CN103953188A - High-altitude supporting mold of structureless floor slab - Google Patents

High-altitude supporting mold of structureless floor slab Download PDF

Info

Publication number
CN103953188A
CN103953188A CN201410139446.2A CN201410139446A CN103953188A CN 103953188 A CN103953188 A CN 103953188A CN 201410139446 A CN201410139446 A CN 201410139446A CN 103953188 A CN103953188 A CN 103953188A
Authority
CN
China
Prior art keywords
girder steel
floor
floor slab
steel beams
temporary platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410139446.2A
Other languages
Chinese (zh)
Inventor
李建军
赵旭光
张巍
肖晨晖
王炜
郭鑫
陈鼎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN YIJIANG CONSTRUCTION ENGINEERING Co Ltd
Original Assignee
TIANJIN YIJIANG CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN YIJIANG CONSTRUCTION ENGINEERING Co Ltd filed Critical TIANJIN YIJIANG CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201410139446.2A priority Critical patent/CN103953188A/en
Publication of CN103953188A publication Critical patent/CN103953188A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention provides a high-altitude supporting mold of a structureless floor slab. The structure of the high-altitude supporting mold is characterized in that a temporary platform is erected on a horizontal structure at the periphery of the structureless floor slab area and comprises main steel beams, secondary steel beams and scaffold boards; the main steel beams are erected on the floor slab of the base structure of a frame body of the horizontal structure at the periphery of the structureless floor slab area; the two side surfaces of the main steel beam are fixed with structure beam plates of a construction layer; the secondary steel beams are erected on the main steel beams and are fixedly connected with the main steel beams; and the scaffold boards are laid on the secondary steel beams to form the temporary platform. The high-altitude supporting mold provided by the invention has the effects that the horizontal structure at the periphery is reasonably utilized for erecting the temporary platform, the applicability to the multilayered structureless floor slabs at the lower part and the erecting height is more than 20m; the erecting height of the supporting frame body is high, the construction risk is large and the construction cost is increased due to long-time leasing; and the temporary platform is erected at the overhead part of the floor slab, so that the erecting height of the supporting frame body is reduced; and the elevated supporting mold is converted into the common beam-plate supporting mold, so that the used amount of erecting materials is reduced by 75%.

Description

Non-structure floor high-altitude formwork
Technical field
The present invention relates to a kind of non-structure floor high-altitude formwork.
Background technology
In building structure construction, construction layer beam slab utilizes supporting frame 5 to reach the temporary supporting system before intensity as beam slab concrete, and supporting frame 5 is seated on support body foundation structure floor 6, forms stable braced structures, meet the construction requirement of construction layer structure beam slab 4, as shown in Figure 1.
As shown in Figure 2, under there are construction layer structure beam slab 4 regions in structure when the situation of multilayer non-structure floor, conventional method is the form construction that adopts superelevation support body formwork, supporting frame 5 bases are seated lower floor structure floor place, in the time that high frame formwork supporting frame 5 is highly greater than 20m, the materials'use amount of setting up of supporting frame 5 increases, difficulty of construction increases, safety factor reduces, set up the increase of materials'use amount, construction cost increases.
Summary of the invention
For deficiency of the prior art, the object of this invention is to provide a kind of non-structure floor high-altitude formwork, this Structure Decreasing construction risk, minimizing construction cost, convenient construction.
For achieving the above object, the technical solution used in the present invention is to provide a kind of non-structure floor high-altitude formwork, the structure of described high-altitude formwork is to set up temporary platform on the surrounding support body foundation structure floor of non-structure floor region, in temporary platform, set up successively supporting frame, construction layer structure beam slab, wherein: described temporary platform includes main girder steel, inferior girder steel, scaffold floor, main girder steel is set up on the support body foundation structure floor of described non-structure floor region surrounding horizontal structure, the two sides of main girder steel and construction layer structure beam slab are fixed, inferior girder steel is erected on main girder steel and with main girder steel and is fixedly connected with, scaffold floor is laid on time girder steel, form temporary platform.
Effect of the present invention is rationally to utilize periphery horizontal structure to set up temporary platform, solves a high-altitude formwork difficult problem for bottom non-structure beam slab, and it is applicable to bottom multilayer non-structure beam slab, and scaffolding height is greater than the high-altitude formwork of 20m.Compare traditional high frame formwork method, supporting frame scaffolding height is high, construction risk is large, leases for a long time a large amount of scaffold tubes increase construction costs high; This non-structure floor high-altitude formwork is set up temporary platform at the built on stilts place of floor, reduces supporting frame scaffolding height, and high frame formwork is converted into common beam slab formwork, sets up material usage and reduces 75%.
Brief description of the drawings
Fig. 1 is the structural representation that prior art has structure floor scaffold;
Fig. 2 is the structural representation of prior art non-structure floor scaffold;
Fig. 3 is that temporary platform of the present invention is set up step floor map;
Fig. 4 is the structural profile schematic diagram of non-structure floor of the present invention high-altitude formwork.
In figure:
1, main girder steel 2, inferior girder steel 3, scaffold floor 4, construction layer structure beam slab
5, supporting frame 6, support body foundation structure floor
Detailed description of the invention
By reference to the accompanying drawings and embodiment the structure of non-structure floor of the present invention high-altitude formwork is illustrated.
As Fig. 3, shown in 4, the structure of non-structure floor of the present invention high-altitude formwork is, the structure of described high-altitude formwork is to set up temporary platform on the support body foundation structure floor 6 of non-structure floor region surrounding, in temporary platform, set up successively supporting frame 5, construction layer structure beam slab 4, described temporary platform includes main girder steel 1, inferior girder steel 2, scaffold floor 3, main girder steel 1 is set up on the support body foundation structure floor 6 of described non-structure floor region surrounding horizontal structure, the two sides of main girder steel 1 and support body foundation structure floor 6 are fixing, inferior girder steel 2 is erected on main girder steel 1 and with main girder steel and is fixedly connected with, scaffold floor 3 is laid on time girder steel 2, form temporary platform.
Non-structure floor of the present invention high-altitude formwork function is achieved in that
Non-structure floor of the present invention high-altitude formwork erecting structure utilizes the support body foundation structure floor 6 of non-floor region, bottom surrounding to lay main girder steel 1, and main girder steel 1 spacing is consistent with supporting frame 5 spacing, and main girder steel 1 two ends and surrounding support body foundation structure floor 6 are fixing; Inferior girder steel 2 is according to being evenly arranged on main girder steel 1 perpendicular to main girder steel 1 direction, and inferior girder steel 2 spacing are consistent with supporting frame 5 spacing, between main girder steel 1 and time girder steel 2, is welded and fixed and forms primary-secondary beam structure; On inferior girder steel 2, completely spread wooden scaffold floor 3 and form temporary platform, the supporting frame 5 of construction layer structure beam slab 4 is erected in temporary platform.
Non-structure floor of the present invention high-altitude formwork is by setting up temporary platform, dangerous larger high frame formwork is converted into conventional common support body formwork, compare the scaffolding height that high frame formwork has greatly reduced supporting frame 5, reduce difficulty of construction, improved safety factor, reduced construction cost.

Claims (2)

1. a non-structure floor high-altitude formwork, the structure of described high-altitude formwork is to set up temporary platform at the horizontal structure of non-structure floor region surrounding, supported support body (5), construction layer structure beam slab (4) successively on the support body foundation structure floor (6) of horizontal structure, is characterized in that:
Described temporary platform includes main girder steel (1), inferior girder steel (2), scaffold floor (3), main girder steel (1) is set up on the support body foundation structure floor (6) of described non-structure floor region surrounding horizontal structure, the two sides of main girder steel (1) and construction layer structure beam slab (4) are fixing, inferior girder steel (2) is erected on main girder steel (1) and with main girder steel and is fixedly connected with, scaffold floor (3) is laid on time girder steel (2), forms temporary platform.
2. non-structure floor according to claim 1 high-altitude formwork, described main girder steel (1), inferior girder steel (2) are many and be arranged in parallel, main girder steel (1) and time girder steel (2) vertical being fixedly connected with mutually.
CN201410139446.2A 2014-04-09 2014-04-09 High-altitude supporting mold of structureless floor slab Pending CN103953188A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410139446.2A CN103953188A (en) 2014-04-09 2014-04-09 High-altitude supporting mold of structureless floor slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410139446.2A CN103953188A (en) 2014-04-09 2014-04-09 High-altitude supporting mold of structureless floor slab

Publications (1)

Publication Number Publication Date
CN103953188A true CN103953188A (en) 2014-07-30

Family

ID=51330523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410139446.2A Pending CN103953188A (en) 2014-04-09 2014-04-09 High-altitude supporting mold of structureless floor slab

Country Status (1)

Country Link
CN (1) CN103953188A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070074934A1 (en) * 2005-09-20 2007-04-05 Hitachi Plant Engineering & Construction Co., Ltd. Inspection scaffold of large component for boiler and building method thereof
CN101100902A (en) * 2007-07-31 2008-01-09 龙信建设集团有限公司 Inclined drawing steel truss high-supported formwork structure system and construction method thereof
CN202090577U (en) * 2011-05-24 2011-12-28 南通市中房建设工程有限公司 Template supporting construction platform for lift wells in high-rise buildings
CN103114713A (en) * 2013-03-21 2013-05-22 北京六建集团有限责任公司 Hollow ultrahigh template section steel platform and construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070074934A1 (en) * 2005-09-20 2007-04-05 Hitachi Plant Engineering & Construction Co., Ltd. Inspection scaffold of large component for boiler and building method thereof
CN101100902A (en) * 2007-07-31 2008-01-09 龙信建设集团有限公司 Inclined drawing steel truss high-supported formwork structure system and construction method thereof
CN202090577U (en) * 2011-05-24 2011-12-28 南通市中房建设工程有限公司 Template supporting construction platform for lift wells in high-rise buildings
CN103114713A (en) * 2013-03-21 2013-05-22 北京六建集团有限责任公司 Hollow ultrahigh template section steel platform and construction method thereof

Similar Documents

Publication Publication Date Title
CN106760529B (en) Roof steel truss sliding assembly construction platform and installation method
US9506266B2 (en) Concrete deck with lateral force resisting system
CN103711201A (en) Large-span prestressed concrete beam board frame structural system
CN110512719B (en) Construction method of large-span interval corridor high-altitude formwork steel platform for high-rise residence
CN102733606A (en) Construction method of high large cantilever structure
TWI689652B (en) Beam-slab structure and construction method
CN102587659A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
US20140175259A1 (en) Modular Panel Concrete Form For Self-Lifting Concrete Form System
CN102561690A (en) Construction method for supporting structures on two sides of post-cast strip by use of brick column
CN111779248A (en) High formwork system and construction method thereof
CN206319610U (en) Roof system steel truss slipping and assembling construction platform structure
CN103774838B (en) A kind of construction of lift well assembling safe operation platform and using method
CN202509765U (en) Overhung platform template
CN106032704A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
CN201915631U (en) High-altitude long-span reinforced concrete corridor construction supporting structure
CN213953189U (en) Supporting device for ensuring smooth surface of lower cone shell of prefabricated water tank
CN212507296U (en) High formwork system
CN203783105U (en) Fast construction operating platform used for section steel column interior pouring concrete
CN103015693A (en) Three-dimensional construction device for super high-rise core tube beam-slab structure
CN202882377U (en) Hanging scaffold for integral hanging construction of truss
CN205116749U (en) A track strutting arrangement that is used for large -span steel construction wholly to slide
CN102587649B (en) Template profiled bar supporting system of high and large cantilever structure
CN201915630U (en) Combined platform of fire control joint gallery form supporting steel beam
CN206174441U (en) Elevator shaft operation platform
CN103953188A (en) High-altitude supporting mold of structureless floor slab

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140730