and the top of fagging 1 and bottom are respectively There is raised 3 and groove 4, the top of left side flank 2 and bottom are respectively provided with raised 5 and groove 6, right side flank 2 Top and bottom are respectively provided with raised 7 and groove 8;Second building block is " h " shape, has positioned at middle fagging 9 and two Fin 10, fagging 9 middle part perforate 11, fagging 9 top both sides have equidirectional with fagging 9 raised 12, fin 10 top two Side has raised 13 and raised 14, and fin 10 two bottom sides have groove 15 and groove 16, and fin 10 is convex in front and back Play 13, raised 14, groove 15 different with groove 16 position.Have between flank 2 top of the first building block and fagging 1 Prevent the reinforced hole 17 used by reinforcing bar, the second building block fin 10 top both sides have reinforced hole 17.
Further, the flank 2 of the first building block has the symmetrical gusset 18 vertical with flank 2;Described second block Fagging 9 both sides of block have the gusset 18 vertical with fagging 9.
The same layer building block of level course forms level course a by the first building block mutual Tenon self-locking, needs the side of the first building block The wing 2 raised 5 and raised 7 is combined, and correspondingly, the groove 6 of bottom and groove 8 are combined, such as accompanying drawing 18th, shown in 19;Or form level course b by the mutual Tenon of the second building block and in two ends Tenon first building block, need to build second The fin 10 raised 13 and raised 14 of block is combined, and the projection 13 of end and the projection 5 of the first building block combine, The projection 7 of the projection 14 of end and the first building block combines, and correspondingly, the groove 15 of bottom and groove 16 combine, recessed Groove 15 and groove 6 combine, and groove 16 and groove 8 combine as shown in accompanying drawing 20,21.
" one " shape wall, is formed by level course a and level course b in the vertical direction are mutually overlapping, the projection in each building block and Groove or the projection combining and groove mutual Tenon self-locking.
" l " shape wall, is shown in accompanying drawing 22,23, and each level course is formed by level course a and level course b, in the vertical direction, Adjacent level layer a and level course b replaces Tenon self-locking, and self-locking form is with " one " shape wall.
" t " shape wall, is shown in accompanying drawing 24,25, and each level course is formed by level course a and level course b, in the vertical direction, Adjacent level layer a and level course b replaces Tenon self-locking, and self-locking form is with " one " shape wall.
When using having insulation construction, that is, having the building block of gusset 18 structure (see accompanying drawing 16,17), " one " shape wall, " l " Shape wall is identical with the building block assembly form of not sheet with rib 18 structure with the Tenon self-locking of " t " shape wall.Wherein, the level of " one " shape wall Layer a and level course b construction diagrams as shown in accompanying drawing 26-29, the construction diagrams such as accompanying drawing of the level course a and level course b of " l " shape wall 30th, shown in 31, the construction diagrams of the level course a and level course b of " t " shape wall are as shown in accompanying drawing 32,33.
The shear wall of above split structure, has that internal cavities all communicate up and down, level local communicates, outer horizontal leads to Seam, the structure of the upper and lower fissure of displacement.Vertical reinforcement can be placed in the appropriate location of cavity, horizontal reinforcement is laid in reinforced hole 17.Tool There is the shear wall of the concrete block masonry of gusset 18 structure, the upper and lower identical of less vertical direction surrounding in gusset 18 and building block is empty Interior filling insulation material, makes shear wall play the effect of energy-saving heat preserving.Casting concrete is also needed in cavity.
When building shear wall by laying bricks or stones, the vertical reinforcement of the good shear wall of first colligation, the first water will be carried out according to above-mentioned assembly form The assembled self-locking of flat bed, then vertical reinforcement is placed in the cavity of shear wall, places afterwards on the reinforced hole 17 of building block One layer of horizontal reinforcement, horizontal reinforcement and vertical reinforcing bar is carried out node and ties up, then splice the building block of the second level course, colligation again Horizontal reinforcement, repeats to splice level course and colligation horizontal reinforcement, when body of wall is close to beam bottom position, by top layer masonry local After propping up good common templates, placing concrete vibration compacting toward in internal cavities, make the concrete newly pouring and building block form one Individual entirety, cooperation;Vertical and horizontal reinforcement in cavity is wrapped in interior, after concrete setting by the concrete newly pouring It is the formation of shear wall.

Claims (5)

1. a kind of shear wall replacing template to pour with mortise and tenon type precast concrete segment it is characterised in that: described shear wall by Two kinds have the mutually corresponding building block fastening joinery and its construction up and down and are spliced into masonry, and described masonry has on internal cavities All communicate down, level local communicates, outer horizontal straight joint, the structure of the upper and lower fissure of displacement, dispose respectively in the cavity within masonry There is vertical and horizontal reinforcement, and a casting concrete, described building block includes the first building block and second block of edge mutual Tenon self-locking Block;First building block is " Qian " shape, has positioned at middle fagging and two flanks, the top of fagging and bottom are respectively provided with projection And groove, the top of left side flank and bottom be respectively provided with projection and groove, and the top of right side flank and bottom are respectively There is projection and groove;Second building block is " h " shape, has positioned at middle fagging and two fins, perforate in the middle part of fagging, Fagging top both sides have the equidirectional projection with fagging, and flap apex both sides have projection and projection, fin bottom Both sides have groove and groove, and raised, the raised, groove of fin is different with groove location in front and back.
2. the shear wall replacing template to pour with mortise and tenon type precast concrete segment according to claim 1, its feature exists In: between the flank top of described first building block and fagging, there is reinforced hole, the second building block flap apex both sides have placement steel Hole used by muscle.
3. the shear wall replacing template to pour with mortise and tenon type precast concrete segment according to claim 1, its feature exists In: the flank of described first building block has the symmetrical gusset vertical with flank;The fagging both sides tool of described second building block There is the gusset vertical with fagging.
4. the shear wall that template pours of being replaced with mortise and tenon type precast concrete segment one of according to claim 1-3, its It is characterised by: described shear wall is " one " shape wall, " l " shape wall or " t " shape wall.
5. a kind of shear wall replacing template to pour with mortise and tenon type precast concrete segment one of as described in claim 1-3 Construction method it is characterised in that: the vertical reinforcement of first colligation good shear wall during construction, mutual for building block self-locking is spliced into the first water Flat bed, then vertical reinforcement is placed in the cavity of shear wall, afterwards in one layer of level of horizontal level colligation of building block cavity Reinforcing bar, then splices one layer of building block, colligation horizontal reinforcement again, repeats to splice level course and colligation horizontal reinforcement, until body of wall Close to beam bottom position when, after the good common templates of top layer masonry local, integrated poured concrete is carried out to whole shear wall.
CN201410774744.9A 2014-12-16 2014-12-16 Shear wall cast with tenon-and-mortise precast concrete blocks replacing formworks and construction method thereof Active CN104532985B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410774744.9A CN104532985B (en) 2014-12-16 2014-12-16 Shear wall cast with tenon-and-mortise precast concrete blocks replacing formworks and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410774744.9A CN104532985B (en) 2014-12-16 2014-12-16 Shear wall cast with tenon-and-mortise precast concrete blocks replacing formworks and construction method thereof

Publications (2)

Publication Number Publication Date
CN104532985A CN104532985A (en) 2015-04-22
CN104532985B true CN104532985B (en) 2017-02-01

Family

ID=52848592

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410774744.9A Active CN104532985B (en) 2014-12-16 2014-12-16 Shear wall cast with tenon-and-mortise precast concrete blocks replacing formworks and construction method thereof

Country Status (1)

Country Link
CN (1) CN104532985B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105569216B (en) * 2016-02-04 2018-07-27 北京天基新材料股份有限公司 One kind plus cable-styled swollen stone faced wall
CN105569225A (en) * 2016-02-04 2016-05-11 北京天基新材料股份有限公司 Bentonite stone combined wall
CN108487505B (en) * 2018-05-10 2023-12-29 常州工程职业技术学院 Free assembly structure of section steel confined concrete wallboard
CN109306752A (en) * 2018-11-09 2019-02-05 朱新伟 Assembled cross wall
CN109306753A (en) * 2018-11-09 2019-02-05 朱新伟 Assembled L shape wall
CN109306760A (en) * 2018-11-09 2019-02-05 朱新伟 Assembled wall and assembled architecture building block
CN109322436A (en) * 2018-11-09 2019-02-12 朱新伟 Assembled cylinder
CN109306751A (en) * 2018-11-09 2019-02-05 朱新伟 Assembled T shape wall

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204343486U (en) * 2014-12-16 2015-05-20 河南众鼎智拓环保科技有限公司 The shear wall that a kind of mortise and tenon type precast concrete segment replaces template to build

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4075808A (en) * 1974-11-25 1978-02-28 Sanford Pearlman Building construction system using mortar-less modular building block elements
FR2482163A1 (en) * 1980-05-06 1981-11-13 Decamps Claude Hollow structural block for wall of building - is in plan and uses basal cross wall notches keyed to bed joints and interlocked with vertical joints
AUPN033194A0 (en) * 1994-12-30 1995-01-27 Jannock Limited Dry stackable masonry unit and methods of manufacture and use
JP2005139872A (en) * 2003-11-04 2005-06-02 Masaru Iizuka Fitting type concrete block and its construction method
CN102409796B (en) * 2011-08-24 2014-03-05 中国建筑设计研究院 Fabricated blocks, fabricated-block building system and construction method thereof
CN203097069U (en) * 2013-03-15 2013-07-31 株洲博尔曼科技发展有限公司 Double-H shaped Moka block
CN103216024A (en) * 2013-04-30 2013-07-24 株洲博尔曼科技发展有限公司 Self-heat-preservation mortar-free block masonry shear wall system and construction method thereof

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204343486U (en) * 2014-12-16 2015-05-20 河南众鼎智拓环保科技有限公司 The shear wall that a kind of mortise and tenon type precast concrete segment replaces template to build

Also Published As

Publication number Publication date
CN104532985A (en) 2015-04-22

Similar Documents

Publication Publication Date Title
CN104532985B (en) Shear wall cast with tenon-and-mortise precast concrete blocks replacing formworks and construction method thereof
CN106013531B (en) The concrete shear wall structure based on 3D printing with concave convex texture
CN105298020B (en) Semi-precast circular steel pipe regenerated mixed concrete pillar and preparation method thereof
CN110777983A (en) Synchronous construction structure and method for concrete filled wall and cast-in-place structure
CN103161241A (en) Filling-hole non-mortar reinforcement building block brickwork shear wall and construction method thereof
CN106113230B (en) The non-type prefabricated for bench, template system and its construction method can be had enough to meet the need
CN207402953U (en) For pouring sectional die, vertical die component and the prefabricated overlapping wall body structure of prefabricated overlapping wall
CN111335355A (en) Special-shaped block post-pouring type light retaining wall supporting structure and construction method thereof
CN107514083A (en) Side hangs reinforcing bar band shear key reinforced concrete slab structure and connection method
CN110344844A (en) A kind of track engineering section of track well construction method
CN106337530B (en) A kind of construction of frame beam seams stifled construction method
CN204343486U (en) The shear wall that a kind of mortise and tenon type precast concrete segment replaces template to build
CN203296208U (en) Pouring hole non-mortar reinforcing bar building block brickwork shear wall
CN207419752U (en) One kind can the anti-bank of assembled precast concrete
CN108343234B (en) Modification module capable of being used as cast-in-situ ring beam template of hollow block masonry and application thereof
CN106401276A (en) Construction method for wall column binding bars of frame type building block enclosing wall
CN113618872B (en) Building construction equipment and construction method based on BIM modeling
CN206928647U (en) The precast lintel formwork erecting structure that a kind of live wire pipe passes through
CN212427769U (en) Interlocking building block for mould-disassembly-free constructional column
CN209277362U (en) Prefabricated superimposed sheet concrete segment
CN211774796U (en) Cross wall connection department constructional column exempts from formwork structure
CN211774799U (en) Formwork-supporting-free structure for constructional column at joint of T-shaped wall
CN212336084U (en) Special-shaped block post-pouring type light retaining wall supporting structure
CN211548336U (en) Concrete hollow block product group special for assembled reinforced block masonry wall structure
CN209669686U (en) A kind of box beam head assembled plugging structure

Legal Events

Date Code Title Description
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant