CN103711504A - 地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法 - Google Patents

地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法 Download PDF

Info

Publication number
CN103711504A
CN103711504A CN201310699942.9A CN201310699942A CN103711504A CN 103711504 A CN103711504 A CN 103711504A CN 201310699942 A CN201310699942 A CN 201310699942A CN 103711504 A CN103711504 A CN 103711504A
Authority
CN
China
Prior art keywords
tunnel section
shield
face
tunnel segment
glass fiber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310699942.9A
Other languages
English (en)
Other versions
CN103711504B (zh
Inventor
陈寿根
周泽林
张国亮
刘继强
王太平
宁锐
韩雪峰
张恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
Original Assignee
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University filed Critical Southwest Jiaotong University
Priority to CN201310699942.9A priority Critical patent/CN103711504B/zh
Publication of CN103711504A publication Critical patent/CN103711504A/zh
Application granted granted Critical
Publication of CN103711504B publication Critical patent/CN103711504B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

一种地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法,其步骤是:A、施工完矿山隧道段后在其掌子面前方围岩内水平打入钢套筒,再对掌子面施做喷浆支护;B、紧贴喷浆支护绑扎分隔端头墙的玻璃纤维筋,且玻璃纤维筋与其后的环梁用钢筋绑扎连接,环梁用钢筋又与矿山隧道段的初期支护预留钢筋头焊接连接;再浇筑分隔端头墙和环梁;C、在矿山隧道段底部浇筑混泥土弧形导台;D、盾构机接近矿山隧道段时,降低推进速度,被收容于钢套筒之中;然后,盾构机直接对钢套筒内的围岩、掌子面的喷浆支护和分隔端头墙进行切削破除,并进行注浆、清渣,直至盾构机通过环梁而接收于弧形混泥土导台上。该方法的施工风险低,施工简单、效率高、成本低。

Description

地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法
技术领域
本发明涉及一种地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法。
背景技术
目前修建地铁隧道碰到长距离硬岩地层时,采用盾构掘进存在推进速度慢和刀具磨损快等缺点。因此,常先采用矿山法进行硬岩隧道开挖形成矿山隧道段,然后盾构机推进至盾构隧道段与矿山隧道段结合部位时,先破除分隔端头墙使盾构机进入矿山隧道段,实现盾构隧道段与矿山隧道段的贯通。
由于矿山隧道段要先于盾构隧道段较长一段时间完成,因此,矿山隧道段的掌子面长时间的暴露会使其稳定性逐渐变差,只靠对掌子面施做简单的喷浆支护不足以保证掌子面长期的稳定性,当盾构机到达后并推进至掌子面前方时,盾构机强大的推力作用使掌子面非常容易发生整体坍塌,造成掌子面附近的土层失稳。失稳后处理难度大,增加修建成本和施工风险。
为了保证掌子面的整体稳定性,传统的做法是在盾构隧道段与矿山隧道段的结合部位施做一道钢架混泥土端头墙,盾构机到达前先人工破除该端头墙,然后盾构推进通过结合部位。这种方法在施工中具有较高的风险,尤其是在人工凿除端头墙的过程中风险达到最大:端头墙结构支档着其背后的土体,一旦破除该端头墙,土体将暴露,地层与支档结构之间的力学平衡状态被打破,同时在盾构机强大的推力作用下容易发生土体坍塌,造成地表沉陷,甚至发生人员伤亡事故,是盾构施工中的一个重要的风险因素。
由于盾构机通过结合部位后,盾构机机身将与矿山隧道段对接并进入矿山隧道内的弧形导台上,此时盾构推进路线与隧道设计轴线之间允许偏差误差率低,现有的施工方法对盾构推进偏差的控制要求高、难度大,需要反复调整,存在施工困难、费时长、效率低、成本高等缺点。
发明内容
本发明的目的是提供一种地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法,用该方法施工,盾构隧道段与矿山隧道段结合部位的土体不易失稳,施工风险低,施工简单、效率高、成本低。
本发明实现其发明目的所采用的技术方案是,一种地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法,其步骤是:
一种地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法,其步骤是:
A、先施工完毕矿山隧道段,然后在矿山隧道段掌子面前方围岩内水平打入圆形的钢套筒,钢套筒的后端面与掌子面齐平,再对掌子面施做喷浆支护;
B、紧贴喷浆支护绑扎分隔端头墙的玻璃纤维筋,且玻璃纤维筋与其后面的环梁用钢筋绑扎连接,环梁用钢筋又与矿山隧道段的初期支护预留的钢筋头焊接连接;再浇筑分隔端头墙和环梁;
C、在矿山隧道段底部浇筑混泥土弧形导台;
D、盾构隧道段的盾构机接近矿山隧道段时,降低推进速度,被收容于钢套筒之中;然后,盾构机保持低速推进,直接对钢套筒内的围岩、掌子面的喷浆支护和分隔端头墙进行切削破除,同时进行注浆、清渣,直至盾构机全部通过环梁而被接收于矿山隧道段的弧形混泥土导台上。
与现有技术相比,本发明具的有益效果是:
一、本发明中采用的玻璃纤维筋代替传统钢筋浇筑分隔端头墙,玻璃纤维筋一方面具有与混泥土的黏结强度小、弹性模量小、延性较低、易脆断等特点,在盾构刀盘的削切作用下易断裂,从而可以采用盾构机直接对端头墙进行切削推进而无需人工凿除端头墙,减小了人工凿除端头墙过程中的施工风险,同时加快了施工进度、降低了施工成本;另一方面,玻璃纤维筋又具有抗拉强度高、承载能力大、耐冲击性能好的等特点,并且玻璃纤维筋通过环梁的钢筋与矿山隧道段的钢筋连接,从而分隔端头墙在被切削前能保证掌子面的整体稳定性,同时在被切削后留下的部分也具有较高的抗拉强度,自身稳定性好,也能保证周围土体不失稳,其施工风险小。
二、两隧道段的结合部位盾构机在钢套筒及环梁内推进,通过钢套筒及环梁的定位,能够保证盾构机在顺利削切结合部位围岩和分隔端头墙时,能精确的推进到矿山隧道内的弧形导台上,避免了盾构推进方向的偏差,降低了施工难度,也提高了隧道的掘进效率,降低了施工成本。
三、两隧道段的结合部位打入的钢套筒能对周围的围岩提供较大的支护作用,减少了盾构机掘进时对围岩的扰动,而无需对该部位围岩进行注浆加固,也减少了施工步骤,提高了施工效率。
作为上述技术方案的进一步改进,上述的分隔端头墙墙体内玻璃纤维筋区直径大于钢套筒的外径。
这样,分隔端头墙切削后的剩余部分保留有足够的与环梁钢筋及矿山隧道段支护钢筋相连的玻璃纤维筋,进一步保证切削后的分隔端头墙不失稳,施工风险小。
下面结合附图和具体实施方式对本发明作进一步的详细说明。
附图说明
图1是本发明实施例中盾构机刚被收容于钢套筒之中时的地铁隧道的纵断面示意图。
图2是图1中A-A横断面示意图。
图3是图1中B处的放大图。
具体实施方式
图1-3示出,本发明的一种实施方式是,一种地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法,其步骤是:
一种地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法,其步骤是:
A、先施工完毕矿山隧道段21,然后在矿山隧道段21掌子面21a前方围岩内水平打入圆形的钢套筒31,钢套筒31的后端面与掌子面21a齐平,再对掌子面21a施做喷浆支护;
B、紧贴喷浆支护绑扎分隔端头墙的玻璃纤维筋34,且玻璃纤维筋34与其后面的环梁用钢筋35绑扎连接,环梁用钢筋35又与矿山隧道段21的初期支护22预留的钢筋头36焊接连接;再浇筑分隔端头墙32和环梁33;
C、在矿山隧道段21底部浇筑混泥土弧形导台23;
D、盾构隧道段11的盾构机12接近矿山隧道段21时,降低推进速度,被收容于钢套筒31之中;然后,盾构机12保持低速推进,直接对钢套筒31内的围岩、掌子面的喷浆支护和分隔端头墙32进行切削破除,同时进行注浆、清渣,直至盾构机12全部通过环梁33而被接收于矿山隧道段21的弧形混泥土导台23上。
本例的分隔端头墙32墙体内玻璃纤维筋区直径大于钢套筒的外径。

Claims (2)

1.一种地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法,其步骤是:
A、先施工完毕矿山隧道段(21),然后在矿山隧道段(21)掌子面(21a)前方围岩内水平打入圆形的钢套筒(31),钢套筒(31)的后端面与掌子面(21a)齐平,再对掌子面(21a)施做喷浆支护;
B、紧贴喷浆支护绑扎分隔端头墙的玻璃纤维筋(34),且玻璃纤维筋(34)与其后面的环梁用钢筋(35)绑扎连接,环梁用钢筋(35)又与矿山隧道段(21)的初期支护(22)预留的钢筋头(36)焊接连接;再浇筑分隔端头墙(32)和环梁(33);
C、在矿山隧道段(21)底部浇筑混泥土弧形导台(23);
D、盾构隧道段(11)的盾构机(12)接近矿山隧道段(21)时,降低推进速度,被收容于钢套筒(31)之中;然后,盾构机(12)保持低速推进,直接对钢套筒(31)内的围岩、掌子面的喷浆支护和分隔端头墙(32)进行切削破除,同时进行注浆、清渣,直至盾构机(12)全部通过环梁(33)而被接收于矿山隧道段(21)的弧形混泥土导台(23)上。
2.根据权利要求1所述的地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法,其特征在于:所述的分隔端头墙(32)墙体内玻璃纤维筋(34)区域的直径大于钢套筒(31)的外径。
CN201310699942.9A 2013-12-18 2013-12-18 地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法 Expired - Fee Related CN103711504B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310699942.9A CN103711504B (zh) 2013-12-18 2013-12-18 地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310699942.9A CN103711504B (zh) 2013-12-18 2013-12-18 地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法

Publications (2)

Publication Number Publication Date
CN103711504A true CN103711504A (zh) 2014-04-09
CN103711504B CN103711504B (zh) 2016-02-03

Family

ID=50404807

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310699942.9A Expired - Fee Related CN103711504B (zh) 2013-12-18 2013-12-18 地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法

Country Status (1)

Country Link
CN (1) CN103711504B (zh)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863651A (zh) * 2016-05-30 2016-08-17 中铁工程装备集团有限公司 一种盾构与新奥法相结合的隧道施工方法
CN106285691A (zh) * 2016-08-05 2017-01-04 中铁工程装备集团有限公司 一种护盾式多臂掘进机与新奥法相结合的隧道施工方法
CN106907164A (zh) * 2017-03-27 2017-06-30 中铁隧道勘测设计院有限公司 一种水底矿山盾构隧道组合对接结构形式及其施工方法
CN107091101A (zh) * 2017-03-27 2017-08-25 中铁隧道勘测设计院有限公司 海域中部矿山盾构交接隧道叠合型接头结构及施工方法
CN109026043A (zh) * 2018-09-18 2018-12-18 中铁第六勘察设计院集团有限公司 一种长距离水下隧道矿山盾构动态自联合敷设型式及方法
CN109505612A (zh) * 2018-12-21 2019-03-22 中铁二十五局集团第五工程有限公司 大下坡暗挖隧道盾构空推结构及施工工艺
CN110080296A (zh) * 2019-04-29 2019-08-02 中铁四局集团有限公司 一种用于盾构洞门地连墙的单侧玻璃筋-钢筋笼结构
CN110159291A (zh) * 2019-05-06 2019-08-23 广州电力设计院有限公司 隧道施工方法及隧道结构
CN110792457A (zh) * 2019-10-12 2020-02-14 成都建工路桥建设有限公司 一种盾构顶掘过矿山法隧道的洞门结构安装方法
CN110905527A (zh) * 2019-12-11 2020-03-24 中铁二十局集团第四工程有限公司 一种上软下硬地层隧道施工方法
CN112901176A (zh) * 2020-12-24 2021-06-04 南昌轨道交通集团有限公司 一种减少扰动的盾构机通过方法

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE1029262B1 (fr) * 2022-06-24 2023-07-25 China 19Th Metallurgical Group Co Ltd Méthode de construction de la section de passage du tunnel par la méthode du bouclier et la méthode de la mine

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1072995A (ja) * 1996-08-30 1998-03-17 Taisei Corp 分岐トンネルの構築方法および本線トンネルの分岐部の構造
CN101403307A (zh) * 2008-08-04 2009-04-08 中铁十一局集团城市轨道工程有限公司 复合土压平衡盾构机穿越浅埋富水砂层的施工方法
CN102400694A (zh) * 2011-10-28 2012-04-04 上海市第一市政工程有限公司 盾构隧道与矿山法隧道结合部的加固方法
CN103206228A (zh) * 2013-03-28 2013-07-17 西南交通大学 一种盾构隧道用柔性管片

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1072995A (ja) * 1996-08-30 1998-03-17 Taisei Corp 分岐トンネルの構築方法および本線トンネルの分岐部の構造
CN101403307A (zh) * 2008-08-04 2009-04-08 中铁十一局集团城市轨道工程有限公司 复合土压平衡盾构机穿越浅埋富水砂层的施工方法
CN102400694A (zh) * 2011-10-28 2012-04-04 上海市第一市政工程有限公司 盾构隧道与矿山法隧道结合部的加固方法
CN103206228A (zh) * 2013-03-28 2013-07-17 西南交通大学 一种盾构隧道用柔性管片

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863651B (zh) * 2016-05-30 2018-06-22 中铁工程装备集团有限公司 一种盾构与新奥法相结合的隧道施工方法
CN105863651A (zh) * 2016-05-30 2016-08-17 中铁工程装备集团有限公司 一种盾构与新奥法相结合的隧道施工方法
CN106285691A (zh) * 2016-08-05 2017-01-04 中铁工程装备集团有限公司 一种护盾式多臂掘进机与新奥法相结合的隧道施工方法
CN106285691B (zh) * 2016-08-05 2018-08-03 中铁工程装备集团有限公司 一种护盾式多臂掘进机与新奥法相结合的隧道施工方法
CN107091101B (zh) * 2017-03-27 2023-09-01 中铁第六勘察设计院集团有限公司 海域中部矿山盾构交接隧道叠合型接头结构及施工方法
CN106907164A (zh) * 2017-03-27 2017-06-30 中铁隧道勘测设计院有限公司 一种水底矿山盾构隧道组合对接结构形式及其施工方法
CN107091101A (zh) * 2017-03-27 2017-08-25 中铁隧道勘测设计院有限公司 海域中部矿山盾构交接隧道叠合型接头结构及施工方法
CN109026043A (zh) * 2018-09-18 2018-12-18 中铁第六勘察设计院集团有限公司 一种长距离水下隧道矿山盾构动态自联合敷设型式及方法
CN109026043B (zh) * 2018-09-18 2023-11-10 中铁第六勘察设计院集团有限公司 一种长距离水下隧道矿山盾构动态自联合敷设型式及方法
CN109505612A (zh) * 2018-12-21 2019-03-22 中铁二十五局集团第五工程有限公司 大下坡暗挖隧道盾构空推结构及施工工艺
CN110080296A (zh) * 2019-04-29 2019-08-02 中铁四局集团有限公司 一种用于盾构洞门地连墙的单侧玻璃筋-钢筋笼结构
CN110080296B (zh) * 2019-04-29 2021-02-02 中铁四局集团有限公司 一种用于盾构洞门地连墙的单侧玻璃筋-钢筋笼结构
CN110159291A (zh) * 2019-05-06 2019-08-23 广州电力设计院有限公司 隧道施工方法及隧道结构
CN110792457A (zh) * 2019-10-12 2020-02-14 成都建工路桥建设有限公司 一种盾构顶掘过矿山法隧道的洞门结构安装方法
CN110905527A (zh) * 2019-12-11 2020-03-24 中铁二十局集团第四工程有限公司 一种上软下硬地层隧道施工方法
CN110905527B (zh) * 2019-12-11 2021-09-03 中铁二十局集团第四工程有限公司 一种上软下硬地层隧道施工方法
CN112901176A (zh) * 2020-12-24 2021-06-04 南昌轨道交通集团有限公司 一种减少扰动的盾构机通过方法

Also Published As

Publication number Publication date
CN103711504B (zh) 2016-02-03

Similar Documents

Publication Publication Date Title
CN103711504B (zh) 地铁隧道中盾构隧道段与矿山隧道段结合部位的推进方法
CN110017144B (zh) 一种考虑基底加固处理的黄土隧道三台阶施工方法
CN101963060B (zh) 基于钢管拱肋支护结构的隧道施工方法
CN102562099B (zh) 黄土隧道双排小导管快速进洞施工方法
CN103643979B (zh) 用于巷道临时支护的液压支架及其架设、使用方法
CN104481546B (zh) 一种软岩隧道斜井进入正洞的双曲拱的施工方法
CN110486021B (zh) 大断面隧洞向两条小断面隧洞转换施工方法
CN102400689B (zh) 特大断面暗挖隧道回旋开挖法
CN104389612A (zh) 一种隧道局部塌方的治理方法
CN107218045A (zh) 岩质地层暗挖地铁车站出入口暗挖段的快速施工方法
CN104847393A (zh) 一种隧道移动支护结构及其保护下的隧道施工方法
CN203742611U (zh) 一种在初期支护条件下隧道侧墙开马头门的加强支护结构
CN104632227A (zh) 单层梁拱结构的地铁车站开挖工艺
CN104912559A (zh) 长大双连拱隧道快速施工方法
CN104295301A (zh) 一种浅埋暗挖碎裂岩体地铁隧道交叉点的施工方法
CN105041327A (zh) 暗挖隧道反挖盾构接收方法
CN109339800A (zh) 一种处于桥隧相连段的隧道快速施工方法
CN113107500A (zh) 一种变截面隧道施工方法
CN105626090A (zh) 多功能操作臂及地下隧道挖掘设备
CN104912554B (zh) 一种带压自移式掘支机组及带压自移方法
CN105422107A (zh) 一种盾构机隧道内接收方法
CN208252120U (zh) 一种立井井筒与井底车场连接部
CN110145314A (zh) 一种特大断面暗挖隧道高大核心土拆除的方法
CN205189880U (zh) 盾构拼装管片过暗挖隧道施工结构
CN214247369U (zh) 造孔、注浆、装锚一体化工作装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160203

Termination date: 20181218