CN103924788B - Syndeton and construction method between existing building - Google Patents

Syndeton and construction method between existing building Download PDF

Info

Publication number
CN103924788B
CN103924788B CN201410190634.8A CN201410190634A CN103924788B CN 103924788 B CN103924788 B CN 103924788B CN 201410190634 A CN201410190634 A CN 201410190634A CN 103924788 B CN103924788 B CN 103924788B
Authority
CN
China
Prior art keywords
main girder
bracket
syndeton
girder steel
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410190634.8A
Other languages
Chinese (zh)
Other versions
CN103924788A (en
Inventor
董有
谢建明
马凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanchang Zhiku Intellectual Property Service Co ltd
Original Assignee
BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd filed Critical BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201410190634.8A priority Critical patent/CN103924788B/en
Publication of CN103924788A publication Critical patent/CN103924788A/en
Application granted granted Critical
Publication of CN103924788B publication Critical patent/CN103924788B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The present invention relates to syndeton and construction method between a kind of existing building, belong to strengthening reconstruction technical field, comprise existed building first, existed building second, frame column, encased steel plate, bracket, main girder steel, slip rubber support arrange encased steel plate on original frame column, adopt chemical anchor bolts to connect, and on steel plate, weld bracket, and should guarantee that every layer of bracket upper surface absolute altitude is consistent, will increase main girder steel newly and be sitting on bracket, main girder steel is I-steel, and node adopts slip rubber support. The present invention adopts the connected node of slip rubber support as two adjacent architecturals, has solved two buildings with different natural frequencies, amplitude and after structure connects, has received and when earthquake or other are compared with strong vibration, produce a difficult problem for structural deterioration.

Description

Syndeton and construction method between existing building
Technical field
The present invention relates to syndeton and construction method between a kind of existing building, belong to strengthening reconstruction technical field.
Background technology
Along with living standards of the people improve constantly, rural and urban construction plans are constantly looked for novelty, and produce development, and people are to existing eachThe use function that class is produced, room is used in life and condition can constantly propose new requirement, make its constantly needs of adaptation new situations development,Must have like this engineering that existing building is transformed.
At present, in China's old room transformation process, often can run into because of development and manage needs, needing adjacent two buildings to be connected toOne, increases usable floor area or makes walking convenient. The particularly building such as market, hospital and school, but consider two adjacent buildingBuild and the version difference of newly-increased coupling part, its intrinsic frequency, amplitude difference, be subject to temperature, earthquake or other stronger shakingUnder moving impact, the distortion difference of generation, two adjacent architecturals easily produce structural deterioration, and event even collapses.
Summary of the invention
In order to overcome the problems referred to above, the present invention proposes syndeton and construction method between a kind of existing building. Use slip rubberBearing, as the connected node of two adjacent architecturals, has solved two buildings with different natural frequencies, amplitude after structure connectsReceive and when earthquake or other are compared with strong vibration, produce a difficult problem for structural deterioration.
Technical scheme of the present invention is as follows:
Syndeton between a kind of existing building, comprises adjacent existed building first and existed building second, described existed building first andThe relative both sides of existed building second are provided with row's frame column, on described frame column, are provided with encased steel plate, frame column and outsourcingBetween steel plate, adopt chemical anchor bolts to connect, encased steel plate one side is welded with bracket, and main girder steel is arranged on bracket, main girder steelAnd between bracket, adopt slip rubber support as connected node, between each main girder steel, adopt groined type to interconnect,The newly-increased coupling part of common composition one, thus adjacent existed building first and existed building second are coupled together.
Described encased steel plate thickness is 20mm.
Described main girder steel is I-steel.
Bracket on described frame column is one or more layers. Further, every layer of bracket upper surface absolute altitude is consistent.
All arranged in a crossed manner on four faces of described encased steel plate have many chemical anchor bolts.
Between described main girder steel bottom surface and slip rubber support end face, adopt bolt to fix.
Described chemical anchor bolts diameter is 20mm.
On described newly-increased coupling part, be equipped with steel plate or concrete prefabricated board.
The construction method of syndeton between above-mentioned existing building, comprises the following steps:
Step 1: according to design drawing, the first basis of reinforcing frame trestle, to meet the load of bearing newly-increased coupling part, top;
Step 2: respective design position arranges encased steel plate on the frame column of existed building first and existed building second opposite side, and useChemical anchor bolts are connected it with frame column;
Step 3: at encased steel plate one side welding bracket, bracket absolute altitude is determined according to design drawing;
Step 4: slip rubber support is installed on bracket, and the rubber support that respectively slides should be accurately in place, and keep at grade,There is eccentric compression phenomenon in the rubber support of avoiding sliding;
Step 5: on each slip rubber support, main girder steel is installed; When main steel girder erection, for preventing main girder steel and slip rubber supportThere is horizontal sliding, need be first with wooden triangle cushion block in the interim positioning supports in main girder steel both sides, treat that main steel girder erection work is all completeAfter finishing, remove;
Step 6: will between the main girder steel on each bracket, adopt groined type to interconnect, form a newly-increased coupling part,Adjacent existed building first and existed building second are coupled together.
Beneficial effect: the present invention has well solved the difficult problem that two adjacent different buildings connect, and adopts slip rubber support not only canMake support node large compression, obtain enough bearing capacities in the case of not occurring, and collaborative two adjacent architecturals is intrinsicAmplitude, frequency, thus eliminate or reduce temperature, the destruction of distortional stress to original structure, simultaneously again can balanced bottom bracing structureStress, and the method is simple in structure, it is convenient to install, change, service time is long.
Brief description of the drawings
Fig. 1 is syndeton schematic diagram of the present invention;
Fig. 2 is newly-increased bracket schematic diagram;
Fig. 3 is newly-increased bracket axonometric drawing;
Fig. 4 is node connection diagram;
In figure: 1, existed building first; 2, existed building second; 3, frame column; 4, encased steel plate; 5, chemical anchor bolts; 6,Bracket; 7, main girder steel; 8, slip rubber support; 9, newly-increased coupling part.
Detailed description of the invention
The specific embodiment of the present invention is as follows:
As shown in Figure 1-2, syndeton between a kind of existing building of the present invention, comprises adjacent existed building first 1 and existingBuilding second 2, existed building first 1 both sides relative with existed building second 2 are provided with row's frame column 3, on each frame column 3Being provided with thickness is the encased steel plate 4 of 20mm, and between frame column 3 and encased steel plate 4, adopting diameter is the chemistry of 20mmCrab-bolt 5 connects, and all arranged in a crossed manner on 4 four faces of encased steel plate have many chemical anchor bolts 5. Encased steel plate 4 one sides outsideSide is welded with bracket 6, and main girder steel 7 is arranged on bracket 6, and main girder steel 7 adopts I-steel, between main girder steel 7 and bracket 6Adopt slip rubber support 8 as connected node, between main girder steel 7 bottom surfaces and slip rubber support 8 end faces, adopt bolt to fix.Between each main girder steel 7, adopt groined type to interconnect, jointly form a newly-increased coupling part 9, thereby by adjacentExisted building first 1 and existed building second 2 couple together. On newly-increased coupling part 9, also can lay steel plate or concrete prefabricated board.Wherein, the bracket 6 on frame column 3 is one or more layers, and every layer of bracket 6 upper surface absolute altitude are consistent.
The construction method of above-mentioned syndeton, comprises the following steps:
Step 1: according to design drawing, the first basis of reinforcing frame trestle 3, to meet the lotus of bearing newly-increased coupling part 9, topCarry;
Step 2: respective design position arranges encased steel plate on the frame column 3 of existed building first 1 and existed building second 2 opposite sides4, and it is connected with frame column 3 with chemical anchor bolts 5;
Step 3: at encased steel plate 4 one side welding brackets 6, bracket 6 absolute altitudes are determined according to design drawing;
Step 4: slip rubber support 8 is installed on bracket 6, and the rubber support 8 that respectively slides should be accurately in place, and remain on sameIn plane, there is eccentric compression phenomenon in the rubber support 8 of avoiding sliding;
Step 5: main girder steel 7 is installed on each slip rubber support 8; When main girder steel 7 is installed, for preventing main girder steel 7 and slidingThere is horizontal sliding in rubber support 8, need be first with wooden triangle cushion block in the main girder steel 7 interim positioning supports in both sides, treat main girder steel 7After installment work all, remove;
Step 6: will adopt groined type to interconnect between the main girder steel 7 on each bracket 6, form a newly-increased connecting portionDivide 9, adjacent existed building first 1 and existed building second 2 are coupled together.
Be more than an exemplary embodiments of the present invention, enforcement of the present invention is not limited to this.

Claims (9)

1. a construction method for syndeton between existing building, syndeton bag between described existing buildingDraw together adjacent existed building first (1) and existed building second (2), described existed building first (1) and existing buildingBuild the relative both sides of second (2) and be provided with row's frame column (3), outside being provided with on described frame column (3)Steel plated (4), adopts chemical anchor bolts (5) to be connected between frame column (3) and encased steel plate (4),Encased steel plate (4) one sides are welded with bracket (6), and it is upper that main girder steel (7) is arranged on bracket (6), main girder steel(7) and adopt slip rubber support (8) as connected node between bracket (6), each main girder steel (7)Between adopt groined type to interconnect, jointly form a newly-increased coupling part (9), thus by adjacentExisted building first (1) and existed building second (2) couple together;
It is characterized in that, comprise the following steps:
Step 1: according to design drawing, the first basis of reinforcing frame trestle (3), to meet, to bear top newIncrease the load of coupling part (9);
Step 2: in the upper phase of frame column (3) of existed building first (1) and existed building second (2) opposite sideAnswer design attitude that encased steel plate (4) is set, and it is connected with frame column (3) with chemical anchor bolts (5);
Step 3: at encased steel plate (4) one side welding brackets (6), bracket (6) absolute altitude is according to design drawingPaper is determined;
Step 4: at the upper slip rubber support (8) of installing of bracket (6), the rubber support (8) that respectively slides shouldAccurately in place, and keep at grade, there is eccentric compression phenomenon in the rubber support (8) of avoiding sliding;
Step 5: at the upper main girder steel (7) of installing of each slip rubber support (8); When main girder steel (7) is installed,For preventing that main girder steel (7) and slip rubber support (8) from horizontal sliding occurring, need be first with wooden triangle cushion blockIn the interim positioning supports in main girder steel (7) both sides, treat to remove after main girder steel (7) installment work all;
Step 6: will adopt groined type to be interconnected on one between the main girder steel (7) on each bracket (6)Rise, form a newly-increased coupling part (9), by adjacent existed building first (1) and existed building second (2)Couple together.
2. the construction method of syndeton between existing building according to claim 1, is characterized in that:Described encased steel plate (4) thickness is 20mm.
3. the construction method of syndeton between existing building according to claim 1, is characterized in that:Described main girder steel (7) is I-steel.
4. the construction method of syndeton between existing building according to claim 1, is characterized in that:Bracket (6) on described frame column (3) is one or more layers.
5. the construction method of syndeton between existing building according to claim 4, is characterized in that:Every layer of bracket (6) upper surface absolute altitude is consistent.
6. the construction method of syndeton between existing building according to claim 1, is characterized in that:All arranged in a crossed manner on (4) four faces of described encased steel plate have many chemical anchor bolts (5).
7. the construction method of syndeton between existing building according to claim 1, is characterized in that:Between described main girder steel (7) bottom surface and slip rubber support (8) end face, adopt bolt to fix.
8. the construction method of syndeton between existing building according to claim 1, is characterized in that:Described chemical anchor bolts (5) diameter is 20mm.
9. the construction method of syndeton between existing building according to claim 1, is characterized in that:On described newly-increased coupling part (9), be equipped with steel plate or concrete prefabricated board.
CN201410190634.8A 2014-05-06 2014-05-06 Syndeton and construction method between existing building Expired - Fee Related CN103924788B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410190634.8A CN103924788B (en) 2014-05-06 2014-05-06 Syndeton and construction method between existing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410190634.8A CN103924788B (en) 2014-05-06 2014-05-06 Syndeton and construction method between existing building

Publications (2)

Publication Number Publication Date
CN103924788A CN103924788A (en) 2014-07-16
CN103924788B true CN103924788B (en) 2016-05-18

Family

ID=51143165

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410190634.8A Expired - Fee Related CN103924788B (en) 2014-05-06 2014-05-06 Syndeton and construction method between existing building

Country Status (1)

Country Link
CN (1) CN103924788B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108411787A (en) * 2018-04-11 2018-08-17 中启胶建集团有限公司 Existing curtain wall builds freely-supported conversion beam steel construction crossover construction
CN111236310B (en) * 2020-03-03 2021-03-30 福建工程学院 Construction method of connecting channel of existing underground structure in weak water-rich stratum
CN114086791A (en) * 2021-11-29 2022-02-25 北京建工四建工程建设有限公司 Connecting structure of existing building and newly-built building and construction method thereof

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001262595A (en) * 2000-03-22 2001-09-26 Kajima Corp Building construction method of underground building frame
RU2293830C1 (en) * 2005-07-20 2007-02-20 Николай Борисович Болотин Method for structure erection between ends of existent buildings
CN101294443A (en) * 2008-05-30 2008-10-29 中冶天工上海十三冶建设有限公司 High altitude platform mounting method
CN202181623U (en) * 2011-06-24 2012-04-04 中国水电顾问集团华东勘测设计研究院 Damping structure for generator-floor plate girder of hydropower house
CN102535845A (en) * 2012-02-14 2012-07-04 浙江省建工集团有限责任公司 Construction method of bearing frame of corridor structure
CN102587682A (en) * 2012-04-05 2012-07-18 郭猛 Strengthening method for lightening seismic response of frame structure
CN202627506U (en) * 2012-05-25 2012-12-26 中国葛洲坝集团股份有限公司 Formwork for cast-in-place concrete connecting beams
CN102912981A (en) * 2012-10-26 2013-02-06 中冶天工上海十三冶建设有限公司 Gate type high-rise building connected structure construction device
CN103556823A (en) * 2013-10-28 2014-02-05 山西省第二建筑工程公司 Construction method with silo sliding formwork operating platform as top cover plate formwork supporting system
CN203905523U (en) * 2014-05-06 2014-10-29 北京筑福国际工程技术有限责任公司 Connecting structure between existing buildings

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001262595A (en) * 2000-03-22 2001-09-26 Kajima Corp Building construction method of underground building frame
RU2293830C1 (en) * 2005-07-20 2007-02-20 Николай Борисович Болотин Method for structure erection between ends of existent buildings
CN101294443A (en) * 2008-05-30 2008-10-29 中冶天工上海十三冶建设有限公司 High altitude platform mounting method
CN202181623U (en) * 2011-06-24 2012-04-04 中国水电顾问集团华东勘测设计研究院 Damping structure for generator-floor plate girder of hydropower house
CN102535845A (en) * 2012-02-14 2012-07-04 浙江省建工集团有限责任公司 Construction method of bearing frame of corridor structure
CN102587682A (en) * 2012-04-05 2012-07-18 郭猛 Strengthening method for lightening seismic response of frame structure
CN202627506U (en) * 2012-05-25 2012-12-26 中国葛洲坝集团股份有限公司 Formwork for cast-in-place concrete connecting beams
CN102912981A (en) * 2012-10-26 2013-02-06 中冶天工上海十三冶建设有限公司 Gate type high-rise building connected structure construction device
CN103556823A (en) * 2013-10-28 2014-02-05 山西省第二建筑工程公司 Construction method with silo sliding formwork operating platform as top cover plate formwork supporting system
CN203905523U (en) * 2014-05-06 2014-10-29 北京筑福国际工程技术有限责任公司 Connecting structure between existing buildings

Also Published As

Publication number Publication date
CN103924788A (en) 2014-07-16

Similar Documents

Publication Publication Date Title
KR101194170B1 (en) Joint structure of modular building and method thereof
CN103924788B (en) Syndeton and construction method between existing building
CN205153116U (en) Prefabricated modularization assembled shock insulation building structure
CN103147529A (en) Assembly type energy dissipation and seismic mitigation shear wall structure system
CN104032854A (en) Assembly-type T-shaped mixed coupled wall and construction method thereof
KR20150138785A (en) Vertical expansion remodeling method of existing building with seperate load path
CN203834738U (en) T-shaped prefabricated mixed coupled wall
CN106869379A (en) A kind of assembling type steel structure Side fascia subiculum upper hanging type attachment structure
CN107587643A (en) The ceiling structure of quick grafting assembling
JP4237085B2 (en) Lower floor extension method for existing buildings
CN203808262U (en) Prefabricated superimposed main beam and auxiliary beam connecting structure
CN104895221B (en) Assembled shaped steel confined concrete shear wall structure
CN103195183A (en) Standard unit assembled shock isolating and damping structure system
CN203905523U (en) Connecting structure between existing buildings
CN102912878B (en) Modularized building isolation system
CN104032855A (en) Assembly-type cross-shaped mixed coupled wall and construction method thereof
CN203783004U (en) Reinforced concrete stair structure
CN211547345U (en) Assembled steel-UHPC combined structure based on bolted connection
CN104032862A (en) Assembly-type steel beam joint L-shaped mixed coupled wall and construction method thereof
CN103195162A (en) Standard unit assembled energy dissipating and damping structure system
CN207714516U (en) Prefabricated panel and walling system
CN105970750A (en) Assembling type city vibration isolating road system and fast mounting construction method thereof
CN105464218A (en) Floor truss pin shaft connection joint structure
CN219654121U (en) Assembled stair with bidirectional sliding connection nodes
CN205421557U (en) Roof beam portion base

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20171229

Address after: 102600, room 2, building 2212, pop Center, Xinghua street, Beijing, Daxing District

Patentee after: BEIJING YONGBO TECHNOLOGY CO.,LTD.

Address before: 100043 Shijingshan District, Yang Yang Street, No. 69, No. 1, building an international Park, Fu International

Patentee before: BEIJING AEIDO ENGINEERING TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right

Effective date of registration: 20180516

Address after: 330000 Nanchang economic and Technological Development Zone, Nanchang, Jiangxi

Patentee after: Hong Hao construction Limited by Share Ltd.

Address before: 102600 room 2212, building 2, Pope center, Xinghua street, Daxing District, Beijing.

Patentee before: BEIJING YONGBO TECHNOLOGY CO.,LTD.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190118

Address after: No. 899 Xuefu Avenue, Honggutan New District, Nanchang City, Jiangxi Province, 330000. C1-93, 2nd floor, B Block, Taste Zong Space, Huigu Creative Industry Park

Patentee after: NANCHANG ZHIKU INTELLECTUAL PROPERTY SERVICE CO.,LTD.

Address before: 330000 Nanchang economic and Technological Development Zone, Nanchang, Jiangxi

Patentee before: Hong Hao construction Limited by Share Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160518

CF01 Termination of patent right due to non-payment of annual fee