CN103912089A - Construction method of lift ceiling of auditorium hall - Google Patents

Construction method of lift ceiling of auditorium hall Download PDF

Info

Publication number
CN103912089A
CN103912089A CN201410157380.XA CN201410157380A CN103912089A CN 103912089 A CN103912089 A CN 103912089A CN 201410157380 A CN201410157380 A CN 201410157380A CN 103912089 A CN103912089 A CN 103912089A
Authority
CN
China
Prior art keywords
pulley
counterweight
steel
ceiling
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410157380.XA
Other languages
Chinese (zh)
Other versions
CN103912089B (en
Inventor
马海龙
李军
李建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201410157380.XA priority Critical patent/CN103912089B/en
Publication of CN103912089A publication Critical patent/CN103912089A/en
Application granted granted Critical
Publication of CN103912089B publication Critical patent/CN103912089B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a construction method of the lift ceiling of an auditorium hall and belongs to the technical field of constructional engineering. The construction method comprises the steps of performing measurement and setting-out; assembling and lifting of a steel framework; assembling the steel framework in blocks, including dividing the steel framework into seven blocks and lifting the framework up high instantly after finishing the assembly; mounting grid roof layer pulleys; marking the point location of every pulley according to the measurement and setting-out, fixedly welding pulley bases to a steel-structure equipment beam in a calibrated horizontal mode; mounting a driving mechanism; mounting a balance weight mechanism; mounting steel wire ropes in a penetrating mode, which connect the balance weight mechanism and the driving mechanism; mounting safety rope units; performing electrical installation; performing mechanical test run; mounting limiting units; performing construction of decorative facing layers; performing ceiling test. By means of the method of machining the ceiling steel framework in factory and hoisting the steel framework on site, the construction method of the lift ceiling of the auditorium hall saves the hoisting time, provides a construction field in early and guarantees construction security.

