CN104466953A - Power grid cascading failure restraining method - Google Patents
Power grid cascading failure restraining method Download PDFInfo
- Publication number
- CN104466953A CN104466953A CN201410747329.4A CN201410747329A CN104466953A CN 104466953 A CN104466953 A CN 104466953A CN 201410747329 A CN201410747329 A CN 201410747329A CN 104466953 A CN104466953 A CN 104466953A
- Authority
- CN
- China
- Prior art keywords
- node
- current
- branch
- network
- matrix
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The invention discloses a power grid cascading failure restraining method and belongs to the technical field of safety protection of power systems. According to the method, a node which has largest impact on an overload branch circuit is worked out, the generator tripping and load shedding amount range is determined and optimized many times, generator tripping and load shedding operations are carried out on a power grid network according to the generator tripping and load shedding amount optimized every time, and whether the current value of the overload branch circuit at the next time is within the safety range or not is detected. The method can continuously and cyclically carry out generator tripping and load shedding amount optimization and load shedding operation until the current value of the overload branch circuit reaches the safety range or the number of times of optimization of the generator tripping and load shedding amount exceeds the maximum number. The method can optimize the generator tripping and load shedding amount when the branch circuit is overloaded, reduce loss and effectively restrain cascading failure at the same time.
Description
Technical field
The invention belongs to power system security guard technology field, be specifically related to a kind of suppressing method of power grid cascading fault.
Background technology
Bulk power grid faces many disturbances and risk in running, and wherein, cascading failure is one of catastrophe failure threatening bulk power grid safe and stable operation.A lot of large area blackouts that Abroad in Recent Years occurs are all relevant with cascading failure.So-called cascading failure refers to a certain element fault in electric power system, and then causes other elements to be stopped transport, and this chain reaction rapid spread, finally causes large-scale power outage.Large-scale blackout often cause in electric power system heavy service and break down when faulty line excise the transfer causing trend in electrical network, power flow transfer is by the load of other transmission lines in further heavy system and cause the generation of cascading trip situation.How effectively to prevent the cascading trip event that in electrical network, circuit causes because power flow transfer causes overload, be prevent the important ring occurred of having a power failure on a large scale.
Summary of the invention
For the deficiency that prior art exists, the invention provides a kind of suppressing method of power grid cascading fault.
Technical scheme of the present invention:
A suppressing method for power grid cascading fault, is characterized in that: comprise the steps:
Step 1: determine the topological structure of electricity grid network and statistics network node total number b and branch of a network sum s, the branch of a network determining the branch of a network cut because of fault, power flow transfer occurs;
Step 2: set up the node importance contribute matrix of branch of a network electric current and calculate this matrix;
Generator in this electricity grid network, load are all represented as node Injection Current, then the node importance contribute matrix of branch of a network electric current is:
In formula, R (γ)=YA
tb
-1for b*s rank matrix, Y is the branch admittance matrix of network, and A is the node incidence matrices of network, and B is the node admittance matrix of network; w
jfor the weight coefficient of node, j=1,2 ..., s, c
jfor the cost coefficient of node; Matrix I
m(λ) what represent is the relation importance degree of branch current and node Injection Current, i.e. the significance level that affects branch current of node Injection Current, matrix I
m(λ) the first row element λ in
1j, row k element λ
kj, b row element λ
bjrepresent respectively be node 1 to node s Injection Current respectively on the significance level of Article 1 branch current impact, on the significance level of kth article branch current impact, the significance level on b article of branch current impact;
Step 3: the node provided according to the result of calculation of the node importance contribute matrix of branch of a network electric current in step 2 is on the significance level of branch current impact that power flow transfer occurs, determine to need to carry out the node of machine of cutting and the node of cutting load, and the node number of cutting machine is equal with the node number of cutting load;
Suppose that the branch road that power flow transfer occurs is kth bar branch road, then by matrix I
m(λ) row k element λ in
kjafter sorting according to numerical values recited: choose a corresponding node f from small to large
i(i=1 ..., n), i.e. load bus, as load bus to be cut; Meanwhile, the node g with load bus same number to be cut is chosen from big to small
i(i=1 ..., n), i.e. generator node, as machine node to be cut; The value n of described n need determine in conjunction with working experience according to on-site actual situations;
Step 4: determine initial unit shut algorithm amount;
Should be equal with cutting load amount in electricity grid network middle filling machine amount, and meet following formula:
In formula,
Δ I
kfor the effective value of current change quantity on kth bar branch road, I
kfor the current effective value of kth bar branch road; I
ksetfor the minimum current value corresponding to the protection startup of kth bar branch road, S (S < 1) ensures that the safety factor of cascading trip does not occur branch road;
for row k l in R (γ) matrix
irow, represent electric current and the load bus l of kth bar branch road
iinjection Current between numerical relation;
for row k g in R (γ) matrix
irow, represent electric current and the generator node g of kth bar branch road
iinjection Current between numerical relation;
with
represent load bus l respectively
iload power factor angle and generator node g
igenerator power factor angle;
with
represent load bus l
iwith generator node g
ithe conjugation of voltage vector;
be respectively load bus l
i, generator node g
iresection; All told
for load bus l
iall told,
for generator node g
iall told.
Step 5: the initial unit shut algorithm amount that step 4 obtains is optimized, obtains the optimal value of unit shut algorithm amount;
s.t.
I(t+1)=f(I(t),ΔP
1(t),...,ΔP
n(t))
ΔP
i(t+1)∈[0,ΔP
imax](i=1,...,n)
In formula, J is optimization object function, and I (t) and I (t+1) are respectively kth bar branch road at the current value of t and the current value in t+1 moment after carrying out unit shut algorithm; L (I, Δ P
i) represent and the predeterminated target of unit shut algorithm amount optimal control be generally taken as normal form:
wherein, R and Q is the symmetrical weighting matrix of positive definite; F represents the functional relation of controlled quentity controlled variable and input variable; Δ P
i(t+1) what represent is t+1 moment unit shut algorithm amount; Δ P
imaxrepresent maximum permission resection; F (I) is terminal penalty function, and represent the state of moment t and the deviation of set point, general type is F (I)=I
tpI, wherein, P is terminal weighting matrix.
Step 6: the electricity grid network of unit shut algorithm amount optimal value to current time obtained according to step 5 cuts machine and cutting load;
Step 7: detect the current value of the branch of a network of subsequent time generation power flow transfer and record this current value, judging whether its electric current enters in safe range, no, then go to step 8, be, then go to step 10;
Step 8: judge that unit shut algorithm amount optimizes the number of times whether number of times reaches setting in advance, no, then go to step 2, be, then go to step 9;
Step 9: the current value exporting the branch of a network that power flow transfer occurs;
Step 10: terminate.
Beneficial effect: method of the present invention is: calculate the maximum node of overload branches affect, determine that unit shut algorithm weight range is repeatedly optimized it, according to the unit shut algorithm amount after optimizing each time, machine of cutting and cutting load operation are implemented to electricity grid network, and whether the current value detecting subsequent time overload branch road is in safe range, continuous circulation carries out the optimization of unit shut algorithm amount and implements cutting load operation in this approach, until the current value of overload branch road reaches safe range or unit shut algorithm amount optimization number of times exceedes maximum times stopping.Method of the present invention can optimize unit shut algorithm amount when branch road transships, and reduces loss, effectively suppresses the generation of cascading failure simultaneously.
Accompanying drawing explanation
Fig. 1 is the IEEE30 node electricity grid network structural representation of one embodiment of the present invention;
Fig. 2 is the suppressing method flow chart of the power grid cascading fault of one embodiment of the present invention;
Fig. 3 is the curent change figure of overload branch road when not carrying out unit shut algorithm in the IEEE30 node electricity grid network of one embodiment of the present invention;
Fig. 4 transships the curent change figure of branch road after the IEEE30 node electricity grid network middle filling machine cutting load of one embodiment of the present invention.
Embodiment
Below in conjunction with accompanying drawing, one embodiment of the present invention are described in further detail.
The method suppressing power grid cascading fault is implemented to the IEEE30 node electricity grid network shown in Fig. 1, as shown in Figure 2, comprises the steps:
Step 1: count this electricity grid network and comprise 30 nodes and 35 branch roads, in the network branch road l from the topological structure of the IEEE30 electricity grid network shown in Fig. 1
6cut, make branch road l
11power flow transfer occurs causes protection to start; From the l of branch road shown in Fig. 3
11curent change curve in can find out, at branch road l
6after cut, branch road l
11electric current raise rapidly, in the 30th cycle, there is peak in electric current, and in 62 cycles, minimum appears in electric current, the overload branch road l of period
11current average be 1583.7A, seriously exceed branch road l
11the permission current value 1112.23A of safe operation;
Step 2: set up the node importance contribute matrix of branch of a network electric current and calculate this matrix;
Generator in this electricity grid network, load are all represented as node Injection Current, then the node importance contribute matrix of branch of a network electric current is:
In formula, R (γ)=YA
tb
-1for 35*30 rank matrix, Y is the branch admittance matrix of network, and A is the node incidence matrices of network, and B is the node admittance matrix of network; w
jfor the weight coefficient of node, j=1,2 ..., s, c
jfor the cost coefficient of node; Matrix I
m(λ) what represent is the relation importance degree of branch current and node Injection Current, i.e. the significance level that affects branch current of node Injection Current, matrix I
m(λ) the first row element λ in
1, j, the 11st row element λ
11, j, the 35th row element λ
35, jwhat represent respectively is that the Injection Current of node 1 to node s is respectively to Article 1 branch road (l
1) electric current impact significance level, to Sub_clause 11 branch road (l
11) electric current impact significance level, to the 35th article of branch road (l
35) electric current impact significance level;
By the node importance contribute matrix I of computing network branch current
m(λ) the Sub_clause 11 branch road (l to there is power flow transfer can be selected
11) the large and node that cost is relatively little of electric current impact.The I of table 1 for calculating
m(λ) the importance degree coefficient lambda of part of nodes in the 11st row in
11, i.
In table 1 electricity grid network, part of nodes is to Sub_clause 11 branch road (l
11) importance degree coefficient
λ 11,1 | 0.0583+0.0037i | λ 11,7 | -0.4371-0.0032i | λ 11,13 | 0.0474-0.0021i |
λ 11,2 | 0.8931-0.0017i | λ 11,8 | 0.3744+0.0073i | λ 11,14 | -0.0083-0.0001i |
λ 11,3 | -0.0351-0.0008i | λ 11,10 | -0.0756-0.0024i | λ 11,15 | -0.0175-0.0003i |
λ 11,4 | -0.3142-0.0016i | λ 11,11 | 0.0512-0.0032i | λ 11,16 | -0.0051-0.0001i |
λ 11,5 | 0.0971+0.0006i | λ 11,12 | -0.2640-0.0017i | λ 11,17 | -0.0316-0.0016i |
Step 3: determine to need to carry out the node of machine of cutting and the node of cutting load;
I can be found out from the result of calculation of step 2
m(λ) real part is much larger than imaginary part, and the Injection Current of generator is just, so the Injection Current of load is then negative, therefore by λ
11, ireal part by after ascending sequence, ascendingly choose 3 elements, i.e. λ
11,7, λ
11,4, λ
11,12corresponding node 7,4,12 is as load bus to be cut; Next descendingly again 3 elements, i.e. λ are chosen
11,2, λ
11,8, λ
11,5corresponding node 2,8,5 is as machine node to be cut.Namely these the 3 pairs of nodes selected are to branch road l
11the relatively large and node that cost is relatively little of electric current impact, unit shut algorithm operation will be carried out to these 3 pairs of nodes.
Step 4: determine unit shut algorithm weight range;
Should be equal with cutting load amount in electricity grid network middle filling machine amount, and meet following formula:
In formula,
safety factor S=0.85 is got, I in present embodiment
11, set=1308.5A, Δ I
11for Sub_clause 11 branch road (l
11) effective value of upper current change quantity, I
11for Sub_clause 11 branch road (l
11) current effective value; I
11, setfor Sub_clause 11 branch road (l
11) protection start corresponding to minimum current value, S (S < 1) be that the safety factor of cascading trip does not occur guarantee branch road;
for the 11st row l in R (γ) matrix
irow, represent Sub_clause 11 branch road (l
11) electric current and load bus l
iinjection Current between numerical relation;
for row k g in R (γ) matrix
irow, represent Sub_clause 11 branch road (l
11) electric current and generator node g
iinjection Current between numerical relation;
with
represent load bus l respectively
iload power factor angle and generator node g
igenerator power factor angle;
with
represent load bus l
iwith generator node g
ithe conjugation of voltage vector;
,
be respectively load bus l
i, generator node g
iresection; All told
for load bus l
iall told,
for generator node g
iall told.
Step 5: the unit shut algorithm weight range obtained from step 4 is optimized, and obtains the optimal value of unit shut algorithm amount.As shown in table 2, the unit shut algorithm amount after first time optimization is Δ P
1=18.53MW, Δ P
2=7.32MW, Δ P
3=7.11MW; The optimization object function shown in formula (2) is adopted to be optimized the unit shut algorithm weight range that step 4 obtains;
s.t.
I(t+1)=f(I(t),ΔP
1(t),...,ΔP
n(t))
ΔP
i(t+1)∈[0,ΔP
imax](i=1,...,n)
In formula, J is optimization object function, and I (t) and I (t+1) are respectively kth bar branch road at the current value of t and the current value in t+1 moment after carrying out unit shut algorithm; L (I, Δ P
i) represent and the predeterminated target of unit shut algorithm amount optimal control be generally taken as normal form:
wherein, R and Q is the symmetrical weighting matrix of positive definite; F represents the functional relation of controlled quentity controlled variable and input variable; Δ P
i(t+1) what represent is t+1 moment unit shut algorithm amount; Δ P
imaxrepresent maximum permission resection; F (I) is terminal penalty function, and represent the state of moment t and the deviation of set point, general type is F (I)=I
tpI, wherein, P is terminal weighting matrix.
Step 6: the unit shut algorithm amount optimal value obtained according to step 5 is implemented to cut machine and cutting load to the electricity grid network of current time;
Step 7: the Sub_clause 11 branch road l detecting subsequent time generation power flow transfer
11current value, judge whether its electric current enters in safe range, Sub_clause 11 branch road l
11the permissible value of safe operation electric current be S*I
11, set=1112.23A, no, then go to step 8, be, then go to step 10; As shown in table 2, after having implemented first time unit shut algorithm, branch road l
11current value be 1295.5A, branch road l
11electric current do not enter safe range;
Step 8: judge that unit shut algorithm amount optimizes the number of times whether number of times reaches setting in advance, no, then go to step 2, be, then go to step 9, optimizing number of times to the unit shut algorithm amount of IEEE30 electricity grid network setting in present embodiment is 5 times, after present embodiment has carried out 3 unit shut algorithm amounts optimization to IEEE30 electricity grid network, as can be seen from Figure 4, in the 50th cycle, carry out first time unit shut algorithm after-current value decline rapidly, carrying out second, after three unit shut algorithms, branch road 11 current value is 1083.5A, enter in the scope of safe operation electric current, second, three unit shut algorithms, as shown in table 2, the machine node of cutting is node 8, 1, cutting load node is node 4, 7, second, three times unit shut algorithm amount optimal value is respectively Δ P
1=3.67MW, Δ P
2=3.48MW and Δ P
1=1.58MW, Δ P
2=0.83MW, tributary l after second time unit shut algorithm
11current value be 1158.8A.
Step 9: output overloading branch road l
11current value;
Table 2 IEEE30 electricity grid network unit shut algorithm Information Statistics table
Step 10: terminate.
In present embodiment, IEEE30 electricity grid network is after experienced by three unit shut algorithm amount Optimization Steps, and each unit shut algorithm amount reduces gradually, and the electric current of final overload branch road 11 enters in safe scope, inhibits the generation of cascading failure.
Claims (2)
1. a suppressing method for power grid cascading fault, is characterized in that: comprise the steps:
Step 1: determine the topological structure of electricity grid network and statistics network node total number b and branch of a network sum s, the branch of a network determining the branch of a network cut because of fault, power flow transfer occurs;
Step 2: set up the node importance contribute matrix of branch of a network electric current and calculate this matrix;
Generator in this electricity grid network, load are all represented as node Injection Current, then the node importance contribute matrix of branch of a network electric current is:
In formula, R (γ)=YA
tb
-1for b*s rank matrix, Y is the branch admittance matrix of network, and A is the node incidence matrices of network, and B is the node admittance matrix of network; w
jfor the weight coefficient of node, j=1,2 ..., s, c
jfor the cost coefficient of node; Matrix I
m(λ) what represent is the relation importance degree of branch current and node Injection Current, i.e. the significance level that affects branch current of node Injection Current, matrix I
m(λ) the first row element λ in
1j, row k element λ
kj, b row element λ
bjrepresent respectively be node 1 to node s Injection Current respectively on the significance level of Article 1 branch current impact, on the significance level of kth article branch current impact, the significance level on b article of branch current impact;
Step 3: the node provided according to the result of calculation of the node importance contribute matrix of branch of a network electric current in step 2, on the significance level of branch current impact that power flow transfer occurs, is determined to need to carry out the node of machine of cutting and the node of cutting load;
Suppose that the branch road that power flow transfer occurs is kth bar branch road, then by matrix I
m(λ) row k element λ in
kjafter sorting according to numerical values recited: choose n corresponding node l from small to large
i(i=1 ..., n), i.e. load bus, as load bus to be cut; Meanwhile, the node g with load bus same number to be cut is chosen from big to small
i(i=1 ..., n), i.e. generator node, as machine node to be cut;
Step 4: determine unit shut algorithm weight range;
Should be equal with cutting load amount in electricity grid network middle filling machine amount, and meet following formula:
In formula,
Δ I
kfor the effective value of current change quantity on kth bar branch road, I
kfor the current effective value of kth bar branch road; I
ksetfor the minimum current value corresponding to the protection startup of kth bar branch road, S (S < 1) ensures that the safety factor of cascading trip does not occur branch road;
for row k l in R (γ) matrix
irow, represent electric current and the load bus l of kth bar branch road
iinjection Current between numerical relation;
for row k g in R (γ) matrix
irow, represent electric current and the generator node g of kth bar branch road
iinjection Current between numerical relation;
with
represent load bus l respectively
iload power factor angle and generator node g
igenerator power factor angle;
with
represent load bus l
iwith generator node g
ithe conjugation of voltage vector;
be respectively load bus l
i, generator node g
iresection; All told
for load bus l
iall told,
for generator node g
iall told;
Step 5: the unit shut algorithm weight range that step 4 obtains is optimized, obtains the optimal value of unit shut algorithm amount;
Formula (2) optimization object function is adopted to be optimized the unit shut algorithm weight range that step 4 obtains;
s.t.
I(t+1)=f(I(t),ΔP
1(t),...,ΔP
n(t))
ΔP
i(t+1)∈[0,ΔP
imax](i=1,...,n)
In formula, J is optimization object function, and I (t) and I (t+1) are respectively kth bar branch road at the current value of t and the current value in t+1 moment after carrying out unit shut algorithm; L (I, Δ P
i) represent and the predeterminated target of unit shut algorithm amount optimal control be generally taken as normal form: L (I, Δ P
i)=I
tqI+ Δ P
i tr Δ P
i, wherein, R and Q is the symmetrical weighting matrix of positive definite; F represents the functional relation of controlled quentity controlled variable and input variable; Δ P
i(t+1) what represent is t+1 moment unit shut algorithm amount; Δ P
imaxrepresent maximum permission resection; F (I) is terminal penalty function, and represent the state of moment t and the deviation of set point, general type is F (I)=I
tpI, wherein, P is terminal weighting matrix;
Step 6: the unit shut algorithm amount optimal value obtained according to step 5 is implemented to cut machine and cutting load to the electricity grid network of current time;
Step 7: detect the current value of the branch of a network of subsequent time generation power flow transfer and record this current value, and judging whether its electric current enters in safe range, no, then go to step 8, be, then go to step 10;
Step 8: judge that unit shut algorithm amount optimizes the number of times whether number of times reaches setting in advance, no, then go to step 2, be, then go to step 9;
Step 9: the current value exporting the branch of a network that power flow transfer occurs;
Step 10: terminate.
2. the suppressing method of power grid cascading fault according to claim 1, is characterized in that: when determining unit shut algorithm weight range in described step 4, and the load of excising in network is equal with cutting machine amount need.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410747329.4A CN104466953B (en) | 2014-12-09 | 2014-12-09 | Power grid cascading failure restraining method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410747329.4A CN104466953B (en) | 2014-12-09 | 2014-12-09 | Power grid cascading failure restraining method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104466953A true CN104466953A (en) | 2015-03-25 |
CN104466953B CN104466953B (en) | 2017-01-18 |
Family
ID=52912547
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410747329.4A Expired - Fee Related CN104466953B (en) | 2014-12-09 | 2014-12-09 | Power grid cascading failure restraining method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104466953B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106655167A (en) * | 2016-12-06 | 2017-05-10 | 国网北京市电力公司 | Simulation method and device for cascading failures of power grid |
CN112688323A (en) * | 2021-01-13 | 2021-04-20 | 重庆大学 | Power system cascading failure blocking method based on active minimum generator tripping |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000184600A (en) * | 1998-12-16 | 2000-06-30 | Meidensha Corp | Selected load cut-off apparatus |
CN104133968A (en) * | 2014-08-04 | 2014-11-05 | 云南电网公司电网规划研究中心 | Correlation assessment method of power grid cascading failure accident chains |
-
2014
- 2014-12-09 CN CN201410747329.4A patent/CN104466953B/en not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000184600A (en) * | 1998-12-16 | 2000-06-30 | Meidensha Corp | Selected load cut-off apparatus |
CN104133968A (en) * | 2014-08-04 | 2014-11-05 | 云南电网公司电网规划研究中心 | Correlation assessment method of power grid cascading failure accident chains |
Non-Patent Citations (1)
Title |
---|
祁达才: ""南方电网连锁故障大扰动及应对措施"", 《南方电网技术》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106655167A (en) * | 2016-12-06 | 2017-05-10 | 国网北京市电力公司 | Simulation method and device for cascading failures of power grid |
CN112688323A (en) * | 2021-01-13 | 2021-04-20 | 重庆大学 | Power system cascading failure blocking method based on active minimum generator tripping |
Also Published As
Publication number | Publication date |
---|---|
CN104466953B (en) | 2017-01-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102222890B (en) | Complex power grid cascading failure analysis method considering atrocious weather factor | |
CN101917001B (en) | Fault sequencing method for on-line static security analysis of power system | |
CN103279807A (en) | Static risk assessment method for power grid in severe weather | |
CN103311926B (en) | Power system cascading failure simulation method based on unified power flow controller | |
CN104934971B (en) | Dynamic section control method based on power flow transfer ratio | |
CN103501007B (en) | A kind of low-frequency and low-voltage load-reducing control method taking into account load comprehensive adjustment characteristic | |
CN103985065A (en) | Electric power system risk assessment method based on fault pre-scanning | |
CN103366220A (en) | Evaluation method of operational risk of electric system | |
Omar et al. | Under frequency load shedding (UFLS): Principles and implementation | |
CN103258299A (en) | Net rack optimization method for multi-direct-current centralized fed receiving end power grid | |
CN106327034A (en) | Cascading failure search and weak link analysis method based on operation reliability model | |
CN104638646B (en) | Power grid cascading failure simulation method based on Complex Networks Theory meter and Corrective control | |
CN100576680C (en) | Big grid equipment overload is at the intelligence connection blanking method of line sensitivity | |
CN107658895B (en) | Threshold value setting method for direct-current commutation failure prediction link | |
CN109635331B (en) | Economic short-circuit current limiter optimal configuration method | |
CN105048497A (en) | Doubly-fed wind turbine generator low-voltage ride through method | |
CN110932291B (en) | Active splitting method for preserving stability of local power grid | |
CN104242260B (en) | Fixed time limit protection fixed value optimization method based on risk index | |
CN105375453A (en) | An emergency control method based on a cascading failure damage degree index | |
CN105703356A (en) | Dispatching method for restoring system security of electric power system after multiple failures | |
CN104466953A (en) | Power grid cascading failure restraining method | |
CN105160148A (en) | AC-DC power grid cascading failure key line identification method | |
CN107359619B (en) | Load shedding control method considering voltage stability of system after photovoltaic access | |
CN111030124B (en) | Power grid low-voltage load shedding method and device considering fault voltage recovery characteristics | |
CN105305389B (en) | A kind of emergency control method preventing the chain overload of transmission cross-section |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170118 Termination date: 20171209 |
|
CF01 | Termination of patent right due to non-payment of annual fee |