CN103866701A - Construction method for reserved laterally widened structure of underground box culvert structure - Google Patents

Construction method for reserved laterally widened structure of underground box culvert structure Download PDF

Info

Publication number
CN103866701A
CN103866701A CN201210542246.2A CN201210542246A CN103866701A CN 103866701 A CN103866701 A CN 103866701A CN 201210542246 A CN201210542246 A CN 201210542246A CN 103866701 A CN103866701 A CN 103866701A
Authority
CN
China
Prior art keywords
box culvert
side wall
construction
culvert
space enclosing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201210542246.2A
Other languages
Chinese (zh)
Other versions
CN103866701B (en
Inventor
薛勇
温竹茵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201210542246.2A priority Critical patent/CN103866701B/en
Publication of CN103866701A publication Critical patent/CN103866701A/en
Application granted granted Critical
Publication of CN103866701B publication Critical patent/CN103866701B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The invention discloses a construction method for a reserved laterally widened structure of an underground box culvert structure. The method comprises the following steps: carrying out the future expansion on the side walls for the box culvert structure in advance, additionally arranging reinforced concrete pilasters to be used as vertical components for bearing horizontal water and earth pressure during foundation pits excavation in expansion; using top plates, middle plates and bottom plates to support the side walls of expansion sides, and arranging steel bar connectors in the plates. In later expansion, as the pilasters can be used as load-bearing components for lateral support of foundation pits, construction risk, construction difficulty and influence on the normal operation of an already built tunnel are greatly reduced, the construction is simpler and more convenient, and the construction period is shortened.

Description

The Structural Tectonics method of the reserved lateral widening of a kind of Underground Culvert structure
Technical field
The present invention relates to the construction applications of the underground chamber that adopts the construction of Underground Culvert pattern, be particularly related to and adopt the underground chamber (comprising the tunnel such as road, subway) that Underground Culvert pattern is built to require lateral widening that a kind of reserved Structural Tectonics pattern, specifically the Structural Tectonics method of the reserved lateral widening of a kind of Underground Culvert structure are provided for meeting demand at a specified future date.
Background technology
Underground Culvert structure is carried out lateral widening construction often following problem:
1. construction risk is larger, show as and cut the box culvert structure top/bottom part the reinforcement of concrete that put into effect in advance to be connected with the reinforcing bar that the later stage is widened box culvert structure, because box culvert bight hogging moment is larger, cut original box culvert bight concrete and will slacken box culvert structure integrated carrying ability;
2. be consideration 1, can be runing the interim reinforcing of do in box culvert, so by longer the time that affects normally operation;
Due to the box culvert side wall of implementing be in advance difficult to bear construction in later period foundation ditch to support axle power, often difficulty comparatively of the adjustment that now needs to consider Support Position, increases difficulty of construction, duration and construction risk.
Summary of the invention
The object of the present invention is to provide the Structural Tectonics method of the reserved lateral widening of the more simple and convenient Underground Culvert structure of a kind of construction.
To achieve these goals, technical scheme of the present invention is: the Structural Tectonics method of the reserved lateral widening of a kind of Underground Culvert structure, is characterized in that: the method comprises the following steps:
The Underground Culvert structure that A, construction are implemented in advance widen side side wall, the top of its box culvert, in, base plate chooses box culvert side wall and extends to space enclosing structure, and after reserved, build the required top of box culvert, in, baseplate reinforcing bar connector;
B, widen between side structure and space enclosing structure and along box culvert, vertical pilaster is vertically set every a segment distance at box culvert, be convenient to the support arrangement when later stage, excavation was implemented in structure enlarging;
C, the space of widening side box culvert space enclosing structure and its box culvert side wall, side wall pilaster adopt packing material to tamp;
D, later stage are widened enlarging box culvert after space enclosing structure completes, and in foundation ditch, support successively from top to bottom and set up with soil excavation to cheating the end;
E, then successively from the end,, top board dig out successively each laminate connector connect, assembling reinforcement, build each laminate and side wall concrete, return build to top board;
F, dismounting are supported and are recovered ground at top plate earth-covering, and then side wall, vertical pilaster and packing material in the middle of cutting disassembling, complete the concrete structure engineering of extending box culvert.
According to a preferred embodiment of the invention, the packing material in step C adopts air-entrained concrete building block.Support in step D should be erected at vertical pilaster position.
Technical scheme feature of the present invention is: when extending side wall the long term of implementing in advance box culvert structure and adding steel concrete pilaster as enlarging, excavation of foundation pit bears the vertical member of level to Water And Earth Pressures, top, in, base plate chooses enlarging side side wall reinforcing bar connector is set in plate, in when enlarging in later stage, is due to the bearing carrier that can utilize pilaster as foundation ditch cross binding, greatly reduce construction risk and difficulty and the impact on the normal operation of established tunnel, make construction more simple and convenient, save the duration.
Accompanying drawing explanation
Fig. 1 is the structural representation of first building Underground Culvert.
Fig. 2 is the partial schematic diagram of Fig. 1, the partial enlarged drawing that Fig. 2 a is A, the partial enlarged drawing that Fig. 2 b is B, the partial enlarged drawing that Fig. 2 c is C.
Fig. 3 builds the plan view of Underground Culvert after being.
Fig. 4 builds the sectional drawing of Underground Culvert after being.
Fig. 5 has been the structural representation of rear overall box culvert.
The specific embodiment
Below in conjunction with drawings and Examples, the present invention will be further described.
Below in conjunction with accompanying drawing, this method is further described, its methods && steps of implementation is as follows:
The Underground Culvert structure that A, construction are implemented is in advance widened side side wall, widen side at need, to be reinforcing bar be not connected as diaphragm wall reinforcing bar with space enclosing structure for space enclosing structure 2 and inner box culvert structure separation, the top board of box culvert 10, middle plate 11, base plate 12 are chosen to box culvert side wall 3 and extended to and first build space enclosing structure 2, and after reserved, build the required connection of box culvert top, in, baseplate reinforcing bar connector 8(is shown in Fig. 1 and Fig. 2), side wall and the spacing of first building between space enclosing structure 2 are generally 20 ~ 30cm;
B, between box culvert structure and space enclosing structure 2 every a segment distance (according to a particular embodiment of the invention, this distance is preferably 2.5 ~ 3.5m) along box culvert, vertical pilaster 4(is vertically set and sees Fig. 3, material can adopt steel concrete or other), the horizontal support power transmission of being convenient to when the later stage, excavation of foundation pit was implemented in structure enlarging loads, the width and thickness of vertical pilaster meets structural bearing requirement, generally be not less than 80cm, thickness is according to foundation depth and support arrangement, by calculative determination, the computational process is here those skilled in the art's known technology, do not repeat them here,
C, between space enclosing structure 2 and its box culvert side wall pilaster 4 of implementing in advance and side wall 3, adopt and tamp (see figure 3) as the packing materials such as air-entrained concrete building block 5;
D, later stage are built space enclosing structure 6 after widening enlarging enforcement, then in foundation ditch, support successively from top to bottom and 7 set up (support avoid top, in, base plate, but should support in vertical pilaster 4 positions) and soil excavation to cheating at the end (seeing Fig. 3 and Fig. 4), in this step, also should remove more than excavation of foundation pit face the space enclosing structure 2 of part, after build the Excavation Process of box culvert in remove while digging;
E, then successively from the end,, top board (from bottom to up) connector of digging out successively each laminate in order to connecting, assembling reinforcement, build each laminate and side wall concrete until top board (seeing Fig. 3 and Fig. 4);
F, remove to support also and recover ground at top plate earth-covering, then can cutting disassembling side wall 3, vertical pilaster 4 and packing material 5(be shown in part shown in dotted line in Fig. 5), complete the concrete structure engineering of enlarging box culvert.

Claims (3)

1. the Structural Tectonics method of the reserved lateral widening of Underground Culvert structure, it is characterized in that: the method comprises the following steps: the Underground Culvert structure that A, construction are implemented in advance widen side side wall, the top of its box culvert, in, base plate chooses box culvert side wall and extends to space enclosing structure, and after reserved, build the required top of box culvert, in, baseplate reinforcing bar connector; B, widen between side structure and space enclosing structure and along box culvert, vertical pilaster is vertically set every a segment distance at box culvert, be convenient to the support arrangement when later stage, excavation was implemented in structure enlarging; C, the space of widening side box culvert space enclosing structure and its box culvert side wall, side wall pilaster adopt packing material to tamp; D, later stage are widened enlarging box culvert after space enclosing structure completes, and in foundation ditch, support successively from top to bottom and set up with soil excavation to cheating the end; E, then successively from the end,, top board dig out successively each laminate connector connect, assembling reinforcement, build each laminate and side wall concrete, return build to top board; F, dismounting are supported and are recovered ground at top plate earth-covering, and then side wall, vertical pilaster and packing material in the middle of cutting disassembling, complete the concrete structure engineering of extending box culvert.
2. method according to claim 1, is characterised in that: the packing material in step C adopts air-entrained concrete building block.
3. method according to claim 1, is characterised in that: the support in step D should be erected at vertical pilaster position.
CN201210542246.2A 2012-12-14 2012-12-14 Construction method for reserved laterally widened structure of underground box culvert structure Active CN103866701B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210542246.2A CN103866701B (en) 2012-12-14 2012-12-14 Construction method for reserved laterally widened structure of underground box culvert structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210542246.2A CN103866701B (en) 2012-12-14 2012-12-14 Construction method for reserved laterally widened structure of underground box culvert structure

Publications (2)

Publication Number Publication Date
CN103866701A true CN103866701A (en) 2014-06-18
CN103866701B CN103866701B (en) 2017-05-17

Family

ID=50905682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210542246.2A Active CN103866701B (en) 2012-12-14 2012-12-14 Construction method for reserved laterally widened structure of underground box culvert structure

Country Status (1)

Country Link
CN (1) CN103866701B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104164839A (en) * 2014-07-31 2014-11-26 天津市市政工程设计研究院 Construction method for broadening box culvert
CN105221160A (en) * 2015-10-10 2016-01-06 上海市政工程设计研究总院(集团)有限公司 A kind of vertical fork arrangement of staggered floor tunnel
CN107119711A (en) * 2017-07-06 2017-09-01 中国铁路设计集团有限公司 A kind of connected structure and construction method for abutting existing transfer station on a large scale
CN109853624A (en) * 2019-03-29 2019-06-07 山东省交通规划设计院 A kind of enlarging construction method for existing highway rectangle culvert
CN113356092A (en) * 2021-07-05 2021-09-07 中铁上海设计院集团有限公司 Construction method for widening underpass railway frame bridge
CN115852868A (en) * 2023-02-09 2023-03-28 中交路桥华东工程有限公司 Urban rainwater box culvert expansion construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2059261A1 (en) * 1992-01-13 1993-07-14 Earl Turner Culvert extension
JPH0827805A (en) * 1994-07-15 1996-01-30 Yamamoto Chikasui Kenkyusho:Kk Porous wall water absorption tunnel block body, tunnel using it and landslide prevention method making use thereof
EP1200681A1 (en) * 1999-06-25 2002-05-02 Douglas Ian Nicholas Stormwater sediment and litter trap
CN2539721Y (en) * 2002-02-06 2003-03-12 铁岭陆平机器有限责任公司 Corner-cutting spreading square cabin
CN202090297U (en) * 2011-03-28 2011-12-28 郭红军 A highway extension and highway channel new construction assembly box culvert structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2059261A1 (en) * 1992-01-13 1993-07-14 Earl Turner Culvert extension
JPH0827805A (en) * 1994-07-15 1996-01-30 Yamamoto Chikasui Kenkyusho:Kk Porous wall water absorption tunnel block body, tunnel using it and landslide prevention method making use thereof
EP1200681A1 (en) * 1999-06-25 2002-05-02 Douglas Ian Nicholas Stormwater sediment and litter trap
CN2539721Y (en) * 2002-02-06 2003-03-12 铁岭陆平机器有限责任公司 Corner-cutting spreading square cabin
CN202090297U (en) * 2011-03-28 2011-12-28 郭红军 A highway extension and highway channel new construction assembly box culvert structure

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104164839A (en) * 2014-07-31 2014-11-26 天津市市政工程设计研究院 Construction method for broadening box culvert
CN104164839B (en) * 2014-07-31 2016-08-17 天津市市政工程设计研究院 A kind of construction method widening box culvert
CN105221160A (en) * 2015-10-10 2016-01-06 上海市政工程设计研究总院(集团)有限公司 A kind of vertical fork arrangement of staggered floor tunnel
CN105221160B (en) * 2015-10-10 2020-05-19 上海市政工程设计研究总院(集团)有限公司 Vertical bifurcation arrangement structure of staggered floor tunnel
CN107119711A (en) * 2017-07-06 2017-09-01 中国铁路设计集团有限公司 A kind of connected structure and construction method for abutting existing transfer station on a large scale
CN107119711B (en) * 2017-07-06 2022-09-06 中国铁路设计集团有限公司 Connecting structure for large-range adjacent existing transfer station and construction method
CN109853624A (en) * 2019-03-29 2019-06-07 山东省交通规划设计院 A kind of enlarging construction method for existing highway rectangle culvert
CN109853624B (en) * 2019-03-29 2021-09-14 山东省交通规划设计院集团有限公司 Extension construction method for existing highway rectangular culvert
CN113356092A (en) * 2021-07-05 2021-09-07 中铁上海设计院集团有限公司 Construction method for widening underpass railway frame bridge
CN113356092B (en) * 2021-07-05 2023-08-15 中铁上海设计院集团有限公司 Construction method for widening underpass railway frame bridge
CN115852868A (en) * 2023-02-09 2023-03-28 中交路桥华东工程有限公司 Urban rainwater box culvert expansion construction method

Also Published As

Publication number Publication date
CN103866701B (en) 2017-05-17

Similar Documents

Publication Publication Date Title
CN103866701A (en) Construction method for reserved laterally widened structure of underground box culvert structure
CN104652443B (en) Construction method of the interim horizontal support of deep basal pit as permanent structure beam
CN104032744B (en) Support replacement construction method in the engineering of group hole
CN102839674A (en) Foundation pit excavation supporting structure on near end well shield tunnel and construction method of foundation pit excavation supporting structure
CN103510520A (en) Sectionalized construction method of deep and large foundation pit
CN104912098A (en) Combined construction method for supporting beam plate and structural plate of deep foundation pit
CN109505298A (en) A kind of self-balancing foundation pit enclosure method
CN108071122A (en) Assembled underground pipe gallery and its construction method
CN202865850U (en) Near-end shield tunnel foundation pit excavation supporting structure
CN202559375U (en) H-shaped steel underground diaphragm wall base pit support structure
CN102953385B (en) Construction method for changing support of foundation pit at irregular place of rampway
CN202559363U (en) Foundation pit supporting structure for underground diaphragm wall with steel structure
CN202401461U (en) Novel foundation pit shoring structure
JP5351125B2 (en) Open shield machine start method of open shield method
CN102080551B (en) Three-amplitude construction method for inverted arch of primary support of weak broken wall rock tunnel
JP2012026250A (en) Reinforcement structure and reinforcement method of existing retaining wall
CN201874008U (en) Discontinuous concrete grouting pile and wall structure
CN109519198B (en) Grid cage type tunnel temporary inverted arch and installation method thereof
CN103088831A (en) Overall assembly-type double-row steel pile foundation pit supporting structure
CN105696701A (en) Along-slope shear wall building development platform and construction method thereof
CN215715515U (en) Municipal pipe network construction supporting integrated structure under unfavorable geological conditions
CN209798815U (en) It can dismantle cantilever type retaining wall to imitate sideslip prevention by force
CN209907410U (en) Slope reinforcement supporting structure and pile plate retaining wall
CN102587388A (en) PRM (press-anchor-restrict method) foundation pit supporting method
CN109137884B (en) Assembled guide wall of impervious wall and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant