CN103869216B - The fault handling method and device of network system - Google Patents

The fault handling method and device of network system Download PDF

Info

Publication number
CN103869216B
CN103869216B CN201210526225.1A CN201210526225A CN103869216B CN 103869216 B CN103869216 B CN 103869216B CN 201210526225 A CN201210526225 A CN 201210526225A CN 103869216 B CN103869216 B CN 103869216B
Authority
CN
China
Prior art keywords
power supply
failure
supply unit
user
network system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210526225.1A
Other languages
Chinese (zh)
Other versions
CN103869216A (en
Inventor
叶妍
周霖
靳松华
郭轶
李琼
曾强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING HUASHANG ELECTRIC POWER TECHNOLOGY CENTER
State Grid Corp of China SGCC
Beijing Electric Power Corp
Original Assignee
BEIJING HUASHANG ELECTRIC POWER TECHNOLOGY CENTER
State Grid Corp of China SGCC
Beijing Electric Power Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING HUASHANG ELECTRIC POWER TECHNOLOGY CENTER, State Grid Corp of China SGCC, Beijing Electric Power Corp filed Critical BEIJING HUASHANG ELECTRIC POWER TECHNOLOGY CENTER
Priority to CN201210526225.1A priority Critical patent/CN103869216B/en
Publication of CN103869216A publication Critical patent/CN103869216A/en
Application granted granted Critical
Publication of CN103869216B publication Critical patent/CN103869216B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of fault handling method of network system and device.The fault handling method of the network system includes:Obtain the real time data of the power supply unit in network system;Obtain power supply and lead graph model;The power supply unit of failure is determined according to the real time data;The power supply unit of the failure of this in graph model and user of the power supply relation determination of each user by fault impact are led according to the power supply.The present invention can quickly determine the user that the fault impact is arrived when network system breaks down.

Description

The fault handling method and device of network system
Technical field
The present invention relates to electric field, in particular to the fault handling method and device of a kind of network system.
Background technology
At present, Utilities Electric Co. services a large amount of responsible consumers, including element center and local office of Party, government and army, important place Deng, they exceed the traditional user group defined with economic value, ensure these user security reliable power supplies It is the most important thing of the characteristic work, even more power generation service of supply of electric power with high quality and efficient service.
Power system in long-term application practice, for responsible consumer powered operation engineering construction, production run, Certain technical experience is have accumulated in terms of marketing service, still, there is certain improvement in information communication and business collaboration empty Between, although pass through long-term information engineering construction, electric power information construction has reached a new height, build simultaneously A large amount of degrees of being practical are high, the advanced operation system of technical system, have accumulated mass data resource, but also occur in that simultaneously The problem of network system can not quickly determine the user that the fault impact is arrived when failure.
For the user that the fault impact is arrived can not be quickly determined in correlation technique when network system breaks down The problem of, effective solution is not yet proposed at present.
The content of the invention
It is a primary object of the present invention to provide the fault handling method and device of a kind of network system, to solve in power network The problem of system can not quickly determine the user that the fault impact is arrived when failure.
To achieve these goals, according to an aspect of the invention, there is provided a kind of troubleshooting side of network system Method, including:
Obtain the real time data of the power supply unit in network system;Obtain power supply and lead graph model, wherein, the power supply leads artwork Type includes each power supply unit and each power supply unit in each user in the network system, the network system With the power supply relation of each user;The power supply unit of failure is determined according to the real time data;Graph model is led according to the power supply In the failure power supply unit and each user the determination of power supply relation by fault impact user.
Further, the power supply unit of the failure of this in graph model and the power supply relation of each user are led according to the power supply It is determined that by after the user of fault impact, this method also includes:
Power failure plan information is obtained, the power failure plan information, which includes each power supply unit plan in the network system, to be stopped The period of work;Judge whether the period that the plan of the power supply unit of the failure is stopped includes current time;Wherein, If the period that the plan of the power supply unit of the failure is stopped includes current time, it is determined that failure cause is stopped for plan Electricity;If the period that the plan of the power supply unit of the failure is stopped does not include current time, it is determined that failure cause is non- Scheduled outage.
Further, it is determined that failure cause be scheduled outage after, this method also includes:
The period that the power supply unit plan of the failure is stopped sends the hand-held end by the user of fault impact End.
Further, it is determined that failure cause be unplanned power failure after, this method also includes:
Alarm prompt is carried out by the user of fault impact to this.
Further, in the power supply unit that the failure in graph model is led according to the power supply and the power supply pass of each user System determines that by after the user of fault impact this method also includes:
Obtain the demand information by the user of fault impact;The demand information is classified, the demand information is obtained Demand type;Response message is sent according to the demand type.
To achieve these goals, there is provided a kind of troubleshooting of network system dress according to another aspect of the present invention Put, including:
First acquisition module, the real time data for obtaining the power supply unit in network system;Second acquisition module, is used for Obtain power supply and lead graph model, wherein, the power supply leads graph model including in each user in the network system, the network system Each power supply unit and each power supply unit and the power supply relation of each user;First performing module, is used for The power supply unit of failure is determined according to the real time data;Second performing module, for leading the failure of this in graph model according to the power supply Power supply unit and each user the determination of power supply relation by fault impact user.
Further, the device also includes:
3rd acquisition module, for obtaining power failure plan information, the power failure plan information includes each in the network system The period that individual power supply unit plan is stopped;First judge module, for judging that the plan of power supply unit of the failure stops Whether the period only worked includes current time;Wherein, if the period that the plan of the power supply unit of the failure is stopped Include current time, it is determined that failure cause is scheduled outage;If the time that the plan of the power supply unit of the failure is stopped Section does not include current time, it is determined that failure cause has a power failure to be unplanned.
Further, the device also includes:
3rd performing module, for it is determined that failure cause be scheduled outage after, by the power supply unit plan of the failure The period being stopped sends the handheld terminal by the user of fault impact.
Further, the device also includes:
4th performing module, for determine again failure cause be unplanned power failure after, to the user by fault impact Carry out alarm prompt.
Further, the device also includes:
4th acquisition module, for obtaining the demand information by the user of fault impact;Sort module, for this to be needed Ask information to be classified, obtain the demand type of the demand information;Sending module, for sending response letter according to the demand type Breath.
Power supply unit of the invention by determining failure according to the real time data of power supply unit, leads graph model true according to power supply The user that the power supply unit of the fixed failure has influence on, so as to quickly determine the event when network system breaks down Hinder the user having influence on.
Brief description of the drawings
The accompanying drawing for constituting the part of the application is used for providing a further understanding of the present invention, schematic reality of the invention Apply example and its illustrate to be used to explain the present invention, do not constitute inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is a kind of structure chart of the fault treating apparatus of network system according to embodiments of the present invention;
Fig. 2 is the structure chart of the fault treating apparatus of another network system according to embodiments of the present invention;
Fig. 3 is a kind of flow chart of the fault handling method of network system according to embodiments of the present invention;
Fig. 4 is the flow chart of the fault handling method of another network system according to embodiments of the present invention;
Fig. 5 is the demand response method flow diagram of reception user according to embodiments of the present invention a kind of;And
Fig. 6 is the flow chart of the fault handling method of another network system according to embodiments of the present invention.
Embodiment
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the application can phase Mutually combination.Describe the present invention in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
Fig. 1 is a kind of structure chart of the fault treating apparatus of network system according to embodiments of the present invention, as shown in figure 1, The fault treating apparatus of the network system of the embodiment includes:
First acquisition module 101, the real time data for obtaining the power supply unit in network system.
For example, switch changed position, busbar voltage and power system operating mode real time data can be obtained.
Second acquisition module 102, graph model is led for obtaining power supply, wherein, the power supply, which leads graph model, includes the power network system Each power supply unit and each power supply unit and each user in each user, the network system in system Power supply relation.
The power supply, which leads graph model, to be melted the electric network model from production system, scheduling system, marketing system Close, set up higher level transformer station-higher level's transformer-higher level's bus-higher level with bus outlet switch-higher level with bus outlet- Higher level's outlet switch-higher level's circuit-subordinate's service entrance switch-subordinate's inlet wire-subordinate's inlet wire bus-subordinate is with bus outlet Switch-subordinate is with bus outlet-subordinate's transformer-transformer station of subordinate(Switching station)User's power supply lead graph model;Meanwhile, User's geographical location information, internal operation information, facility information, important load information and internal hidden danger letter can also be included Breath.
First performing module 103, the power supply unit for determining failure according to the real time data.
For example, then the real time data of the power supply unit is relatively sentenced compared with the data of the power supply unit under normal circumstances Break the power supply unit whether failure.
Second performing module 104, power supply unit and each use for leading the failure of this in graph model according to the power supply The power supply relation at family determines the user by fault impact.
For example, the power supply leads power supply unit of the graph model comprising the failure and the power supply relation of each user, if User is powered by the power supply unit of the failure, then the user is the user by fault impact, if user is not by the failure Power supply unit power, then the user is not the user by fault impact.
The fault treating apparatus of network system provided in an embodiment of the present invention, it is true by the real time data according to power supply unit Determine the power supply unit of failure, leading graph model according to power supply determines the user that the power supply unit of the failure has influence on, so as to Network system quickly determines the user that the fault impact is arrived when failure.
Preferably, the fault treating apparatus of the network system of the embodiment includes:
First acquisition module, the real time data for obtaining the power supply unit in network system.
For example, switch changed position, busbar voltage and power system operating mode real time data can be obtained.
Second acquisition module, graph model is led for obtaining power supply, wherein, the power supply leads graph model including in the network system Each user, in the network system each power supply unit and each power supply unit and each user confession Electric relation.
The power supply leads graph model and can be merged the electric network model from production system, scheduling system, marketing system, Set up higher level transformer station-higher level's transformer-higher level's bus-higher level with bus outlet switch-higher level with bus outlet-on Level outlet switch-higher level's circuit-subordinate's service entrance switch-subordinate's inlet wire-subordinate's inlet wire bus-subordinate opens with bus outlet Pass-subordinate is with bus outlet-subordinate's transformer-transformer station of subordinate(Switching station)User's power supply lead graph model;Meanwhile, User's geographical location information, internal operation information, facility information, important load information and internal hidden danger information can be included.
First performing module, the power supply unit for determining failure according to the real time data.
Second performing module, for leading the power supply unit of the failure of this in graph model according to the power supply with each user's Power supply relation determines the user by fault impact.
3rd acquisition module, for obtaining power failure plan information, the power failure plan information includes each in the network system The period that individual power supply unit plan is stopped.
First judge module, for judging period that the plan of power supply unit of the failure is stopped whether comprising working as The preceding time.
Wherein, if the period that the plan of the power supply unit of the failure is stopped includes current time, it is determined that failure Reason is scheduled outage;If the period that the plan of the power supply unit of the failure is stopped does not include current time, it is determined that Failure cause has a power failure to be unplanned.
3rd performing module, for it is determined that failure cause be scheduled outage after, by the power supply unit plan of the failure The period being stopped sends the handheld terminal by the user of fault impact.
4th performing module, for determine again failure cause be unplanned power failure after, to the user by fault impact Carry out alarm prompt.
In addition, can also be to having influence on higher level's power failure, direct-furnish line fault and the direct-furnish of user with parent track event Hinder information and carry out active alarm prompting, for example, fault warning can be divided into active short message alarm, active system alarm prompt two Kind.
The fault treating apparatus of network system provided in an embodiment of the present invention, it is true by the real time data according to power supply unit Determine the power supply unit of failure, leading graph model according to power supply determines the user that the power supply unit of the failure has influence on, so as to Network system quickly determines the user that the fault impact is arrived when failure.
Preferably, Fig. 2 is a kind of structure chart of the fault treating apparatus of network system according to embodiments of the present invention, is such as schemed Shown in 2, the fault treating apparatus of the network system of the embodiment includes:
First acquisition module 201, the real time data for obtaining the power supply unit in network system.
For example, switch changed position, busbar voltage and power system operating mode real time data can be obtained.
Second acquisition module 202, graph model is led for obtaining power supply, wherein, the power supply, which leads graph model, includes the power network system Each power supply unit and each power supply unit and each user in each user, the network system in system Power supply relation.
The power supply leads graph model and can be merged the electric network model from production system, scheduling system, marketing system, Set up higher level transformer station-higher level's transformer-higher level's bus-higher level with bus outlet switch-higher level with bus outlet-on Level outlet switch-higher level's circuit-subordinate's service entrance switch-subordinate's inlet wire-subordinate's inlet wire bus-subordinate opens with bus outlet Pass-subordinate is with bus outlet-subordinate's transformer-transformer station of subordinate(Switching station)User's power supply lead graph model;Meanwhile, User's geographical location information, internal operation information, facility information, important load information and internal hidden danger information can be included.
First performing module 203, the power supply unit for determining failure according to the real time data.
Second performing module 204, power supply unit and each use for leading the failure of this in graph model according to the power supply The power supply relation at family determines the user by fault impact.
4th acquisition module 205, for obtaining the demand information by the user of fault impact.
Sort module 206, for the demand information to be classified, obtains the demand type of the demand information.
Sending module 207, for sending response message according to the demand type.
The fault treating apparatus of network system provided in an embodiment of the present invention, it is true by the real time data according to power supply unit Determine the power supply unit of failure, leading graph model according to power supply determines the user that the power supply unit of the failure has influence on, so as to Network system quickly determines the user that the fault impact is arrived when failure.
Fig. 3 is a kind of flow chart of the fault handling method of network system according to embodiments of the present invention, as shown in figure 3, The fault handling method of the network system of the embodiment includes:
Step 101:Obtain the real time data of the power supply unit in network system.
Step 102:Obtain power supply and lead graph model, wherein, the power supply, which leads graph model, includes each in the network system The power supply relation of each power supply unit and each power supply unit and each user in user, the network system.
Step 103:The power supply unit of failure is determined according to the real time data.
Step 104:The power supply unit of the failure of this in graph model and the power supply relation of each user are led according to the power supply It is determined that by the user of fault impact.
The fault handling method of network system provided in an embodiment of the present invention, it is true by the real time data according to power supply unit Determine the power supply unit of failure, leading graph model according to power supply determines the user that the power supply unit of the failure has influence on, so as to Network system quickly determines the user that the fault impact is arrived when failure.
Preferably, the fault handling method of the network system of the embodiment includes.
Step 201:Obtain the real time data of the power supply unit in network system.
Step 202:Obtain power supply and lead graph model, wherein, the power supply, which leads graph model, includes each in the network system The power supply relation of each power supply unit and each power supply unit and each user in user, the network system.
Step 203:The power supply unit of failure is determined according to the real time data.
Step 204:The power supply unit of the failure of this in graph model and the power supply relation of each user are led according to the power supply It is determined that by the user of fault impact.
Step 205:Power failure plan information is obtained, the power failure plan information includes each power supply unit in the network system Plan the period being stopped.
Step 206:Judge whether the period that the plan of the power supply unit of the failure is stopped includes current time, if It is to perform step 207, if it is not, performing step 208.
Wherein, if the period that the plan of the power supply unit of the failure is stopped includes current time, it is determined that failure Reason is scheduled outage;If the period that the plan of the power supply unit of the failure is stopped does not include current time, it is determined that Failure cause has a power failure to be unplanned.
Step 207:The period that the power supply unit plan of the failure can be stopped sends this by fault impact The handheld terminal of user.
Step 208:It is determined that failure cause be unplanned power failure after, this can be accused by the user of fault impact Alert prompting.
Further, it is also possible to analyze power failure plan information, outage information exhibition is carried out by power failure date and time length Show, task displaying and influence circuit are shown, and then the influence to user is analyzed.And for power supply guarantee, skill Art support, emergency service, Engineering concordance, risk management and control, requirement investigation, special assessment, electrician's training and other services, coordinate Relevant departments of company and resource, activeization service is provided for responsible consumer.Prevention and control risk, ensures the safety of responsible consumer Electricity consumption.
The fault handling method of network system provided in an embodiment of the present invention, it is true by the real time data according to power supply unit Determine the power supply unit of failure, leading graph model according to power supply determines the user that the power supply unit of the failure has influence on, so as to Network system quickly determines the user that the fault impact is arrived when failure.
Preferably, Fig. 4 is a kind of flow chart of the fault handling method of network system according to embodiments of the present invention, is such as schemed Shown in 4, the fault handling method of the network system of the embodiment includes:
Step 301:Obtain the real time data of the power supply unit in network system.
Step 302:Obtain power supply and lead graph model, wherein, the power supply, which leads graph model, includes each in the network system The power supply relation of each power supply unit and each power supply unit and each user in user, the network system.
Step 303:The power supply unit of failure is determined according to the real time data.
Step 304:The power supply unit of the failure of this in graph model and the power supply relation of each user are led according to the power supply It is determined that by the user of fault impact.
Step 305:Obtain the demand information by the user of fault impact.
Step 306:The demand information is classified, the demand type of the demand information is obtained.
Step 307:Response message is sent according to the demand type.
Referring to Fig. 5, Fig. 5 is the demand response method flow diagram of reception user according to embodiments of the present invention a kind of, by To after the demand of user, the demand information of user is classified, then sending different responses according to different classification orders Order.
In addition, referring to Fig. 6, Fig. 6 is the stream of the fault handling method of another network system according to embodiments of the present invention Cheng Tu, after failure occurs, first determines whether accident pattern, and different Service Scheme sides are then formulated for different fault types Case, until restoring electricity, it is ensured that quality of the user to the reliability of supply of electric power, the stability of the quality of power supply and service quality It is required that.
The fault handling method of network system provided in an embodiment of the present invention, it is true by the real time data according to power supply unit Determine the power supply unit of failure, leading graph model according to power supply determines the user that the power supply unit of the failure has influence on, so as to Network system quickly determines the user that the fault impact is arrived when failure.
It should be noted that can be in such as one group computer executable instructions the step of the flow of accompanying drawing is illustrated Performed in computer system, and, although logical order is shown in flow charts, but in some cases, can be with not The order being same as herein performs shown or described step.
Obviously, those skilled in the art should be understood that above-mentioned each module of the invention or each step can be with general Computing device realize that they can be concentrated on single computing device, or be distributed in multiple computing devices and constituted Network on, alternatively, the program code that they can be can perform with computing device be realized, it is thus possible to they are stored Performed in the storage device by computing device, either they are fabricated to respectively each integrated circuit modules or by they In multiple modules or step single integrated circuit module is fabricated to realize.So, the present invention is not restricted to any specific Hardware and software is combined.
The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, for the skill of this area For art personnel, the present invention can have various modifications and variations.Within the spirit and principles of the invention, that is made any repaiies Change, equivalent substitution, improvement etc., should be included in the scope of the protection.

Claims (4)

1. a kind of fault handling method of network system, it is characterised in that including:
Obtain the real time data of the power supply unit in network system;
Obtain power supply and lead graph model, wherein, the power supply, which leads graph model, includes each user in the network system, described The power supply unit of each in network system and each described power supply unit and the power supply relation of each user;
The power supply unit of failure is determined according to the real time data;
The power supply relation that the power supply unit of failure described in graph model and each user are led according to the power supply determine by The user of fault impact,
Wherein, the power supply unit and the power supply relation of each user that failure described in graph model is led according to the power supply are true Determine by after the user of fault impact, methods described also includes:
Power failure plan information is obtained, the power failure plan information, which includes each power supply unit plan in the network system, to be stopped The period of work;
Judge whether the period that the plan of the power supply unit of the failure is stopped includes current time;
Wherein, if the period that the plan of the power supply unit of the failure is stopped includes current time, it is determined that failure is former Because scheduled outage;
If the period that the plan of the power supply unit of the failure is stopped does not include current time, it is determined that failure cause is It is unplanned to have a power failure,
Wherein, in the power supply unit and the power supply relation of each user that failure described in graph model is led according to the power supply It is determined that by after the user of fault impact, methods described also includes:
Obtain the demand information of the user by fault impact;
The demand information is classified, the demand type of the demand information is obtained, wherein, the demand type includes should Anxious power supply requirement, emergency team send demand and emergent spare unit demand;
Response message is sent according to the demand type,
Wherein, it is determined that failure cause be unplanned power failure after, methods described also includes:To the user by fault impact Carry out alarm prompt;To having influence on higher level's power failure, direct-furnish line fault and the direct-furnish of the user with parent track failure Information carries out active alarm prompting.
2. according to the method described in claim 1, it is characterised in that after it is determined that failure cause is scheduled outage, the side Method also includes:
The period that the power supply unit plan of the failure is stopped sends the hand-held end of the user by fault impact End.
3. a kind of fault treating apparatus of network system, it is characterised in that including:
First acquisition module, the real time data for obtaining the power supply unit in network system;
Second acquisition module, graph model is led for obtaining power supply, wherein, the power supply leads graph model including in the network system Each user, each power supply unit and each described power supply unit and each described use in the network system The power supply relation at family;
First performing module, the power supply unit for determining failure according to the real time data;
Second performing module, for the power supply unit that failure described in graph model is led according to the power supply and each described user Power supply relation determine by fault impact user,
Wherein, described device also includes:
3rd acquisition module, for obtaining power failure plan information, the power failure plan information includes each in the network system The period that individual power supply unit plan is stopped;
First judge module, for judging whether the period that the plan of power supply unit of the failure is stopped includes currently Time;
Wherein, if the period that the plan of the power supply unit of the failure is stopped includes current time, it is determined that failure is former Because scheduled outage;
If the period that the plan of the power supply unit of the failure is stopped does not include current time, it is determined that failure cause is It is unplanned to have a power failure;
4th acquisition module, the demand information for obtaining the user by fault impact;
Sort module, for the demand information to be classified, obtains the demand type of the demand information, wherein, it is described Demand type, which includes emergency power supply demand, emergency team, sends demand and emergent spare unit demand;
Sending module, for sending response message according to the demand type,
Wherein, described device also includes:4th performing module, for it is determined that failure cause be unplanned power failure after, to institute State and carried out alarm prompt by the user of fault impact, and to having influence on higher level's power failure, the event of direct-furnish circuit of the user Barrier and direct-furnish carry out active alarm prompting with parent track fault message.
4. device according to claim 3, it is characterised in that described device also includes:
3rd performing module, for it is determined that failure cause be scheduled outage after, the power supply unit plan of the failure is stopped The period only worked sends the handheld terminal of the user by fault impact.
CN201210526225.1A 2012-12-07 2012-12-07 The fault handling method and device of network system Active CN103869216B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210526225.1A CN103869216B (en) 2012-12-07 2012-12-07 The fault handling method and device of network system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210526225.1A CN103869216B (en) 2012-12-07 2012-12-07 The fault handling method and device of network system

Publications (2)

Publication Number Publication Date
CN103869216A CN103869216A (en) 2014-06-18
CN103869216B true CN103869216B (en) 2017-09-29

Family

ID=50907961

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210526225.1A Active CN103869216B (en) 2012-12-07 2012-12-07 The fault handling method and device of network system

Country Status (1)

Country Link
CN (1) CN103869216B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107222339B (en) * 2017-05-27 2020-06-05 全球能源互联网研究院有限公司 Graph database-based fault analysis method and device for power information communication system
CN109698766A (en) * 2018-12-19 2019-04-30 国网辽宁省电力有限公司信息通信分公司 The method and system of communication power supply accident analysis

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101789596B (en) * 2009-01-22 2012-07-25 四川华雁信息产业股份有限公司 Automatic detection method of power grid failure
CN102403798A (en) * 2011-10-31 2012-04-04 广东电网公司江门供电局 Intelligent automatic transformer district monitoring method and system based on GIS (geographical information system)
CN102497018A (en) * 2011-12-04 2012-06-13 江苏省电力公司南京供电公司 Power distribution grid power failure and power supply information push platform and method
CN102646230B (en) * 2012-02-27 2016-03-02 广东电网公司深圳供电局 A kind of infosystem realizing the management of distribution network failure fast power restoration

Also Published As

Publication number Publication date
CN103869216A (en) 2014-06-18

Similar Documents

Publication Publication Date Title
CN103065270B (en) Visual monitored control system is salvageed to electric wire netting trouble
CN108933437B (en) Automatic analysis method for power supply capacity of power distribution network
CN105564465B (en) A kind of railway electric signal plant maintenance operation control system and method
CN103440726B (en) Electric fire disaster warning information processing method and system
CN109188955A (en) A kind of cloud remote supervisory and control(ling) equipment
CN103065215A (en) Power grid dispatching method
CN104535892B (en) A kind of fault detection method and equipment
CN108183814B (en) Troubleshooting method and device for communication channel of electricity utilization information acquisition system
CN105119237B (en) The method that relay protection operation is checked
CN111756581A (en) Power distribution network operation fault processing method and device, computer equipment and storage medium
CN103869216B (en) The fault handling method and device of network system
CN107171438A (en) A kind of net level matches somebody with somebody electricity consumption monitoring and management system
CN103854230A (en) Electric power security risk management and control system and method
CN102692576A (en) Relay protection periodical inspection method
CN103106622A (en) Method and system of power cut overhauling and scheduling
CN108460517A (en) A kind of power distribution network management-control method and device
CN105389667B (en) Support that the distribution system framework of integration is robbed in allotment
CN103473655A (en) Country area company production and operation integrated platform
US20140306819A1 (en) System and a method for locating and notifying fault and handling alarm thereof
CN110048506A (en) Power failure monitoring system and method
CN112730940B (en) User electricity consumption monitoring method and system, computing equipment and storage medium thereof
CN111381156B (en) Distribution room circuit breaker load energy consumption abnormity monitoring method, device, equipment and readable storage medium
CN105321025A (en) Elevator maintenance system and method
CN108306286A (en) A kind of power distribution network active forewarning workform management method and device
CN203102357U (en) An accident auxiliary processing system of a high-voltage DC convertor station

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant