CN104504470B - A kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling - Google Patents

A kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling Download PDF

Info

Publication number
CN104504470B
CN104504470B CN201410801067.5A CN201410801067A CN104504470B CN 104504470 B CN104504470 B CN 104504470B CN 201410801067 A CN201410801067 A CN 201410801067A CN 104504470 B CN104504470 B CN 104504470B
Authority
CN
China
Prior art keywords
engineering
sampling
transmitting
project
link
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410801067.5A
Other languages
Chinese (zh)
Other versions
CN104504470A (en
Inventor
刘辉
胡晓飞
汤伟
刘路登
杨铖
胡世骏
孙向东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Anhui Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Anhui Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410801067.5A priority Critical patent/CN104504470B/en
Publication of CN104504470A publication Critical patent/CN104504470A/en
Application granted granted Critical
Publication of CN104504470B publication Critical patent/CN104504470B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • G06Q10/047Optimisation of routes or paths, e.g. travelling salesman problem
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Game Theory and Decision Science (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Development Economics (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling, and this method includes:Build history project of transmitting and converting electricity operation time series database;The duration of statistical history project of transmitting and converting electricity key link;Filter out the similar engineering collection for treating operation engineering;Using probability sampling to similar engineering collection multiple sampling;Single-candidate processing is carried out to data from the sample survey;Remove the optimal most bad engineering in sampling set;Remove optimal most bad sampling set;It is expected that treat the operation sequential of operation engineering.The present invention compared with prior art, solves the problems, such as that power system operating mode caused by being delayed in power system due to project of transmitting and converting electricity is arranged work repetition modeling and repeatedly analysis, effectively reduces the workload of operation of power networks researcher.

Description

A kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling
Technical field
The present invention relates to electric power network technique field, specifically a kind of project of transmitting and converting electricity operation timing optimization based on probability sampling Method for predicting.
Background technology
Project of transmitting and converting electricity is to build the indispensable important step of electric power networks.To meet economy development requirement, electric power is built It is annual proposed, yet to be built, more and more in the project under construction built and gone into operation if being always ahead of local economic development speed, in order to true Protect each Transmission Projects to go into operation as scheduled, State Grid Corporation of China has formulated detailed management method and taken strong Measure, but in actual implementation process, due to communication and coordination are inadequate, construction environment is complicated, administrative mechanism imperfection, early-stage preparations The various internal and external factors such as deficiency are present, and the comparison that Transmission Projects are often delayed is more.
Modern society's life is high to the degree of dependence of electric power, and power demand increases year by year, once power outage, which occurs, to be given People's each side life make troubles, and caused by social influence it is big.To ensure power network safety operation and reliable power supply, pin Extension to Transmission Projects each time is gone into operation, and operation of power networks will rearrange power system operating mode with administrative department, To solve the problems, such as dispatching of power netwoks supply and demand.Project of transmitting and converting electricity frequently delays to force power system operating mode frequently to change, and each power network Method of operation adjustment work is often relatively more urgent, allows power system operating mode analysis work can't bear the heavy load.Therefore, it is a set of to need structure badly The estimated system of the project of transmitting and converting electricity operation sequential of science, optimizes the links in the project implementation, in order to be filled from multiple angles Point consider power transmission and transforming equipment production time nargin, customized for each Transmission Projects duration and reference frame is provided, allow electricity Network operation is studied and method of operation arrangement has rule to follow, and more set method of operation peaces are once constructed for each project of transmitting and converting electricity Row's scheme, extension is avoided to cause power network to repeat modeling and repeatedly analysis.
The content of the invention
It is an object of the invention to provide a kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling, With solve in power system due to project of transmitting and converting electricity delay caused by power system operating mode arrange work repetition modeling and repeatedly point The defects of analysis.
The technical scheme is that:
A kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling, this method comprise the following steps:
(1)Build history project of transmitting and converting electricity operation time series database;
(2)According to engineering construction time-scale and production time, each history electricity transmitting and converting construction stage each ring is counted The duration of section, the power transmission engineering construction period be divided into basis, group tower, three links of stringing, the power transformation engineering construction period be divided into civil engineering, Three installation, debugging links;
(3)Based on the essential information for treating operation engineering, including engineering type, voltage class, construction scale, administrative division, The similar engineering collection for treating operation engineering is filtered out from database;
(4)Multiple sampling is carried out to similar engineering collection using probability sampling, multiple sampling set is obtained, extracts each The duration of each link of each history engineering construction period in sampling set;
(5)Based on the construction scale for treating operation engineering, respectively to each history engineering construction period in each sampling set The duration of each link carries out single-candidate processing;
(6)By in the sampling set belonging to history engineering from its corresponding to each link single-candidate duration maximum and minimum value Filter out, then for the remaining history engineering in the sampling set, obtain the weighted average of each link single-candidate duration respectively, Sampling results as the sampling set;
(7)Total lever factor according to each sampling results is distributed, by sampling results corresponding to total lever factor maximum and minimum value Filter out, then for remaining sampling results, obtain the weighted average of each link duration respectively, as treating operation engineering construction The predicted value of each link duration in stage, with reference to the on-stream time for treating operation engineering, that is, obtain treating the operation sequential of operation engineering.
The present invention compared with prior art, solves operation of power networks caused by delaying in power system due to project of transmitting and converting electricity Mode is arranged work repetition modeling and multiple the problem of analyzing, and effectively reduces the workload of operation of power networks researcher.
Brief description of the drawings
Fig. 1 is flow chart of the method for the present invention.
Embodiment
Below in conjunction with the accompanying drawings the present invention is further illustrated with specific embodiment.
As shown in figure 1, a kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling, including following step Suddenly:
S1, structure history project of transmitting and converting electricity operation time series database:
The operation timing information of last decade power transmission engineering and power transformation engineering is extracted from filed electronic document, mainly Including engineering type, voltage class, construction scale, project's earlier stage time-scale, engineering time-scale early stage, engineering construction time-scale, Production time etc..
S2, statistical history project of transmitting and converting electricity key link duration:
Project of transmitting and converting electricity progress includes project's earlier stage, engineering early stage, engineering construction three phases, and wherein project of transmitting and converting electricity is thrown Production sequential is estimated to be mainly expected to Construction Phase.Construction Phase represents project and gone into operation, its operation flow Duration is counted respectively by transmission of electricity, power transformation, and the power transmission engineering construction period is divided into three basis, group tower, stringing links, and power transformation engineering is built If the stage is then divided into three civil engineering, installation, debugging links.The duration of each link is by next link time started and this link Time started difference is tried to achieve, and the duration of last link is tried to achieve by production time and this link time started difference.Before project Phase and engineering are project of transmitting and converting electricity design and early-stage preparations stage early stages, main to complete feasibility study evaluation, system of project approval, construction bid Deng work, the non-key analyze data in operation sequential expectancy analysis, not count.
S3, the similar engineering collection for treating operation engineering is filtered out, and similar engineering collection is carried out repeatedly using probability sampling Sampling:
According to the design for treating operation engineering, pass through project of transmitting and converting electricity type(Transmission of electricity/power transformation), voltage class, construction The information such as scale, administrative division filter out the similar engineering collection for treating operation engineering from database, wherein, using construction scale as bar Part is screened, power transmission engineering Primary Reference line length and bar number, power transformation engineering Primary Reference power transformation capacity and transformer platform Number;Using administrative division as screening conditions, history engineering similar in project of transmitting and converting electricity Primary Reference territorial scope.
After similar engineering collection screens, multiple sampling samples sizes are set, multiple sampling is carried out to similar engineering collection, Multiple sampling set are obtained, extract the duration of each link of each history engineering construction period in each sampling set.
S4, treat that the operation timing optimization of operation engineering is estimated:
Based on the construction scale for treating operation engineering, to each link of each history engineering construction period in each sampling set Duration carry out single-candidate processing, reduce or be extended to and treat operation project scale, exemplified by treating operation power transmission engineering, if its build line Road total length is LTreat, the construction total line length of some history power transmission engineering is Li in sampling setSampling, then single-candidate processing ratio For LTreat/LiSampling;If the duration of the history power transmission engineering construction period basic link is TiBasis, group tower link duration be TiGroup tower、 The duration of stringing link is TiStringing, then the duration of each link is respectively after single-candidate processing:(LTreat/LiSampling)*TiBasis、(LTreat/LiSampling)* TiGroup tower、(LTreat/LiSampling)*TiStringing.For treating operation power transformation engineering, carry out similar single-candidate according to main transformer number of units and handle.
Each sampling set after single-candidate processing is filtered:First, all history engineerings in gathering for sampling, point The other single-candidate duration to each link carries out lateral comparison, i.e. the single-candidate duration according to each link is distributed, and will include each ring The history engineering for saving single-candidate duration optimal, most bad situation filters out from sampling set, then to remaining history engineering, then divides The weighted average of each link single-candidate duration, the sampling results as the sampling set are not obtained.
Exemplified by treating operation power transmission engineering, if the sample size of some sampling set is 16, i.e., shared in the sampling set 16 history engineerings, then to this 16 history engineerings, it is respectively compared its basic link, group tower link, the single-candidate work of stringing link Phase, find out respectively these three link single-candidate durations it is optimal, it is most bad in the case of corresponding history engineering, by these history engineerings from this Remove in sampling set, if sharing 5, then to remaining 11 history engineerings, obtain the single-candidate work of its basic link respectively Phase weighted average, single-candidate duration weighted average, the single-candidate duration weighted average of stringing link for organizing tower link, are used as this The sampling results of sampling set.
To obtained multiple sampling resultses, it is distributed according to total lever factor, equally filters out that those total lever factors are optimal, most bad take out Sample result, weighted average is asked respectively according to each link to remaining sampling results, and then draw and treat operation Construction Phase The predicted value of each link duration.Finally, then according to on-stream time it is the most reasonable operation sequential that can obtain treating operation engineering.
The present invention relies on history project of transmitting and converting electricity operation timing sequence library, can estimate out and treat the optimal throwing of operation project of transmitting and converting electricity Sequential is produced, by the multiple probability sampling of different samples, improves the accuracy estimated to the full extent in a manner of average weighted, Treat that operation project of transmitting and converting electricity schedule provides foundation for each, allow operation of power networks research and power system operating mode arrangement personnel The operation sequential of operation project of transmitting and converting electricity, which accomplishes there are rule to follow, to be treated to each, considers from the whole network angle, makes in advance More set power system operating modes arrange scheme, avoid extension from causing power network to repeat modeling and repeatedly analysis.
Embodiment described above is only that the preferred embodiment of the present invention is described, not to the model of the present invention Enclose and be defined, on the premise of design spirit of the present invention is not departed from, technical side of the those of ordinary skill in the art to the present invention The various modifications and improvement that case is made, it all should fall into the protection domain of claims of the present invention determination.

