CN104074364A - Steel casting funnel-shaped structure pre-assembling positioning construction method - Google Patents

Steel casting funnel-shaped structure pre-assembling positioning construction method Download PDF

Info

Publication number
CN104074364A
CN104074364A CN201310102864.XA CN201310102864A CN104074364A CN 104074364 A CN104074364 A CN 104074364A CN 201310102864 A CN201310102864 A CN 201310102864A CN 104074364 A CN104074364 A CN 104074364A
Authority
CN
China
Prior art keywords
steel
casting
assembled
construction
welding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310102864.XA
Other languages
Chinese (zh)
Inventor
来彬
孙兴桥
马连云
谈顺富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310102864.XA priority Critical patent/CN104074364A/en
Publication of CN104074364A publication Critical patent/CN104074364A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to the field of building engineering, and discloses a steel casting funnel-shaped structure pre-assembling positioning construction method, which comprises the following construction work procedures that: after the manufacturing of steel casting components is completed, pre-assembling is carried out in a processing site, so flaws on the integral appearance of steel castings and difficult problems in the splicing process are trimmed and solved in factories; and then, the integral installation precision of the whole steel casing building is ensured through the special measurement and positioning installation technology in the construction sites. The construction technology has the advantages that the splicing precision of the medium-and-large-sized steel castings can be perfectly improved; detours are avoided in the similar structure construction in future; the construction progress is accelerated; the engineering quality is improved; the construction safety is ensured; and the economic cost is effectively saved.

Description

The pre-splicing dress positioning construction method of a kind of steel-casting funnel type structure
Technical field
The present invention relates to building engineering field, relate in particular to the pre-assembled steel member positioning construction method of a kind of bucket type.
Background technology
Along with the economic development of China, large building arises at the historic moment, the building of increasing steel work is rised sheer from level ground, in construction, assembled, the location construction of steel work is an important engineering node, steel work is in the past more regular, be generally i iron, it connects, and location is relatively easy and oneself is ripe.And assembled, the welding between some large-scale steel-castings and steel-casting at present, especially form huge special-shaped cast steel structure such as funnel type steel work with multiple steel-castings, constructional difficulties is higher, effective construction and assembling method are few especially, are current construction Difficulties urgently to be resolved hurrily.
Summary of the invention
In order to solve above technical problem, the invention provides the pre-splicing dress positioning construction method of a kind of steel-casting funnel type structure.It is characterized in that being formed by the following step: (1) steel-casting assembled in advance, lay 20mm thickness steel plate in assembled effective coverage, on steel plate, carry out that bearing is fixed and labeling projection coordinate position, on steel plate, place four H shaped steel along bearing, and be linked to be entirety, (2) plane moulding bed is set on the ground, adjacent steel-casting is carried out to ground assembling, and welding junction scab, appropriate position welded and installed hanger on the surface of steel-casting, at four baffle plates of welding suitable for reading of every joint steel-casting, (3) before assembled, first carry out setting up of scaffold, as the first support system of member, in corresponding height, constructor's operating platform is set simultaneously, (4) after scaffold setting completes, determine the position of column and ground support node according to figure paper size, projection goes out first position of inner side point topmost on the ground simultaneously.(5) in the time of first segment member in place, first choose one of them as reference for installation, check in turn radial distance and the hoop distance of all the other members and this reference feature, to determine the accurate location of member.(6) bearing place adopts otic placode and H shaped steel basis to be welded and fixed, and steel-casting and base plate carry out spot welding in part.When otic placode welding, (7) first segment in place and fixing after, need adjust according to member position the height of local support scaffold, as the vertical supporting of member, arrange at least together radially and hoop rigid support simultaneously, strengthen its stability, according to above identical operation sequence, carry out the in place of the second, three joint member.(8) again carrying out size checks, the elements of a fix point providing according to design, to high process control, adopt level gauge to measure, hoop positioning control takes anchor point to project on ground, relend the method that helps tape measure to check, for the deviation off-gage phenomenon occurring in compound nucleus process, adjust with jack, jack, be as the criterion until meet the demands, after all process steps such as (9) all completes, against assembled process, splice point bolt dismantled, the assembled otic placode welding on member need not cut off, and keeps on-site consolidation and uses.(10) after member has been dismantled, remove support scaffolding and other supports simultaneously, to again set up the support system that meets the assembled requirement of second segment, simultaneously to the H shaped steel of laying on steel plate surface adjust (11) second segment the assembled top using first paragraph one joint steel-casting as second segment bottommost one joint come assembled second segment, (12) repeating step (1) to (9) until all segmentations all complete, (13) steel-casting of pre-installing and dismantling is transported to on-the-spot installation, location, (14) full hall pin hand for on-the-spot construction pin hand getting, the same steel-casting installation location construction of setting up of full hall pin hand is synchronously carried out, set up certain altitude, one joint steel-casting is installed, then continue to set up and continue to construct, (15) after each joint steel-casting is in place, adopt and be welded to connect otic placode in butt weld place of each steel-casting temporarily, temporary fixed with high-strength bolt, adjust after position dimension, tight a bolt, (16) measurement of steel-casting absolute altitude relies on a measurement observation platform is set in center, the cast steel member that is centered around surrounding is accomplished to all standing, observation platform promotes along with the lifting of steel-casting setting height(from bottom), (17) measurement of steel-casting installation site adopts total powerstation chord position to measure outside member, prism set-point is set when measurement on steel-casting corner angle, designer provides the three-dimensional coordinate of this point to proofread and correct for in-site measurement, (18) after each steel-casting in same plane is all proofreaied and correct, immediately steel-casting radially and be arranged circumferentially rigid support, guarantee its resistance to overturning, (19) steel-casting welding, (20) repeat above-mentioned steps (15) to (19) until all installation welding is complete.
The present invention compared with prior art has following beneficial effect:
The invention provides the pre-splicing dress positioning construction method of a kind of steel-casting funnel type structure, can in the time of pre-installation, find in time and solve the problem of steel-casting in splicing, in construction, avoid detours, accelerating construction progress, improve workmanship, guarantee construction safety, effectively save financial cost, ensure in the time of practice of construction, can by overall large cast steel member assembled accurately.
Brief description of the drawings
Accompanying drawing described herein is used to provide a further understanding of the present invention, forms the application's a part, does not form inappropriate limitation of the present invention, in the accompanying drawings:
Fig. 1 is the general structure design sketch of large cast steel member of the present invention,
Fig. 2 is that the installation on ground in the present invention is laid steel plate and shaped steel schematic diagram,
Fig. 3 is the schematic diagram of pre-assembled segmentation of the present invention,
Fig. 4 is the scaffold floor map in pre-assembled segmentation of the present invention,
Rigid support schematic diagram when Fig. 5 is actual installation of the present invention,
Instrumentation plan when Fig. 6 is actual installation of the present invention,
The overall construction drawing of construction scaffolding when Fig. 7 is actual installation of the present invention and large cast steel member.
Detailed description of the invention
Describe the present invention in detail below in conjunction with accompanying drawing and specific embodiment, be used for explaining the present invention in this illustrative examples of the present invention and explanation, but not as a limitation of the invention.
The present embodiment provides a kind of steel-casting funnel type structure pre-splicing dress positioning construction method
(1) steel-casting is assembled in advance, lay 20mm thickness steel plate in assembled effective coverage, on steel plate, carry out that bearing is fixed and labeling projection coordinate position, on steel plate, place four H shaped steel along bearing, and be linked to be entirety, (2) plane moulding bed is set on the ground, adjacent steel-casting is carried out to ground assembling, and welding junction scab, appropriate position welded and installed hanger on the surface of steel-casting, at four baffle plates of welding suitable for reading of every joint steel-casting, (3) before assembled, first carry out setting up of scaffold, as the first support system of member, in corresponding height, constructor's operating platform is set simultaneously, (4) after scaffold setting completes, determine the position of column and ground support node according to figure paper size, projection goes out first position of inner side point topmost on the ground simultaneously.(5) in the time of first segment member in place, first choose one of them as reference for installation, check in turn radial distance and the hoop distance of all the other members and this reference feature, to determine the accurate location of member.(6) bearing place adopts otic placode and H shaped steel basis to be welded and fixed, and steel-casting and base plate carry out spot welding in part.When otic placode welding, (7) first segment in place and fixing after, need adjust according to member position the height of local support scaffold, as the vertical supporting of member, arrange at least together radially and hoop rigid support simultaneously, strengthen its stability, according to above identical operation sequence, carry out the in place of the second, three joint member.(8) again carrying out size checks, the elements of a fix point providing according to design, to high process control, adopt level gauge to measure, hoop positioning control takes anchor point to project on ground, relend the method that helps tape measure to check, for the deviation off-gage phenomenon occurring in compound nucleus process, adjust with jack, jack, be as the criterion until meet the demands, after all process steps such as (9) all completes, against assembled process, splice point bolt dismantled, the assembled otic placode welding on member need not cut off, and keeps on-site consolidation and uses.(10) after member has been dismantled, remove support scaffolding and other supports simultaneously, to again set up the support system that meets the assembled requirement of second segment, simultaneously to the H shaped steel of laying on steel plate surface adjust (11) second segment the assembled top using first paragraph one joint steel-casting as second segment bottommost one joint come assembled second segment, (12) repeating step (1) to (9) until all segmentations all complete, (13) steel-casting of pre-installing and dismantling is transported to on-the-spot installation, location, (14) full hall pin hand for on-the-spot construction pin hand getting, the same steel-casting installation location construction of setting up of full hall pin hand is synchronously carried out, set up certain altitude, one joint steel-casting is installed, then continue to set up and continue to construct, (15) after each joint steel-casting is in place, adopt and be welded to connect otic placode in butt weld place of each steel-casting temporarily, temporary fixed with high-strength bolt, adjust after position dimension, tight a bolt, (16) measurement of steel-casting absolute altitude relies on a measurement observation platform is set in center, the cast steel member that is centered around surrounding is accomplished to all standing, observation platform promotes along with the lifting of steel-casting setting height(from bottom), (17) measurement of steel-casting installation site adopts total powerstation chord position to measure outside member, prism set-point is set when measurement on steel-casting corner angle, designer provides the three-dimensional coordinate of this point to proofread and correct for in-site measurement, (18) after each steel-casting in same plane is all proofreaied and correct, immediately steel-casting radially and be arranged circumferentially rigid support, guarantee its resistance to overturning, (19) steel-casting welding, (20) repeat above-mentioned steps (15) to (19) until all installation welding is complete.
The technical scheme above embodiment of the present invention being provided is described in detail, applied principle and the embodiment of specific case to the embodiment of the present invention herein and set forth, the explanation of above embodiment is only applicable to help to understand the principle of the embodiment of the present invention; , for one of ordinary skill in the art, according to the embodiment of the present invention, in detailed description of the invention and range of application, all will change, in sum, this description should not be construed as limitation of the present invention meanwhile.

Claims (1)

1. the pre-splicing dress positioning construction method of steel-casting funnel type structure.It is characterized in that being formed by the following step: (1) steel-casting assembled in advance, lay 20mm thickness steel plate in assembled effective coverage, on steel plate, carry out that bearing is fixed and labeling projection coordinate position, on steel plate, place four H shaped steel along bearing, and be linked to be entirety, (2) plane moulding bed is set on the ground, adjacent steel-casting is carried out to ground assembling, and welding junction scab, appropriate position welded and installed hanger on the surface of steel-casting, at four baffle plates of welding suitable for reading of every joint steel-casting, (3) before assembled, first carry out setting up of scaffold, as the first support system of member, in corresponding height, constructor's operating platform is set simultaneously, (4) after scaffold setting completes, determine the position of column and ground support node according to figure paper size, projection goes out first position of inner side point topmost on the ground simultaneously.(5) in the time of first segment member in place, first choose one of them as reference for installation, check in turn radial distance and the hoop distance of all the other members and this reference feature, to determine the accurate location of member.(6) bearing place adopts otic placode and H shaped steel basis to be welded and fixed, and steel-casting and base plate carry out spot welding in part.When otic placode welding, (7) first segment in place and fixing after, need adjust according to member position the height of local support scaffold, as the vertical supporting of member, arrange at least together radially and hoop rigid support simultaneously, strengthen its stability, according to above identical operation sequence, carry out the in place of the second, three joint member.(8) again carrying out size checks, the elements of a fix point providing according to design, to high process control, adopt level gauge to measure, hoop positioning control takes anchor point to project on ground, relend the method that helps tape measure to check, for the deviation off-gage phenomenon occurring in compound nucleus process, adjust with jack, jack, be as the criterion until meet the demands, after all process steps such as (9) all completes, against assembled process, splice point bolt dismantled, the assembled otic placode welding on member need not cut off, and keeps on-site consolidation and uses.(10) after member has been dismantled, remove support scaffolding and other supports simultaneously, to again set up the support system that meets the assembled requirement of second segment, simultaneously to the H shaped steel of laying on steel plate surface adjust (11) second segment the assembled top using first paragraph one joint steel-casting as second segment bottommost one joint come assembled second segment, (12) repeating step (1) to (9) until all segmentations all complete, (13) steel-casting of pre-installing and dismantling is transported to on-the-spot installation, location, (14) full hall pin hand for on-the-spot construction pin hand getting, the same steel-casting installation location construction of setting up of full hall pin hand is synchronously carried out, set up certain altitude, one joint steel-casting is installed, then continue to set up and continue to construct, (15) after each joint steel-casting is in place, adopt and be welded to connect otic placode in butt weld place of each steel-casting temporarily, temporary fixed with high-strength bolt, adjust after position dimension, tight a bolt, (16) measurement of steel-casting absolute altitude relies on a measurement observation platform is set in center, the cast steel member that is centered around surrounding is accomplished to all standing, observation platform promotes along with the lifting of steel-casting setting height(from bottom), (17) measurement of steel-casting installation site adopts total powerstation chord position to measure outside member, prism set-point is set when measurement on steel-casting corner angle, designer provides the three-dimensional coordinate of this point to proofread and correct for in-site measurement, (18) after each steel-casting in same plane is all proofreaied and correct, immediately steel-casting radially and be arranged circumferentially rigid support, guarantee its resistance to overturning, (19) steel-casting welding, (20) repeat above-mentioned steps (15) to (19) until all installation welding is complete.
CN201310102864.XA 2013-03-28 2013-03-28 Steel casting funnel-shaped structure pre-assembling positioning construction method Pending CN104074364A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310102864.XA CN104074364A (en) 2013-03-28 2013-03-28 Steel casting funnel-shaped structure pre-assembling positioning construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310102864.XA CN104074364A (en) 2013-03-28 2013-03-28 Steel casting funnel-shaped structure pre-assembling positioning construction method

Publications (1)

Publication Number Publication Date
CN104074364A true CN104074364A (en) 2014-10-01

Family

ID=51595934

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310102864.XA Pending CN104074364A (en) 2013-03-28 2013-03-28 Steel casting funnel-shaped structure pre-assembling positioning construction method

Country Status (1)

Country Link
CN (1) CN104074364A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104763152A (en) * 2015-04-28 2015-07-08 中国十九冶集团有限公司 Construction method of steel structure water tower basket support
CN106960110A (en) * 2017-04-12 2017-07-18 中国二十二冶集团有限公司 The connection method of steel-casting comprising multinode
CN113089820A (en) * 2021-04-09 2021-07-09 上海通正铝结构建设科技有限公司 Construction method of single-layer oblique-crossing special-shaped curved surface aluminum alloy structure in limited space
CN113154422A (en) * 2021-04-14 2021-07-23 山东国舜建设集团有限公司 Construction process for adding baffle door to steel chimney and chimney structure thereof
CN113323153A (en) * 2021-06-08 2021-08-31 中国建筑第八工程局有限公司 Bending-twisting aluminum alloy structure in existing complex space and construction method
CN115506606A (en) * 2022-10-28 2022-12-23 中国二十二冶集团有限公司 Construction method for central steel column of high formwork of tubular structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09317183A (en) * 1996-05-28 1997-12-09 Sato Kogyo Co Ltd Construction method of building
JPH10219822A (en) * 1997-02-10 1998-08-18 Shinichi Tsumura Steel framework construction method for building
CN102102444A (en) * 2009-12-18 2011-06-22 上海市机械施工有限公司 Assembling and positioning construction method of large steel casting members
CN102108788A (en) * 2010-12-31 2011-06-29 华煜建设集团有限公司 Method for constructing hanging in the air large-span support
CN102864936A (en) * 2012-10-10 2013-01-09 江苏南通六建建设集团有限公司 Combination lifting construction method for large-scale high hollow building roof of steel structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09317183A (en) * 1996-05-28 1997-12-09 Sato Kogyo Co Ltd Construction method of building
JPH10219822A (en) * 1997-02-10 1998-08-18 Shinichi Tsumura Steel framework construction method for building
CN102102444A (en) * 2009-12-18 2011-06-22 上海市机械施工有限公司 Assembling and positioning construction method of large steel casting members
CN102108788A (en) * 2010-12-31 2011-06-29 华煜建设集团有限公司 Method for constructing hanging in the air large-span support
CN102864936A (en) * 2012-10-10 2013-01-09 江苏南通六建建设集团有限公司 Combination lifting construction method for large-scale high hollow building roof of steel structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
来彬等: "上海文化广场钢屋盖异形区域的结构施工", 《建筑施工》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104763152A (en) * 2015-04-28 2015-07-08 中国十九冶集团有限公司 Construction method of steel structure water tower basket support
CN106960110A (en) * 2017-04-12 2017-07-18 中国二十二冶集团有限公司 The connection method of steel-casting comprising multinode
CN113089820A (en) * 2021-04-09 2021-07-09 上海通正铝结构建设科技有限公司 Construction method of single-layer oblique-crossing special-shaped curved surface aluminum alloy structure in limited space
CN113154422A (en) * 2021-04-14 2021-07-23 山东国舜建设集团有限公司 Construction process for adding baffle door to steel chimney and chimney structure thereof
CN113323153A (en) * 2021-06-08 2021-08-31 中国建筑第八工程局有限公司 Bending-twisting aluminum alloy structure in existing complex space and construction method
CN115506606A (en) * 2022-10-28 2022-12-23 中国二十二冶集团有限公司 Construction method for central steel column of high formwork of tubular structure

Similar Documents

Publication Publication Date Title
CN102102444B (en) Assembling and positioning construction method of large steel casting members
CN104074364A (en) Steel casting funnel-shaped structure pre-assembling positioning construction method
CN204703182U (en) Crab-bolt stock
CN101736698B (en) Accurate positioning method for cable-stayed bridge pylon cable guide pipe
CN103556836B (en) Spherical reticulated shells assembling and construction method under restricted clearance condition
CN103526954B (en) Construction method of overweight precision embedded part
CN105019665A (en) Method for mounting long-span structure beam based on total station
CN105887915A (en) Foundation bolt locating method based on BIM
CN104674665B (en) Large-spatial structures vestibule bridge installation method
CN104763156A (en) Assembling method of steel safety housing bottom seal head of nuclear power plant
CN104141318A (en) Installation and construction method of column base of large-diameter steel pipe column
Liu et al. Assembly study for HL-2M tokamak
CN103088843B (en) Pipe gallery embedded iron parts construction method of installation
CN111254835A (en) Continuous matching construction method for steel box girder segments in factory
CN107274942A (en) The installation method of AP1000 nuclear power stations middle and lower part in-pile component
CN204001428U (en) A kind of Large-diameter Steel tubing string suspension column is installed pre-buried location structure and suspension column structure thereof
CN201560398U (en) Inner steel mould for accurately positioning tower column cable sleeves of cable-stayed bridge
CN109057366A (en) A kind of steel construction spiral stairs segmented assembly method
CN103696369B (en) Steel box girder segment four point positioning mounting method
CN115977401A (en) High-altitude installation method for steel structure
CN103470036B (en) A kind of outer construction method of choosing structure
CN104746433A (en) Rotating hinge positioning method
CN204001429U (en) A kind of Large-diameter Steel tubing string suspension column structure and suspension column absolute altitude adjustment fixing structure thereof
CN112096090B (en) Large-span space pipe truss single-point support butt joint step-by-step unloading device and construction method
CN105040992A (en) Reverse inverted-insertion type construction method for structural steel columns

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
DD01 Delivery of document by public notice

Addressee: Lai Bin

Document name: Notification of Publication and of Entering the Substantive Examination Stage of the Application for Invention

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20141001