CN103457268A - 基于并行模式搜索的最优切负荷控制方法 - Google Patents
基于并行模式搜索的最优切负荷控制方法 Download PDFInfo
- Publication number
- CN103457268A CN103457268A CN2013104234649A CN201310423464A CN103457268A CN 103457268 A CN103457268 A CN 103457268A CN 2013104234649 A CN2013104234649 A CN 2013104234649A CN 201310423464 A CN201310423464 A CN 201310423464A CN 103457268 A CN103457268 A CN 103457268A
- Authority
- CN
- China
- Prior art keywords
- search
- load
- target function
- cutting load
- searching
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
- Y02B70/3225—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/222—Demand response systems, e.g. load shedding, peak shaving
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
本发明公开了一种基于并行模式搜索的最优切负荷控制方法,包括:利用计算机读入电力***数据,包含线路参数、发电机参数、负荷参数;对电力***进行初始仿真,得到各个时刻每台发电机的功角,计算目标函数值,为初始迭代点;在所有的负荷中选取个可切负荷;初始化并行模式搜索的参数,包括迭代次数、搜索精度和初始搜索步长,根据步骤3确定的可切负荷,确定搜索方向的集合等。本发明方法是一种无梯度优化方法,极大地减少了计算工作量,能可靠获得最优的控制策略,而且能针对实际运行情况随时调整控制策略。同时,并行搜索的框架实现了暂态稳定计算任务的合理分配,提高了搜索的效率,为其在实际电力***中的应用打下坚实基础。
Description
技术领域
本发明属于电力***的分析与控制领域,具体涉及一种基于并行模式搜索的最优切负荷控制方法。
背景技术
随着我国经济建设的快速发展,人均所需用电量日益增长,电力已成为社会生产的直接动力。在这过程中,电力***规模不断增大,电网结构日益复杂,单机容量进一步提高,同时区域间联络线和远距离大容量输电***不断出现,其安全性和经济性之间的矛盾日趋加剧。
当电力***发生故障需要采用安全稳定紧急控制措施时,切负荷控制方法是常用的一种措施。在电网发生严重故障或失去大量电源后,切除一部分负荷可以减少网络中的功率不平衡,维持***的稳定运行。
目前,实际制定紧急控制策略的方法主要是试凑法。试凑法通过数值积分计算不断地试凑出控制策略,直到找到一种能够使***稳定而控制代价又较小的控制策略。因此这种算法需要很大的计算工作量,而且难以获得最佳的控制策略。而且实际***的网络结构、运行方式以及预想事故都是在不断变化的,所以当前方法为减少工作量,只能对***运行的某种极限方式,难以针对实际运行情况随时调整紧急控制策略。因此,急需一种能够考虑实际电网运行情况、快速获得控制策略的最优切负荷控制方法。
发明内容
本发明的目的是提供一种基于并行模式搜索的最优切负荷控制方法,以在最优切负荷控制方法中考虑实际复杂的电力***模型,提高计算效率和结果可靠性。
本发明提供的基于并行模式搜索的最优切负荷控制方法,包括如下步骤:
步骤1、利用计算机读入电力***数据,包含线路参数、发电机参数、负荷参数;
式中:
式中:
步骤9、根据步骤5获得的切负荷控制量作为电网切负荷控制措施的方案,用以控制各个负荷的切除量,以提高***整体经济性和安全性。
进一步的技术方案是:
原暂态稳定约束:
式中:
()是各个负荷原有功功率;
灵敏度计算:
式中:
是摄动量。
所述步骤7中,所述搜索项是多个进程同时进行并行暂态稳定计算,实现并行模式搜索,以加快求解速度。
本发明的有益效果是,本发明方法采用了并行模式搜索方法,并且利用约束转化方法,将考虑复杂***模型的最优切负荷控制问题转化为无约束优化问题,同时根据搜索过程中搜索点之间相互解耦的特点,用并行计算技术大幅度提高求解速度,为其在实际电力***中的应用打下坚实基础。与现有的最优切负荷控制方法相比,本发明提出的方法主要有以下改进:
1、该方法对于初值和参数的要求低,且基本没有收敛性问题,可以有效地给出稳定控制策略。
2、并行模式搜索可以有效地减少单个进程的动态仿真次数,从而提高整体计算速度。
3、迭代过程中可以给出可行的切负荷控制策略,而且得到一个可行解所需的动态仿真次数很少。
附图说明
图1是本发明方法的流程示意图。
图2是本发明方法获得切负荷控制措施的有效性验证图。
图3是本发明方法在不同进程数下的效率对比图。
具体实施方式
基于并行模式搜索的最优切负荷控制方法,包括如下步骤:
1、利用计算机读入电力***数据,包含线路参数、发电机参数、负荷参数等;
2、对电力***进行初始仿真,得到各个时刻每台发电机的功角,利用约束转化技术,将暂态稳定约束加以转化,作为惩罚项加入目标函数中,计算目标函数值,为初始迭代点,使得最优切负荷控制成为一个无约束优化问题;
原暂态稳定约束:
式中:
是仿真终端时刻;
是发电机相对功角上限;
灵敏度计算:
式中:
式中:
式中:
由于各个搜索项之间没有耦合关系,因此搜索项可以多个进程同时进行并行暂态稳定计算,通过并行计算技术来加快求解速度;
9、根据步骤5获得的切负荷控制量作为电网切负荷控制措施的方案,用以控制各个负荷的切除量,以提高***整体经济性和安全性。
以下结合附图,对本发明的实施例作详细说明,本发明的流程图如图1所示。
应用实例:
本发明方法考虑一个145节点的电网,内含50台带励磁的发电机、64个负荷,由步骤1利用计算机读入电力***数据,包含401条线路的参数、50台发电机的参数、64个负荷的参数等,***的发电机模型均采用高阶动态模型,并有少量或调速***,初始时刻发生6号节点和7号节点之间的短路故障,切故障时刻为=0.0583s,切负荷控制时刻=0.15s。
表1 各个负荷的灵敏度(前10)
优化时取仿真终端时刻均为3s,步长均为0.008333s,最大允许功角均为160°。
由步骤5-8,利用并行模式搜索方法不断迭代,使得目标函数不断减小同时更新迭代点信息,直到步骤5判断当前搜索步长小于搜索精度,退出搜索过程。特别是步骤7中,为了实现并行模式搜索加快求解速度,优化过程中共开启8个进程,包括1个主进程和7个子进程,主进程负责分配任务、更新相关变量等,7个子进程并行地计算各个搜索点的目标函数值。在这过程中,子进程需要调用PSS/E来获得***中各台发电机每个时刻的功角,从而获得目标函数值。
在步骤9中,将优化后的切负荷控制量作为电网切负荷控制措施的方案,控制各个负荷的切除量,以提高***整体经济性和安全性。具体各可切负荷切除比例优化结果如表2所示:
表2 各可切负荷的切除比例
该方法使用的暂态稳定判据为各发电机功角与惯性中心的偏差不超过某一角度,图2作出了***中失稳发电机在切负荷控制前后功角曲线的变化。由图可以直观的看出切负荷后相对功角曲线的振荡不断减小,事实上更长时间的仿真结果也说明了功角曲线是是趋于稳定的,这证明了该方法给出的切负荷控制策略的有效性。
表3中的比例关系是前后两个动态仿真次数的比值。可以看出,串行搜索的动态仿真次数是7个进程时单个进程仿真次数的10倍左右,因此并行搜索可以大幅降低一个进程需要的动态仿真次数,从而使整体的计算时间得到大幅的减少。
表3 一个进程的动态仿真次数对比
该方法的另一个特点是可以快速得到一个可行的切负荷控制策略。实际上,在每次进行并行搜索并更新迭代点后,该迭代点就是一个新的控制策略,此时***的稳定性也能由之前的动态仿真结果得到。在对切负荷的经济性要求不高时,为了更加快速地得到使***稳定的控制策略,完全可以取迭代中间的结果作为实际的控制策略。实际优化过程中,开启7个子进程并行搜索求解,单个进程只需要一次暂态稳定计算就可以得到一个稳定控制策略。
Claims (5)
1.一种基于并行模式搜索的最优切负荷控制方法,其特征在于,包括如下步骤:
步骤1、利用计算机读入电力***数据,包含线路参数、发电机参数、负荷参数;
式中:
式中:
步骤9、根据步骤5获得的切负荷控制量作为电网切负荷控制措施的方案,用以控制各个负荷的切除量,以提高***整体经济性和安全性。
原暂态稳定约束:
式中:
是罚函数因子,取很大的数;
5.根据权利要求1所述基于并行模式搜索的最优切负荷控制方法,其特征在于,所述步骤7中,所述搜索项是多个进程同时进行并行暂态稳定计算,实现并行模式搜索,以加快求解速度。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013104234649A CN103457268A (zh) | 2013-09-17 | 2013-09-17 | 基于并行模式搜索的最优切负荷控制方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013104234649A CN103457268A (zh) | 2013-09-17 | 2013-09-17 | 基于并行模式搜索的最优切负荷控制方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103457268A true CN103457268A (zh) | 2013-12-18 |
Family
ID=49739360
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2013104234649A Pending CN103457268A (zh) | 2013-09-17 | 2013-09-17 | 基于并行模式搜索的最优切负荷控制方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103457268A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104573383A (zh) * | 2015-01-23 | 2015-04-29 | 浙江大学 | 一种适用于楼宇设备综合优化模型的分布式演化方法 |
EP2894750A3 (en) * | 2014-01-09 | 2015-11-04 | Kabushiki Kaisha Toshiba | Power system stabilizing device |
CN109471100A (zh) * | 2018-10-16 | 2019-03-15 | 湖北航天技术研究院总体设计所 | 一种sar多普勒调频率估计方法及*** |
CN109586298A (zh) * | 2018-12-11 | 2019-04-05 | 国网山东省电力公司电力科学研究院 | 一种多直流受端电网综合负荷优化控制方法与*** |
CN115048690A (zh) * | 2022-05-09 | 2022-09-13 | 中存大数据科技有限公司 | 一种基于模式搜索的水泥烧成模型优化方法 |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20110035077A1 (en) * | 2009-08-10 | 2011-02-10 | Korea Electric Power Corporation | Distribution automation system for reactive power compensation and its voltage control method |
-
2013
- 2013-09-17 CN CN2013104234649A patent/CN103457268A/zh active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20110035077A1 (en) * | 2009-08-10 | 2011-02-10 | Korea Electric Power Corporation | Distribution automation system for reactive power compensation and its voltage control method |
Non-Patent Citations (2)
Title |
---|
姚国强等: "最优切负荷控制问题的并行模式搜索算法", 《电力***自动化》, vol. 36, no. 4, 25 February 2012 (2012-02-25), pages 11 - 15 * |
毕兆东等: "基于数值积分法灵敏度的快速切负荷算法", 《电网技术》, vol. 26, no. 8, 31 August 2002 (2002-08-31) * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2894750A3 (en) * | 2014-01-09 | 2015-11-04 | Kabushiki Kaisha Toshiba | Power system stabilizing device |
US9768786B2 (en) | 2014-01-09 | 2017-09-19 | Kabushiki Kaisha Toshiba | Power system stabilizing device |
CN104573383A (zh) * | 2015-01-23 | 2015-04-29 | 浙江大学 | 一种适用于楼宇设备综合优化模型的分布式演化方法 |
CN104573383B (zh) * | 2015-01-23 | 2018-02-09 | 浙江大学 | 一种适用于楼宇设备综合优化模型的分布式演化方法 |
CN109471100A (zh) * | 2018-10-16 | 2019-03-15 | 湖北航天技术研究院总体设计所 | 一种sar多普勒调频率估计方法及*** |
CN109586298A (zh) * | 2018-12-11 | 2019-04-05 | 国网山东省电力公司电力科学研究院 | 一种多直流受端电网综合负荷优化控制方法与*** |
CN109586298B (zh) * | 2018-12-11 | 2021-01-15 | 国网山东省电力公司电力科学研究院 | 一种多直流受端电网综合负荷优化控制方法与*** |
CN115048690A (zh) * | 2022-05-09 | 2022-09-13 | 中存大数据科技有限公司 | 一种基于模式搜索的水泥烧成模型优化方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Feng et al. | A comprehensive approach for preventive and corrective control to mitigate voltage collapse | |
CN103279639B (zh) | 基于响应的受端电网电压稳定全过程态势评估及防控方法 | |
Sakthivel et al. | Optimal location of SVC for voltage stability enhancement under contingency condition through PSO algorithm | |
CN102436534B (zh) | 一种电力***仿真方法 | |
CN102346442B (zh) | 适于节点分析框架的微网暂态仿真并行计算方法 | |
CN103457268A (zh) | 基于并行模式搜索的最优切负荷控制方法 | |
CN103810646B (zh) | 一种基于改进投影积分算法的有源配电***动态仿真方法 | |
CN104156542B (zh) | 一种基于隐式投影的有源配电***稳定性仿真方法 | |
Hajian et al. | A chance-constrained optimization approach for control of transmission voltages | |
Chamorro et al. | A network control system for hydro plants to counteract the non-synchronous generation integration | |
CN103093037A (zh) | 基于主从问题交替优化的电力***解列断面搜索方法 | |
Zenelis et al. | A model-free sparse wide-area damping controller for inter-area oscillations | |
Djari et al. | Voltage stability assessment using the VQ sensitivity and modal analyses methods | |
Wang et al. | A three-machine equivalent system frequency response model and its closed-form solution | |
JP2017028915A (ja) | 電力貯蔵機器の配置算定装置、電力貯蔵機器の配置算定方法、電力貯蔵機器の配置算定システム及びプログラム | |
Lin et al. | A two-layer frequency control method for large-scale distributed energy storage clusters | |
Liu et al. | Surface roughness prediction method of titanium alloy milling based on CDH platform | |
Honari et al. | A scalable blockchain-based smart contract model for decentralized voltage stability using sharding technique | |
Melo et al. | Voltage stability assessment using modal analysis based on power systems state estimation | |
Ding et al. | Continuation power flow model for interconnected systems considering the electricity market influence and its corresponding distributed algorithm | |
Liu et al. | Comparison of multi-area reactive power optimization parallel algorithm based on Ward and REI equivalent | |
CN104935249A (zh) | 光伏发电***稳定性的校验方法及装置 | |
Divshali et al. | Application of bifurcation theory in dynamic security constrained optimal dispatch in deregulated power system | |
CN104022512A (zh) | 基于响应信息的电力***紧急控制方法 | |
Rabby et al. | Bifurcation analysis to identify voltage collapse in bangladesh power system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20131218 |