CN103669895B - Old structural steel industrial building side column becomes the online quick transformation method of center pillar - Google Patents

Old structural steel industrial building side column becomes the online quick transformation method of center pillar Download PDF

Info

Publication number
CN103669895B
CN103669895B CN201210355954.5A CN201210355954A CN103669895B CN 103669895 B CN103669895 B CN 103669895B CN 201210355954 A CN201210355954 A CN 201210355954A CN 103669895 B CN103669895 B CN 103669895B
Authority
CN
China
Prior art keywords
column
new
steel
frange plate
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210355954.5A
Other languages
Chinese (zh)
Other versions
CN103669895A (en
Inventor
毛承高
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201210355954.5A priority Critical patent/CN103669895B/en
Publication of CN103669895A publication Critical patent/CN103669895A/en
Application granted granted Critical
Publication of CN103669895B publication Critical patent/CN103669895B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A kind of old structural steel industrial building side column becomes the online quick transformation method of center pillar, it is characterized in that comprising the following steps: a column hypomere increases by a root post, increases by a root post at factory building column hypomere, to meet crane beam and track installation needs; The amendment of b epimere list steel column local, epimere list steel column side frange plate carries out cutting certain distance toward web direction, make the new frange plate (5) of local displacement and the former frange plate of new-track centre distance and opposite side with existing orbit centre apart from equal, to ensure that driving is current smoothly; Increase gusset (4), the manhole (7) be simultaneously positioned between new frange plate (5) and gusset (4) carries out shutoff with steel plate, and new frange plate (5) is connected with manhole side plate high-strength bolt (6).Old structural steel industrial building side column of the present invention become center pillar online quick transformation method have old factory rehabilitation reduced investment, speed fast, resume production early and advantage that workmanship is safe and reliable.

Description

Old structural steel industrial building side column becomes the online quick transformation method of center pillar
Technical field
The present invention relates to a kind of old steel-structure factory building remodeling method, specifically, is that a kind of old structural steel industrial building side column becomes the online quick transformation method of center pillar.
Background technology
Along with unit apparatus for production line is constantly updated, production technology is updated, and production capacity constantly expands, and output increases day by day, and in old structural steel industrial building, material reservoir area capacity can not practical requirement.For two across and above old structural steel industrial building, when existence is across with time unequal across factory building length, row is stepped into shorter length factory building and extends extending capacity reformation, the old factory building column of part will become center pillar from side column, see B row in Fig. 1 112,113,114 post, ensure the installation of newly-increased crane beam and track, guarantee that old driving normally can run in prolongation factory building, also to complete these Online revamp contents with the fastest speed simultaneously, resume production as early as possible.
Summary of the invention
Object of the present invention, is to propose a kind of online quick transformation method of old structural steel industrial building side column change center pillar shorter length factory building being stepped into row prolongation extending capacity reformation.
For achieving the above object, technical solution of the present invention is:
A kind of old structural steel industrial building side column becomes the online quick transformation method of center pillar, it is characterized in that comprising the following steps:
A, column hypomere increase by a root post
Increase by a root post at factory building column hypomere, i.e. single steel column, to meet crane beam and track installation needs;
The amendment of b, epimere list steel column local
Epimere list steel column side frange plate needs to carry out cutting certain distance toward web direction, makes the new frange plate of local displacement and the former frange plate of new-track centre distance and opposite side with existing orbit centre apart from equal, to ensure that driving is current smoothly; Increase gusset, the manhole steel plate simultaneously between new frange plate and gusset carries out shutoff, new frange plate and manhole side plate high strength exploitation.
After adopting technique scheme, old structural steel industrial building side column of the present invention becomes the online quick transformation method of center pillar and has the following advantages:
1, old factory rehabilitation reduced investment, speed fast, resume production early;
2, workmanship is safe and reliable;
3, economic benefit and social benefit remarkable.
Accompanying drawing explanation
Fig. 1 is known old factory building and prolongation factory building plan-position schematic diagram;
Fig. 2 is increase by the root post schematic diagram of the embodiment of the present invention;
Fig. 3 is that schematic diagram is revised in the side column epimere list steel column local of the embodiment of the present invention;
Fig. 4 is the high strength exploitation schematic diagram of the embodiment of the present invention.
In figure: 1 pair of steel column, 2 columns, 3 single steel columns, 4 gussets, 5 new frange plates, 6 high-strength bolts, 7 manholes.
Detailed description of the invention
Below in conjunction with embodiment and accompanying drawing thereof, the present invention is illustrated further.
Old structural steel industrial building column generally forms by upper and lower two sections, and hypomere is two steel columns, and epimere is single steel column.Factory building side column and center pillar different in upper portion structural configuration, and hypomere part-structure arrange substantially identical.
Center pillar: L1=L2, namely epimere list steel column center is equal with the distance at the two steel column center of hypomere, is symmetrical structure.Crane beam center, both sides overlaps respectively with two steel column center.
Side column: L1 > L2, namely the distance at epimere list steel column center and hypomere double steel column center is unequal, is unsymmetric structure.Crane beam center, L1 side and double steel column center superposition, L2 side is without crane beam.
Fig. 2 is increase by the root post schematic diagram of the embodiment of the present invention.
It is increase by a root post at factory building column hypomere that old structural steel industrial building side column of the present invention becomes the online quick transformation method of center pillar, and namely single steel column 3, makes L1=L3, to meet crane beam and track installation needs.
Fig. 3 is that schematic diagram is revised in the side column epimere list steel column local of the embodiment of the present invention, and Fig. 4 is the high strength exploitation schematic diagram of the embodiment of the present invention.
The second step of old factory rehabilitation is in the amendment of side column epimere list steel column local, ensures that driving is current smoothly:
Because side column is unsymmetric structure, its upper prop side frange plate and newly-increased orbit centre distance are less than opposite side frange plate and existing orbit centre distance, and driving is by impassable.Therefore upper prop side frange plate needs to carry out cutting certain distance toward web direction, the new frange plate 5 of local displacement is made to get final product (L4=L5) with existing orbit centre apart from equal with the former frange plate of new-track centre distance and opposite side, to ensure that driving is current smoothly.
In order to ensure improved upper prop intensity, add gusset 4, the manhole 7 simultaneously between new frange plate 5 and gusset carries out shutoff with steel plate.The new edge of a wing 5 plate is connected with manhole side plate high-strength bolt 6.
Old structural steel industrial building side column of the present invention becomes the online quick transformation method of center pillar and uses in species abundance in Baosteel in Shanghai flat cold-rolled sheet factory improvement project, technological transformation that existing structural steel industrial building carries out " extending dilatation ", from shutdown, transformation completes to transformation and resumes production, altogether use 5 days and complete the online quick transformation of old structural steel industrial building side column change center pillar, Be very effective, increase reservoir area capacity, alleviate the nervous contradiction in reservoir area, be conducive to making milling train in order and connecting the total logistics cost between moving back, ensure milling train and connect the normal performance of moving back unit production capacity, also the balance of these two unit maintenance strength is beneficial to, realize utilizing the resource in existing factory building region simultaneously as far as possible, to reduce construction investment.
Above embodiment is used for illustrative purposes only, but not limitation of the present invention, person skilled in the relevant technique, without departing from the spirit and scope of the present invention, can also make various conversion or change.Therefore, all equivalent technical schemes also should belong to category of the present invention, should be limited by each claim.

Claims (1)

1. old structural steel industrial building side column becomes the online quick transformation method of center pillar, and old structural steel industrial building column forms by upper and lower two sections, and hypomere is two steel columns (1), and epimere is single steel column (2), it is characterized in that comprising the following steps:
A, column hypomere increase by a root post
Increase by a root post at factory building column hypomere, i.e. single steel column (3), to meet crane beam and track installation needs;
The amendment of b, epimere list steel column local
Epimere list steel column side frange plate carries out cutting certain distance toward web direction, makes the new frange plate (5) of local displacement and the former frange plate of new-track centre distance and opposite side with existing orbit centre apart from equal, to ensure that driving is current smoothly; Increase gusset (4), the manhole (7) be simultaneously positioned between new frange plate (5) and gusset (4) carries out shutoff with steel plate, and new frange plate (5) is connected with manhole side plate high-strength bolt (6).
CN201210355954.5A 2012-09-24 2012-09-24 Old structural steel industrial building side column becomes the online quick transformation method of center pillar Active CN103669895B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210355954.5A CN103669895B (en) 2012-09-24 2012-09-24 Old structural steel industrial building side column becomes the online quick transformation method of center pillar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210355954.5A CN103669895B (en) 2012-09-24 2012-09-24 Old structural steel industrial building side column becomes the online quick transformation method of center pillar

Publications (2)

Publication Number Publication Date
CN103669895A CN103669895A (en) 2014-03-26
CN103669895B true CN103669895B (en) 2016-01-20

Family

ID=50308604

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210355954.5A Active CN103669895B (en) 2012-09-24 2012-09-24 Old structural steel industrial building side column becomes the online quick transformation method of center pillar

Country Status (1)

Country Link
CN (1) CN103669895B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1705313A2 (en) * 2004-03-24 2006-09-27 Peem, spol. s.r.o. Reinforced console column and the method of its production
JP2011074566A (en) * 2009-09-29 2011-04-14 Nishinippon Iron Co Aseismatic reinforcing structure of building, and aseismatic reinforcing method of building
CN202249004U (en) * 2011-09-08 2012-05-30 贵州汇通申发钢结构有限公司 Improved steel structure plant structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1705313A2 (en) * 2004-03-24 2006-09-27 Peem, spol. s.r.o. Reinforced console column and the method of its production
JP2011074566A (en) * 2009-09-29 2011-04-14 Nishinippon Iron Co Aseismatic reinforcing structure of building, and aseismatic reinforcing method of building
CN202249004U (en) * 2011-09-08 2012-05-30 贵州汇通申发钢结构有限公司 Improved steel structure plant structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"对改建工程中边柱变中柱的尝试";刘晓玲等;《建设科技》;20061231(第21期);全文 *

Also Published As

Publication number Publication date
CN103669895A (en) 2014-03-26

Similar Documents

Publication Publication Date Title
CN104480862B (en) A kind of erection method of cable stayed bridge end bay steel truss girder
CN202945003U (en) Portal crane for mounting large-scale equipment
CN103240562B (en) Chained turnover equipment for H-shaped steel
CN103541300A (en) Railway concrete continuous beam implemented based on flat-pushing method and construction method thereof
LU502791B1 (en) Full hoisting construction method for assembled subway station in pile-anchor retaining structure system
CN201933415U (en) Highway and railway twin-girder bridge erection machine
CN203855899U (en) Non-counterweight self-balance movable die carrier
CN103352425A (en) Accurate positioning method and device for integral carrying of bridge
CN203498743U (en) Railway concrete continuous beam implemented on basis of flat pushing method
CN103669895B (en) Old structural steel industrial building side column becomes the online quick transformation method of center pillar
CN203237934U (en) End beam device of electric hoist crane
CN203419675U (en) Traveling track for girder crane
CN102900027B (en) Dismounting method of bailey beam with upwardly strode existing lines and underneath penetrated existing bridge
CN204644878U (en) A kind of transom pier steel truss girder lifting construction device
CN203640122U (en) Node structure of elevation difference of floor carrier plates of rebar trusses
CN103470077A (en) Novel steel-structured plant
CN203669879U (en) Down-hole hydraulic support assembling chamber
CN202337945U (en) Outer side in-place beam body lifting device
CN206343805U (en) Positioner for lower frame of excavator
CN102733285A (en) Overlapping type airfield pavement structure
CN203782573U (en) Drag runway structure for erecting steel pipe arch bridge
CN202830789U (en) Beam moving work platform
CN203819964U (en) Transverse movement equipment
CN203282123U (en) Chain-type turnover equipment used for H-type steel
CN204980923U (en) Balancing unit is used in bridge crane installation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant