CN103821381B - A kind ofly make the molten building renovation technique be integrated of new and old concrete - Google Patents

A kind ofly make the molten building renovation technique be integrated of new and old concrete Download PDF

Info

Publication number
CN103821381B
CN103821381B CN201410013060.7A CN201410013060A CN103821381B CN 103821381 B CN103821381 B CN 103821381B CN 201410013060 A CN201410013060 A CN 201410013060A CN 103821381 B CN103821381 B CN 103821381B
Authority
CN
China
Prior art keywords
concrete
old concrete
template
new
integrated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410013060.7A
Other languages
Chinese (zh)
Other versions
CN103821381A (en
Inventor
邓浣尘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410013060.7A priority Critical patent/CN103821381B/en
Publication of CN103821381A publication Critical patent/CN103821381A/en
Application granted granted Critical
Publication of CN103821381B publication Critical patent/CN103821381B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The present invention relates to and a kind ofly make the molten building renovation technique be integrated of new and old concrete, its processing step is, first carries out intensity detection, destroys damage or the concrete that burns out of fire, measure the old concrete strength of residue with Schmidt hammer, residue concrete strength >=1OO# (C1O) namely can be used as to strengthen mending repairs foundation admittedly; Then carry out calcium carbide detection, then carry out doing template, carry out template by size, one side will be created smooth in order to the demoulding inwards, and ensure the quality of products for convenience of operation, column template should be divided into two to three joints; Carry out pickling again, wipe the concrete surface of staggering with wet rag clear, dip in pickle with bamboo band handle hairbrush after dry and be evenly applied to old concrete surface; Again smash pouring concrete, first installation form can be smash and water, and sulfuric acid concrete is wanted to smash while insert real, smashes and tamps from charging above to during capital; Finally carry out form removal, concrete can remove template after smashing and watering 2 days, need not showering curing.In sum, pickling technical economic benefit, social benefit and ecological benefits are remarkable, and technology maturation is practical, the feature that DEVELOPMENT PROSPECT is wide.

Description

A kind ofly make the molten building renovation technique be integrated of new and old concrete
Technical field
The invention belongs to concrete structure reforming technology technical field, relate to and a kind ofly make the molten building renovation technique be integrated of new and old concrete.
Background technology
Modern building be unable to do without concrete.Concrete invention and use existing more than 100 year history, brings splendidness to modern architecture industry.But the technical barrier that long-standing problem new-old concrete can not moltenly be integrated, fails effectively to be solved all the time.To maintenance and renovation old building, generally all can make following construction processing: 1. suitably improve concrete strength, to increase adhesion stress; 2. by old concrete surface turk, to increase adhesive power; 3. old concrete is cleaned in cleaning, new-old concrete is contacted as far as possible tightr.
Above-mentioned measure has certain booster action, but fundamentally can not solve new-old concrete and to combine closely problem, will unclamp through new and old concrete after a while, peel off, come off.Trace it to its cause, be concrete ramming after three months, its inside will carbonize, and generates calcium carbide.Calcium carbide does not affect concrete intensity, but it can form separation layer at new-old concrete interface, has a strong impact on both combining closely, brings potential potential safety hazard to maintenance and renovation engineering.
Summary of the invention
For overcoming above-mentioned technical disadvantages, the invention provides one to repair most of obsolete building, the calcium carbide of old concrete interface can be removed, make that new-old concrete is molten to be integrated, what fundamentally can solve that new-old concrete combines closely problem makes the molten pickle that is integrated of new and old concrete and using method thereof simultaneously .
The present invention solves the technical method that its technical problem adopts: a kind ofly make the molten building renovation technique be integrated of new and old concrete, and its processing step is:
The first step: intensity detection, destroys damage or the concrete that burns out of fire, measures the old concrete strength of residue with Schmidt hammer, and residue concrete strength >=1OO# (C1O) namely can be used as to strengthen mending repairs foundation admittedly;
Second step: calcium carbide detects, the old concrete of the part that staggers or destroy the old concrete of damage, dips in upper phenolphthalein liquid with cotton fibre and is applied to the old concrete of residue on the surface, show the old concrete of pink expression and carbonize, should carry out pickling after 1 minute;
3rd step: do template, carry out template by size, one side will be created smooth in order to the demoulding inwards, and ensure the quality of products for convenience of operation, column template should be divided into two to three joints;
4th step: pickling, wipes the concrete surface (not rinsing with water) of staggering clear with wet rag, dips in pickle and is evenly applied to old concrete surface, require once to complete, do not repeat after dry with bamboo band handle hairbrush;
5th step: smash pouring concrete, first installation form can be smash and water, sulfuric acid concrete wants on-the-spot artificial hand to fry, and now fries existing use, how many and how much fries, smash while insert real, namely install second section template and smash after having smash first segment and water, the one side of Section of three template will stay a breach (the top board place of post), finally fills up from breach charging, or from boring a hole upstairs, smashing and tamping from charging above to during capital;
6th step: form removal, concrete can remove template after smashing and watering 2 days, need not showering curing.
Its component of pickle and the weight ratio of described 4th step are: 27% commercial sulphuric acid 1.15 ~ 1.5, clean water 100.
Described 5th step sulfuric acid concrete 1m 3materials: 400 grade cement with 402 kilograms, the cobble smashed or granite stones (particle diameter 10mm) 0.82m 3, medium sand 0.63m 3, clean water 200 kilograms, 27% commercial sulphuric acid 2.21 kilograms.
Described sulfuric acid should load compared with heavy sheet glass bottle or solid plastic ware, and can not use ironware, operating personnel should be with safety goggles, mouth mask, Rubber gloves, wear anti-skidding rubber overshoes, in order to avoid burn.
Sulfuric acid, when preparing, should be poured into water by described pickle and sulfuric acid concrete slowly, with falling with stirring, water can not be poured in sulfuric acid, in order to avoid set off an explosion.
Rubble in described sulfuric acid concrete with the cobble smashed or granite, must forbid limestone.
Described pickle and can not disorderly falling everywhere for the surplus waste water of above-mentioned technique, care should be used to pours sewer into.
During the residual building of described first step detection of fires, for safety, should successively prick to shore in advance and prop up, make provision against emergencies.
Described first step intensity detection, successively should divide flooring, wall, post subregion multi-site determination, ensures that data are representative.
The invention has the beneficial effects as follows: 1, use this technique can repair the building of most of obsolete building, particularly concrete on fire; 2, can significantly reduce costs, the shortening time; 3, applying after the form removal of this technology need not trickle maintenance, can saving water resource and the energy, for the region that freshwater resources lack, has great meaning; In sum, pickling technical economic benefit, social benefit and ecological benefits are remarkable, and technology maturation is practical, the feature that DEVELOPMENT PROSPECT is wide.
Detailed description of the invention
Below in conjunction with embodiment, the present invention is further described.
Make the molten building renovation technique be integrated of new and old concrete, its processing step is:
The first step: intensity detection, destroys damage or the concrete that burns out of fire, measures the old concrete strength of residue with Schmidt hammer, and residue concrete strength >=1OO# (C1O) namely can be used as to strengthen mending repairs foundation admittedly;
Second step: calcium carbide detects, the old concrete of the part that staggers or destroy the old concrete of damage, dips in upper phenolphthalein liquid with cotton fibre and is applied to the old concrete of residue on the surface, show the old concrete of pink expression and carbonize, should carry out pickling after 1 minute;
3rd step: do template, carry out template by size, one side will be created smooth in order to the demoulding inwards, and ensure the quality of products for convenience of operation, column template should be divided into two to three joints;
4th step: pickling, wipes the concrete surface (not rinsing with water) of staggering clear with wet rag, dips in pickle and is evenly applied to old concrete surface, require once to complete, do not repeat after dry with bamboo band handle hairbrush;
5th step: smash pouring concrete, first installation form can be smash and water, sulfuric acid concrete wants on-the-spot artificial hand to fry, and now fries existing use, how many and how much fries, smash while insert real, namely install second section template and smash after having smash first segment and water, the one side of Section of three template will stay a breach (the top board place of post), finally fills up from breach charging, or from boring a hole upstairs, smashing and tamping from charging above to during capital;
6th step: form removal, concrete can remove template after smashing and watering 2 days, need not showering curing.
Its component of pickle and the weight ratio of described 4th step are: 27% commercial sulphuric acid 1.15 ~ 1.5, clean water 100.
Described 5th step sulfuric acid concrete 1m 3materials: 400 grade cement with 402 kilograms, the cobble smashed or granite stones (particle diameter 10mm) 0.82m 3, medium sand 0.63m 3, clean water 200 kilograms, 27% commercial sulphuric acid 2.21 kilograms.
Described sulfuric acid should load compared with heavy sheet glass bottle or solid plastic ware, and can not use ironware, operating personnel should be with safety goggles, mouth mask, Rubber gloves, wear anti-skidding rubber overshoes, in order to avoid burn.
Sulfuric acid, when preparing, should be poured into water by described pickle and sulfuric acid concrete slowly, with falling with stirring, water can not be poured in sulfuric acid, in order to avoid set off an explosion.
Rubble in described sulfuric acid concrete with the cobble smashed or granite, must forbid limestone.
Described pickle and can not disorderly falling everywhere for the surplus waste water of above-mentioned technique, care should be used to pours sewer into.
During the residual building of described first step detection of fires, for safety, should successively prick to shore in advance and prop up, make provision against emergencies.
Described first step intensity detection, successively should divide flooring, wall, post subregion multi-site determination, ensures that data are representative.
Embodiment 1:1991 applies this technology January, repairs the roof truss that in former Shaoguan valve plant, butterfly workshop three Pin damages, only uses fund about 50,000 yuan, 29 days used times, rebuild if dismantle and about need fund 400,000 yuan, about half a year consuming time, contrast economizes on the use of funds 350,000 yuan, time shorten 5 months.
Embodiment 2:1991 applies the Red Star department store, Shaoguan, fire residual building of this technology reparation May, test through 22 years (1991-2013), still as excellent as before, not occurring any problem, is exactly fabulous illustration, whole maintenance cost about 500,000 yuan, the only 105 days used time (time has packed and repaiied air-conditioning, water power, counter interior), if push over reconstruction four layers about need fund 6,630,000 yuan, need to build more than 2 years, contrast economizes on the use of funds 6,130,000 yuan, shortens 24 months time.
Embodiment 3: 70 years last century Shanghai Machinery Import and Export Corporation, buy one and be built in the nineteen twenty-two high three floor half area 3500m in building 2aging blocks, amassed 6000m for reconstructing into six aspects 2new building, earnestly find building constructor 8 years in Shanghai City unmanned ready to work, my company applied this technology after entering and carried out strengthening reconstruction afterwards, became six floor modern architectures.After completion, Shanghai Machinery Import and Export Corporation and Shanghai City capital construction commission very satisfied.Shanghai City capital construction commission has specially met my company cadres and technical personnel, and Shanghai Machinery Import and Export Corporation also sent special messenger afterwards, comes Shaoguan from afar and gives silk banner, express thanks.
The present invention possesses 1, uses this technique can repair the building of most of obsolete building, particularly concrete on fire; 2, can significantly reduce costs, the shortening time; 3, applying after the form removal of this technology need not trickle maintenance, can saving water resource and the energy, for the region that freshwater resources lack, has great meaning; In sum, pickling technical economic benefit, social benefit and ecological benefits are remarkable, and technology maturation is practical, the feature that DEVELOPMENT PROSPECT is wide.

Claims (7)

1. make the molten building renovation technique be integrated of new and old concrete, it is characterized in that processing step is:
The first step: intensity detection, destroys damage or the concrete that burns out of fire, measures the old concrete strength of residue with Schmidt hammer, and residue concrete strength >=1OO# (C1O) namely can be used as to strengthen mending repairs foundation admittedly;
Second step: calcium carbide detects, the old concrete of the part that staggers or destroy the old concrete of damage, dips in upper phenolphthalein liquid with cotton fibre and is applied to the old concrete of residue on the surface, show the old concrete of pink expression and carbonize, should carry out pickling after 1 minute;
3rd step: do template, carry out template by size, one side will be created smooth in order to the demoulding inwards, and ensure the quality of products for convenience of operation, column template should be divided into two to three joints;
4th step: pickling, wipes the concrete surface of staggering clear with wet rag, do not rinse concrete surface with water, dips in pickle and is evenly applied to old concrete surface, require once to complete, do not repeat after dry with bamboo band handle hairbrush;
5th step: smash pouring concrete, first installation form can be smash and water, sulfuric acid concrete wants on-the-spot artificial hand to fry, now fry existing using, want how many how much to fry, smash while insert real, namely install second section template and smash after having smash first segment and water, the one side of Section of three template will stay a breach, and breach is positioned at the top board place of post, finally fill up from breach charging, or from boring hole upstairs, smashing and tamping from charging above to during capital, the rubble in sulfuric acid concrete must with the cobble smashed or granite, forbidding limestone, wherein sulfuric acid concrete 1m 3materials: 400 grade cement with 402 kilograms, the cobble of the particle diameter 10mm smashed or granite stones 0.82m 3, medium sand 0.63m 3, clean water 200 kilograms, 27% commercial sulphuric acid 2.21 kilograms;
6th step: form removal, concrete can remove template after smashing and watering 2 days, need not showering curing.
2. make the molten building renovation technique be integrated of new and old concrete as claimed in claim 1, it is characterized in that: its component of pickle and the weight ratio of described 4th step are: 27% commercial sulphuric acid 1.15 ~ 1.5, clean water 100.
3. make the molten building renovation technique be integrated of new and old concrete as claimed in claim 1, it is characterized in that: described sulfuric acid should load compared with heavy sheet glass bottle or solid plastic ware, can not use ironware, operating personnel should be with safety goggles, mouth mask, Rubber gloves, wear anti-skidding rubber overshoes, in order to avoid burn.
4. make the molten building renovation technique be integrated of new and old concrete as claimed in claim 1, it is characterized in that: sulfuric acid, when preparing, should be poured into water by described pickle and sulfuric acid concrete slowly, with falling with stirring, water can not be poured in sulfuric acid, in order to avoid set off an explosion.
5. make the molten building renovation technique be integrated of new and old concrete as claimed in claim 1, it is characterized in that: described pickle and can not disorderly falling everywhere for the surplus waste water of above-mentioned technique, care should be used to pours sewer into.
6. make the molten building renovation technique be integrated of new and old concrete as claimed in claim 1, it is characterized in that: during the residual building of described first step detection of fires, for safety, should successively prick to shore in advance and prop up, make provision against emergencies.
7. make the molten building renovation technique be integrated of new and old concrete as claimed in claim 1, it is characterized in that: described first step intensity detection, successively should divide flooring, wall, post subregion multi-site determination, ensure that data are representative.
CN201410013060.7A 2014-01-13 2014-01-13 A kind ofly make the molten building renovation technique be integrated of new and old concrete Expired - Fee Related CN103821381B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410013060.7A CN103821381B (en) 2014-01-13 2014-01-13 A kind ofly make the molten building renovation technique be integrated of new and old concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410013060.7A CN103821381B (en) 2014-01-13 2014-01-13 A kind ofly make the molten building renovation technique be integrated of new and old concrete

Publications (2)

Publication Number Publication Date
CN103821381A CN103821381A (en) 2014-05-28
CN103821381B true CN103821381B (en) 2016-03-02

Family

ID=50756646

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410013060.7A Expired - Fee Related CN103821381B (en) 2014-01-13 2014-01-13 A kind ofly make the molten building renovation technique be integrated of new and old concrete

Country Status (1)

Country Link
CN (1) CN103821381B (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3983002B2 (en) * 2001-03-07 2007-09-26 トピー工業株式会社 Method and structure for repairing and reinforcing steel structural members of existing construction structures
KR100432318B1 (en) * 2001-08-24 2004-05-22 김기태 use a carbon point the existing structure of repair & reinforcement method or construction
CN102070317B (en) * 2010-11-26 2012-07-25 北京新奥混凝土集团有限公司 Mineral admixture concrete

Also Published As

Publication number Publication date
CN103821381A (en) 2014-05-28

Similar Documents

Publication Publication Date Title
CN105421254B (en) In-situ repairing method of upper pinner of rail transit bridge support and pinner formwork
CN107059536B (en) A kind of new-to-old concrete interface bar planting adhesive method
CN108032424A (en) A kind of production technology of prefabricated component stair
CN102839824A (en) Steel-bonded reinforcement method for steel structure
CN102678136B (en) Dual-reduction turnover construction process for sprayed concrete
CN105756365B (en) A kind of method of rapid reinforcement beams of concrete
CN101871267B (en) Composite strengthening technology of aged reinforced concrete beam
CN104389439A (en) Strengthening method for reinforced concrete column
CN106316325A (en) High-strength repairing material for concrete cracks and construction method of high-strength repairing material
CN104060760A (en) Layered construction method for oversized concrete beam of structural transfer floor of high-rise building
CN103526953B (en) The roof panel processing method that bearing capacity is inadequate
CN103821381B (en) A kind ofly make the molten building renovation technique be integrated of new and old concrete
CN102676181B (en) Coke oven door lining brick repairing process
CN203546602U (en) Prestressed corrugated-pipe protecting device used in concrete-pouring process of beam
CN104453235B (en) Current conversion station fire wall construction technology
CN110863670A (en) Method for repairing corrosion of tower foot of transmission steel tower
CN101551049B (en) A method for reinforcing overhead concrete pipeline
CN208777143U (en) A kind of oblique prestressing force cement concrete cracks repairing structure
CN106337566A (en) High-strength repairing method for hole of cement prefabricated component
CN205857636U (en) A kind of Mortar spraying machine with elevating function
CN211621264U (en) Glue injection device for treating concrete cracks
CN208056611U (en) A kind of wall-connecting piece being used in turn
CN209429284U (en) A kind of overlength reinforced concrete water pond expansion joint processing mechanism
CN202482897U (en) Concrete structure
CN202787098U (en) Maintenance and reinforcement structure for aged concrete construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160302

Termination date: 20190113