Claims (1)

1. a kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling, it is characterised in that this method includes Following steps:
(1) history project of transmitting and converting electricity operation time series database is built;
(2) according to engineering construction time-scale and production time, each history electricity transmitting and converting construction stage each link is counted Duration, power transmission engineering construction period are divided into three basis, group tower, stringing links, and the power transformation engineering construction period is divided into civil engineering, peace Three dress, debugging links;
(3) based on the essential information for treating operation engineering, including engineering type, voltage class, construction scale, administrative division, from number The similar engineering collection for treating operation engineering according to being filtered out in storehouse;
(4) multiple sampling is carried out to similar engineering collection using probability sampling, obtains multiple sampling set, extract each sampling The duration of each link of each history engineering construction period in set;
(5) it is each to each history engineering construction period in each sampling set respectively based on the construction scale for treating operation engineering The duration of link carries out single-candidate processing;
The ratio of the single-candidate processing is LTreat/LiSampling, wherein LTreatTo treat the construction total line length of operation engineering, LiSamplingFor sampling The construction total line length of some history engineering in set;
(6) will be filtered in the sampling set belonging to history engineering from its corresponding to each link single-candidate duration maximum and minimum value Fall, then for the remaining history engineering in the sampling set, obtain the weighted average of each link single-candidate duration respectively, as The sampling results of the sampling set;
(7) total lever factor according to each sampling results is distributed, and sampling results corresponding to total lever factor maximum and minimum value is filtered Fall, then for remaining sampling results, obtain the weighted average of each link duration respectively, as treating operation Construction Phase The predicted value of each link duration, with reference to the on-stream time for treating operation engineering, that is, obtain treating the operation sequential of operation engineering.
CN201410801067.5A 2014-12-22 2014-12-22 A kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling Expired - Fee Related CN104504470B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410801067.5A CN104504470B (en) 2014-12-22 2014-12-22 A kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410801067.5A CN104504470B (en) 2014-12-22 2014-12-22 A kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling

Publications (2)

Publication Number Publication Date
CN104504470A CN104504470A (en) 2015-04-08
CN104504470B true CN104504470B (en) 2017-12-01

Family

ID=52945865

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410801067.5A Expired - Fee Related CN104504470B (en) 2014-12-22 2014-12-22 A kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling

Country Status (1)

Country Link
CN (1) CN104504470B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103632200A (en) * 2013-12-05 2014-03-12 国家电网公司 Method for building engineering construction progress early-warning model on basis of time probabilities
CN103714411A (en) * 2012-10-08 2014-04-09 魏赐聪 Project management system
CN103761614A (en) * 2014-01-20 2014-04-30 北京仿真中心 Project progress management method based on critical chain

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103714411A (en) * 2012-10-08 2014-04-09 魏赐聪 Project management system
CN103632200A (en) * 2013-12-05 2014-03-12 国家电网公司 Method for building engineering construction progress early-warning model on basis of time probabilities
CN103761614A (en) * 2014-01-20 2014-04-30 北京仿真中心 Project progress management method based on critical chain

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
乌审召220KV输变电工程项目进度管理;康宁;《中国优秀硕士学位论文全文数据库》;20131215(第S2期);正文第9,21-23页 *
关于施工企业内部施工定额编制办法的探讨;陈大山 等;《企业导报》;20121231(第24期);第74页 *

Also Published As

Publication number Publication date
CN104504470A (en) 2015-04-08

Similar Documents

Publication Publication Date Title
AU2022204116B2 (en) Verification method for electrical grid measurement data
CN103530347B (en) A kind of Internet resources method for evaluating quality based on big data mining and system
CN104616205A (en) Distributed log analysis based operation state monitoring method of power system
CN102955977A (en) Energy efficiency service method and energy efficiency service platform adopting same on basis of cloud technology
CN102722764A (en) Integrated power grid optimization auxiliary decision analysis system
CN103198139B (en) The energy analysis method of custom power data
CN103440556A (en) Electricity consumption prediction method based on economic conduction
CN108920609A (en) Electric power experimental data method for digging based on multi dimensional analysis
CN105956781A (en) Power grid equipment life cycle cost calculation method
Popovic et al. Smart grid data analytics for digital protective relay event recordings
CN105958652A (en) Unattended operation transformer substation pre-warning system and method based on big data analysis
CN103258255B (en) A kind of Methods of Knowledge Discovering Based being applicable to grid management systems
CN104504470B (en) A kind of project of transmitting and converting electricity operation timing optimization method for predicting based on probability sampling
CN112232985B (en) Power distribution and utilization data monitoring method and device for ubiquitous power Internet of things
Qin et al. Modeling and optimizing the delay propagation in Chinese aviation networks
CN104867061A (en) State repair management system for relay protection device
CN102592004A (en) System and method for on-line analysis and diagnosis of whole-process energy-consuming conditions of integrated iron and steel works
CN112052985A (en) Lightgbm-based medium-short term low voltage prediction method
CN104133912A (en) Method for managing open government datasets
Xue et al. An efficient and robust case sorting algorithm for transient stability assessment
CN112785109A (en) Power grid equipment fault analysis method and system based on regulation cloud
CN103729682B (en) A kind of three-phase imbalance method of discrimination
CN111078779A (en) Big data center operation monitoring system
CN104036433A (en) Method for evaluating running management level of power distribution network
Sokol et al. The structural and parametrical organization of elements of a power supply system in the conditions of network centrism

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171201

Termination date: 20211222

CF01 Termination of patent right due to non-payment of annual fee