CN104328920A - Building material conveying method - Google Patents
Building material conveying method Download PDFInfo
- Publication number
- CN104328920A CN104328920A CN201410510071.6A CN201410510071A CN104328920A CN 104328920 A CN104328920 A CN 104328920A CN 201410510071 A CN201410510071 A CN 201410510071A CN 104328920 A CN104328920 A CN 104328920A
- Authority
- CN
- China
- Prior art keywords
- hoist engine
- level
- building
- supporting seat
- elevator shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention relates to a building material conveying method, which comprises the following steps that A, hoisting equipment is erected, and the erecting comprises the following work procedures regardless of sequences: 1, a hoisting support frame is erected; 2, an electric block for hoisting a cross beam is arranged at the top of a building; 3, a windlass used for hoisting materials is arranged on the cross beam; 4, a horizontal transfer rail and a translation trolley are erected at a material conveying target ground floor; B, materials are hoisted on the windlass, and the materials are hoisted above the horizontal transfer rail by the windlass; C, the materials are unfastened from the windlass and are placed on the translation trolley; D, the materials are transferred by the translation trolley; E, the electric block is used for lifting the hoisting support frame, the horizontal transfer rail and the translation trolley are transferred to an upper floor, and the steps from B to D are repeated. The building material conveying method has the advantages that the material conveying efficiency can be effectively improved, and the building construction safety can be improved.
Description
Technical field
The present invention relates to technical field of building construction, be specifically related to a kind of carrying method of constructional materials.
Background technology
At present, when building for highrise building, normally successively build, constructional materials used needs carrying out successively to carry, and existing constructional materials normally adopts the tower crane of great cantilever to lift.
In architectural process, safety is matter of utmost importance, when utilizing tower crane to lift building material at present, because material is suspended from building outside, there is the risk of larger falling from high altitude; In addition, in hoisting process, first utilize tower crane to lift material, then tower crane swings to corresponding position, and arrive materials station by traversing for material afterwards, the whole process used time is longer, and the efficiency of conveying is relatively low, affects the duration.
Summary of the invention
For the deficiencies in the prior art, object of the present invention is intended to provide a kind of constructional materials carrying method, and it has higher safety, and can improve the efficiency of mass transport.
For achieving the above object, the present invention adopts following technical scheme:
Constructional materials carrying method, comprises the steps:
Steps A, hanging device are built, and it comprises the following operation of order in no particular order:
Operation one, in two opposed inner walls of building elevator shaft respectively pre-buried supporting seat, supporting seat is hinged with fall arrest support member; In elevator shaft, hoisting bracket is set, this hoisting bracket comprises crossbeam and two vertical beams be oppositely arranged, two vertical beams are individually fixed in above the two ends of crossbeam, and the arranged outside of vertical beam has the multiple teeth groove along highly arrangement, the fall arrest support member of the supporting seat in elevator shaft two opposed inner walls is embedded in the teeth groove of two vertical beams respectively;
Operation two, top of building arrange the electric block being used for lifting cross beam;
Operation three, hoist engine for lifting material is set on crossbeam;
Operation four, mass transport destination floor set up level transhipment track, this level transhipment track extend to elevator shaft inside, level transhipment track on translating trolleys is set;
Step B, material is lifted on hoist engine, utilizes hoist engine by above material lifting to level transhipment track;
Below step C, mobile translating trolleys to material, material is untied from hoist engine and makes material be placed on translating trolleys;
Step D, by translating trolleys level transport material;
Step e, utilize electric block to promote hoisting bracket, level is transported the floor that track and translating trolleys are transferred to top, repeat above-mentioned steps B to step D.
Hoisting bracket comprises two crossbeams parallel to each other, and the body cross-over connection of hoist engine is fixed on the centre position of two crossbeam length directions.
Level transhipment track comprises straightway and bend section.
Supporting seat is also provided with the stopper slot limiting vertical beam and move up and down.
Beneficial effect of the present invention is:
Compared to prior art, the present invention is owing to adopting the mode of vertical lifting material, effectively can improve the efficiency of mass transport, thus shorten the building operations duration, and whole material conveying process completes in the elevator shaft watering building inside, there is not outdoor work, improve the safety of building operations.
Accompanying drawing explanation
Fig. 1 is the structural representation of hanging device of the present invention;
Fig. 2 is the sectional view of hanging device of the present invention;
Fig. 3 is the zoomed-in view at A place in Fig. 2;
Wherein: 10, elevator shaft; 20, hoisting bracket; 21, crossbeam; 22, vertical beam; 30, hoist engine; 40, level transhipment track; 50, translating trolleys; 60, supporting seat; 61, fall arrest support member.
Detailed description of the invention
Below, by reference to the accompanying drawings and detailed description of the invention, the present invention is described further:
Building material carrying method, it comprises the steps:
Build hanging device shown in steps A, foundation Fig. 1,2,3, this step specifically comprises the following operation of order in no particular order:
Operation one, in the opposed inner walls of the elevator shaft 10 of building respectively pre-buried supporting seat 60, supporting seat 60 upper hinge is connected with fall arrest support member 61, can be at the inner pre-embedding metal part of the cement components of elevator shaft 10 when building elevator shaft 10, then supporting seat 60 being welded on pre-buried metalwork, in elevator shaft 10 inside, hoisting bracket 20 is set, this hoisting bracket 20 comprises crossbeam 21, and two vertical beams be oppositely arranged 22, two vertical beams 22 are individually fixed in above the two ends of crossbeam 21, and the arranged outside of vertical beam 22 has the multiple teeth groove along short transverse arrangement, by in two the vertical beams 22 respectively stopper slot of cross-under on supporting seat 60, the fall arrest support member 61 be oppositely arranged is made to be plugged in the teeth groove of two vertical beams 22 respectively, thus utilize fall arrest support member 61 to support hoisting bracket 20, and when hoisting bracket 20 moves upward, fall arrest support member 61 rotates towards the direction of supporting seat 60, stop moving up hoisting bracket 20, fall arrest support member 61 supports vertical beam 22 again.In order to ensure stability, prevent vertical beam 22 beat, stopper slot on above-mentioned supporting seat 60 is consistent with the width of vertical beam 22, for limiting moving up and down of vertical beam 22, also can be for each is with the adaptive two or more supporting seat 60 of vertical beam 22, moving up and down of vertical beam 22 can either be limited further, the gravity of hoisting bracket 20 and the material on it can be disperseed simultaneously.
Operation two, to arrange at top of building and be used for the electric block of lifting cross beam 21;
Operation three, hoist engine 30 for lifting material is set on crossbeam 21; Above-mentioned hoisting bracket 20 can be comprise two crossbeams 21, and the body part of hoist engine 30 is connected across the centre position of two crossbeam 21 length directions;
Operation four, set up level transhipment track 40 at mass transport destination floor, it is inner that this level transhipment track 40 extends to elevator shaft 10, and level transhipment track 40 arranges translating trolleys 50;
Step B, material to be lifted on hoist engine 30, to utilize hoist engine 30 by above material lifting to level transhipment track 40;
Below step C, mobile translating trolleys 50 to material, material is untied from hoist engine 30 and makes material be placed on translating trolleys 50;
Step D, by translating trolleys 50 level transport material;
Step e, utilize electric block to promote hoisting bracket 20, level is transported the floor that track 40 and translating trolleys 50 shift top, repeat above-mentioned steps B to step D.
In said method of the present invention, owing to adopting the mode of vertical lifting material, effectively can improve the efficiency of mass transport, thus shorten the building operations duration, and whole material conveying process completes in the elevator shaft 10 watering building inside, there is not outdoor work, improve the safety of building operations.
To one skilled in the art, according to technical scheme described above and design, other various corresponding change and deformation can be made, and all these change and deformation all should belong within the protection domain of the claims in the present invention.
Claims (4)
1. constructional materials carrying method, is characterized in that, comprises the steps:
Steps A, hanging device are built, and it comprises the following operation of order in no particular order:
Operation one, in two opposed inner walls of building elevator shaft respectively pre-buried supporting seat, supporting seat is hinged with fall arrest support member; In elevator shaft, hoisting bracket is set, this hoisting bracket comprises crossbeam and two vertical beams be oppositely arranged, two vertical beams are individually fixed in above the two ends of crossbeam, and the arranged outside of vertical beam has the multiple teeth groove along highly arrangement, the fall arrest support member of the supporting seat in elevator shaft two opposed inner walls is embedded in the teeth groove of two vertical beams respectively;
Operation two, top of building arrange the electric block being used for lifting cross beam;
Operation three, hoist engine for lifting material is set on crossbeam;
Operation four, mass transport destination floor set up level transhipment track, this level transhipment track extend to elevator shaft inside, level transhipment track on translating trolleys is set;
Step B, material is lifted on hoist engine, utilizes hoist engine by above material lifting to level transhipment track;
Below step C, mobile translating trolleys to material, material is untied from hoist engine and makes material be placed on translating trolleys;
Step D, by translating trolleys level transport material;
Step e, utilize electric block to promote hoisting bracket, level is transported the floor that track and translating trolleys are transferred to top, repeat above-mentioned steps B to step D.
2. constructional materials carrying method as claimed in claim 1, it is characterized in that, hoisting bracket comprises two crossbeams parallel to each other, and the body cross-over connection of hoist engine is fixed on the centre position of two crossbeam length directions.
3. constructional materials carrying method as claimed in claim 1, is characterized in that, level transhipment track comprises straightway and bend section.
4. constructional materials carrying method as claimed in claim 1, is characterized in that, supporting seat is also provided with the stopper slot limiting vertical beam and move up and down.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410510071.6A CN104328920B (en) | 2014-09-28 | 2014-09-28 | Construction material carrying method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410510071.6A CN104328920B (en) | 2014-09-28 | 2014-09-28 | Construction material carrying method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104328920A true CN104328920A (en) | 2015-02-04 |
CN104328920B CN104328920B (en) | 2016-09-28 |
Family
ID=52403720
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410510071.6A Expired - Fee Related CN104328920B (en) | 2014-09-28 | 2014-09-28 | Construction material carrying method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104328920B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105565178A (en) * | 2015-12-30 | 2016-05-11 | 华北冶建工程建设有限公司 | Elevator shaft material hoisting device |
CN112408288A (en) * | 2020-09-21 | 2021-02-26 | 上海宝冶冶金工程有限公司 | Jacking sliding equipment special for blast furnace |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2236477Y (en) * | 1995-05-08 | 1996-10-02 | 大连第二建筑工程公司 | High bulk material lifting apparatus |
CN2703832Y (en) * | 2004-05-10 | 2005-06-08 | 唐裕新 | Elevator well creeping formwork hoisting frame |
WO2005084185A2 (en) * | 2004-02-20 | 2005-09-15 | Otis Elevator Company | A device for moving a platform along elevator guide rails |
CN1982193A (en) * | 2005-12-16 | 2007-06-20 | 王�忠 | Installation of high-building construction vertical transferring apparatus by elevator well |
CN102341336A (en) * | 2009-03-06 | 2012-02-01 | 通力股份公司 | Elevator arrangement and method |
CN102459053A (en) * | 2009-04-06 | 2012-05-16 | 通力股份公司 | Method and elevator arrangement |
-
2014
- 2014-09-28 CN CN201410510071.6A patent/CN104328920B/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2236477Y (en) * | 1995-05-08 | 1996-10-02 | 大连第二建筑工程公司 | High bulk material lifting apparatus |
WO2005084185A2 (en) * | 2004-02-20 | 2005-09-15 | Otis Elevator Company | A device for moving a platform along elevator guide rails |
CN2703832Y (en) * | 2004-05-10 | 2005-06-08 | 唐裕新 | Elevator well creeping formwork hoisting frame |
CN1982193A (en) * | 2005-12-16 | 2007-06-20 | 王�忠 | Installation of high-building construction vertical transferring apparatus by elevator well |
CN102341336A (en) * | 2009-03-06 | 2012-02-01 | 通力股份公司 | Elevator arrangement and method |
CN102459053A (en) * | 2009-04-06 | 2012-05-16 | 通力股份公司 | Method and elevator arrangement |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105565178A (en) * | 2015-12-30 | 2016-05-11 | 华北冶建工程建设有限公司 | Elevator shaft material hoisting device |
CN112408288A (en) * | 2020-09-21 | 2021-02-26 | 上海宝冶冶金工程有限公司 | Jacking sliding equipment special for blast furnace |
Also Published As
Publication number | Publication date |
---|---|
CN104328920B (en) | 2016-09-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101434366B (en) | Hoisting tool and hoisting method for column component | |
CN103774857A (en) | Hoisting construction method for fixed hydraulic lifting large-sized equipment in frame | |
GB201209006D0 (en) | High rise building elevation concept | |
CN104140037A (en) | Wallboard lifting system | |
CN202751338U (en) | Rail type suspension basket | |
CN204000830U (en) | Merogenesis take-over type sand drain machine | |
CN204185120U (en) | Mobile unit dolly in place | |
CN104120701B (en) | A kind of construction method of vertical ship lift great good lifting and device | |
CN104895336A (en) | Method for installing steel beam of stiff hybrid structure in place | |
CN104328920A (en) | Building material conveying method | |
CN204626998U (en) | A kind of attached lift scaffold discharging platform | |
CN104291222A (en) | Rigid protection and crane integration system inside super high-rise building core tube | |
CN104016260A (en) | Compartment funnel slipping mounting method and slipping mounting mechanism | |
RU140819U1 (en) | Gantry crane | |
CN103654610A (en) | Rail type hanging basket | |
CN203783105U (en) | Fast construction operating platform used for section steel column interior pouring concrete | |
CN203333143U (en) | Building construction basket | |
CN106276602B (en) | A kind of across high ferro Business Line beam body hangs method | |
CN202810176U (en) | Mobile operation platform | |
CN209353734U (en) | For installing the double-track device of curtain wall | |
CN204001751U (en) | Super high steel structure construction overhanging unloading platform | |
RU2016111128A (en) | Tower structure | |
CN103291078B (en) | A kind of steel girder erection equipment | |
CN202337945U (en) | Outer side in-place beam body lifting device | |
CN201128882Y (en) | Lifting and supporting brackets integrated construction device for bridge arch rib |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160928 Termination date: 20170928 |
|
CF01 | Termination of patent right due to non-payment of annual fee |