CN103778683B - A kind of tunnel structure electronic polling system and its application method - Google Patents

A kind of tunnel structure electronic polling system and its application method Download PDF

Info

Publication number
CN103778683B
CN103778683B CN201210415286.0A CN201210415286A CN103778683B CN 103778683 B CN103778683 B CN 103778683B CN 201210415286 A CN201210415286 A CN 201210415286A CN 103778683 B CN103778683 B CN 103778683B
Authority
CN
China
Prior art keywords
electronic
inspection
electronic tag
data acquisition
sensor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210415286.0A
Other languages
Chinese (zh)
Other versions
CN103778683A (en
Inventor
周质炎
杨玉泉
赵晓燕
杨元伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201210415286.0A priority Critical patent/CN103778683B/en
Publication of CN103778683A publication Critical patent/CN103778683A/en
Application granted granted Critical
Publication of CN103778683B publication Critical patent/CN103778683B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Alarm Systems (AREA)

Abstract

The invention discloses a kind of tunnel structure electronic polling system, electronic polling system mainly includes electronic tag, sensor data acquisition module, electronic tag scanner, electronic cyclic instrument and the terminal with positioning function.The present invention is not only able to carry out quantitative assessment and timely early warning and feedback to tunnel structure disease, it and being capable of specification inspection workflow, patrol officer is made to be detached from original paper formula inspection work, ensure the arrival rate of patrol officer, ensure that data are true and reliable, the work incentive and work quality of patrol officer is improved, prevents false retrieval and missing inspection.The unfavorable factors such as the arrival rate of the invention for both having overcome original manual inspection is low, work quality is not high, personnel's enthusiasm is not strong, it overcomes again when being monitored using sensor automation, the drawbacks of disease other than monitoring region is not easy to identify, thus as substituting a kind of novel maintenance technology of conventional tunnel structure maintenance work.

Description

A kind of tunnel structure electronic polling system and its application method
Technical field
The present invention relates to a kind of tunnel structure maintenance technologies, and in particular to a kind of tunnel structure electronic polling system and its Application method.
Background technology
The defense structure that tunnel passes through as city vehicle, is generally in adverse circumstances, inevitable within the operation phase Ground is by various influences, so as to which the durability of structure, reliability and safety be made constantly to reduce.Due to tunnel have mileage it is long, The features such as passing through complicated geology, inner space relative closure so that it is very inconvenient to carry out in the maintenance work of operation phase.
At present, the tunnel maintenance work in China is still the hand inspection based on paper form formula, that is, manages the personnel of supporting according to The detecting appraisal table being set at the scene checks constructional appearance situation this test mode is time-consuming, laborious, data Accuracy is poor and personnel's enthusiasm is not high enough, false retrieval and missing inspection easily occurs, personnel's arrival rate is low, and to the pass of tunnel structure Key cannot be quantified by force parameter and be detected, so that cannot early warning early to the urgent accident occurred in tunnel;Moreover, using During sensor automation monitoring of structures state, the status information other than Sensor monitoring region cannot still be predicted well, because And easily cause great Loss of Life and property.
Invention content
It is an object of the invention to propose a kind of tunnel structure electronic polling system, which is not only able to specification maintenance and patrols Examine work, it is ensured that tunnel structure maintenance work quality, and improve work efficiency.
To realize this purpose, technical scheme is as follows:A kind of tunnel structure electronic polling system, is characterized in that Each inspection point is provided with electronic tag in tunnel structure, in addition, the device still includes electronic cyclic instrument, with the electronic cyclic The electronic tag scanner of instrument connection, the terminal being connect with the electronic cyclic instrument, in part, inspection point is equipped with sensing Device and the data acquisition module with sensor cooperation, the electronic cyclic instrument and the data acquisition module are wirelessly It is communicated.Electronic tag uses active or non-active operation mode, and read-write frequency uses low frequency, intermediate frequency or high frequency.Electronic tag Scanner and electronic cyclic instrument for mutually independent equipment or become one.Data acquisition locating module is adopted including data Collect module protection cover, data acquisition memory module, electronic tag is equipped in the data acquisition module protective cover and positioned at data Acquire the analog and digital signal modular converter between memory module and electronic tag, the data acquisition memory module and sensor It is connected, data acquisition memory module and analog and digital signal modular converter and analog and digital signal modular converter and electronics mark It is connected between label by communication line.Data acquisition module is the data acquisition equipment with built-in electronic tag, is not only had Data acquire and store function, and can send data to built-in electronic tag, so as to fulfill sensor and inspection point Positioning, and convenient for the acquisition and read-write of electronic cyclic instrument progress data.The sensor, data acquisition module and electronic tag energy It is enough to be laid in tunnel structure inside or surface for a long time in a manner of pre-buried or surface mount.
It is a further object of the present invention to provide a kind of application methods of tunnel structure electronic polling system, and this method is with electronics Inspection device is not only able to specification maintenance inspection work to rely on, it is ensured that tunnel structure maintenance work quality, and improve work Make efficiency.
To realize this purpose, technical scheme is as follows:A kind of user of tunnel structure electronic polling system Method, it is characterised in that this method includes the following steps:Inspection work planning is completed on computer terminals, that is, determines each secondary inspection Action, inspection point position and the corresponding patrol officer of task, then data management terminal inspection open space planning is sent out It send to each electronic cyclic instrument, patrol officer holds electronic cyclic instrument and carries out data acquisition to scene;Position in being planned by inspection Be laid with electronic tag, sensor and the data that coordinate with the sensor and acquire locating module, each electronic tag and Data acquire locating module and corresponding inspection point is corresponding, patrol officer according to inspection programme path in electronic cyclic instrument, according to It is secondary to carry out inspection by inspection point each in ordered pair tunnel structure, at each inspection point, by electronic tag scanner to electronics mark Label scanning, and information is fed back into electronic cyclic instrument, electronic cyclic instrument calls the inspection point institute according to the information in electronic tag It is required that the scope of examination, checked by patrol officer and judged, personnel to be inspected are completed after checking information at this, will be corresponding Inspection result is written to electronic tag by scanner and is stored, when being laid with sensor at inspection point, patrol officer with Wireless mode collects monitoring parameters in electronic cyclic instrument from the mating data acquisition module of sensor, and by live inspection Electronic tag built in information write-in data acquisition module completes the inspection work at the inspection point, according to the monitoring parameters Determine the safe class of the inspection point.
The present invention realizes all electronic of tunnel structure inspection work, specification tunnel structure using electronic equipment to rely on Inspection works, it is ensured that the arrival rate and work quality of patrol officer improves efficiency and enthusiasm, and therefore, which provides A kind of new paragon of tunnel structure maintenance work.
Description of the drawings
Fig. 1 forms schematic diagram for the structure of electronic polling system relied in the present invention.
Fig. 2 is that the data acquisition module block structure in the present invention with positioning function forms schematic diagram.
Fig. 3 is the sensor layout diagram of one embodiment of the invention, and wherein Fig. 3 a are the section load diagram of the embodiment, Fig. 3 b are section bending moment diagram, and Fig. 3 c are the sensor artwork of the embodiment.
Fig. 4 is the curve graph of polling period.
Specific embodiment
A kind of tunnel structure electronic polling system, it is characterised in that in tunnel structure 1 each inspection point be provided with sensor 3, With data acquisition module 4, the electronic tag 2 of sensor cooperation, which includes electronic cyclic instrument 6, the electronic tag scanner 5 being connect with the electronic cyclic instrument, the terminal 7 being connect with the electronic cyclic instrument.This The technical solution of invention mainly rely on tunneling electron cruising inspection system complete, the system mainly include electronic cyclic instrument 6, sensor 3, 7 six part of data acquisition module 4, electronic tag 2, electronic tag scanner 5 and terminal with positioning function is such as schemed 1 signal.
The data acquisition module 4 with positioning function includes the data being connected with sensor 3 acquisition and storage mould in Fig. 2 Block 8, built-in electronic tag 9, analog and digital signal modular converter 10, built-in data acquisition module and analog-to-digital conversion and mould Communication line 11 between number conversion and electronic tag, data acquisition module, analog-to-digital conversion module, electronic tag and communication line are equal Included in data acquisition module protective cover 12, to be pasted on body structure surface or to be embedded in inside configuration.
Sensor 3 in Fig. 1 is laid in 1 inside of tunnel structure or surface for a long time in a manner of pre-buried or surface mount, with Obtain the status information of operation phase tunnel structure;Data memory module 4 is used to acquire and the monitoring data of storage sensor 3, and The data of storage are periodically sent to built-in electronic tag;Electronic cyclic instrument 6 is used for the acquisition of live inspection data;Electronics mark Label 2 are laid in 1 inside of tunnel structure or surface for a long time in a manner of pre-buried or surface mount, for inspection point location and when secondary The record of inspection result and inspection information;Electronic tag scanner 5 mainly according to the instruction of electronic cyclic instrument, completes electronic tag The reading writing working of information;Terminal 7 is mainly used for completing the storage of inspection work planning and inspection result and management work Make.
According to a particular embodiment of the invention, can be that all inspection points are equipped with electronic tag 2 or part inspection point Equipped with electronic tag 2, inspection point in part is equipped with sensor 3, the sensor 3 and 4 mating setting of data acquisition module, general next The type for saying sensor 3 is mainly displacement meter, strain gauge, reinforcing rib meter, earth pressure gauge and convergence gauge etc., and each sensor 3 should be chosen The key sections of tunnel structure stress are laid, the positions of key sections should according to the practical geological conditions passed through in tunnel and by Power situation is simultaneously chosen after calculating and analyzing, and should generally be chosen at bearing capacity relatively weakness under least favorable load action There are biased position, segment joint position etc. in the larger position of the poor position of position, residing geological conditions, water pressure, every A key sections sensor is preferably laid in deformation or the larger position of internal force etc., such as in the relatively weak section of bearing capacity and has The section of bias should add strain gauge according to actual loading, and position that is poor in geological conditions and having section of jurisdiction longitudinal seam should be added Displacement meter and earth pressure gauge.
According to one embodiment of present invention, certain tunnel outer radius is 3.00m, inside radius 2.70m, and section of jurisdiction width is 1.2m, section of jurisdiction thickness are 0.3m, and piecemeal number is 6 pieces, and section of jurisdiction concrete is C50.The geological condition of the Tunnel Passing from up to It is respectively artificial earth fill, silt and silty clay, silty sand clay down;Tunnel is located in farinose argillic horizon, buried depth 10m ~ 30m; Underground water is 1 ~ 3m of subsurface.By taking the section of buried depth 12m as an example, stress is as shown in Figure 3a(Wherein data unit is kNm). Under least favorable load action, section institute bending moment such as Fig. 3 b(Wherein data unit is kNm), section of jurisdiction inside top and It is pressurized on the inside of tension on the outside of side, section of jurisdiction top outer and side, moment of flexure maximum value is respectively 125.5 kNm and 80 kN M according to concrete material characteristic, should lay strain gauge 11 in position as shown in Fig. 3 c on the outside of the section of jurisdiction inside top and side, When monitor value is more than 58με(The crack stress of corresponding concrete)When, it should pay close attention to, when monitor value is more than 800μεWhen, Ying Jin Enter the state of alert.
The inspection that the position setting of inspection point is then provided according to terminal is planned to complete, in general, inspection point position By tunnel component(Tunnel duct piece, vertical shaft, unicom road, guarded drainage facility etc.)It lays respectively, it should be long by component when being laid per component Degree or area are evenly dividing, and for the more serious disease occurred during inspection, inspection point should be added at this, strengthens inspection It looks into.The vertical range of the laying height distance pavement of road of inspection point should be less than 2m.The electronic cyclic instrument has corresponding inspection Software can be acquired and store to inspection data, and with wired or wireless data-transformation facility.
The polling period of tunnel inspection work is preferably calculated by following equation,
Wherein N represents the design life of structure,nRepresent the service time of structure, D represents the inspection week of inspection work Phase.By the formula it is found that structure polling period meets curvilinear motion relationship shown in Fig. 4 with the service time(It is with N=100 year Example).Tunnel structure is at the initial stage of building up it can be seen from the curve(0 ~ 20 year)Polling period is preferably 40 days ~ 37 days, runs mid-term (21 years ~ 60 years)Polling period be preferably 37 days ~ 32 days, run the later stage(61 years ~ 100 years)Preferably 32 days ~ 7 days.
The workflow of tunnel structure electronization cruising inspection system is as follows.
First, inspection work planning is completed on computer terminals, that is, determines action, the inspection of each secondary patrol task Position and corresponding patrol officer are put, then inspection open space planning is sent to each electronic cyclic instrument by data management terminal, is patrolled Inspection personnel hold electronic cyclic instrument and carry out data acquisition to scene;Position in being planned by inspection be laid with electronic tag, Sensor and the data acquisition locating module with sensor cooperation, each electronic tag and data acquisition locating module and phase The inspection point answered is corresponding, and patrol officer is according to inspection programme path in electronic cyclic instrument, successively by each in ordered pair tunnel structure Inspection point carries out inspection, and at each inspection point, electronic tag is scanned, and information is fed back to by electronic tag scanner Electronic cyclic instrument, electronic cyclic instrument call the scope of examination required by the inspection point, by inspection according to the information in electronic tag Personnel are checked and are judged, and personnel to be inspected are completed after checking information at this, and corresponding inspection result is write by scanner Enter to electronic tag and stored, when being laid with sensor at inspection point, patrol officer adopts the data mating with sensor The data of collection module are wirelessly collected in electronic cyclic instrument, and live inspection information is written built in data acquisition module Electronic tag, complete the inspection work at the inspection point, the safe class of the inspection point determined according to the monitoring parameters. In electronic cyclic instrument, by the monitoring parameters of sensor(The strain value of such as key sections, section of jurisdiction faulting of slab ends value, soil pressure force value)By three Grade is divided, respectively safe condition(In the range of the safety value of parameter), pay close attention to state(Safety value ~ ginseng of parameter The 40% of number limiting value)And the state of alert(The 60% of 40% ~ parameter limits of parameter limits), when being judged as paying close attention to During state, the polling period at the inspection point is preferably foreshortened into original 1/3rd, monitoring;When be judged as warning shape During state, inspection should be carried out daily, and report relevant departments, find out disease causes in time and repair.
The present invention realizes all electronic of tunnel structure inspection work, specification inspection people using electronic equipment to rely on The work on the spot of member improves patrol officer's work quality, efficiency and enthusiasm, and therefore, which provides a kind of tunnel Structure maintenance work new paragon.

Claims (4)

1. a kind of tunnel structure electronic polling system is characterized in that in tunnel structure each inspection point is provided with electronic tag, this Outside, which further includes electronic cyclic instrument, the electronic tag scanner being connect with the electronic cyclic instrument, with the electronic cyclic The terminal of instrument connection, in part, inspection point is equipped with sensor and acquires positioning mould with the mating data of the sensor Block, the electronic cyclic instrument are wirelessly communicated with data acquisition locating module;
The sensor, data acquisition locating module and electronic tag can be for a long time laid in a manner of pre-buried or surface mount Inside tunnel structure or surface;
Sensor is displacement meter, strain gauge, reinforcing rib meter, earth pressure gauge or convergence gauge, and sensor is arranged on tunnel structure stress Key sections, be included in the poor position of the relatively weak position of bearing capacity under least favorable load action, residing geological conditions, There are biased position, segment joint position in the larger position of water pressure;
At each inspection point, electronic tag is scanned, and information is fed back to electronic cyclic instrument by electronic tag scanner, Electronic cyclic instrument calls the scope of examination required by the inspection point, is examined by patrol officer according to the information in electronic tag It looks into and judges, personnel to be inspected are completed after checking information at this, and corresponding inspection result is written by electronic tag scanner It is stored to electronic tag, when being laid with sensor at inspection point, patrol officer is wirelessly mating from sensor Monitoring parameters are collected in electronic cyclic instrument in data acquisition locating module, and the write-in data acquisition of live inspection information is fixed Electronic tag built in the module of position completes the inspection work at the inspection point, the inspection point is determined according to the monitoring parameters Safe class, and polling period is adjusted according to the safe class.
2. electronic polling system as described in claim 1, it is characterised in that it is fixed that data acquisition locating module includes data acquisition Position module protection cover, be equipped in the data acquisition locating module protective cover data acquisition memory module, built-in electronic tag with And acquire the analog and digital signal modular converter between memory module and built-in electronic tag, the data acquisition positioned at data Memory module is connected with sensor, data acquisition memory module and analog and digital signal modular converter and analog and digital signal It is connected between modular converter and built-in electronic tag by communication line.
3. electronic polling system as described in claim 1, it is characterised in that the geological condition of certain Tunnel Passing divides from top to bottom It Wei not artificial earth fill, silt and silty clay, silty sand clay;Tunnel is located in farinose argillic horizon, buried depth 10m ~ 30m;Underground Water is 1 ~ 3m of subsurface, on the section of buried depth 12m, tension on the outside of section of jurisdiction inside top and side, and section of jurisdiction top outer and side It is pressurized on the inside of face, section of jurisdiction inside top moment of flexure maximum value is 125.5 kNm, and moment of flexure maximum value is 80 on the outside of the side of section of jurisdiction KNm according to concrete material characteristic, lays strain gauge on the outside of the section of jurisdiction inside top and side, when monitor value is more than 58με When, it should pay close attention to, when monitor value is more than 800μεWhen, the state of alert should be entered.
A kind of 4. application method of tunnel structure electronic polling system as described in claim 1, it is characterised in that this method packet Include following steps:Inspection work planning is completed on computer terminals, that is, determines action, the inspection point of each secondary patrol task Position and corresponding patrol officer, then terminal inspection work planning is sent to each electronic cyclic instrument, inspection people The hand-held electronic cyclic instrument of member carries out data acquisition to scene;It carries out being laid with electronics by the inspection point position in inspection work planning Label, sensor and the data acquisition locating module with sensor cooperation, each electronic tag and data acquisition positioning mould Block is corresponding with corresponding inspection point respectively, and patrol officer is according to inspection work planning in electronic cyclic instrument, successively by ordered pair tunnel Each inspection point carries out inspection in road structure, at each inspection point, electronic tag is scanned by electronic tag scanner, and will Information feeds back to electronic cyclic instrument, and electronic cyclic instrument calls the inspection required by the inspection point according to the information in electronic tag Content is checked by patrol officer and is judged, and personnel to be inspected are completed after checking information at this, and corresponding inspection result is led to It crosses electronic tag scanner and is written to electronic tag and stored, when being laid with sensor at inspection point, patrol officer is with nothing Line mode collects monitoring parameters in electronic cyclic instrument, and scene is patrolled from the mating data acquisition locating module of sensor The electronic tag built in information write-in data acquisition locating module is examined, the inspection work at the inspection point is completed, according to the prison The safe class that parameter determines the inspection point is surveyed, and polling period is adjusted according to the safe class.
CN201210415286.0A 2012-10-26 2012-10-26 A kind of tunnel structure electronic polling system and its application method Active CN103778683B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210415286.0A CN103778683B (en) 2012-10-26 2012-10-26 A kind of tunnel structure electronic polling system and its application method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210415286.0A CN103778683B (en) 2012-10-26 2012-10-26 A kind of tunnel structure electronic polling system and its application method

Publications (2)

Publication Number Publication Date
CN103778683A CN103778683A (en) 2014-05-07
CN103778683B true CN103778683B (en) 2018-06-19

Family

ID=50570878

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210415286.0A Active CN103778683B (en) 2012-10-26 2012-10-26 A kind of tunnel structure electronic polling system and its application method

Country Status (1)

Country Link
CN (1) CN103778683B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104504769A (en) * 2014-12-03 2015-04-08 上海市政工程设计研究总院(集团)有限公司 Electronic disease collection system for rail transit bridge and tunnel structure and collection and analysis method
CN104965477A (en) * 2015-01-29 2015-10-07 中铁建大桥工程局集团第一工程有限公司 Tunnel automatic monitoring system and method
CN106846529A (en) * 2016-12-12 2017-06-13 国网北京市电力公司 The method for inspecting and inspection device of cable
CN107424237A (en) * 2017-06-20 2017-12-01 中国铝业股份有限公司 A kind of new equipment method for inspecting
CN107270912B (en) * 2017-07-13 2021-02-05 成都天奥电子股份有限公司 Room patrol management system based on indoor positioning technology and working method thereof
CN109948759B (en) * 2019-03-25 2022-04-01 云南云路工程检测有限公司 Method for maintaining and inspecting tunnel based on RFID technology
CN110245734A (en) * 2019-06-26 2019-09-17 重庆交通大学 Tunnel structure disease recognition System and method for based on rail mounted crusing robot
CN111271127B (en) * 2020-01-19 2021-11-30 北京海益同展信息科技有限公司 Environment detection method, equipment and system
CN115457674B (en) * 2022-08-18 2024-02-02 深圳市华毓科技有限公司 Park safety management method, device and storage medium

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101059875A (en) * 2007-04-13 2007-10-24 沈阳唯实数码科技发展有限公司 Hand-held mobile electronic visiting system with fingerprint identity recognition function, and the visiting method
CN101136110A (en) * 2007-08-15 2008-03-05 常州信力汉克电子有限公司 Safety patrolling and checking management system
CN201063174Y (en) * 2007-04-13 2008-05-21 沈阳唯实数码科技发展有限公司 Handhold mobile electric inspection system with fingerprint personal identification function
CN101673420A (en) * 2009-09-27 2010-03-17 西安迅腾科技有限责任公司 System and method for comprehensively examining wireless sensor network node
CN101847285A (en) * 2010-04-16 2010-09-29 深圳市洲智电子有限公司 Radio frequency identification device (RFID) management system for routing inspection and point inspection
CN102176252A (en) * 2011-01-26 2011-09-07 新疆中钜电子科技有限公司 Equipment and facility safety inspection intelligent patrolling operation system and application method thereof
CN202150874U (en) * 2011-08-11 2012-02-22 广东商学院 Electric power equipment patrolling and checking system
CN102509367A (en) * 2011-10-28 2012-06-20 江苏省电力公司常州供电公司 Three-dimensional (3D) simulation polling system of electric power automation motor room
CN102722917A (en) * 2012-06-27 2012-10-10 上海格瑞特科技实业有限公司 Comprehensive equipment and pipeline inspection and management system and method
CN102750753A (en) * 2012-06-25 2012-10-24 惠州紫旭科技有限公司 System and method for routing inspection
CN202887275U (en) * 2012-10-26 2013-04-17 上海市政工程设计研究总院(集团)有限公司 Electronic patrolling device for tunnel structure

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101059875A (en) * 2007-04-13 2007-10-24 沈阳唯实数码科技发展有限公司 Hand-held mobile electronic visiting system with fingerprint identity recognition function, and the visiting method
CN201063174Y (en) * 2007-04-13 2008-05-21 沈阳唯实数码科技发展有限公司 Handhold mobile electric inspection system with fingerprint personal identification function
CN101136110A (en) * 2007-08-15 2008-03-05 常州信力汉克电子有限公司 Safety patrolling and checking management system
CN101673420A (en) * 2009-09-27 2010-03-17 西安迅腾科技有限责任公司 System and method for comprehensively examining wireless sensor network node
CN101847285A (en) * 2010-04-16 2010-09-29 深圳市洲智电子有限公司 Radio frequency identification device (RFID) management system for routing inspection and point inspection
CN102176252A (en) * 2011-01-26 2011-09-07 新疆中钜电子科技有限公司 Equipment and facility safety inspection intelligent patrolling operation system and application method thereof
CN202150874U (en) * 2011-08-11 2012-02-22 广东商学院 Electric power equipment patrolling and checking system
CN102509367A (en) * 2011-10-28 2012-06-20 江苏省电力公司常州供电公司 Three-dimensional (3D) simulation polling system of electric power automation motor room
CN102750753A (en) * 2012-06-25 2012-10-24 惠州紫旭科技有限公司 System and method for routing inspection
CN102722917A (en) * 2012-06-27 2012-10-10 上海格瑞特科技实业有限公司 Comprehensive equipment and pipeline inspection and management system and method
CN202887275U (en) * 2012-10-26 2013-04-17 上海市政工程设计研究总院(集团)有限公司 Electronic patrolling device for tunnel structure

Also Published As

Publication number Publication date
CN103778683A (en) 2014-05-07

Similar Documents

Publication Publication Date Title
CN103778683B (en) A kind of tunnel structure electronic polling system and its application method
CN103968800B (en) A kind of shield tunnel deformation wireless monitor system and method
CN202688979U (en) Integral monitoring system of foundation pit under construction
CN108280969A (en) A kind of high slope surface deformation monitoring and warning system and its method for early warning
CN103088806B (en) A kind of high-fill roadbed and earth and rockfill dam are out of shape wireless real time monitoring system
CN103353280B (en) For in-ground sensor network and the dispositions method thereof of the monitoring of highway life-span
CN107024425A (en) Cold area's roadbed freeze thawing monitoring system and its implementation
CN202330214U (en) Displacement-sensor-based real-time detection system for compaction degree of foundation
CN108519044A (en) A kind of measuring system and measurement method of foundation pit deformation
CN109459094A (en) Grid displacement test system and method based on ten axle sensors
CN104504769A (en) Electronic disease collection system for rail transit bridge and tunnel structure and collection and analysis method
CN111636406A (en) Intelligent monitoring system for dynamic compaction machine
CN106323223B (en) Highway cutting slope deformation monitoring and early warning system
CN209639759U (en) A kind of downstream Tailings Dam dam inside ess-strain comprehensive monitor system
CN107025771A (en) A kind of massif disaster intelligent monitoring early warning system
CN106638728A (en) Method for sensing and checking danger of deep foundation pit in real time
CN201142127Y (en) Landslide monitoring apparatus
CN206399414U (en) One kind is based on GPRS power transmission line line pole tower tilt detection systems
CN109458924B (en) Resistance smart grid deformation testing system and method based on ten-axis sensor
CN208172969U (en) A kind of high slope surface deformation monitoring and warning system
CN212620695U (en) Automatic monitoring system for subway engineering structure
CN215447745U (en) Monitoring system for tunnel exit side slope
CN109342226A (en) Geology electronic map display systems and geology electronic map marker method
CN207923106U (en) A kind of foundation pit deformation measuring device
CN214372603U (en) Intelligent road safety monitoring and operation management system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant