CN104131566A - 一种地下室无水平支撑基坑的施工方法 - Google Patents

一种地下室无水平支撑基坑的施工方法 Download PDF

Info

Publication number
CN104131566A
CN104131566A CN201410227624.7A CN201410227624A CN104131566A CN 104131566 A CN104131566 A CN 104131566A CN 201410227624 A CN201410227624 A CN 201410227624A CN 104131566 A CN104131566 A CN 104131566A
Authority
CN
China
Prior art keywords
cement mixing
basement
mixing pile
foundation pit
foundation ditch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410227624.7A
Other languages
English (en)
Other versions
CN104131566B (zh
Inventor
苏伟
安家伟
陈逸宾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN201410227624.7A priority Critical patent/CN104131566B/zh
Publication of CN104131566A publication Critical patent/CN104131566A/zh
Application granted granted Critical
Publication of CN104131566B publication Critical patent/CN104131566B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

本发明公开了一种地下室无水平支撑基坑的施工方法。该方法采用二级基坑支护法进行施工;第一级是先沿地下室外缘施工一圈闭合的水泥搅拌桩,利用水泥搅拌桩在地下室外缘形成闭合的止水帷幕;然后在闭合的止水帷幕内通过降水井降低地下水位,进行第一阶段土方开挖,并同时完成预制管柱的施工;第二级是采用SMW工法完成基坑的二级支护和止水帷幕,通过降水井降水后,然后再进行以下土方的开挖。本发明在满足基坑支护安全的前提下,取消了基坑水平内支撑,可节约施工成本和加快施工进度。

Description

一种地下室无水平支撑基坑的施工方法
技术领域
本发明涉及一种地下室无水平支撑基坑的施工方法,属于土建施工技术领域。
背景技术
随着我国建筑业的不断发展,各类建筑型式不断涌现,超大基坑工程越来越多,常规工程地下室正作法施工中,在基坑原始地面进行桩基的施工,再进行基坑支护施工、土方开挖。这种作法造成较大浪费,不满足目前国家节能减排的思路。
发明内容
本发明的目的在于,提供一种地下室无水平支撑基坑的施工方法,在满足基坑支护安全的前提下,取消基坑水平内支撑,以节约施工成本和加快施工进度,从而克服现有技术的不足。
本发明的技术方案是这样实现的:
本发明的一种地下室无水平支撑基坑的施工方法为,该方法采用二级基坑支护法进行施工;第一级是先沿地下室外缘施工一圈闭合的水泥搅拌桩,利用水泥搅拌桩在地下室外缘形成闭合的止水帷幕;然后在闭合的止水帷幕内通过降水井降低地下水位,进行第一阶段土方开挖,并同时完成预制管柱的施工;第二级是采用SMW工法完成基坑的二级支护和止水帷幕,然后再进行以下土方的开挖。
前述方法中,所述水泥搅拌桩的深度深至地面以下的中砂层中部,水泥搅拌桩顶部内侧通过向下倾斜25度,长度1.2米的锚管与基坑锚固;水泥搅拌桩顶部内侧采用C20混凝土喷射护面将锚管端部封闭;水泥搅拌桩顶部外侧设有施工道路,施工道路与水泥搅拌桩之间设有排水沟。
前述方法中,所述第一阶段土方开挖深度挖至杂填土层以下的粉砂层;第一阶段土方开挖的底部边缘设有排水沟。
前述方法中,所述二级支护采用三轴水泥搅拌桩,三轴水泥搅拌桩的深度深至地面以下的砾砂层,并在三轴水泥搅拌桩内***H型钢,形成二级止水帷幕和二级支护结构;三轴水泥搅拌桩内侧通过向下倾斜30度,长度1.3米的锚杆与基坑锚固;三轴水泥搅拌桩顶部通过钢筋砼冠梁将锚杆端部封闭。
前述方法中,所述以下土方的开挖深度挖至粉砂层以下的中砂层;土方开挖的底部边缘设有排水沟。
由于采用了上述技术方案,本发明与现有技术相比,本发明在设计初期,考虑地下室水位较高,基坑采用无水平支撑体系的二级基坑支护。本发明的优势在于,取消基坑水平内支撑,可以加快施工进度。基坑支护施工过程中,可同时***预桩基施工。在第一级基坑支护完成和第一级降水完全形成后,可同时***第一阶段土方开挖,接着再进行桩基施工,可以节省切割预制管柱长度或节省冲(钻)孔灌注桩深度,节约成本。待第一阶段土方开挖完、桩基施工完后,接着再进行第二级基坑支护、基坑降水、第二阶段土方开挖及地下室结构施工,可加快施工进度。
附图说明
图1是本发明的施工方法示意图。
图中的标记为:1-杂土填层,2-粉砂层,3-中砂层,4-砾砂层,5-单轴水泥搅拌桩,6-锚管,7-C20混凝土喷射护面,8-H型钢桩,9-三轴水泥搅拌桩,10-道路,11-排水沟,12-锚杆,13-钢筋混凝土冠梁。
具体实施方式
下面结合附图和实施例对本发明作进一步的详细说明,但不作为对本发明的任何限制。
本发明的一种地下室无水平支撑基坑的施工方法为,该方法采用二级基坑支护法进行施工;第一级是先沿地下室外缘施工一圈闭合的水泥搅拌桩1,利用水泥搅拌桩在地下室外缘形成闭合的止水帷幕;然后在闭合的止水帷幕内通过降水井降低地下水位,进行第一阶段土方开挖,并同时完成预制管柱的施工;第二级是采用SMW工法完成基坑的二级支护2和降水,然后再进行以下土方的开挖。水泥搅拌桩的深度深至地面以下的中砂层中部,水泥搅拌桩顶部内侧通过向下倾斜25度,长度1.2米的锚管与基坑锚固;水泥搅拌桩顶部内侧采用C20混凝土喷射护面将锚管端部封闭;水泥搅拌桩顶部外侧设有施工道路,施工道路与水泥搅拌桩之间设有排水沟。第一阶段土方开挖深度挖至杂填土层以下的粉砂层;第一阶段土方开挖的底部边缘设有排水沟。二级支护采用三轴水泥搅拌桩,三轴水泥搅拌桩的深度深至地面以下的砾砂层,并在三轴水泥搅拌桩内***H型钢,形成二级止水帷幕和二级支护结构;三轴水泥搅拌桩内侧通过向下倾斜30度,长度1.3米的锚杆与基坑锚固;三轴水泥搅拌桩顶部通过钢筋砼冠梁将锚杆端部封闭。所述以下土方的开挖深度挖至粉砂层以下的中砂层;土方开挖的底部边缘设有排水沟。
实施例
如图1所示,图中标号1-4是地面以下土层的标号,1为杂土填层,2为粉砂层,3为中砂层,4为砾砂层。本例适用于地下室两层及两层以内的超大基坑大开挖施工的工程。施工方式是采用二级基坑支护施工技术。
第一级按以下步骤施工:
1、先采用单轴水泥搅拌桩5沿地下室外缘施工一圈水泥搅拌桩形成闭合的止水帷幕;水泥搅拌桩的深度深至地面以下的中砂层2中部;
2、水泥搅拌桩顶部内侧通过向下倾斜25度,长度1.2米的锚管6与基坑侧壁锚固;水泥搅拌桩顶部内侧采用C20混凝土喷射护面7将锚管端部封闭;
3、第一级降水井施工;
4、基坑内第一级降水,水位降低设计要求,进行第一阶段土方开挖,同时也进行桩基施工。
第二级按以下步骤施工:
1、二级支护采用HN700×300×13×24型钢桩,止水帷幕采用三轴水泥搅拌桩9,兼作H型钢桩8***桩孔,桩径为??850×600mm;
2、三轴水泥搅拌桩施工步骤主要为:搅拌桩机就位→边搅拌边喷浆下沉→复搅提升→***H型钢桩;
3、扩孔式预应力土层锚杆施工;扩孔锚杆的施工顺序主要为:锚杆制作→放样、定位→自由段钻孔→锚固段扩孔注浆→安放锚杆→二次注浆→养护→张拉锁定;
4、扩孔式预应力土层锚杆有效孔径不少于??350mm,锚杆12的拉杆采用?? 25精轧螺纹钢,σ s =830N/mm
5、二级支护桩的钢筋混凝土冠梁13施工;
6、第二级降水井施工及降水;
7、地下室第二阶段土方开挖;
8、地下室结构施工。
最后施工如图1所示的道路10和排水沟11。

Claims (5)

1. 一种地下室无水平支撑基坑的施工方法,其特征在于:该方法采用二级基坑支护法进行施工;第一级是先沿地下室外缘施工一圈闭合的水泥搅拌桩,利用水泥搅拌桩在地下室外缘形成闭合的止水帷幕;然后在闭合的止水帷幕内通过降水井降低地下水位,进行第一阶段土方开挖,并同时完成预制管柱的施工;第二级是采用SMW工法完成基坑的二级支护和止水帷幕,然后再进行以下土方的开挖。
2.根据权利要求1所述地下室无水平支撑基坑的施工方法,其特征在于:所述水泥搅拌桩的深度深至地面以下的中砂层中部,水泥搅拌桩顶部内侧通过向下倾斜25度,长度1.2米的锚管与基坑锚固;水泥搅拌桩顶部内侧采用C20混凝土喷射护面将锚管端部封闭;水泥搅拌桩顶部外侧设有施工道路,施工道路与水泥搅拌桩之间设有排水沟。
3.根据权利要求1所述地下室无水平支撑基坑的施工方法,其特征在于:所述第一阶段土方开挖深度挖至杂填土层以下的粉砂层;第一阶段土方开挖的底部边缘设有排水沟。
4.根据权利要求1所述地下室无水平支撑基坑的施工方法,其特征在于:所述二级支护采用三轴水泥搅拌桩,三轴水泥搅拌桩的深度深至地面以下的砾砂层,并在三轴水泥搅拌桩内***H型钢,形成二级止水帷幕和二级支护结构;三轴水泥搅拌桩内侧通过向下倾斜30度,长度1.3米的锚杆与基坑锚固;三轴水泥搅拌桩顶部通过钢筋砼冠梁将锚杆端部封闭。
5.根据权利要求1所述地下室无水平支撑基坑的施工方法,其特征在于:所述以下土方的开挖深度挖至粉砂层以下的中砂层;土方开挖的底部边缘设有排水沟。
CN201410227624.7A 2014-05-27 2014-05-27 一种地下室无水平支撑基坑的施工方法 Active CN104131566B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410227624.7A CN104131566B (zh) 2014-05-27 2014-05-27 一种地下室无水平支撑基坑的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410227624.7A CN104131566B (zh) 2014-05-27 2014-05-27 一种地下室无水平支撑基坑的施工方法

Publications (2)

Publication Number Publication Date
CN104131566A true CN104131566A (zh) 2014-11-05
CN104131566B CN104131566B (zh) 2016-08-24

Family

ID=51804405

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410227624.7A Active CN104131566B (zh) 2014-05-27 2014-05-27 一种地下室无水平支撑基坑的施工方法

Country Status (1)

Country Link
CN (1) CN104131566B (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695446A (zh) * 2015-03-13 2015-06-10 朱奎 地下室支护施工方法
CN104831737A (zh) * 2015-04-29 2015-08-12 孔志坚 地铁车站地下室支护施工方法
CN104947686A (zh) * 2015-06-11 2015-09-30 叶长青 软土地区地下室支护结构
CN106400810A (zh) * 2015-12-29 2017-02-15 上海建工五建集团有限公司 基坑支护结构及其施工方法
CN110747861A (zh) * 2019-10-30 2020-02-04 中国建筑第四工程局有限公司 一种高水位深基坑开挖施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101270579A (zh) * 2007-03-19 2008-09-24 上海市第一建筑有限公司 深基坑向浅基坑的扩展施工的基坑围护方法
CN101892667A (zh) * 2010-07-23 2010-11-24 中国建筑第二工程局有限公司 基坑支护装置及施工方法
CN102108708A (zh) * 2010-12-16 2011-06-29 张继红 一种复合锚杆基坑围护结构及其施工方法、所用的水泥土开槽器
CN203256751U (zh) * 2013-05-22 2013-10-30 中国建筑第八工程局有限公司 软土地基深基坑支护结构
CN103603357A (zh) * 2013-10-12 2014-02-26 姚攀峰 一种多平台无内支撑自防水基坑围护结构及其施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101270579A (zh) * 2007-03-19 2008-09-24 上海市第一建筑有限公司 深基坑向浅基坑的扩展施工的基坑围护方法
CN101892667A (zh) * 2010-07-23 2010-11-24 中国建筑第二工程局有限公司 基坑支护装置及施工方法
CN102108708A (zh) * 2010-12-16 2011-06-29 张继红 一种复合锚杆基坑围护结构及其施工方法、所用的水泥土开槽器
CN203256751U (zh) * 2013-05-22 2013-10-30 中国建筑第八工程局有限公司 软土地基深基坑支护结构
CN103603357A (zh) * 2013-10-12 2014-02-26 姚攀峰 一种多平台无内支撑自防水基坑围护结构及其施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄伟达: ""SMW工法及扩孔锚杆在深大基坑中的工程实践"", 《岩土工程学报》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695446A (zh) * 2015-03-13 2015-06-10 朱奎 地下室支护施工方法
CN104695446B (zh) * 2015-03-13 2016-08-24 朱奎 地下室支护施工方法
CN104831737A (zh) * 2015-04-29 2015-08-12 孔志坚 地铁车站地下室支护施工方法
CN105926671A (zh) * 2015-04-29 2016-09-07 孔志坚 地铁车站的地下室支护施工技术
CN105926670A (zh) * 2015-04-29 2016-09-07 孔志坚 地铁车站的地下室施工方法
CN105926671B (zh) * 2015-04-29 2018-02-27 孔志坚 地铁车站的地下室支护施工技术
CN105926670B (zh) * 2015-04-29 2018-03-02 孔志坚 地铁车站的地下室施工方法
CN104947686A (zh) * 2015-06-11 2015-09-30 叶长青 软土地区地下室支护结构
CN106400810A (zh) * 2015-12-29 2017-02-15 上海建工五建集团有限公司 基坑支护结构及其施工方法
CN110747861A (zh) * 2019-10-30 2020-02-04 中国建筑第四工程局有限公司 一种高水位深基坑开挖施工方法

Also Published As

Publication number Publication date
CN104131566B (zh) 2016-08-24

Similar Documents

Publication Publication Date Title
CN108868778B (zh) 一种大型地下结构非开挖修建方法
CN202969392U (zh) 复杂地质深基坑联合支护
CN105201516B (zh) 一种地铁车站主体结构及其四联拱pba暗挖施工方法
CN110905530B (zh) 穿越断层破碎带的富水软岩隧道稳定性控制施工方法
CN106013053B (zh) 一种用于建造地下车库沉井的钢板桩支护施工方法
CN105064397A (zh) 一种在地铁区间盾构隧道基础上扩挖车站的明挖施工方法
CN105804119A (zh) 一桩二用地下廊道结构及其施工方法
CN111502696A (zh) 暗挖隧道的密网式超前支护***及施工方法
CN110566223B (zh) 一种深埋pba地铁车站断面设计方法
CN105804089A (zh) 一种原深基坑施工后局部增深支护体系及其施工方法
CN112160755B (zh) 一种先行施工盾构隧道后扩挖车站的地铁线路施工方法
CN104131566B (zh) 一种地下室无水平支撑基坑的施工方法
CN112663625A (zh) 一种高寒区浅埋偏压软弱围岩隧道洞口施工及防护方法
CN103452120B (zh) 一种用于基坑支护的高强预应力管桩的桩顶冠梁结构及其施工方法
JP2024007536A (ja) 大深度地下鉄駅における縦方向に直交する突き出し型風道構造及び施工方法
CN111734425A (zh) 一种下穿机场航站楼的暗挖隧道的施工方法
CN211500658U (zh) 一种适用于砂土地基的浅埋近接隧道支护结构
CN102330436B (zh) 一种用于半岩土层超深圆形旋流池的组合支护结构及方法
CN105442605A (zh) 拔出phc桩再利用于深基坑支护施工方法
CN113236259A (zh) 一种团结隧道开挖及支护专项施工工艺
CN106930768A (zh) 隧洞施工方法及应用
CN110080779A (zh) 隧道隧底溶洞处理施工方法
CN110117959B (zh) 一种临近江河基坑支护施工方法
CN110259456B (zh) 一种隧道施工用的溶洞处理方法
CN108374674A (zh) 六导洞十二步地下空间开挖支护方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant