CN103629438B - Based on the built-up type transition running line cage of bridge running line under cable - Google Patents

Based on the built-up type transition running line cage of bridge running line under cable Download PDF

Info

Publication number
CN103629438B
CN103629438B CN201310583662.1A CN201310583662A CN103629438B CN 103629438 B CN103629438 B CN 103629438B CN 201310583662 A CN201310583662 A CN 201310583662A CN 103629438 B CN103629438 B CN 103629438B
Authority
CN
China
Prior art keywords
running line
line cage
cage
section
framework
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310583662.1A
Other languages
Chinese (zh)
Other versions
CN103629438A (en
Inventor
林贤浩
黄鹏贤
庄英平
林光如
王容华
陈强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN POWER TRANSMISSION & DISTRIBUTION ENGINEERING Co Ltd
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Original Assignee
FUJIAN POWER TRANSMISSION & DISTRIBUTION ENGINEERING Co Ltd
State Grid Corp of China SGCC
State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN POWER TRANSMISSION & DISTRIBUTION ENGINEERING Co Ltd, State Grid Corp of China SGCC, State Grid Fujian Electric Power Co Ltd filed Critical FUJIAN POWER TRANSMISSION & DISTRIBUTION ENGINEERING Co Ltd
Priority to CN201310583662.1A priority Critical patent/CN103629438B/en
Publication of CN103629438A publication Critical patent/CN103629438A/en
Application granted granted Critical
Publication of CN103629438B publication Critical patent/CN103629438B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/04Protective tubing or conduits, e.g. cable ladders or cable troughs
    • H02G3/0456Ladders or other supports
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/04Protective tubing or conduits, e.g. cable ladders or cable troughs
    • H02G3/0406Details thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of technology for bridge under running line in bridge bridge cable engineering, particularly a kind of built-up type transition running line cage based on bridge running line under cable, its structure main points are, include first section of running line cage, tail section running line cage and a plurality of middle section running line cage, the angle steel framework of first section of running line cage is screwed into connecting screw hole by bolt and be fixedly connected with the angle steel framework of middle section running line cage one end, transition running line cage adopts multiple middle section running line cage head and the tail to be connected to form section in the middle of arc, the angle steel framework of the other end of last middle section running line cage then angle steel framework with tail section running line cage be bolted to connection. the feature of the present invention is: adopting modular point to install, constructing operation is simple and convenient, time saving and energy saving, efficiency height, security are good, it may also be useful to scope is wide, and cable all primings in caged framework, cable is played the effect of four directions encirclement by running line cage, is therefore not easily damaged to cable.

Description

Based on the built-up type transition running line cage of bridge running line under cable
Technical field
The present invention relates to a kind of technology for bridge under running line in bridge bridge cable engineering, particularly a kind of built-up type transition running line cage based on bridge running line under cable.
Background technology
In bridge bridge cable engineering, it is fixing that cable testing bridge is positioned at the bridge abdomen hanging of bridge both sides, cable causes from bridge floor must by one section of free face bridge abdomen cable testing bridge below bridge floor, site operation is except arranging except lower bridge service platform at free face, for control difficult problems such as bending radius when bridge lays under solution cable, wall pressure, damages, generic way adopts to set up steel pipe frame on lower bridge service platform, and in frame body, multiple spot installing annular coaster controls. But described annular coaster needs to be arranged by calculating and the in-site modeling of complexity, in the provisioning process if there is local deviation, it is easy to cause that radius of cable bends is excessively little, wall pressure increases, damage cable; In addition, annular coaster owing to cable is not located, must adjust position in real time in cable running process, waste time and energy after arranging, and efficiency is low, and subsequent construction is numerous and diverse.
Summary of the invention
It is an object of the invention to provide the built-up type transition running line cage based on bridge running line under cable of a kind of time saving and energy saving, efficiency height, non-easy damaged cable according to the deficiencies in the prior art part.
It is an object of the invention to be realized by following approach:
Based on the built-up type transition running line cage of bridge running line under cable, its structure main points are, include first section of running line cage, tail section running line cage and a plurality of middle section running line cage, wherein, the constitution element of first section of running line cage, tail section running line cage and each middle section running line cage has included guide roller frame, angle steel framework and steel pipe; Described guide roller frame is trilateral or square planar framework, every bar limit of framework is all provided with the waist drum shape pulley of a waist line indent, the pulley waist line on every bar limit forms the space of a similar round in framework, and this spatial area is adaptive with the cable cross section to be passed through; Described angle steel framework and guide roller frame are adaptive, are also trilateral or square framework, are that limit is formed taking angle steel, each angle steel is reserved with connecting screw hole; The two then is connected to get up by steel pipe by connecting the corresponding vertex of guide roller frame and angle steel framework, thus forms a kind of caged framework structure;
Concrete, first section of running line cage is identical with tail section running line basket structure, the steel pipe adopted is straight shape steel tube, and this first section of running line cage and tail section running line cage are by straight shape steel tube and lay respectively at straight shape steel tube two ends and a guide roller frame being connected of shape steel tube straight with this, an angle steel framework form; The steel pipe that middle section running line cage adopts is fan-shaped steel pipe, and the both ends of this sector steel pipe are connected to an angle steel framework, and guide roller frame is then positioned at the mid-way of fan-shaped steel pipe;
The angle steel framework of first section of running line cage is screwed into connecting screw hole by bolt and be fixedly connected with the angle steel framework of middle section running line cage one end, transition running line cage adopts multiple middle section running line cage head and the tail to be connected to form section in the middle of arc, the angle steel framework of the other end of last middle section running line cage then angle steel framework with tail section running line cage be bolted to connection.
Section and tail section running line cage in the middle of first section of running line cage, arc are just constituted the built-up type transition running line cage for bridge running line under cable of the present invention after sequentially connecting. Wherein, it is possible to adjust the quantity of the middle section running line cage of arc intermediate stage as required, when making, it is also possible to according to the radian size of steel pipe fan-shaped on section running line cage in the middle of the processing of the structure of concrete bridge. During use, cable is introduced the guide roller frame of first section of running line cage, under the drive of waist drum shape pulley and under action of gravity, cable sequentially passes the guide roller frame of multiple middle section running line cage in built-up type transition running line cage, last draw from the guide roller frame of tail section running line cage, complete bridge running line under cable.
First section of running line cage of the present invention, tail section running line cage and middle section running line cage are all the component units of built-up type transition running line cage; produce with the structure of modularization; arbitrary combination can be carried out according to actual needs during installation; lower bridge Piecemeal erection can be completed by manpower to fix; or adopt after bridge floor segmentation series connection assembling; utilize the auxiliary lifting of crane fixing on the operational platform; forming a full guard at lower bridge free face and lay passage, cable can be worn running line cage from bridge floor and cause the crane span structure below bridge abdomen. Constructing operation is simple and convenient, time saving and energy saving, efficiency height, and cable all primings in caged framework, and cable is played the effect of four directions encirclement by running line cage, is therefore not easily damaged to cable.
Described angle steel framework is fixedly connected with steel pipe by welding. Described guide roller frame is fixedly connected with steel pipe by welding.
Owing to the top of each angle steel framework and guide roller frame can be connected to steel pipe, every root steel pipe all needs to connect a summit of a framework, owing to adopting modular design, therefore each module can be fixed connection by welding, to reach most stable structure. And only need between module with module to be undertaken being connected by bolt.
In sum, the technology feature of the present invention is:
1, owing to adopting modular point to install, it is possible to integrated molding installation, eliminating complicated construction and calculate and in-site modeling operation, under effectively solving cable, bridge bending radius, wall pressure, damage etc. control a difficult problem; Simultaneously can also cost saving: adopt segmentation, built-up type, trucking costs can be reduced while solving a long part transport difficult problem and crane uses platform class rental expenses.
2, simplicity is installed. It is simple to operate that section is connected the common zinc coated bolt of employing with section, it is not necessary to by external impetus, equipment, also can complete to install fixing, time saving and energy saving by means of only manpower.
3, use safety. Once shaped can be installed, cable running process need not carry out two sub-band load adjustments by workmen again, ensure construction safety; Improve construction operation efficiency simultaneously, reduce and manually work.
4, use range is wide. The present invention can use in tunnel, underground or similar engineering.
Accompanying drawing explanation
Fig. 1 is the structural representation of the built-up type transition running line cage based on bridge running line under cable described in the embodiment of the present invention, and owing to employing cross section is square structure, therefore end face is consistent with bottom surface structure.
Fig. 2 show first section of running line cage described in the embodiment of the present invention and the structural representation of tail section running line cage. Fig. 3 show the A-A of Fig. 2 to structural representation; Fig. 4 show the B-B of Fig. 2 and Fig. 5 to structural representation.
Fig. 5 show the structural representation of the middle section running line cage described in the embodiment of the present invention. Fig. 6 show the C-C direction view of Fig. 5.
Fig. 7 show the structural representation of the angle steel framework described in the embodiment of the present invention.
Below in conjunction with embodiment, the present invention is described further.
Embodiment
Most preferred embodiment:
With reference to accompanying drawing 1, based on the built-up type transition running line cage of bridge running line under cable, include the middle section running line cage 3 of first section of running line cage 1, tail section running line cage 2 and more than 2. The constitution element of first section of running line cage 1, tail section running line cage 2 and each middle section running line cage 3 has included guide roller frame 4, angle steel framework 5 and steel pipe.
With reference to accompanying drawing 2 and accompanying drawing 3, first section of running line cage 1 is identical with tail section running line cage 2 structure, the steel pipe 6 adopted is straight shape steel tube, and this first section of running line cage 1 and tail section running line cage 2 are by straight shape steel tube 6 and lay respectively at straight shape steel tube 6 two ends and a guide roller frame 4, angle steel framework 5 that shape steel tube 6 straight with this is connected forms. The structure of concrete guide roller frame 4 is with reference to accompanying drawing 4, described guide roller frame is square-shaped planar framework, four summits formed that connect by four edges and four edges form, every bar limit includes the waist drum shape pulley 42 of round steel pipe 41 with the waist line indent gone here and there in round steel pipe 41, four summits are welded in four straight shape steel tube 6 in a welding manner respectively, the plane orthogonal of these four straight shape steel tube 6 and guide roller frame. Concrete angle steel framework 5 is with reference to accompanying drawing 7, and described angle steel framework 5 is adaptive with guide roller frame 4, is also square frame, formed taking angle steel 51 as limit, being reserved with connecting screw hole 52 on each angle steel 51, same, its four summits are also welded in four be connected with guide roller frame straight shape steel tube 6.
With reference to accompanying drawing 5 and accompanying drawing 6, the steel pipe that middle section running line cage 2 adopts is fan-shaped steel pipe 7, the both ends of this sector steel pipe 7 are connected to an angle steel framework 5, guide roller frame 4 is then positioned at the mid-way of fan-shaped steel pipe 7, four summits of angle steel framework 5 and coaster framework 4 are welded on four fan-shaped steel pipes 7, such as the weld 8 in figure. The angle steel framework 5 of middle section running line cage 2 and guide roller frame 4 all with first section, consistent in tail section running line cage, reference accompanying drawing 7 and accompanying drawing 4 respectively.
With reference to accompanying drawing 1, the angle steel framework of first section of running line cage 1 is screwed into connecting screw hole by bolt and be fixedly connected with the angle steel framework of middle section running line cage 2 one end, adopt multiple middle section running line cage 2 head and the tail to be connected to form section in the middle of arc, the angle steel framework of the other end of last middle section running line cage 2 then angle steel framework with tail section running line cage 3 be bolted to connection.
Head and the tail section segment length 0.5 meter; middle section segment length 1 meter; radian is processed on request; scene can carry out arbitrary combination use according to actual needs; lower bridge Piecemeal erection can be completed by manpower to fix, or adopt after bridge floor segmentation series connection assembling, utilize the auxiliary lifting of crane fixing on the operational platform; forming a full guard at lower bridge free face and lay passage, cable can be worn running line cage from bridge floor and cause the crane span structure below bridge abdomen. It is same as the prior art that the present invention does not state part.

Claims (3)

1. based on the built-up type transition running line cage of bridge running line under cable, it is characterized in that, include first section of running line cage, tail section running line cage and a plurality of middle section running line cage, wherein, the constitution element of first section of running line cage, tail section running line cage and each middle section running line cage has included guide roller frame, angle steel framework and steel pipe; Described guide roller frame is trilateral or square planar framework, every bar limit of framework is all provided with the waist drum shape pulley of a waist line indent, the pulley waist line on every bar limit forms the space of a similar round in framework, and this spatial area is adaptive with the cable cross section to be passed through; Described angle steel framework and guide roller frame are adaptive, are also trilateral or square framework, are that limit is formed taking angle steel, each angle steel is reserved with connecting screw hole; The two then is connected to get up by steel pipe by connecting the corresponding vertex of guide roller frame and angle steel framework, thus forms a kind of caged framework structure;
Concrete, first section of running line cage is identical with tail section running line basket structure, the steel pipe adopted is straight shape steel tube, and this first section of running line cage and tail section running line cage are by straight shape steel tube and lay respectively at straight shape steel tube two ends and a guide roller frame being connected of shape steel tube straight with this, an angle steel framework form; The steel pipe that middle section running line cage adopts is fan-shaped steel pipe, and the both ends of this sector steel pipe are connected to an angle steel framework, and guide roller frame is then positioned at the mid-way of fan-shaped steel pipe;
The angle steel framework of first section of running line cage is screwed into connecting screw hole by bolt and be fixedly connected with the angle steel framework of middle section running line cage one end, transition running line cage adopts multiple middle section running line cage head and the tail to be connected to form section in the middle of arc, the angle steel framework of the other end of last middle section running line cage then angle steel framework with tail section running line cage be bolted to connection.
2. the built-up type transition running line cage based on bridge running line under cable according to claim 1, it is characterised in that, described angle steel framework is fixedly connected with steel pipe by welding.
3. the built-up type transition running line cage based on bridge running line under cable according to claim 1, it is characterised in that, described guide roller frame is fixedly connected with steel pipe by welding.
CN201310583662.1A 2013-11-20 2013-11-20 Based on the built-up type transition running line cage of bridge running line under cable Active CN103629438B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310583662.1A CN103629438B (en) 2013-11-20 2013-11-20 Based on the built-up type transition running line cage of bridge running line under cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310583662.1A CN103629438B (en) 2013-11-20 2013-11-20 Based on the built-up type transition running line cage of bridge running line under cable

Publications (2)

Publication Number Publication Date
CN103629438A CN103629438A (en) 2014-03-12
CN103629438B true CN103629438B (en) 2016-06-01

Family

ID=50210765

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310583662.1A Active CN103629438B (en) 2013-11-20 2013-11-20 Based on the built-up type transition running line cage of bridge running line under cable

Country Status (1)

Country Link
CN (1) CN103629438B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105703310B (en) * 2016-04-25 2018-01-12 李宾 Fan-shaped buffer for cable retractor device
CN114458829A (en) * 2022-04-13 2022-05-10 中国电建集团山东电力建设第一工程有限公司 Method for assembling and installing comprehensive pipe frame and cable bridge in place for high-end equipment

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202217970U (en) * 2011-08-31 2012-05-09 广东威恒输变电工程有限公司 Cable pavement guide device
CN202602232U (en) * 2012-05-17 2012-12-12 西安供电局 Cable well head unreeling pulley block
CN202903404U (en) * 2012-11-09 2013-04-24 广州供电局有限公司 A side pressure monitor used for laying cables and a cable turning laying device
CN203656365U (en) * 2013-11-20 2014-06-18 国家电网公司 Combination-type transition cable leading cage based on cable leading towards lower bridge surface

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000034073A (en) * 1998-07-21 2000-02-02 Hitachi Ltd Guide device for compensating cable
JP3754952B2 (en) * 2002-11-18 2006-03-15 株式会社冨山設備工業 Crossover support frame

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202217970U (en) * 2011-08-31 2012-05-09 广东威恒输变电工程有限公司 Cable pavement guide device
CN202602232U (en) * 2012-05-17 2012-12-12 西安供电局 Cable well head unreeling pulley block
CN202903404U (en) * 2012-11-09 2013-04-24 广州供电局有限公司 A side pressure monitor used for laying cables and a cable turning laying device
CN203656365U (en) * 2013-11-20 2014-06-18 国家电网公司 Combination-type transition cable leading cage based on cable leading towards lower bridge surface

Also Published As

Publication number Publication date
CN103629438A (en) 2014-03-12

Similar Documents

Publication Publication Date Title
CN103633583B (en) Bridge running line method under cable based on combined type running line cage
CN104060542B (en) Compound beam cable stayed bridge direction across bridge prestress application device and applying method thereof
CN106049707A (en) Prefabricated wall body, prefabricated house building and construction method
CN205012629U (en) Assembled modularization platform of unloading of encorbelmenting
CN106121234A (en) The mounting tool of a kind of roof large span large-diameter pipeline and installation method
CN104612057A (en) Assembled rack and using method
CN103629438B (en) Based on the built-up type transition running line cage of bridge running line under cable
CN203947421U (en) Compound beam cable stayed bridge direction across bridge prestress application device
CN203656365U (en) Combination-type transition cable leading cage based on cable leading towards lower bridge surface
CN107720542B (en) Hoisting track composite beam
CN203947756U (en) Exterior wall protective frame
CN106505484A (en) Piping lane cable laying method
CN106185642A (en) Tower crane Upon Flexible Adhesion steel wire rope pre-tightening device
CN201908429U (en) Assembly integral building overhanging discharging platform
CN102011432B (en) Novel polygonal combined steel pipe
CN206000178U (en) A kind of mounting tool of roof large span large-diameter pipeline
CN201851780U (en) Arched cable passing bridge stand
CN109469338A (en) A kind of tall and big workshop self-control grid platform and its construction method as electromechanical pipeline
CN111236603A (en) Comprehensive construction method for steel plate mesh overhanging scaffold
CN204298741U (en) Working platform in a kind of bridge pier rapid construction
CN207251110U (en) A kind of large span power cable crane span structure
CN203361596U (en) Auxiliary support of integrated lifting operation platform
CN203795824U (en) Suspension type fastener scaffold erecting device
CN204615305U (en) Mechatronics bridge
CN104612166A (en) Combined supporting device and method for hole wall supporting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant