CN101551049B - A method for reinforcing overhead concrete pipeline - Google Patents

A method for reinforcing overhead concrete pipeline Download PDF

Info

Publication number
CN101551049B
CN101551049B CN2009101025522A CN200910102552A CN101551049B CN 101551049 B CN101551049 B CN 101551049B CN 2009101025522 A CN2009101025522 A CN 2009101025522A CN 200910102552 A CN200910102552 A CN 200910102552A CN 101551049 B CN101551049 B CN 101551049B
Authority
CN
China
Prior art keywords
pipeline
steel strand
reinforcing
concrete
crack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009101025522A
Other languages
Chinese (zh)
Other versions
CN101551049A (en
Inventor
孙伟
孙康
叶波
孙家福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUIZHOU KANGXIN CONSTRUCTION REINFORCEMENT TECHNOLOGY Co Ltd
Original Assignee
GUIZHOU KANGXIN CONSTRUCTION REINFORCEMENT TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUIZHOU KANGXIN CONSTRUCTION REINFORCEMENT TECHNOLOGY Co Ltd filed Critical GUIZHOU KANGXIN CONSTRUCTION REINFORCEMENT TECHNOLOGY Co Ltd
Priority to CN2009101025522A priority Critical patent/CN101551049B/en
Publication of CN101551049A publication Critical patent/CN101551049A/en
Application granted granted Critical
Publication of CN101551049B publication Critical patent/CN101551049B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a method for reinforcing overhead concrete pipeline, belonging to the building reinforcement method, which is object to provided a method for repairing and reinforcing concretepipeline. Its technical scheme includes: cleaning pipeline surface, sanding pipeline surface, imbedding encapsulating compound mouth, sealing cracks, injecting encapsulating glue, arranging and tense steel strand, setting several pads and using hoop for banding the steel strands, coating surfactant on the pipeline surface, and applying cement mortar on the pipeline surface. The invention not only has a short duration, low cost, no need of large-scale hoisting machinery, and the like advantages, but also can enhance the structural strength, enhance anti-infiltration, anti-freezing and anti-cra cking and other indicators of the pipeline; and can be widely used for repairing and reinforcing a variety of overhead concrete water transfer and pollution discharge pipelines.

Description

Method for reinforcing overhead concrete pipeline
Technical field:
The present invention relates to a kind of strengthening method of building, relate in particular to a kind of restoring and fastening method of concrete duct.
Background technique:
Concrete duct is a kind of pipeline that extensively adopts in water delivery and the drainage project, and two kinds are generally buried and maked somebody a mere figurehead to its installation form underground; Overhead concrete pipeline causes aging, cracking, reinforcing bar damage such as to expose because of it exposes for a long time easily.At present, the mode of normally taking thoroughly to change is recovered damaged overhead concrete pipeline, therefore has long in time limit, defectives such as cost is high, lifting trouble, and construction period can influence the normal use of pipeline.
Summary of the invention:
At the above-mentioned defective that exists in the prior art, the present invention aim to provide a kind of construction period pipeline still can normally use and the low method for reinforcing overhead concrete pipeline of cost.
To achieve these goals, the present invention is by the following technical solutions: it comprises surface clean, surface finish, mends a split, and concrete steps are as follows:
1) according to a conventional method pipe surface is cleaned;
2) according to a conventional method pipe surface is polished;
3) bury the encapsulating mouth underground at the place, crack, seal the crack, in the crack, fill with base joint grouting glue, seal the encapsulating mouth then by described encapsulating mouth with epoxy resin daub;
4) arrange some steel strand on the surface of pipeline along generatrix direction, the two ends of each described steel strand are separately fixed on the pipe support, strain steel strand then and reach the stress design requirement, guarantee that the spacing of each steel strand reaches designing requirement;
5) some cushion blocks are set between each steel strand and pipeline, each steel strand banding are fixed, guarantee that the steel strand and the spacing of pipeline and the spacing of each stirrup reach designing requirement with some stirrups;
6) pipe surface brushing interfacial agents;
7) pipe surface is smeared and is stuck with paste slush and reach designing requirement.
In technique scheme, described slush can be common slush, but in order to improve the formulated polymer cement mortar of raw material that strengthening quality preferably adopts water and following weight portion: label is that 325 cement 50, sandstone 100, interfacial agents 25, the granularity that granularity is 2~4mm are silica 18, basalt fibre 0.2, entringite type dilatant 0.04, concrete early strength agent 0.04, the concrete early strength water-reducing agent 0.04 of 2~4mm; Wherein, the ratio of water and above-mentioned each raw material disposes according to a conventional method.
Compared with the prior art, the present invention is owing to adopted technique scheme, so biggest advantage is the normal function of use that does not influence pipeline in construction period; Not only have the duration short, cost is low, need not advantage such as large-scale hoisting machinery, but also can improve the intensity of structure, the impermeabilisation, the anti-freezing that strengthen pipeline frozen and index such as cracking resistance.
Embodiment:
Being that 0.8m, length are 120m with the repairing and reinforcement diameter below, be example across the municipal drain pipe of river surface, and the invention will be further described in conjunction with specific embodiments:
Embodiment 1
1) according to a conventional method pipe surface is cleaned the greasy dirt of removal pipe surface, foreign material etc.;
2) according to a conventional method pipe surface is polished to increase the roughness of pipe surface, remove simultaneously that pipe surface exists peel off, deterioration parts such as honeycomb, corrosion, remove the loose material of fracture faces and the foreign matter in the crack;
3) bury disposable encapsulating mouth underground at crack place, the crack is sealed, in the crack, fill with base joint grouting glue by described encapsulating mouth then, sealing encapsulating mouth with epoxy resin daub by the PVC material; The encapsulating mouth is arranged on or termination or the broad place in crack or the infall in crack in crack as far as possible; If the crack is longer, then every interval 0.8~1m is provided with an encapsulating mouth;
4) arrange some steel strand on the surface of pipeline along generatrix direction, the two ends of each described steel strand are fixed on the pipe support by chemical anchor bolts respectively, strain steel strand then and reach the stress design requirement, and guarantee that the spacing of each steel strand is 6cm; It is that 3.5~4mm, the form of the composition are that 6 * 7+IWS metal thigh core regular-lay right lay, tensile strength are the steel strand of 1770N/mm that steel strand adopt diameter;
5) some cushion blocks are set between each steel strand and pipeline, with some stirrups each steel strand banding are fixed, and guarantee that the spacing of steel strand and pipeline reaches 1.5cm, the spacing that guarantees each stirrup is 25cm;
6) in the external coating interfacial agents of pipeline, to improve the cohesive force of slush and pipeline;
7) smear three layers of slush of paste on the surface of pipeline, controlling every layer thickness is about 1cm.
Embodiment 2
Each step is with embodiment 1; Wherein, described slush is substituted with polymer cement mortar can further improve strengthening quality; Described polymer cement mortar is formulated by the raw material of water and following weight portion: label is 325 50 parts of cement, 25 parts of 100 parts of sandstones, the interfacial agents that granularity is 2~4mm, 0.2 part of 8 parts of silica 1s, basalt fibre, 0.04 part of entringite type dilatant, 0.04 part of concrete early strength agent, 0.04 part of the concrete early strength water-reducing agent that granularity is 2~4mm; It is that 3800~4800MPa, diameter are that 0.02mm, length are that the weak point of 5~6cm is cut basalt fibre that described basalt fibre adopts tensile strength.

Claims (2)

1. a method for reinforcing overhead concrete pipeline comprises surface clean, surface finish, mends a split, and it is characterized in that concrete steps are as follows:
1) according to a conventional method pipe surface is cleaned;
2) according to a conventional method pipe surface is polished;
3) bury the encapsulating mouth underground at the place, crack, seal the crack, in the crack, fill with base joint grouting glue, seal the encapsulating mouth then by described encapsulating mouth with epoxy resin daub;
4) arrange some steel strand on the surface of pipeline along generatrix direction, the two ends of each described steel strand are separately fixed on the pipe support, strain steel strand then and reach the stress design requirement, guarantee that the spacing of each steel strand reaches designing requirement;
5) some cushion blocks are set between each steel strand and pipeline, each steel strand banding are fixed, guarantee that the steel strand and the spacing of pipeline and the spacing of each stirrup reach designing requirement with some stirrups;
6) pipe surface brushing interfacial agents;
7) pipe surface is smeared and is stuck with paste slush and reach designing requirement.
2. method for reinforcing overhead concrete pipeline according to claim 1 is characterized in that described slush is by the formulated polymer cement mortar of the raw material of water and following weight portion: label is that 325 cement 50, sandstone 100, interfacial agents 25, the granularity that granularity is 2~4mm are silica 18, basalt fibre 0.2, entringite type dilatant 0.04, concrete early strength agent 0.04, the concrete early strength water-reducing agent 0.04 of 2~4mm.
CN2009101025522A 2009-05-08 2009-05-08 A method for reinforcing overhead concrete pipeline Expired - Fee Related CN101551049B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101025522A CN101551049B (en) 2009-05-08 2009-05-08 A method for reinforcing overhead concrete pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101025522A CN101551049B (en) 2009-05-08 2009-05-08 A method for reinforcing overhead concrete pipeline

Publications (2)

Publication Number Publication Date
CN101551049A CN101551049A (en) 2009-10-07
CN101551049B true CN101551049B (en) 2010-11-10

Family

ID=41155443

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101025522A Expired - Fee Related CN101551049B (en) 2009-05-08 2009-05-08 A method for reinforcing overhead concrete pipeline

Country Status (1)

Country Link
CN (1) CN101551049B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104197129B (en) * 2014-07-25 2017-08-22 深圳市清源管道科技发展有限公司 A kind of novel reinforced concrete drainage pipe and its manufacture method
CN105090677B (en) * 2015-09-30 2017-04-19 山东钢铁股份有限公司 Leakage stoppage method for root leakage of storage tank
CN109723933A (en) * 2019-02-16 2019-05-07 中铝矿业有限公司 A kind of Rapid leakage repairing method of pipeline leakage point
CN110117984A (en) * 2019-05-09 2019-08-13 王福州 Concrete duct settles method for repairing seepage

Also Published As

Publication number Publication date
CN101551049A (en) 2009-10-07

Similar Documents

Publication Publication Date Title
CN101503881B (en) Method for reinforcing underwater structure by fiber-reinforced composite material grid ribs
CN105625197A (en) Concrete beam bending reinforcing method based on steel plate-prestressed carbon fiber plate
CN110952996B (en) Method and material for reinforcing electric power tunnel by fiber grid reinforced polymer mortar
CN103964767B (en) Cement-based composite and mending method of concrete cracks
CN101691818A (en) Building strengthening method
CN104179128A (en) Concrete bridge pier reinforcement method
CN102691851A (en) Method for reinforcing pipeline by adopting fibrous composite fabric
CN104675141A (en) FRP (Fiber Reinforced Plastic) pipe confined cement based composite material reinforced pier column structure
CN102561412A (en) Reinforcement method for fiber reinforced composite plastic and concrete
CN101551049B (en) A method for reinforcing overhead concrete pipeline
CN105650400A (en) Internal strengthening and reinforcing method and strengthening combined structure for PCCP (prestressed concrete cylinder pipes) with broken wires
CN107013040A (en) The construction method of floor is poured after a kind of sleeve built-in type
CN111502326A (en) Rapid prestress FRP grid reinforcing method
CN102587681A (en) Building reinforced structure and reinforcing method
CN104389439A (en) Strengthening method for reinforced concrete column
CN111980180B (en) Concrete permeation reinforcing and protecting structure and construction method thereof
CN1811087A (en) Inner deposited and outer hung heat insulating coating for wall and its making process
CN204060021U (en) The concrete beam that a kind of FRP plate is reinforced
CN201554235U (en) Polymer modified cement mortar reinforcement mesh surface layer reinforcing structure
CN203129623U (en) Composite strengthening structure for building
CN107829568A (en) The small-bore FRP pipes reinforced steel concrete rod structure of prefabricated concrete filled and method
CN107460995A (en) A kind of anti-buckling thin-wall steel tube steel fiber reinforced concrete coupled column and its construction method
JP3880738B2 (en) Reinforcement method of concrete structure by cement mortar composite board with carbon fiber sheet
CN110593600A (en) Beam-slab reinforcing structure of existing building and construction method
CN202483200U (en) Building reinforcing structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101110

Termination date: 20120508