CN104264662A - 富含水土层中深嵌硬质岩咬合桩施工方法 - Google Patents
富含水土层中深嵌硬质岩咬合桩施工方法 Download PDFInfo
- Publication number
- CN104264662A CN104264662A CN201410552112.8A CN201410552112A CN104264662A CN 104264662 A CN104264662 A CN 104264662A CN 201410552112 A CN201410552112 A CN 201410552112A CN 104264662 A CN104264662 A CN 104264662A
- Authority
- CN
- China
- Prior art keywords
- rock
- pile
- depth
- hole
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0061—Production methods for working underwater
- E02D2250/0076—Drilling
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
本发明公开了一种富含水土层中深嵌硬质岩咬合桩施工方法,包括:测放桩位,全套管全回旋钻机带动套管旋转下磨切割岩石至套管进入施工面以下2.5~3m,取土至岩石面后,采用小型潜孔锤进行引孔制造破裂面,再用冲击锤冲击岩石,取岩石至孔深达到成桩深度,浇筑混凝土,逐次连续间隔成型A桩,相邻两个所述A桩的最近边缘间隔小于待加工B桩的直径;以相邻两个A桩中心连线的中点为套管的中心,全套管全回旋钻机带动套管下磨切割初凝后的A桩至套管进入施工面以下2.5~3m,进行取土、小潜孔锤引孔、冲击岩石、取石,至达到成桩深度时安放钢筋笼及浇筑混凝土,逐次连续间隔成型B桩,形成咬合。本发明的施工方法操作简单易行,能够适用于各种土层、岩石,且成桩安全系数高。
Description
技术领域
本发明涉及一种建筑施工方法,具体涉及一种富含水土层中深嵌硬质岩咬合桩施工方法。
背景技术
随着社会的发展和城市的密集建设,基坑围护工程越来越复杂,嵌岩咬合桩现阶段应用越来越多,传统的咬合桩施工工艺一般适用于各种土层、强风化岩石、中风化岩石强度为60Mpa以下,嵌岩深度为1~2m,如遇硬质岩石,如花岗岩、玄武岩等,岩石强度为60Mpa以上,嵌岩深度为3~10m,传统的嵌岩咬合桩施工方法根本无法施工。
现有技术中,如中国发明专利CN102002943A公开了一种嵌岩咬合灌注桩的施工方法,包括步骤:(1)测放桩位,潜孔锤钻机连续间隔预成孔,进行排土、凿岩、排碴、成孔至岩石面下,回灌砂或土,或灌注≤C5的低标号砼,移到下一工位;(2)全套管钻机就位,在回灌孔之间压入套管、取土、成孔至岩石面,灌注超缓凝砼、拔出套管、连续成桩;(3)全套管钻机再就位,与相邻超缓凝砼桩相切,压入套管、取土、二次成孔至岩石面下,测量孔深、清底;(4)安装钢筋笼,灌注砼,拔出套管,嵌岩咬合灌注桩成型。上述技术方案中,采用全套管钻机,仅能用于土层或软岩层,进入硬岩较困难,并且因为需要先用潜孔锤钻机预成孔,而潜孔锤钻机只能进行干作业,所以上述技术方案在含水的土层中无法作业,另外,上述技术方案采用荤(B桩)桩长,素(A桩)桩短的成桩形式,荤桩进入岩石面以下,素桩不进入岩石面以下,这种成桩形式安全系数较低,且采用超缓凝砼需要控制好B桩的时间,否则容易造成质量事故。
因此,需要一种能够适用于任何土层、岩石,且成桩安全系数高的咬合桩施工方法。
发明内容
本发明的发明目的是提供一种富含水土层中深嵌硬质岩咬合桩施工方法,其操作简单易行,能够适用于各种土层、岩石,且成桩安全系数高。
为达到上述发明目的,本发明采用的技术方案是:一种富含水土层中深嵌硬质岩咬合桩施工方法,包括如下步骤:
(1)测放桩位,全套管全回旋钻机就位,带动套管旋转下磨切割岩石至套管进入施工面以下2.5~3m,冲抓斗取土至岩石面后,采用小型潜孔锤进行引孔制造破裂面,再用冲击锤冲击岩石,冲抓斗取岩石,测量孔深,若孔深未达到成桩深度,则继续向下成孔,若孔深达到成桩深度,则浇筑混凝土,成型A桩,移到下一工位,重复上述步骤,逐次连续间隔成型A桩,相邻两个所述A桩的最近边缘间隔小于待加工B桩的直径;
(2)以相邻两个A桩中心连线的中点为套管的中心,再次就位全套管全回旋钻机,带动套管下磨切割初凝后的A桩至套管进入施工面以下2.5~3m,冲抓斗取土至岩石面后,采用小型潜孔锤进行引孔制造破裂面,再用冲击锤冲击岩石,冲抓斗取岩石,测量孔深,若孔深未达到成桩深度,则继续向下成孔,若孔深达到成桩深度,则安放钢筋笼及浇筑混凝土,逐次连续间隔成型B桩,形成咬合。
上述技术方案中,所述引孔直径为100mm,深度比设计孔深深50cm。
优选的技术方案,相邻两个所述A桩的最近边缘间隔为650mm。
由于上述技术方案运用,本发明与现有技术相比具有下列优点:
1.本发明先用全套管全回旋钻机带动套管切割岩石至套管进入施工面以下2.5~3m,截断岩石裂隙水和微承压水,实现水下湿作业变为干作业,配合使用小潜孔锤在岩石上引孔制造破裂面,降低了破岩难度,因此本发明适用于各种土层、岩石。
2. 本发明浇筑普通混凝土,相比于现有技术,不需要控制好B桩的施工时间,不会造成质量事故,节约成本。
3. 本发明成桩全部进入岩面以下,围护体系的安全系数更高。
附图说明
图1是实施例一中本发明的施工方法流程图。
图2是实施例一中A桩施工示意图。
图3是实施例一中B桩施工示意图。
具体实施方式
下面结合附图及实施例对本发明作进一步描述:
实施例一:参见图1至3所示,一种富含水土层中深嵌硬质岩咬合桩施工方法,包括如下步骤:
(1)测放桩位,全套管全回旋钻机就位,带动套管旋转下磨切割岩石至套管进入施工面以下2.5~3m,冲抓斗取土至岩石面后,采用小型潜孔锤进行引孔制造破裂面,再用冲击锤冲击岩石,冲抓斗取岩石,测量孔深,若孔深未达到成桩深度,则继续向下成孔,若孔深达到成桩深度,则浇筑混凝土,逐次连续间隔成型A桩,相邻两个所述A桩的最近边缘间隔为650mm,移到下一工位;
(2)以相邻两个A桩中心连线的中点为套管的中心,再次就位全套管全回旋钻机,带动套管下磨切割初凝后的A桩至套管进入施工面以下2.5~3m,冲抓斗取土至岩石面后,采用小型潜孔锤进行引孔制造破裂面,再用冲击锤冲击岩石,冲抓斗取岩石,测量孔深,若孔深未达到成桩深度,则继续向下成孔,若孔深达到成桩深度,则安放钢筋笼及浇筑混凝土,逐次连续间隔成型B桩,形成咬合。
本实施例中,所述引孔直径为100mm,深度比设计孔深深50cm。
Claims (3)
1.一种富含水土层中深嵌硬质岩咬合桩施工方法,其特征在于,包括如下步骤:
(1)测放桩位,全套管全回旋钻机就位,带动套管旋转下磨切割岩石至套管进入施工面以下2.5~3m,冲抓斗取土至岩石面后,采用小型潜孔锤进行引孔制造破裂面,再用冲击锤冲击岩石,冲抓斗取岩石,测量孔深,若孔深未达到成桩深度,则继续向下成孔,若孔深达到成桩深度,则浇筑混凝土,成型A桩,移到下一工位,重复上述步骤,逐次连续间隔成型A桩,相邻两个所述A桩的最近边缘间隔小于待加工B桩的直径;
(2)以相邻两个A桩中心连线的中点为套管的中心,再次就位全套管全回旋钻机,带动套管下磨切割初凝后的A桩至套管进入施工面以下2.5~3m,冲抓斗取土至岩石面后,采用小型潜孔锤进行引孔制造破裂面,再用冲击锤冲击岩石,冲抓斗取岩石,测量孔深,若孔深未达到成桩深度,则继续向下成孔,若孔深达到成桩深度,则安放钢筋笼及浇筑混凝土,逐次连续间隔成型B桩,形成咬合。
2.根据权利要求1所述的一种富含水土层中深嵌硬质岩咬合桩施工方法,其特征在于:所述引孔直径为100mm,深度比设计孔深深50cm。
3.根据权利要求1所述的一种富含水土层中深嵌硬质岩咬合桩施工方法,其特征在于:相邻两个所述A桩的最近边缘间隔为650mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410552112.8A CN104264662A (zh) | 2014-10-17 | 2014-10-17 | 富含水土层中深嵌硬质岩咬合桩施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410552112.8A CN104264662A (zh) | 2014-10-17 | 2014-10-17 | 富含水土层中深嵌硬质岩咬合桩施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104264662A true CN104264662A (zh) | 2015-01-07 |
Family
ID=52156226
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410552112.8A Pending CN104264662A (zh) | 2014-10-17 | 2014-10-17 | 富含水土层中深嵌硬质岩咬合桩施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104264662A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105862708A (zh) * | 2016-04-26 | 2016-08-17 | 北京振冲工程机械有限公司 | 一种潜孔锤配合引孔的振冲碎石桩复合地基的施工方法 |
CN110273417A (zh) * | 2019-07-07 | 2019-09-24 | 韩少鹏 | 一种建筑工程灌注桩施工方法 |
CN110344400A (zh) * | 2019-07-17 | 2019-10-18 | 北京建材地质工程有限公司 | 旋挖钻机遇坚硬岩成孔成桩施工工艺 |
CN113882358A (zh) * | 2021-09-01 | 2022-01-04 | 武汉市政工程设计研究院有限责任公司 | 一种上软下硬复杂地层基坑墙体施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2352718C1 (ru) * | 2007-10-16 | 2009-04-20 | Открытое акционерное общество "Мостотрест" (ОАО "Мостотрест") | Способ сооружения пакета буронабивных свай |
CN201362852Y (zh) * | 2008-11-13 | 2009-12-16 | 王立建 | 咬合桩支护体系 |
CN201762702U (zh) * | 2010-09-17 | 2011-03-16 | 中铁十九局集团轨道交通工程有限公司 | 钻孔咬合桩 |
CN102535440A (zh) * | 2012-01-11 | 2012-07-04 | 昆明捷程桩工有限责任公司 | 全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法 |
CN103276723A (zh) * | 2013-04-27 | 2013-09-04 | 瑞华建设集团有限公司 | 混凝土钻孔咬合桩的施工方法 |
-
2014
- 2014-10-17 CN CN201410552112.8A patent/CN104264662A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2352718C1 (ru) * | 2007-10-16 | 2009-04-20 | Открытое акционерное общество "Мостотрест" (ОАО "Мостотрест") | Способ сооружения пакета буронабивных свай |
CN201362852Y (zh) * | 2008-11-13 | 2009-12-16 | 王立建 | 咬合桩支护体系 |
CN201762702U (zh) * | 2010-09-17 | 2011-03-16 | 中铁十九局集团轨道交通工程有限公司 | 钻孔咬合桩 |
CN102535440A (zh) * | 2012-01-11 | 2012-07-04 | 昆明捷程桩工有限责任公司 | 全套管钻机组合旋挖钻机进行嵌岩咬合桩墙的施工方法 |
CN103276723A (zh) * | 2013-04-27 | 2013-09-04 | 瑞华建设集团有限公司 | 混凝土钻孔咬合桩的施工方法 |
Non-Patent Citations (1)
Title |
---|
李建文: "全套管全回旋钻咬合桩的应用研究", 《四川建材》, vol. 40, no. 178, 30 April 2014 (2014-04-30), pages 199 - 201 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105862708A (zh) * | 2016-04-26 | 2016-08-17 | 北京振冲工程机械有限公司 | 一种潜孔锤配合引孔的振冲碎石桩复合地基的施工方法 |
CN110273417A (zh) * | 2019-07-07 | 2019-09-24 | 韩少鹏 | 一种建筑工程灌注桩施工方法 |
CN110344400A (zh) * | 2019-07-17 | 2019-10-18 | 北京建材地质工程有限公司 | 旋挖钻机遇坚硬岩成孔成桩施工工艺 |
CN113882358A (zh) * | 2021-09-01 | 2022-01-04 | 武汉市政工程设计研究院有限责任公司 | 一种上软下硬复杂地层基坑墙体施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103046931B (zh) | 一种竖井/导井冲击式钻机冲击成孔施工方法 | |
CN104631438B (zh) | 长螺旋钻孔压灌混凝土抗拔桩施工方法 | |
CN101851922B (zh) | 用全套管钻机切断地下锚索/杆的处理方法 | |
CN103603342A (zh) | 大直径组合套管超长灌注桩施工方法 | |
CN104947690A (zh) | 地下连续墙入岩成槽施工方法 | |
CN103758123A (zh) | 人工挖孔灌注桩护壁衬的施工方法 | |
WO2014187171A1 (zh) | 一种高突煤层穿层钻孔网络化加固方法 | |
CN106194193A (zh) | 一种大断面竖井非***大孔径群孔辅助开挖方法 | |
CN104264662A (zh) | 富含水土层中深嵌硬质岩咬合桩施工方法 | |
CN106837382B (zh) | 一种地铁隧道围岩地面预注浆加固工艺 | |
CN103321244A (zh) | 砂土地基既有建筑增设地下室的施工方法 | |
CN104963346A (zh) | 复杂地质的深基坑围护施工方法 | |
CN105239564A (zh) | 全套管组合泥浆护壁的灌注桩施工方法 | |
CN101982614A (zh) | 全套管钻机凿取岩石成桩的方法 | |
CN204299468U (zh) | 一种潜孔钻钻孔的定位导向***装置 | |
CN105113976B (zh) | 钢丝刷钻头回旋钻机及解决埋钻、掉钻、卡钻的方法 | |
CN104762970B (zh) | 一种深孔岩溶注浆辅助拔管装置及施工方法 | |
CN109610494B (zh) | 一种大口径桩基嵌岩施工工艺 | |
CN104805830B (zh) | 非***岩石抗拔桩施工方法 | |
CN103981860A (zh) | 一种干取土节能潜孔锤灌注桩及其设备 | |
CN204609897U (zh) | 一种管幕冻结法支护结构 | |
CN102002943B (zh) | 嵌岩咬合灌注桩的施工方法 | |
CN203583501U (zh) | 一种抵抗岩体滑动的深层抗剪装置 | |
CN204782730U (zh) | 钢丝刷钻头回旋钻机 | |
CN205100226U (zh) | 地下连续墙入岩成槽施工设备 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150107 |
|