CN103983148B - Tunnel photoface exploision full-automatic big gun hole setting out method - Google Patents

Tunnel photoface exploision full-automatic big gun hole setting out method Download PDF

Info

Publication number
CN103983148B
CN103983148B CN201410167544.7A CN201410167544A CN103983148B CN 103983148 B CN103983148 B CN 103983148B CN 201410167544 A CN201410167544 A CN 201410167544A CN 103983148 B CN103983148 B CN 103983148B
Authority
CN
China
Prior art keywords
tunnel
setting
big gun
full
gun hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410167544.7A
Other languages
Chinese (zh)
Other versions
CN103983148A (en
Inventor
高飞
李波
刘学伟
潘红桂
唐满轲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of CTCE Group
Original Assignee
Second Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of CTCE Group filed Critical Second Engineering Co Ltd of CTCE Group
Priority to CN201410167544.7A priority Critical patent/CN103983148B/en
Publication of CN103983148A publication Critical patent/CN103983148A/en
Application granted granted Critical
Publication of CN103983148B publication Critical patent/CN103983148B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of tunnel photoface exploision full-automatic big gun hole setting out method, it is instrument and equipment and software kit selection, data inputting, the operation of setting-out job site, total powerstation full-automatic big gun hole respectively that the method mainly comprises three steps, the maximum advantage of the inventive method is to improve setting-out efficiency, control photoface exploision quality, in constructing tunnel, control there is remarkable result for out break; Save skilled workforce compared with the setting out method of traditional big gun hole, reduce tunneling operation circulation timei, effectively control out break, reduce the amount of backbreaking.

Description

Tunnel photoface exploision full-automatic big gun hole setting out method
Technical field
The present invention relates to blasting method, particularly relate to a kind of full-automatic big gun hole setting out method adopted in tunnel in photoface exploision digging process.
Background technology
Current most of constructing tunnel still adopts Mining Method, and the method for explosion periphery hole measured by artificial steel tape.In the construction of growing up curved tunnel, the method more and more can not meet fast, the requirement of the construction that becomes more meticulous.Newly-built the long 1343m of Tang Tielu pearl ridge tunnel entrance that my company undertakes the construction of, rear hedge tunnel exit 1585m, two stratum, tunnel are Yin Zhiji (γ 5) granite.Granite: canescence folder flesh pink, middle coarse grained texture, massive structure, joint fissure is comparatively grown, and master joint occurrence is 240 ° of ∠ 75 ° and 95 ° of ∠ 80 °, and spacing is respectively 40 ~ 80cm and 30 ~ 100cm.II, III grade of country rock accounts for more than 75% of construction mileage, all needs to carry out photoface exploision, requires high to bursting quality.There is some shortcoming according to traditional setting out method: one is that the setting-out time is longer, affect tunnel operation circulation; Two is oxygen evolution rate lower (adopting traditional centering to draw chi positioning mode etc.), the more difficult control of Tunnel Overbreak & Underbreak; Three is that layout point is less, and workman executes and bores randomness greatly.Therefore tunnel photoface exploision full-automatic big gun hole setting out method directly has influence on tunnel photoface exploision quality and working procedure duration.
Summary of the invention
Goal of the invention of the present invention is the shortcoming in order to overcome above-mentioned background technology, needs according to on-the-spot photoface exploision, has invented a set of high speed, accurate, full-automatic big gun hole setting out method.
Technical scheme of the present invention is: a kind of tunnel photoface exploision full-automatic big gun hole setting out method, the method comprises the steps:
Step one: instrument and equipment and software kit are selected;
Instrument and equipment is selected to mainly contain: to select the total powerstation that can carry out fully-automatic laser non-prism measuring system, supporting transect layout and big gun hole setting-out software, reflecting piece, tripod, single prism group;
Step 2: data inputting;
First the operation in newly-built this tunnel in software, secondly typing tunnel cross-section, tunnel line data and horizontal curve, vertical curve, CAD can be adopted to scheme direct lead-in mode when profile data typing, must note the relation between the selection of datum line and datum line and tunnel line when typing, the last big gun hole data corresponding according to tunnel design of smooth blasting carries out selecting and typing reliever section;
Step 3: setting-out job site, total powerstation full-automatic big gun hole operates;
(1) backsight point is arranged: backsight point adopts a control point and a construction to draw a composition, in Tunnel, control point adopts two-conductor line to arrange, apart from minimum be 150m, be 200m to the maximum, form closed hoop with hole outer conductor accurately to measure, construction is drawn some tunnel in-cavity construction for convenience and is buried underground a little temporarily, be arranged between two control points, be arranged to two point, distance between two points 5m is distributed in center line both sides, tunnel, hole inside conductor point open traverse is utilized to measure, in hole, the measurement of higher degree all adopts three, fourth-order leveling, in tunnel, measurement point protection adopts Φ 100mm steel pipe to protect as casing,
(2) establish station: adopt Free Station mode and resection to establish station efficient and convenient, but will notice that rear intersection point distance must be greater than forward sight and after two, intersection point can not at same straight line, answer minimum 30 ° of selected angle, when maximum 120 °, precision is higher;
Secondly (3) setting-out: first carry out the selection of circuit data, according to explosion design alternative suitable cross-section and periphery hole section and reliever section, finally by the full-automatic big gun hole setting-out of multi-functional excavation stand; In setting-out process when face country rock is poor or in tunnel air quality poor can not reflects laser and measurement data time can realize measuring in conjunction with reflecting piece, and setting-out efficiency can be improved; The mode lengthening spread pen can be taked when adopting spread pen, paint marks point;
(4) technical force's configuration: full-automatic big gun hole setting out method need configure two technical staff, a people puts mirror, a people to backsight and face measuring point mark;
(5) tunnel photoface exploision out break measure: after this circulation setting-out terminates on the quick-fried out break inspection of a circulation light; Adopt section survey software full-automatic or manual random measurement can go out section out break situation, if adopt all automatic measurement pattern automatically to carry out section survey when over excavation and under excavation area is larger, otherwise it is to adopt random detection pattern only to measure owing to dig position that local exists out break, setting-out terminates rear section survey result directly can go out measurement report on computer section software, can control out break better like this and adjust sun-exposed skin in time.
The invention has the beneficial effects as follows: the maximum advantage of the inventive method is to improve setting-out efficiency, control photoface exploision quality, in constructing tunnel, control there is remarkable result for out break.Save skilled workforce compared with the setting out method of traditional big gun hole, reduce tunneling operation circulation timei, effectively control out break, reduce the amount of backbreaking.
Accompanying drawing explanation
Fig. 1 is step schematic diagram of the present invention.
Detailed description of the invention
The present embodiment is a kind of tunnel photoface exploision full-automatic big gun hole setting out method, it is characterized in that the method comprises the steps:
Step one: instrument and equipment and software kit are selected;
Instrument and equipment is selected to mainly contain: to select the total powerstation that can carry out fully-automatic laser non-prism measuring system, supporting transect layout and big gun hole setting-out software, reflecting piece, tripod, single prism group;
Step 2: data inputting;
First the operation in newly-built this tunnel in software, secondly typing tunnel cross-section, tunnel line data and horizontal curve, vertical curve, CAD can be adopted to scheme direct lead-in mode when profile data typing, must note the relation between the selection of datum line and datum line and tunnel line when typing, the last big gun hole data corresponding according to tunnel design of smooth blasting carries out selecting and typing reliever section;
Step 3: setting-out job site, total powerstation full-automatic big gun hole operates;
(1) backsight point is arranged: backsight point adopts a control point and a construction to draw a composition, in Tunnel, control point adopts two-conductor line to arrange, apart from minimum be 150m, be 200m to the maximum, form closed hoop with hole outer conductor accurately to measure, construction is drawn some tunnel in-cavity construction for convenience and is buried underground a little temporarily, be arranged between two control points, be arranged to two point, distance between two points 5m is distributed in center line both sides, tunnel, hole inside conductor point open traverse is utilized to measure, in hole, the measurement of higher degree all adopts three, fourth-order leveling, in tunnel, measurement point protection adopts Φ 100mm steel pipe to protect as casing,
(2) establish station: adopt Free Station mode and resection to establish station efficient and convenient, but will notice that rear intersection point distance must be greater than forward sight and after two, intersection point can not at same straight line, answer minimum 30 ° of selected angle, when maximum 120 °, precision is higher;
Secondly (3) setting-out: first carry out the selection of circuit data, according to explosion design alternative suitable cross-section and periphery hole section and reliever section, finally by the full-automatic big gun hole setting-out of multi-functional excavation stand; In setting-out process when face country rock is poor or in tunnel air quality poor can not reflects laser and measurement data time can realize measuring in conjunction with reflecting piece, and setting-out efficiency can be improved; The mode lengthening spread pen can be taked when adopting spread pen, paint marks point;
(4) technical force's configuration: full-automatic big gun hole setting out method need configure two technical staff, a people puts mirror, a people to backsight and face measuring point mark;
(5) tunnel photoface exploision out break measure: after this circulation setting-out terminates on the quick-fried out break inspection of a circulation light; Adopt section survey software full-automatic or manual random measurement can go out section out break situation, if adopt all automatic measurement pattern automatically to carry out section survey when over excavation and under excavation area is larger, otherwise it is to adopt random detection pattern only to measure owing to dig position that local exists out break, setting-out terminates rear section survey result directly can go out measurement report on computer section software, can control out break better like this and adjust sun-exposed skin in time.

Claims (1)

1. a tunnel photoface exploision full-automatic big gun hole setting out method, is characterized in that the method comprises the steps:
Step one: instrument and equipment and software kit are selected
Instrument and equipment is selected to mainly contain: to select the total powerstation that can carry out fully-automatic laser non-prism measuring system, supporting transect layout and big gun hole setting-out software, reflecting piece, tripod, single prism group;
Step 2: data inputting
First the operation in newly-built this tunnel in software, secondly typing tunnel cross-section, tunnel line data and horizontal curve, vertical curve, adopt CAD to scheme direct lead-in mode when profile data typing, must note the relation between the selection of datum line and datum line and tunnel line when typing, the last big gun hole data corresponding according to tunnel design of smooth blasting carries out selecting and typing reliever section;
Step 3: setting-out job site, total powerstation full-automatic big gun hole operates
(1) backsight point is arranged: backsight point adopts a control point and a construction to draw a composition, in Tunnel, control point adopts two-conductor line to arrange, apart from minimum be 150m, be 200m to the maximum, form closed hoop with hole outer conductor accurately to measure, construction is drawn some tunnel in-cavity construction for convenience and is buried underground a little temporarily, be arranged between two control points, be arranged to two point, distance between two points 5m is distributed in center line both sides, tunnel, hole inside conductor point open traverse is utilized to measure, in hole, the measurement of higher degree all adopts three, fourth-order leveling, in tunnel, measurement point protection adopts Φ 100mm steel pipe to protect as casing,
(2) establish station: adopt Free Station mode and resection to establish station efficient and convenient, but will notice that rear intersection point distance must be greater than forward sight and after two, intersection points can not at same straight line, when answering selected angle 30 ° ~ 120 °, precision is higher;
Secondly (3) setting-out: first carry out the selection of circuit data, according to explosion design alternative suitable cross-section and periphery hole section and reliever section, finally by the full-automatic big gun hole setting-out of multi-functional excavation stand; In setting-out process when face country rock is poor or in tunnel air quality poor can not reflects laser and measurement data time can realize measuring in conjunction with reflecting piece, and setting-out efficiency can be improved; The mode lengthening spread pen is taked when adopting spread pen, paint marks point;
(4) technical force's configuration: full-automatic big gun hole setting out method need configure two technical staff, a people puts mirror, a people to backsight and face measuring point mark;
(5) tunnel photoface exploision out break measure: after this circulation setting-out terminates on the quick-fried out break inspection of a circulation light; Adopt section survey software full-automatic or manual random measurement can go out section out break situation, if adopt all automatic measurement pattern automatically to carry out section survey when over excavation and under excavation area is larger, otherwise local adopts random detection pattern only to measure owing to dig position when there is out break, setting-out terminates rear section survey result and directly go out measurement report on computer section software, can control out break better like this and adjust sun-exposed skin in time.
CN201410167544.7A 2014-04-24 2014-04-24 Tunnel photoface exploision full-automatic big gun hole setting out method Active CN103983148B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410167544.7A CN103983148B (en) 2014-04-24 2014-04-24 Tunnel photoface exploision full-automatic big gun hole setting out method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410167544.7A CN103983148B (en) 2014-04-24 2014-04-24 Tunnel photoface exploision full-automatic big gun hole setting out method

Publications (2)

Publication Number Publication Date
CN103983148A CN103983148A (en) 2014-08-13
CN103983148B true CN103983148B (en) 2015-10-07

Family

ID=51275214

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410167544.7A Active CN103983148B (en) 2014-04-24 2014-04-24 Tunnel photoface exploision full-automatic big gun hole setting out method

Country Status (1)

Country Link
CN (1) CN103983148B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108362215B (en) * 2017-10-09 2021-07-16 同济大学 Automatic deformation monitoring system and method for free station setting of multiple measuring robots
CN107816981A (en) * 2017-10-20 2018-03-20 中建三局第建设工程有限责任公司 Tunnel intelligent construction survey setting out method based on BIM
CN108387221A (en) * 2018-01-17 2018-08-10 西安理工大学 A kind of tunnel excavation speedy lofting device and setting out method
CN108398064A (en) * 2018-03-21 2018-08-14 福建海峡科化富兴建设工程有限公司 A kind of room-and-pillar method goaf partition board construction of explosion setting out method
CN109000526B (en) * 2018-08-21 2021-04-20 四川中鼎***工程有限公司 Total station lofting hole distribution method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101487376A (en) * 2009-02-14 2009-07-22 中国葛洲坝集团股份有限公司 One-time excavation construction method for large-diameter large-depth pressure regulating well pilot shaft
CN102679826A (en) * 2012-03-27 2012-09-19 中钢集团武汉安全环保研究院有限公司 Method for precisely excavating directional window on high and large concrete chimney
CN103017620A (en) * 2012-11-28 2013-04-03 泰兴市第一建筑安装工程有限公司 Controlled blasting construction method for rock foundation pit
CN103017621A (en) * 2012-11-29 2013-04-03 青海山金矿业有限公司 Blasting method for reducing depletion in steeply inclined thin ore body recovery
CN103323530A (en) * 2013-06-18 2013-09-25 山东科技大学 Method for detecting stability of roadway group surrounding rock by utilizing blasting operation vibration waves
CN103276649B (en) * 2013-06-21 2015-09-09 云南云岭高速公路建设集团有限公司 Side is had to limit layering many thickness Stone Filled Embankment construction method

Also Published As

Publication number Publication date
CN103983148A (en) 2014-08-13

Similar Documents

Publication Publication Date Title
CN103983148B (en) Tunnel photoface exploision full-automatic big gun hole setting out method
CN106382121B (en) A kind of measuring method of subway tunnel shield driving
CN105178967B (en) Development machine autonomous positioning orientation system and method
CN106123776B (en) A kind of push pipe intelligence jacking measuring system and measurement method
CN106840129B (en) Method for rapidly measuring three-dimensional coordinates of center of subway segment
CN104251688A (en) Method for linear directional measurement by utilizing laser in pipe jacking engineering
CN101368472A (en) Method for accurately positioning and orienting drill hole of top arch
CN203422091U (en) Device for dynamically measuring positions and attitudes of push bench in real time
CN105865416A (en) Leveling rod suspended leveling method for settlement monitoring
CN204007587U (en) A kind of automatic measurement guidance system about jacking construction
CN101705814B (en) Advancing direction measurement method of vertical and slant orepasses
CN205537635U (en) Simple and easy control survey system in long distance straight line push pipe center
CN102636153A (en) Observation method of crown settlement and periphery convergence of tunnel
CN109403984A (en) Long distance curved pipe jacking automatic guiding system
CN206223091U (en) A kind of push pipe intelligence jacking measuring system
CN107238377B (en) A kind of measurement method suitable for large underground hole speedy lofting bolthole position
CN204831145U (en) Porthole verifying ware
CN108896015B (en) Double-laser collimation measuring method for tunnel structural surface attitude
CN112146588A (en) Method for rapidly judging blasting quality of mine roadway excavation
CN109184702A (en) The measurement method of out break is controlled under the conditions of the more curves of Tunnel Engineering, minor radius
CN209413903U (en) Long distance curved pipe jacking automatic guiding system
CN102374861A (en) Centering under point operation method of total station or target for generating plumb laser beam
CN105627985A (en) Mine shaft elevation transmission method
CN106289164A (en) A kind of cavern section method for fast measuring
CN102636101B (en) Roadway surface convergence measuring method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant