CN103387835B - Coke oven heat-state pumping grouting construction method - Google Patents

Coke oven heat-state pumping grouting construction method Download PDF

Info

Publication number
CN103387835B
CN103387835B CN201310335192.7A CN201310335192A CN103387835B CN 103387835 B CN103387835 B CN 103387835B CN 201310335192 A CN201310335192 A CN 201310335192A CN 103387835 B CN103387835 B CN 103387835B
Authority
CN
China
Prior art keywords
coke oven
slurry
mud
slip casting
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310335192.7A
Other languages
Chinese (zh)
Other versions
CN103387835A (en
Inventor
刘忠宝
刘明
张华骞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201310335192.7A priority Critical patent/CN103387835B/en
Publication of CN103387835A publication Critical patent/CN103387835A/en
Application granted granted Critical
Publication of CN103387835B publication Critical patent/CN103387835B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

The invention provides a coke oven heat-state pumping grouting construction method. The coke oven heat-state pumping grouting construction method comprises the following construction steps: arranging a slurry mixer on a middle platform or an end platform, arranging a slurry storage box in the front of the slurry mixer, and arranging a vertical slurry pump in the storage box; putting up a support frame with the height of 500 to 600 mm on the top of a furnace, and fixing a main slurry pipeline on the support frame, wherein one end of the main slurry pipeline is connected with the vertical slurry pump; arranging grouting branch pipes at the two sides of the main slurry pipeline at intervals, and arranging stop valves between the grouting branch pipes and the main slurry pipeline; and in the whole grouting process, injecting slurry into each grouting branch pipe all the time, and controlling the stop valve on each grouting branch pipe so as to realize the control on grouting points; and after the periodical grouting is finished, pumping clean water by the vertical slurry pump so as to clean the pipeline. The coke oven heat-state pumping grouting construction method has the advantages that a conventional manual conveying manner is replaced by a manner of conveying the slurry by the pipelines, so that the labor intensity of workers is greatly alleviated, the setting rate of slurry is reduced, the working efficiency is improved, the construction cost is reduced, and the construction period is shortened.

Description

The hot pumping grout construction method of coke oven
Technical field
The present invention relates to a kind of coke oven grout construction method, specifically the hot pumping grout construction method of a kind of coke oven.
Background technology
In coke oven construction process, the hot grouting of furnace roof and protecting sheet accounts for 70% of hot construction amount.Coke oven enters hot construction and indicates that coke oven is about to put into operation, and furnace roof and protecting sheet grouting are again the work that must complete before coke oven is gone into operation, and the heat that coke oven distributes is larger, and mud setting rate is very fast, so the transportation of mud is comparatively arduous.Present transporting method mostly is artificial transport, and because hot furnace roof and protecting sheet grouting operating ambient temperature is higher, workman's physical consumption is larger, and labour intensity is large, and inefficiency restricts whole construction speed.
Summary of the invention
The present invention be directed to the deficiency existing in the hot grouting technique of current coke oven, a kind of mud setting rate, hot pumping grout construction method of coke oven without artificial transport mud of reducing is provided.
The technical scheme that realizes above-mentioned purpose employing is: the hot pumping grout construction method of a kind of coke oven, construct according to following steps:
A, slurry mixer be arranged on coke oven one side between platform or end platform on, a mud torage tank is set before slurry mixer, in this torage tank, Veritical mud pump is housed;
B, the bracing frame that is 500-600mm at oven top of coke oven scaffolding height are fixed mud main pipeline on bracing frame, and one end of this mud main pipeline is connected with Veritical mud pump;
C, at the interval, both sides of mud main pipeline, slip casting arm is set respectively, between each slip casting arm and mud main pipeline, is provided with stopping valve;
D, startup Veritical mud pump are in the milk, and in whole filling process, each slip casting arm keeps logical slurry, realizes the control to slip casting point by the stopping valve of controlling on each slip casting arm;
When e, filling stage property finish, pipeline is cleaned with Veritical mud pump pumping clear water.
Between mud main pipeline and Veritical mud pump, adopt DN50 high-pressure air hose to connect.
Mud main pipeline adopts the weldless steel tube of Φ 48.
On mud main pipeline, every five carbonizing chambers, a slip casting arm is set.
Mud main pipeline is arranged along the horizontal center line of oven top of coke oven.
The slurry output end of each slip casting arm is installed respectively one section of steel pipe.
Slip casting arm respectively evenly interval be arranged in the both sides of mud main pipeline, by the one-sided slip casting of each stopping valve control or bilateral slip casting.
This constructional method disclosed in this invention has substituted traditional artificial transport by pipeline slurry conveyed, greatly reduces workman's labour intensity, reduces the setting rate of mud, increases work efficiency, and reduces construction cost, the reduction of erection time.
Brief description of the drawings
Fig. 1 is equipment layout schematic diagram of the present invention.
In figure: a platform 1, slurry mixer 2, mud torage tank 3, Veritical mud pump 4, mud main pipeline 5, slip casting arm 6, stopping valve 7, furnace roof 8, end platform 9.
Embodiment
Below in conjunction with drawings and Examples, the present invention will be further described.
Referring to accompanying drawing 1, the hot pumping grout construction method of this coke oven disclosed in this invention, constructs according to following steps.
A, a platform 1 and end platform 9 are separately positioned on the both sides of coke oven, slurry mixer 2 be arranged on coke oven one side between on platform 1, a mud torage tank 3 is set before slurry mixer 2, mud torage tank is generally rectangle, its size is according to service condition field fabrication.Veritical mud pump 4 is housed in mud torage tank 3, and the present embodiment adopts PNL Veritical mud pump.
B, the bracing frame that is 500-600mm at oven top of coke oven 8 scaffolding heights, the scaffolding of working-yard is fixed mud main pipeline 5 on bracing frame, mud main pipeline 5 is fixed on bracing frame with web members such as tying up silk.Mud main pipeline is along the horizontal center line layout of oven top of coke oven 8, and one end of mud main pipeline 5 and Veritical mud pump 4 adopt DN50 high-pressure air hose to link together, and mud main pipeline adopts the weldless steel tube of Φ 48.
C, at the interval, both sides of mud main pipeline 5, slip casting arm 6 is set respectively, between each slip casting arm 6 and mud main pipeline 5, is provided with stopping valve 7; On mud main pipeline, every five carbonizing chambers, a slip casting arm 6 is set, the slurry output end of each slip casting arm 6 is installed respectively one section of steel pipe, easy to use, and the length of slip casting arm 6 is definite according to having a lot of social connections.Slip casting arm generally adopts sebific duct, facilitates mobile slip casting point.
D, startup Veritical mud pump are in the milk, and in whole filling process, each slip casting arm keeps logical slurry, realizes the control to slip casting point by the stopping valve of controlling on each slip casting arm; Pulp absorbing hole at Veritical mud pump is wrapped with gauze, and the clod of avoiding not stirring is inhaled into and causes line clogging.In pumping filling process, if suspend slip casting, valve is turned down, forbid to shut, connect the mud of outflow with liquid dump bailer; If long-time intermittently or stage stop grouting, pipeline is cleaned with Veritical mud pump pumping clear water, prevent obstruction.
Slip casting arm respectively evenly interval be arranged in the both sides of mud main pipeline, be in the milk by each stopping valve controlling machine, the one-sided grouting of coke side or bilateral simultaneously.

Claims (7)

1. the hot pumping grout construction method of coke oven, is characterized in that, constructs according to following steps:
A, slurry mixer be arranged on coke oven one side between platform or end platform on, a mud torage tank is set before slurry mixer, in this torage tank, Veritical mud pump is housed;
B, prolong at oven top of coke oven the bracing frame that coke oven medullary ray scaffolding height is 500-600mm, fix mud main pipeline on bracing frame, one end of this mud main pipeline is connected with Veritical mud pump;
The interval, both sides of c, mud main pipeline arranges respectively slip casting arm, between each slip casting arm and mud main pipeline, is provided with stopping valve;
D, startup Veritical mud pump are in the milk, and in whole filling process, each slip casting arm keeps logical slurry, realizes the control to furnace roof and protecting sheet slip casting by the stopping valve of controlling on each slip casting arm;
When e, filling stage property finish, pipeline is cleaned with Veritical mud pump pumping clear water.
2. the hot pumping grout construction method of coke oven according to claim 1, is characterized in that, adopts DN50 high-pressure air hose to connect between mud main pipeline and Veritical mud pump.
3. the hot pumping grout construction method of coke oven according to claim 1, is characterized in that, described mud main pipeline adopts the weldless steel tube of Φ 48.
4. the hot pumping grout construction method of coke oven according to claim 1, is characterized in that, on mud main pipeline, every five carbonizing chambers, a slip casting arm is set.
5. the hot pumping grout construction method of coke oven according to claim 1, is characterized in that, mud main pipeline is arranged along the horizontal center line of oven top of coke oven.
6. the hot pumping grout construction method of coke oven according to claim 1, is characterized in that, the slurry output end of each slip casting arm is installed respectively one section of steel pipe.
7. the hot pumping grout construction method of coke oven according to claim 1, is characterized in that, slip casting arm respectively evenly interval be arranged in the both sides of mud main pipeline, by the one-sided slip casting of each stopping valve control or bilateral slip casting.
CN201310335192.7A 2013-08-05 2013-08-05 Coke oven heat-state pumping grouting construction method Active CN103387835B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310335192.7A CN103387835B (en) 2013-08-05 2013-08-05 Coke oven heat-state pumping grouting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310335192.7A CN103387835B (en) 2013-08-05 2013-08-05 Coke oven heat-state pumping grouting construction method

Publications (2)

Publication Number Publication Date
CN103387835A CN103387835A (en) 2013-11-13
CN103387835B true CN103387835B (en) 2014-06-11

Family

ID=49532258

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310335192.7A Active CN103387835B (en) 2013-08-05 2013-08-05 Coke oven heat-state pumping grouting construction method

Country Status (1)

Country Link
CN (1) CN103387835B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104789233A (en) * 2015-04-03 2015-07-22 中国五冶集团有限公司 Furnace top mud conveying system for coke oven hot construction and implementation method of furnace top mud conveying system
CN104848037B (en) * 2015-06-11 2017-05-31 中国二十二冶集团有限公司 Opening construction technique does not build mud automatic conveying system by laying bricks or stones to hot-blast stove
CN112195032A (en) * 2020-09-30 2021-01-08 中国一冶集团有限公司 Inside fire-resistant mud conveying system of coke oven big-arch shelter

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2848853Y (en) * 2005-12-10 2006-12-20 攀枝花新钢钒股份有限公司 Fire brick building device of coke oven carbonation chamber bottom
CN101748894A (en) * 2009-12-08 2010-06-23 中国第一冶金建设有限责任公司 Auxiliary quick construction method of temporary light rail in coke furnace building thermal state project
CN201627375U (en) * 2010-04-16 2010-11-10 中国葛洲坝集团股份有限公司 Injection grouting construction device for inside corner position
CN101922150A (en) * 2009-06-11 2010-12-22 王毅 Method for manufacturing structure of riveting panel (wall) and device thereof
CN102296961A (en) * 2011-05-31 2011-12-28 中铁二十局集团有限公司 Karst tunnel large-scale cavern processing method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2848853Y (en) * 2005-12-10 2006-12-20 攀枝花新钢钒股份有限公司 Fire brick building device of coke oven carbonation chamber bottom
CN101922150A (en) * 2009-06-11 2010-12-22 王毅 Method for manufacturing structure of riveting panel (wall) and device thereof
CN101748894A (en) * 2009-12-08 2010-06-23 中国第一冶金建设有限责任公司 Auxiliary quick construction method of temporary light rail in coke furnace building thermal state project
CN201627375U (en) * 2010-04-16 2010-11-10 中国葛洲坝集团股份有限公司 Injection grouting construction device for inside corner position
CN102296961A (en) * 2011-05-31 2011-12-28 中铁二十局集团有限公司 Karst tunnel large-scale cavern processing method

Also Published As

Publication number Publication date
CN103387835A (en) 2013-11-13

Similar Documents

Publication Publication Date Title
CN104265302B (en) Jacking pipe joints stopping device
CN106246209B (en) A kind of tunnel inner lining concrete insulated curing constructing device and its construction method
CN103387835B (en) Coke oven heat-state pumping grouting construction method
CN103291322B (en) A kind of double-coil output concreting in cold-weather heat supply means to prevent freezing
CN203654684U (en) Tile soaking device in tall-building transporting system for tiles
CN103321255A (en) Underground concrete structural engineering joint waterproof construction method
CN107191222B (en) A kind of device and method using pressure-air conveying lotion
CN111472358A (en) Cooling method for interior of mass concrete foundation
CN108612118A (en) A kind of construction method of the disposable horizontal backfill of pipe curtain steel pipe inner concrete
CN202417520U (en) Concrete pumping distribution device used in construction of secondary linings of tunnel
CN210686007U (en) Single-line tunnel window-by-window lining concrete pouring device
CN205475710U (en) Steel -pipe column concrete jacking interface turnover device
CN203701600U (en) Masonry raining type maintenance device
CN105114118A (en) Flat hole gas extraction structure and implementing method thereof
CN201599041U (en) Synchronous slip casting device for shielding machine
CN107010993B (en) Cooling system for mass concrete
CN205329759U (en) Horizontal water pump siphon is supplied water system for wet -type ore dressing system
CN204921021U (en) Flat hole gas drainage structure
CN204312094U (en) A kind of tunnel excavation construction grid steel frame
CN103883348B (en) The welding method of a kind of minery gas pumping well ground pipeline
CN219045419U (en) Prevent shield and construct section of jurisdiction come-up slip casting structure
CN201087773Y (en) Long distance red mud pipe of aluminum oxide factory
CN205777332U (en) A kind of vertical drain outlet system of construction of super highrise building
CN203582793U (en) Coke furnace hot grouting device
CN207740040U (en) A kind of coal mine underground waste rock filling device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant