CN103821059A - Lateral restraining and reinforcing structure for stabilizing high-fill embankment with soft oil foundation built on bed rock - Google Patents

Lateral restraining and reinforcing structure for stabilizing high-fill embankment with soft oil foundation built on bed rock Download PDF

Info

Publication number
CN103821059A
CN103821059A CN201410042509.2A CN201410042509A CN103821059A CN 103821059 A CN103821059 A CN 103821059A CN 201410042509 A CN201410042509 A CN 201410042509A CN 103821059 A CN103821059 A CN 103821059A
Authority
CN
China
Prior art keywords
reinforced concrete
embankment
bored pile
side reinforced
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410042509.2A
Other languages
Chinese (zh)
Inventor
姚裕春
李安洪
袁碧玉
徐骏
李楚根
周成
叶世斌
曾永红
李井元
赵青海
张敏静
邓敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201410042509.2A priority Critical patent/CN103821059A/en
Publication of CN103821059A publication Critical patent/CN103821059A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

A lateral restraining and reinforcing structure for stabilizing a high-fill embankment with a soft oil foundation built on a bed rock is used for the lateral restraining and reinforcing of the foundation of the embankment in a region which is limited in the construction of a dug pile. The stability problem of the high-fill embankment and the construction difficulty of the dug pile are overcome, and the problems of insufficient horizontal bearing capability and large deformation of the traditional cast-in-situ bored piles are improved. The structure comprises left reinforced concrete cast-in-situ bored piles and right reinforced concrete cast-in-situ bored piles, which are symmetrically arranged at slope toes at the two sides of the embankment in the longitudinal direction at an interval, left reinforced concrete top beams and right reinforced concrete top beams, which are fixedly connected with the left reinforced concrete cast-in-situ bored piles and the right reinforced concrete cast-in-situ bored piles into a whole are respectively arranged at the tops of the piles, and anchor cables of which the two ends are connected with the top beams in an anchoring way are arranged between the left reinforced concrete top beams and the right reinforced concrete top beams in the extension direction of the embankment at an interval.

Description

The high embankment that covers soft foundation on basement rock is stablized lateral restraint reinforcing construction
Technical field
The present invention relates to geotechnical engineering, the high embankment that particularly covers soft foundation on a kind of basement rock is stablized lateral restraint reinforcing construction.
Background technology
China Higher level railway, highway is built in a large number, in the process of road construction great development, run into a large amount of soft foundation embankment engineerings, and there is the high embankment engineering of a considerable amount of soft foundations, under many circumstances soft foundation being adopted separately to composite foundation stabilization is the stability that can not meet embankment engineering on soft foundation, while overlying on basement rock as weak soil, because composite foundation measure can not enter basement rock, can there is the broken line type sliding failure along bedrock surface in high embankment engineering, at this moment stablizing for high embankment on assurance soft foundation, need to take lateral restraint measure to high embankment engineering, conventionally apply lateral restraint stake, if adopt hole digging pile lateral restraint to reinforce on soft foundation, constructional difficulties is (even if hole digging pile can be constructed, but its working security problem is always controversial, even forbid to use hole digging pile in many countries and regions, in addition, labour cost is also more and more higher), therefore conventionally adopt bored pile, but because Pile footpath is little, Its ultimate bearing capacity is not enough and distortion is larger, its stressed effect of while is bad and construction investment is larger.Therefore solve problems in the urgent need to a kind of new lateral restraint pilework.
Summary of the invention
Technical problem to be solved by this invention is to provide the high embankment that covers soft foundation on a kind of basement rock and stablizes lateral restraint reinforcing construction, applying to the restricted regional road ground lateral restraint of hole digging pile reinforces, to overcome high embankment stability and an excavation pile construction difficult problem, and improve the problem that conventional borehole castinplace pile horizontal bearing capacity is not enough and distortion is large.
The technical solution adopted for the present invention to solve the technical problems is as follows:
The high embankment that covers soft foundation on basement rock of the present invention is stablized lateral restraint reinforcing construction, comprise the embankment of constructing on foundation soil, its feature comprises: under the toe of described embankment both sides, longitudinal separation is symmetrical arranged left side reinforced concrete bored pile, right side reinforced concrete bored pile, its stake top arranges and left side reinforced concrete bored pile respectively, the fixed left side steel concrete Guan Liang being integrated of right side reinforced concrete bored pile, right side steel concrete Guan Liang, left side steel concrete Guan Liang, its two ends difference anchor cable of anchor connection is with it set along embankment bearing of trend interval between the steel concrete hat beam of right side.
The invention has the beneficial effects as follows, applying to the high road ground lateral restraint in the restricted area of hole digging pile reinforces, can solve high embankment stability and excavation pile construction difficult problem, can improve again the problem that conventional borehole castinplace pile horizontal bearing capacity is not enough and distortion is large, improve its stress simultaneously, save the length of construction stake, have obvious economic benefit, structure stress is simply clear and definite, and construction safety, globality are strong, good stability, meet the trend of engineering development, there is wide popularizing application prospect.
Accompanying drawing explanation
This manual comprises following three width accompanying drawings:
Fig. 1 is the cross-sectional drawing that the high embankment that covers soft foundation on basement rock of the present invention is stablized lateral restraint reinforcing construction;
Fig. 2 is the plan view that the high embankment that covers soft foundation on basement rock of the present invention is stablized lateral restraint reinforcing construction;
Fig. 3 is the front view that the high embankment that covers soft foundation on basement rock of the present invention is stablized lateral restraint reinforcing construction;
Component shown in figure, toponym and corresponding mark: left side reinforced concrete bored pile 11, left side steel concrete hat beam 11a, right side reinforced concrete bored pile 12, right side steel concrete hat beam 12a, anchor cable 20, embankment 30, foundation soil A, horizon d B.
The specific embodiment
Below in conjunction with drawings and Examples, the present invention is further described.
With reference to Fig. 1, Fig. 2 and Fig. 3, the high embankment that covers soft foundation on basement rock of the present invention is stablized lateral restraint reinforcing construction, comprises the embankment 30 of constructing on foundation soil A.Under described embankment 30 both sides toes, longitudinal separation is symmetrical arranged left side reinforced concrete bored pile 11, right side reinforced concrete bored pile 12, its top arranges respectively and left side reinforced concrete bored pile 11, fixed left side steel concrete hat beam 11a, the right side steel concrete being integrated of right side reinforced concrete bored pile 12 are preced with beam 12a, between left side steel concrete hat beam 11a, right side steel concrete hat beam 12a, its two ends difference anchor cable 20 of anchor connection is with it set along embankment 30 bearing of trend intervals.
Anchor cable 20 forms lateral restraint to left side reinforced concrete bored pile 11, right side reinforced concrete bored pile 12, effectively solves excavation pile construction difficult problem, and resists high embankment lateral force, guarantees that high embankment is stable.Utilize left side steel concrete hat beam 11a, right side steel concrete hat beam 12a to improve left side reinforced concrete bored pile 11, right side reinforced concrete bored pile 12 globalities and rigidity.Can effectively improve the stress of left side reinforced concrete bored pile 11, right side reinforced concrete bored pile 12 to the anchor cable 20 drawing, unfavorable lateral force outside embankment 30 both sides be converted into mutual utilization to pulling force, can effectively improve Its ultimate bearing capacity and the level of control distortion of combining structure, and can greatly reduce the length that arranges of left side reinforced concrete bored pile 11, right side reinforced concrete bored pile 12, thereby save construction investment.This structure has that globality is strong, good stability, stressed simple clear and definite, and the advantage such as safety and environmental protection, meets the trend of engineering development, has wide popularizing application prospect.
Described left side steel concrete hat beam 11a, right side steel concrete hat beam 12a arrange shrinkage joint every 20~30m one in the middle of adjacent two left side reinforced concrete bored piles 11, right side reinforced concrete bored pile 12.When foundation soil A is soft layer, the degree of depth that the bottom of described left side reinforced concrete bored pile 11, right side reinforced concrete bored pile 12 enters ground horizon d B through foundation soil A is no less than 3m.
Described the anchor cable 20 drawing is determined row is set according to high road ground lateral force size.Anchor cable 20 must be carried out anti-corrosion measure and guarantee its durability, when it is installed, answers stretch-draw straight, and initial stage stretching force should not be greater than 10% of anchorage cable design stretching force.
The high embankment that covers soft foundation on the above basement rock of the present invention that just explains through diagrams is stablized some principles of lateral restraint reinforcing construction, be not the present invention to be confined to shown in and in described concrete structure and the scope of application, therefore the corresponding modify being likely utilized every and equivalent, all belong to the scope of the claims that the present invention applies for.

Claims (4)

1. the high embankment that covers soft foundation on basement rock is stablized lateral restraint reinforcing construction, comprise the embankment (30) of constructing on foundation soil (A), its feature comprises: under the toe of described embankment (30) both sides, longitudinal separation is symmetrical arranged left side reinforced concrete bored pile (11), right side reinforced concrete bored pile (12), its stake top arranges and left side reinforced concrete bored pile (11) respectively, the fixed left side steel concrete Guan Liang (11a) being integrated of right side reinforced concrete bored pile (12), right side steel concrete Guan Liang (12a), left side steel concrete Guan Liang (11a), its two ends difference anchor cable of anchor connection (20) is with it set along embankment (30) bearing of trend interval between right side steel concrete Guan Liang (12a).
2. the high embankment that covers soft foundation on basement rock as claimed in claim 1 is stablized lateral restraint reinforcing construction, it is characterized in that: described left side steel concrete Guan Liang (11a), right side steel concrete Guan Liang (12a) arrange one shrinkage joint in the middle of adjacent two left side reinforced concrete bored piles (11), right side reinforced concrete bored pile (12) every 20~30m.
3. the high embankment that covers soft foundation on basement rock as claimed in claim 1 is stablized lateral restraint reinforcing construction, it is characterized in that: the degree of depth that the bottom of described left side reinforced concrete bored pile (11), right side reinforced concrete bored pile (12) enters ground horizon d (B) through foundation soil (A) is no less than 3m.
4. the high embankment that covers soft foundation on basement rock as claimed in claim 1 is stablized lateral restraint reinforcing construction, it is characterized in that: the spacing of described anchor cable (20) is not less than 3m.
CN201410042509.2A 2014-01-28 2014-01-28 Lateral restraining and reinforcing structure for stabilizing high-fill embankment with soft oil foundation built on bed rock Pending CN103821059A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410042509.2A CN103821059A (en) 2014-01-28 2014-01-28 Lateral restraining and reinforcing structure for stabilizing high-fill embankment with soft oil foundation built on bed rock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410042509.2A CN103821059A (en) 2014-01-28 2014-01-28 Lateral restraining and reinforcing structure for stabilizing high-fill embankment with soft oil foundation built on bed rock

Publications (1)

Publication Number Publication Date
CN103821059A true CN103821059A (en) 2014-05-28

Family

ID=50756327

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410042509.2A Pending CN103821059A (en) 2014-01-28 2014-01-28 Lateral restraining and reinforcing structure for stabilizing high-fill embankment with soft oil foundation built on bed rock

Country Status (1)

Country Link
CN (1) CN103821059A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948233A (en) * 2017-03-15 2017-07-14 温州市阳光建设有限公司 A kind of town road asphalt concrete construction method
CN108867200A (en) * 2018-06-05 2018-11-23 中铁二院工程集团有限责任公司 A kind of Resistant heave high-speed railway rock chasm structuref and design method
CN111118993A (en) * 2019-11-03 2020-05-08 中铁二院工程集团有限责任公司 Embankment high-cantilever bilateral road shoulder pile slab wall reinforcing structure and construction method
CN111691250A (en) * 2020-05-25 2020-09-22 中国路桥工程有限责任公司 Construction method and equipment for cement concrete pavement
CN113215864A (en) * 2021-05-08 2021-08-06 中铁二院工程集团有限责任公司 Earth-rock interbed embankment structure and design method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0796776B2 (en) * 1990-09-03 1995-10-18 鹿島建設株式会社 Yamadome method
JPH1114476A (en) * 1997-06-19 1999-01-22 Nishiki:Kk Earth pressure measuring method using clinometer and safety managing system
CN101962929A (en) * 2010-11-05 2011-02-02 华中科技大学 Novel method for processing soft soil subgrade by pile-supporting reinforcing technology
CN202323922U (en) * 2011-09-09 2012-07-11 中铁二院工程集团有限责任公司 Tilted stratum soft foundation reinforcing structure of high-speed railway
CN103306289A (en) * 2013-06-28 2013-09-18 中国三冶集团有限公司第一建筑工程公司 Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN204325837U (en) * 2014-01-28 2015-05-13 中铁二院工程集团有限责任公司 Basement rock covers the high roadbed reclamation lateral restraint reinforcing construction of soft foundation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0796776B2 (en) * 1990-09-03 1995-10-18 鹿島建設株式会社 Yamadome method
JPH1114476A (en) * 1997-06-19 1999-01-22 Nishiki:Kk Earth pressure measuring method using clinometer and safety managing system
CN101962929A (en) * 2010-11-05 2011-02-02 华中科技大学 Novel method for processing soft soil subgrade by pile-supporting reinforcing technology
CN202323922U (en) * 2011-09-09 2012-07-11 中铁二院工程集团有限责任公司 Tilted stratum soft foundation reinforcing structure of high-speed railway
CN103306289A (en) * 2013-06-28 2013-09-18 中国三冶集团有限公司第一建筑工程公司 Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN204325837U (en) * 2014-01-28 2015-05-13 中铁二院工程集团有限责任公司 Basement rock covers the high roadbed reclamation lateral restraint reinforcing construction of soft foundation

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948233A (en) * 2017-03-15 2017-07-14 温州市阳光建设有限公司 A kind of town road asphalt concrete construction method
CN108867200A (en) * 2018-06-05 2018-11-23 中铁二院工程集团有限责任公司 A kind of Resistant heave high-speed railway rock chasm structuref and design method
CN111118993A (en) * 2019-11-03 2020-05-08 中铁二院工程集团有限责任公司 Embankment high-cantilever bilateral road shoulder pile slab wall reinforcing structure and construction method
CN111691250A (en) * 2020-05-25 2020-09-22 中国路桥工程有限责任公司 Construction method and equipment for cement concrete pavement
CN111691250B (en) * 2020-05-25 2021-11-23 中国路桥工程有限责任公司 Construction method and equipment for cement concrete pavement
CN113215864A (en) * 2021-05-08 2021-08-06 中铁二院工程集团有限责任公司 Earth-rock interbed embankment structure and design method thereof
CN113215864B (en) * 2021-05-08 2022-05-03 中铁二院工程集团有限责任公司 Earth-rock interbed embankment structure and design method thereof

Similar Documents

Publication Publication Date Title
CN103758134B (en) A kind of construction method combining Double-row Piles Support system
CN205134331U (en) Foundation ditch excavation bearing structure
CN202830942U (en) Combined supporting structure with anchor cables and cast-in-situ bored piles
CN103821059A (en) Lateral restraining and reinforcing structure for stabilizing high-fill embankment with soft oil foundation built on bed rock
CN205013013U (en) Secretly dig station supporting construction suitable for last soft hard formation down
CN103774675A (en) Combined double-row-pile combined vertical prestress anchor rod supporting system and construction method thereof
CN105178327A (en) Composite retaining structure of foundation pit project and construction method thereof
CN103726488A (en) Pi-shaped concrete pile
CN108277814A (en) Stake top counterfort wall supporting construction and construction method
CN109441456A (en) A kind of the tunnel structure and its construction method of weakness Facility-sliding strata
CN104895121B (en) Transverse partition method for reducing ground surface settlement and building structure deformation of underground structure construction
CN104727340A (en) High cutting slope anchor rope space framework supporting and retaining structure
CN105155548A (en) Cable double-row pile (wall) supporting structure
CN103243724A (en) Bedding cutting high slope closing reinforcement structure
CN204325837U (en) Basement rock covers the high roadbed reclamation lateral restraint reinforcing construction of soft foundation
CN204940298U (en) A kind of Composite Enclosure Structure of base pit engineering
CN204780938U (en) Novel recoverable anchor formula double row pile supporting construction that draws
CN103643687A (en) Frame type anti-skid cutting structure
CN110055973A (en) Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time
CN103527204A (en) Wall-first arch-second cross middle partition wall tunnel construction method
CN109538236A (en) A kind of tunnel structure and tunnel construction method
CN203547763U (en) High backfilling anti-sliding open cut tunnel structure
CN204491683U (en) A kind of ruggedized construction to municipal piping lane existing within the scope of deep pit digging
CN209195412U (en) A kind of tunnel structure suitable for weak Facility-sliding strata
CN204662246U (en) steep slope bridge pier structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140528