Description

A kind of construction method of lifting furred ceiling of auditorium
Technical field
The present invention relates to construction engineering technical field, specifically a kind of construction method of lifting furred ceiling of auditorium.
Background technology
General, the ceiling construction preparation time of the auditorium of grand theater is long, and equipment preparation is various, technological process complexity, structure manufacture difficulty, the on-the-spot confusion of installing, the lifting time is long, and construction safety can not well ensure, in the work progress of furred ceiling, the input of large-scale construction equipment, constructs loaded down with trivial details, complicated, and economy, human and material resources have high input.
Summary of the invention
Technical assignment of the present invention is to solve the deficiencies in the prior art, and a kind of construction method of lifting furred ceiling of auditorium is provided.
Technical scheme of the present invention realizes in the following manner, the construction method of the lifting furred ceiling of this kind of auditorium, and the step of this construction method is:
A, measurement unwrapping wire
B, steel frame splicing assembling and lifting
The assembling of steel frame piecemeal, is divided into into seven, after having assembled, lifts immediately to high-altitude;
C, installation grid top layer pulley
According to measuring the each pulley point of unwrapping wire institute mark position, pulley base levelling is fixedly welded on Steel structure equipment beam;
D, installation driving mechanism;
E, installation balance weight mechanism;
F, wear connect counterweight, drive wire rope;
G, installation insurance rope device;
H, electric installation;
I, machinery trial run;
J, mounting limit device;
K, architectural surface construction;
L, furred ceiling debugging.
The concrete steps of this construction method are:
A, measurement unwrapping wire
(1) with survey tool by auditorium's absolute altitude, center line and the entablature wall auditorium side cornice of pedestal, taking these two lines and absolute altitude as benchmark, be marked on grid top layer;
(2) with survey tool, embedment for Civil Works space is measured, whether suitable to confirm space;
(3) press the position of working drawing and reference line mark ceiling layer angle pulley, suspension centre pulley, driving arrangement, Weighting system;
(4) eject each ceiling separator bar with the line of ink marker at grid top layer;
(5) check deviation, verticality and the absolute altitude situation of the each built-in fitting of counterweight well, and note down;
B, steel frame splicing assembling and lifting
The assembling of steel frame piecemeal, is divided into into seven, after having assembled, lifts immediately to high-altitude;
(1) on auditorium's first layer ground, set up steel frame platform for lining, in conjunction with jack, adjust platform for lining deviation;
(2) on first layer ground, hoist engine is installed, with hoist engine by the handling of steel frame member on platform for lining, by steelframe assembling splicing;
(3) after steel frame is spelled and assembled, in overhead, steel frame is sling and slowly risen by the wire rope of four hoist engines, the wire rope of two hoist engines and two cable wind ropes are held steel frame and are prevented that steel frame from rocking in uphill process from below simultaneously; Steel frame winches to behind precalculated position, temporary fixed firmly with wire rope;
C, installation grid top layer pulley
According to measuring the each pulley point of unwrapping wire institute mark position, pulley base levelling is fixedly welded on Steel structure equipment beam;
D, installation driving mechanism
(1) drive motors is placed according to the position line having marked;
(2) fixed drive motor base;
E, installation balance weight mechanism
(1) with hoist engine, counterweight track is adjusted in counterweight well, vertical and insert is fixed;
(2) counterweight frame is winched to correct position, in single counterweight frame, pre-install appropriate balancing weight, with bolt, counterweight frame is led to boots and be connected on counterweight frame, make to coordinate with weight guide;
F, wear connect counterweight, drive wire rope
(1) reeve: wire rope is penetrated in the slotted eye on reel around Liang Quan, fix with pressing plate; Then after wire rope being penetrated to counterweight frame lifting tackle, return to grid top layer through crossing pulley, carry out terminal and fix;
(2) counterweight armored rope first counterweight pulley is entered to return after groove grid top layer penetrate again transition pulley again after angle pulley to suspension centre pulley and fleet wheel, then return to grid top layer and carry out terminal by figure and fix;
(3) with hoist engine, steelframe is promoted to highest order, tightens up counterweight armored rope and carry out terminal and fix;
(4) the temporary fixed wire rope of releasing suspended ceiling steel skeleton;
(5) pass through hoist engine retractable wire rope by steel frame leveling;
G, installation insurance rope device
(1) first safety rope take-up frame is fixed on steelframe;
(2) then that safety rope device is fixing on grid top steel structure girder bottom and steelframe;
H, electric installation
(1) electric part carries out strong and weak electricity crane span structure and cable laying by preformed hole position;
(2) after electric piping, line insulation test, be connected with drive motors sub-control box case and switch board;
I, machinery trial run
J, mounting limit device
(1), after electric trial run, after measurement stroke, mechanical position limitation and over-hoisting protection device are installed;
(2) stopping means is arranged on respectively two positions, and a place is the top and bottom of counterweight frame stroke, and another place is the top and bottom of furred ceiling stroke;
K, architectural surface construction
(1) measure unwrapping wire location
Auditorium's lifting furred ceiling is dropped to lowest order; In conjunction with rationally piecemeal of liftable machinery, furred ceiling is divided into several regions, in each region, carry out again the in-depth of plate, reasonable Arrangement keel and facing lattice;
Measure after unwrapping wire, by wherein second, four, six pieces rise to a high position, facilitate four furred ceilings of position, the end to carry out other surface constructions; After four furred ceiling related works complete, rise to a high position, drop to low level by other three simultaneously and carry out surface construction;
(2) installation of keel and leveling
Keel installation order is, after first established angle steel joist, lightgage steel joist is installed, keel complete immediately absolute altitude, the size of installing are carried out comprehensively checking and checking the problem of the absolute altitude of its finished surface of priority control, the accuracy of gauge of moulding and planeness, then hidden examination;
(3) cement fibrolite plate is installed
What smallpox panel adopted is multilayer cement fibrolite plate, thereby between plate and plate, exists space to form cavity, smears professional bonding adhesive between plate and plate, stays in seam 3mm, then with the gap filler processing of squeegeeing between plate;
(4) the covering with paint processing of cement fibrolite plate
Special processing is carried out in its negative and positive angle metal protection corner tape is installed;
Adopt special putty that cement fibrolite plate is hung and put down, modifies out after decorating, point time brushing paint;
L, furred ceiling debugging
A: commissioning content:
(1) before the energising of power distribution cabinet switch board, check,
(2) before site plant energising, detect,
(3) energising checks,
(4) speed control device debugging comprises frequency converter setting, frequency converter open loop operation, limit switch adjustment, encoder adjustment, frequency converter operation with closed ring;
B: lifting ceiling debugging step:
(1) major loop wiring and limit switch wiring, measures insulaion resistance; Whether commissioning device traffic direction is consistent with software set direction; Whether limit switch, overtravel limit switch, load transducer be effective, and whether spacing position, direction be correct;
(2) rotary encoder wiring are installed;
(3) confirm that whether rotary encoder work is normal, whether direction of rotation is consistent with software counting direction;
(4) carry out device rate closed-loop regulation;
(5) carry out device location closed-loop regulation.
The beneficial effect that the present invention compared with prior art produced is:
The construction method of the lifting furred ceiling of a kind of auditorium of the present invention is taked the method for suspended ceiling steel skeleton at factory process, on-site hoisting, has economized the lifting time, provides construction plant in advance, has ensured construction safety.
In the construction method of the lifting furred ceiling of a kind of auditorium of the present invention, the handling of the material such as suspended ceiling framework, elevation and subsidence mechanical and lifting adopt hoist engine to carry out cleverly; Reduce the input of large-scale construction equipment, improved the flexibility of construction.
When the decorative cover of furred ceiling is constructed in the construction method of the lifting furred ceiling of a kind of auditorium of the present invention, furred ceiling is fallen to lowest order, reduced the height of decorative cover constructing operation layer, reduced input, increased safety assurance coefficient.
Furred ceiling piecemeal dislocation construction in the construction method of the lifting furred ceiling of a kind of auditorium of the present invention, the effectively reduction of erection time.
Detailed description of the invention
The construction method of the lifting furred ceiling to a kind of auditorium of the present invention is described in detail below below.
The step of the construction method of the lifting furred ceiling of a kind of auditorium of the present invention is:
1, measure unwrapping wire
1) with survey tools such as level gauges, line pendant, 50m tape measure, 3m steel ruler by auditorium's absolute altitude, center line and the entablature wall auditorium side cornice of pedestal, taking these two lines and absolute altitude as benchmark, be marked on grid top layer;
2) with survey tools such as 50m tape measures, embedment for Civil Works space is measured, whether suitable to confirm space;
3) press the positions such as working drawing and reference line mark ceiling layer angle pulley, suspension centre pulley, driving arrangement, Weighting system;
4) eject each ceiling separator bar with the line of ink marker at grid top layer;
5) check deviation, verticality and the absolute altitude situation of the each built-in fitting of counterweight well, and note down.
2, steel frame splicing assembling and lifting
The assembling of steel frame piecemeal, is divided into into seven, after having assembled, lifts immediately to high-altitude.
1) on auditorium's first layer ground, set up steel frame platform for lining, in conjunction with jack, by platform for lining deviation adjusting to meeting code requirement.
2) on first layer ground, hoist engine is installed, with hoist engine by the handling of steel frame member on platform for lining, by steelframe assembling splicing, require dimensional errors between welding and bolt connection quality and member to be no more than code requirement according to working drawing.
3) after steel frame is spelled and assembled, in overhead, steel frame is sling and slowly risen by the wire rope of four hoist engines, the wire rope of two hoist engines and two cable wind ropes are held steel frame and are prevented that steel frame from rocking in uphill process from below simultaneously; Steel frame winches to behind precalculated position, temporary fixed firmly with wire rope.
3, grid top layer pulley is installed
According to measuring the each pulley point of unwrapping wire institute mark position, pulley base levelling is fixedly welded on Steel structure equipment beam.
4, driving mechanism is installed
1) drive motors is placed according to the position line having marked;
2) fixed drive motor base.
5, balance weight mechanism is installed
1) with hoist engine, counterweight track is adjusted in counterweight well, by figure requirements vertically and insert fix;
2) with cucurbit, counterweight frame is winched to correct position, in single counterweight frame, pre-install appropriate balancing weight, with bolt, counterweight frame is led to boots and be connected on counterweight frame, make to coordinate with weight guide.
6, wear and connect counterweight, driving wire rope
1) reeve: will drive wire rope to penetrate in the slotted eye on reel around Liang Quan, fix with pressing plate; Then wire rope is penetrated and return to grid top layer after counterweight frame lifting tackle and carry out terminal by designing requirement and fix through crossing pulley.
2) counterweight armored rope first counterweight pulley is entered to return after groove grid top layer penetrate again transition pulley again after angle pulley to suspension centre pulley and fleet wheel, then return to grid top layer and carry out terminal by figure and fix.
3) with hoist engine, steelframe is promoted to highest order, tightens up counterweight armored rope and carry out terminal and fix.
4) the temporary fixed wire rope of releasing suspended ceiling steel skeleton.
5) pass through hoist engine retractable wire rope by steel frame leveling.
7, installation insurance rope device
1) first the concrete size of safety rope take-up frame opsition dependent is fixed on steelframe;
2) then that safety rope device is fixing on grid top steel structure girder bottom and steelframe.
8, electric installation
1) electric part carries out strong and weak electricity crane span structure and cable laying by drawing preformed hole position;
2) after electric piping, line insulation test, be connected with drive motors sub-control box case and switch board.
9, machinery trial run
1) before equipment trial run, should unify to arrange, reasonable arrangement, the personnel of guarantee put in place, step unified, and password is consistent;
2) trial run, must not have abnormal sound and clamping stagnation, and current of electric meets standard.
3) lifting drive of furred ceiling should assemble in factory, debug complete, and normal operation, without any clamping stagnation and abnormal sound.
10, mounting limit device
1), after electric trial run, after measurement stroke, mechanical position limitation and over-hoisting protection device are installed.
2) stopping means is arranged on respectively two positions, and a place is the top and bottom of counterweight frame stroke, and another place is the top and bottom of furred ceiling stroke.
11, architectural surface construction
1) measure unwrapping wire location
Auditorium's lifting furred ceiling is dropped to lowest order; In conjunction with rationally piecemeal of liftable machinery, furred ceiling is divided into several regions, in each region, carry out again the in-depth of plate, reasonable Arrangement keel and facing lattice.
Measure after unwrapping wire, wherein three (second, four, six piece) are risen to a high position, facilitate four furred ceilings of position, the end to carry out other surface constructions; After four furred ceiling related works complete, rise to a high position, drop to low level by other three simultaneously and carry out surface construction.
2) installation of keel and leveling
Keel installation order is, after first established angle steel joist, lightgage steel joist is installed.Keel complete immediately absolute altitude, the size of installing are carried out comprehensively checking and checking the problem of the absolute altitude of its finished surface of priority control, the accuracy of gauge of moulding and planeness, then hidden examination.
3) cement fibrolite plate is installed
What in this engineering arenas, smallpox panel adopted is multilayer cement fibrolite plate, thereby between plate and plate, exist space to form cavity, therefore we will take following measures in construction: between plate and plate, smear professional bonding adhesive, between plate, stay in the general 3mm of seam, then use the processing of squeegeeing of the identical or approaching professional gap filler of same cement fibrolite plate character.
4) the covering with paint processing of cement fibrolite plate
Special processing is carried out in its negative and positive angle metal protection corner tape is installed, Founder can be processed in negative and positive angle on the one hand, also improved on the other hand traditional-handwork and processed the efficiency of this class operation and greatly improved perception effect.
Adopt special putty that cement fibrolite plate is hung and put down, modifies out after decorating, point time brushing paint.
12, furred ceiling debugging
1) commissioning content: check before (1) power distribution cabinet (switch board) energising, (2) before site plant energising, detect, (3) energising checks, the debugging of (4) speed control device comprises frequency converter setting, frequency converter open loop operation, limit switch adjustment, encoder adjustment, frequency converter operation with closed ring.
2) lifting ceiling debugging step:
(1) major loop wiring and limit switch wiring, measures insulaion resistance; Whether commissioning device traffic direction is consistent with software set direction; Whether limit switch, overtravel limit switch, load transducer be effective, and whether spacing position, direction be correct.
(2) rotary encoder wiring are installed;
(3) confirm that whether rotary encoder work is normal, whether direction of rotation is consistent with software counting direction;
(4) carry out device rate closed-loop regulation;
(5) carry out device location closed-loop regulation.

Claims (2)

1. a construction method for the lifting furred ceiling of auditorium, is characterized in that the step of this construction method is:
A, measurement unwrapping wire
B, steel frame splicing assembling and lifting
The assembling of steel frame piecemeal, is divided into into seven, after having assembled, lifts immediately to high-altitude;
C, installation grid top layer pulley
According to measuring the each pulley point of unwrapping wire institute mark position, pulley base levelling is fixedly welded on Steel structure equipment beam;
D, installation driving mechanism;
E, installation balance weight mechanism;
F, wear connect counterweight, drive wire rope;
G, installation insurance rope device;
H, electric installation;
I, machinery trial run;
J, mounting limit device;
K, architectural surface construction;
L, furred ceiling debugging.
2. a construction method for the lifting furred ceiling of auditorium, is characterized in that the step of this construction method is:
A, measurement unwrapping wire
(1) with survey tool by auditorium's absolute altitude, center line and the entablature wall auditorium side cornice of pedestal, taking these two lines and absolute altitude as benchmark, be marked on grid top layer;
(2) with survey tool, embedment for Civil Works space is measured, whether suitable to confirm space;
(3) press the position of working drawing and reference line mark ceiling layer angle pulley, suspension centre pulley, driving arrangement, Weighting system;
(4) eject each ceiling separator bar with the line of ink marker at grid top layer;
(5) check deviation, verticality and the absolute altitude situation of the each built-in fitting of counterweight well, and note down;
B, steel frame splicing assembling and lifting
The assembling of steel frame piecemeal, is divided into into seven, after having assembled, lifts immediately to high-altitude;
(1) on auditorium's first layer ground, set up steel frame platform for lining, in conjunction with jack, adjust platform for lining deviation;
(2) on first layer ground, hoist engine is installed, with hoist engine by the handling of steel frame member on platform for lining, by steelframe assembling splicing;
(3) after steel frame is spelled and assembled, in overhead, steel frame is sling and slowly risen by the wire rope of four hoist engines, the wire rope of two hoist engines and two cable wind ropes are held steel frame and are prevented that steel frame from rocking in uphill process from below simultaneously; Steel frame winches to behind precalculated position, temporary fixed firmly with wire rope;
C, installation grid top layer pulley
According to measuring the each pulley point of unwrapping wire institute mark position, pulley base levelling is fixedly welded on Steel structure equipment beam;
D, installation driving mechanism
(1) drive motors is placed according to the position line having marked;
(2) fixed drive motor base;
E, installation balance weight mechanism
(1) with hoist engine, counterweight track is adjusted in counterweight well, vertical and insert is fixed;
(2) counterweight frame is winched to correct position, in single counterweight frame, pre-install appropriate balancing weight, with bolt, counterweight frame is led to boots and be connected on counterweight frame, make to coordinate with weight guide;
F, wear connect counterweight, drive wire rope
(1) reeve: wire rope is penetrated in the slotted eye on reel around Liang Quan, fix with pressing plate; Then after wire rope being penetrated to counterweight frame lifting tackle, return to grid top layer through crossing pulley, carry out terminal and fix;
(2) counterweight armored rope first counterweight pulley is entered to return after groove grid top layer penetrate again transition pulley again after angle pulley to suspension centre pulley and fleet wheel, then return to grid top layer and carry out terminal by figure and fix;
(3) with hoist engine, steelframe is promoted to highest order, tightens up counterweight armored rope and carry out terminal and fix;
(4) the temporary fixed wire rope of releasing suspended ceiling steel skeleton;
(5) pass through hoist engine retractable wire rope by steel frame leveling;
G, installation insurance rope device
(1) first safety rope take-up frame is fixed on steelframe;
(2) then that safety rope device is fixing on grid top steel structure girder bottom and steelframe;
H, electric installation
(1) electric part carries out strong and weak electricity crane span structure and cable laying by preformed hole position;
(2) after electric piping, line insulation test, be connected with drive motors sub-control box case and switch board;
I, machinery trial run
J, mounting limit device
(1), after electric trial run, after measurement stroke, mechanical position limitation and over-hoisting protection device are installed;
(2) stopping means is arranged on respectively two positions, and a place is the top and bottom of counterweight frame stroke, and another place is the top and bottom of furred ceiling stroke;
K, architectural surface construction
(1) measure unwrapping wire location
Auditorium's lifting furred ceiling is dropped to lowest order; In conjunction with rationally piecemeal of liftable machinery, furred ceiling is divided into several regions, in each region, carry out again the in-depth of plate, reasonable Arrangement keel and facing lattice;
Measure after unwrapping wire, by wherein second, four, six pieces rise to a high position, facilitate four furred ceilings of position, the end to carry out other surface constructions; After four furred ceiling related works complete, rise to a high position, drop to low level by other three simultaneously and carry out surface construction;
(2) installation of keel and leveling
Keel installation order is, after first established angle steel joist, lightgage steel joist is installed, keel complete immediately absolute altitude, the size of installing are carried out comprehensively checking and checking the problem of the absolute altitude of its finished surface of priority control, the accuracy of gauge of moulding and planeness, then hidden examination;
(3) cement fibrolite plate is installed
What smallpox panel adopted is multilayer cement fibrolite plate, thereby between plate and plate, exists space to form cavity, smears professional bonding adhesive between plate and plate, stays in seam 3mm, then with the gap filler processing of squeegeeing between plate;
(4) the covering with paint processing of cement fibrolite plate
Special processing is carried out in its negative and positive angle metal protection corner tape is installed;
Adopt special putty that cement fibrolite plate is hung and put down, modifies out after decorating, point time brushing paint;
L, furred ceiling debugging
A: commissioning content:
(1) before the energising of power distribution cabinet switch board, check,
(2) before site plant energising, detect,
(3) energising checks,
(4) speed control device debugging comprises frequency converter setting, frequency converter open loop operation, limit switch adjustment, encoder adjustment, frequency converter operation with closed ring;
B: lifting ceiling debugging step:
(1) major loop wiring and limit switch wiring, measures insulaion resistance; Whether commissioning device traffic direction is consistent with software set direction; Whether limit switch, overtravel limit switch, load transducer be effective, and whether spacing position, direction be correct;
(2) rotary encoder wiring are installed;
(3) confirm that whether rotary encoder work is normal, whether direction of rotation is consistent with software counting direction;
(4) carry out device rate closed-loop regulation;
(5) carry out device location closed-loop regulation.
CN201410157380.XA 2014-04-18 2014-04-18 A kind of construction method of the lifting furred ceiling of auditorium Active CN103912089B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410157380.XA CN103912089B (en) 2014-04-18 2014-04-18 A kind of construction method of the lifting furred ceiling of auditorium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410157380.XA CN103912089B (en) 2014-04-18 2014-04-18 A kind of construction method of the lifting furred ceiling of auditorium

Publications (2)

Publication Number Publication Date
CN103912089A true CN103912089A (en) 2014-07-09
CN103912089B CN103912089B (en) 2016-06-08

Family

ID=51038059

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410157380.XA Active CN103912089B (en) 2014-04-18 2014-04-18 A kind of construction method of the lifting furred ceiling of auditorium

Country Status (1)

Country Link
CN (1) CN103912089B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105372034A (en) * 2015-12-07 2016-03-02 昆山市建设工程质量检测中心 Constructional lightgage steel joist and fitting one-piece test apparatus
CN105822072A (en) * 2016-05-20 2016-08-03 北京西飞世纪门窗幕墙工程有限责任公司 Hoisting construction structure and method for air corridor ceiling

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5816016A (en) * 1995-12-11 1998-10-06 Zarnick; Bernard F. Method of installing acoustical panels in an arena
CN201221193Y (en) * 2008-06-17 2009-04-15 北京城建集团有限责任公司 High altitude packway ceiling construction operating platform
CN101514586A (en) * 2009-01-14 2009-08-26 北京江河幕墙股份有限公司 Hanger rail type electric hanging boat and high-rise long span house, bridge building construction method and use thereof
CN101696601A (en) * 2009-10-19 2010-04-21 上海中建八局装饰有限责任公司 Method for assembling large-area safety net
CN102220795A (en) * 2011-04-14 2011-10-19 广东省建筑装饰工程有限公司 Ceiling system applicable to large-span space steel structure and construction method thereof
CN202324567U (en) * 2011-11-18 2012-07-11 中建七局建筑装饰工程有限公司 Moving type large-scale operation platform
CN102691406A (en) * 2012-06-07 2012-09-26 苏州苏明装饰有限公司 Ceiling model positioning system and construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5816016A (en) * 1995-12-11 1998-10-06 Zarnick; Bernard F. Method of installing acoustical panels in an arena
CN201221193Y (en) * 2008-06-17 2009-04-15 北京城建集团有限责任公司 High altitude packway ceiling construction operating platform
CN101514586A (en) * 2009-01-14 2009-08-26 北京江河幕墙股份有限公司 Hanger rail type electric hanging boat and high-rise long span house, bridge building construction method and use thereof
CN101696601A (en) * 2009-10-19 2010-04-21 上海中建八局装饰有限责任公司 Method for assembling large-area safety net
CN102220795A (en) * 2011-04-14 2011-10-19 广东省建筑装饰工程有限公司 Ceiling system applicable to large-span space steel structure and construction method thereof
CN202324567U (en) * 2011-11-18 2012-07-11 中建七局建筑装饰工程有限公司 Moving type large-scale operation platform
CN102691406A (en) * 2012-06-07 2012-09-26 苏州苏明装饰有限公司 Ceiling model positioning system and construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘兰涛,等: "青岛大剧院音乐厅GRC吊顶板施工技术研究", 《青岛理工大学学报》, vol. 32, no. 4, 30 April 2011 (2011-04-30) *
刘永涛,等: "大空间双曲面室内铝板吊顶施工技术", 《建筑施工》, vol. 36, no. 2, 28 February 2014 (2014-02-28) *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105372034A (en) * 2015-12-07 2016-03-02 昆山市建设工程质量检测中心 Constructional lightgage steel joist and fitting one-piece test apparatus
CN105372034B (en) * 2015-12-07 2017-11-10 昆山市建设工程质量检测中心 Lightgage steel joist and fittings integrated experimental rig for building
CN105822072A (en) * 2016-05-20 2016-08-03 北京西飞世纪门窗幕墙工程有限责任公司 Hoisting construction structure and method for air corridor ceiling
CN105822072B (en) * 2016-05-20 2018-05-18 北京西飞世纪门窗幕墙工程有限责任公司 The lifting construction structure and its construction method of aerial vestibule furred ceiling

Also Published As

Publication number Publication date
CN103912089B (en) 2016-06-08

Similar Documents

Publication Publication Date Title
CN106193618B (en) A kind of aerial steel structure truss construction of Long span
CN1033571C (en) Elevator hoistway working platform
CN104831846B (en) Hoisting method for indoor inclined curtain wall super-large glass
CN113431340B (en) Construction method of rose-shaped special-shaped space grid steel structure
CN205558304U (en) Hoist and mount system of large -scale steel gallery truss
CN109025291A (en) A kind of construction method of separate type precast stair
CN109779244A (en) A kind of self-elevating type elevator hoistway exterior wall creeping formwork operating platform construction
CN113356597A (en) Lifting process of large-span net rack and truss combined roof
CN103912089B (en) A kind of construction method of the lifting furred ceiling of auditorium
CN203143872U (en) Mobile platform for elevator installation construction
CN207700708U (en) A kind of shellring shape ceiling mounted tracks of unit glass curtain wall
CN104404888B (en) A kind of large-scale aerial gradient adjustment Lift-on/Lift-off System and application
CN203430066U (en) Closed protective platform for core tube
CN108894509B (en) Steel structure assembly type house prefabricated sandwich heat-insulation external wall panel construction method without external frame
CN111119493A (en) Construction method for integrally and synchronously lifting light steel keel
CN202023298U (en) Roof truss-sectioned roof girder structure capable of being hoisted by cross type tower crane
CN116062626A (en) Curtain wall hoisting equipment and hoisting method for crown part of super high-rise building tower
CN104060838A (en) Grouping and air-pairing installation method for corridor
CN110424808B (en) Skin construction method of steel structure indirect cooling tower
CN211472175U (en) Aerial working platform device suitable for steel bridge construction
CN102733612B (en) Mounting method of electric hoist orbit
CN218754515U (en) Assembled stair lifting device
CN104806001A (en) Safety operation platform for sliding and lifting of elevator shaft guide rail and construction method
CN2651217Y (en) Elevator lifting slideway working platform
CN207469110U (en) A kind of concrete-steel Beam prefabricated bridge self erecting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant