CN103352427A - Cast-in-place box beam lateral die sliding construction device and method - Google Patents

Cast-in-place box beam lateral die sliding construction device and method Download PDF

Info

Publication number
CN103352427A
CN103352427A CN2013102785223A CN201310278522A CN103352427A CN 103352427 A CN103352427 A CN 103352427A CN 2013102785223 A CN2013102785223 A CN 2013102785223A CN 201310278522 A CN201310278522 A CN 201310278522A CN 103352427 A CN103352427 A CN 103352427A
Authority
CN
China
Prior art keywords
side form
cast
sliding rail
lateral die
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013102785223A
Other languages
Chinese (zh)
Inventor
王勇
崔淑斌
黄建平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Electrification Engineering Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Electrification Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Electrification Engineering Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Electrification Engineering Co Ltd
Priority to CN2013102785223A priority Critical patent/CN103352427A/en
Publication of CN103352427A publication Critical patent/CN103352427A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a cast-in-place box beam lateral die sliding construction device. The cast-in-place box beam lateral die sliding construction device is characterized by comprising a movable lateral die, a sliding rail and a lifting jack. The movable lateral die is composed of a lateral die body and a walking pulley which is fixedly arranged at the bottom of the lateral die body, the sliding rail is fixedly arranged on a support, the movable lateral die is movably installed on the sliding rail, and the lifting jack is installed between the upper portion of the support and the bottom of the lateral die. The invention further relates to a cast-in-place box beam lateral die sliding construction method. By the adoption of the cast-in-place box beam lateral die sliding construction device and method, the phenomenon that in the construction process of a traditional cast-in-place beam, a large number of hoisting devices and transport vehicles are needed for demounting, reshipping and hoisting the lateral die is effectively avoided, and the cast-in-place box beam lateral die sliding construction device and method are economical, practical, simple in operation, and capable of effectively saving expenditures, shortening labor hours, and possessing obvious economic benefits and social benefits.

Description

Cast-in-situ box girder side form slippage construction device and method
Technical field
The invention belongs to technical field of bridge construction, particularly a kind of cast-in-situ box girder side form slippage construction device and method.
Background technology
With the national economic development, the scale of city intersection, speedway viaduct, elevated bridge of high speed railway is increasing, a large amount of construction of cast-in-situ box-beams occurs.Conventional construction method is: at the bottom of setting up the support → installation side form → bed die → colligation of mating formation, web reinforcement → installation internal mold → colligation top board reinforcement installation built-in fitting → concreting → concrete curing → form removal.After having built generally speaking a hole case beam, utilize crane and wooden handcart to have bad luck to next hole case beam after needing to remove side form, the recycling crane is installed side form.As seen, existing in-situ beam casting method is very complicated, wastes time and energy.
Summary of the invention
The object of the invention is to overcome the deficiencies in the prior art, a kind of cast-in-situ box girder side form slippage construction device is provided, it can effectively reduce difficulty of construction, and is simple to operate, and efficiency of construction is provided.
The present invention solves its technical problem and takes following technical scheme to realize:
A kind of cast-in-situ box girder side form slippage construction device; it is characterized in that: consisted of by removable side form, sliding rail and jack; removable side form is made of side form, side form truss and the traveling pulley that is fixedly mounted with side form truss bottom; be fixedly mounted with described sliding rail at support; removable side form moves and is installed on this sliding rail, between support top and side form bottom jack is installed.
2, a kind of cast-in-situ box girder side form gliding construction method, it is characterized in that: it comprises the steps:
⑴ when, construction the first hole case beam, adopt jack that side form is adjusted to design elevation, and locked jack;
⑵, built the concrete of the first hole case beam, after concrete reaches strength of mould stripping, with the jack of homonymy synchronously, slowly fall;
⑶, the traveling pulley of removable side form is dropped on the sliding rail;
⑷, the second hole box beam bracket continuous with the first hole case beam is installed, and installed sliding rail at support, and guarantee that the sliding rail connection on first, second hole box beam bracket is smooth-going;
⑸, utilization are installed in the dilatory side form of hoist engine of front end Dun Ding, removable side form moves forward along track, move to design attitude after, stop to draw, removable side form position is finely tuned, and utilize jack that removable side form is pushed up to design elevation, locked;
⑹, repetition above-mentioned steps, the sliding construction of realization Cast-in-situ Beam side form.
Advantage of the present invention and good effect are:
1. this cast-in-situ box girder side form slippage construction device and job practices; utilize following two characteristics of Cast-in-situ Beam: continuous poriferous employing cast-in-situ construction method is constructed; and the box beam bracket mode of continuous placing is identical; adopt gliding construction method; effectively having reduced needs a large amount of hanging devices, haulage vehicle that side form is dismantled, has bad luck, lifted in traditional in-situ beam casting process, economical and practical, simple to operate.
2. this cast-in-situ box girder side form slippage construction device and job practices; can effectively save funds and shorten man-hour, as in the continuous 8 hole in-situ beam castings of the single-minded seat of Shen Dan visitor, save about 160,000 yuan of machinery expenses; save 16 days durations, have obvious economic benefit and social benefit.
Description of drawings
Fig. 1 is structural representation of the present invention;
Fig. 2 is the A section enlarged drawing of Fig. 1.
Reference numeral:
1-side form, 2-side form truss, 3-traveling pulley, 4-jack, 5-sliding rail, 6-support.
The specific embodiment
The invention will be further described below in conjunction with accompanying drawing, by specific embodiment.Following examples are descriptive, are not determinate, can not limit protection scope of the present invention with this.
A kind of cast-in-situ box girder side form slippage construction device; consisted of by removable side form, sliding rail 5 and jack 4; removable side form is by side form 1, side form truss 2 and be fixedly mounted with and drain capable pulley 3 with two of side form truss bottom and consist of; be fixedly mounted with side by side sliding rail at support 6; removable side form moves and is installed on this sliding rail, the symmetrical jack of installing between support top and side form bottom.Jack position card is close to the position of traveling wheel.Above-mentioned removable side form, sliding rail are the same structures that is positioned at case beam both sides.
A kind of cast-in-situ box girder side form gliding construction method, it comprises the steps:
⑴ when, construction the first hole case beam, adopt jack that side form is adjusted to design elevation, and locked jack.
⑵, built the concrete of the first hole case beam, after concrete reaches strength of mould stripping, with the jack of homonymy synchronously, slowly fall.
⑶, the traveling pulley of removable side form is dropped on the sliding rail; Track adopts worker's 16 i iron.
⑷, the second hole box beam bracket continuous with the first hole case beam is installed, and installed sliding rail at support, and guarantee that the sliding rail connection on first, second hole box beam bracket is smooth-going.
⑸, utilize the dilatory side form of the hoist engine be installed in front end Dun Ding, removable side form moves forward along track, move to design attitude after, stop to draw, removable side form position is finely tuned, and utilizes jack that side form is pushed up to design elevation, locked.
⑹, repetition above-mentioned steps, the sliding construction of realization Cast-in-situ Beam side form.
Although disclose for the purpose of illustration embodiments of the invention and accompanying drawing, but it will be appreciated by those skilled in the art that: in the spirit and scope that do not break away from the present invention and claims, various replacements, variation and modification all are possible, therefore, scope of the present invention is not limited to embodiment and the disclosed content of accompanying drawing.

Claims (2)

1. cast-in-situ box girder side form slippage construction device; it is characterized in that: consisted of by removable side form, sliding rail and jack; removable side form is made of side form, side form truss and the traveling pulley that is fixedly mounted with side form truss bottom; be fixedly mounted with described sliding rail at support; removable side form moves and is installed on this sliding rail, between support top and side form bottom jack is installed.
2. cast-in-situ box girder side form gliding construction method, it is characterized in that: it comprises the steps:
⑴ when, construction the first hole case beam, adopt jack that side form is adjusted to design elevation, and locked jack;
⑵, built the concrete of the first hole case beam, after concrete reaches strength of mould stripping, with the jack of homonymy synchronously, slowly fall;
⑶, the traveling pulley of removable side form is dropped on the sliding rail;
⑷, the second hole box beam bracket continuous with the first hole case beam is installed, and installed sliding rail at support, and guarantee that the sliding rail connection on first, second hole box beam bracket is smooth-going;
⑸, utilization are installed in the dilatory side form of hoist engine of front end Dun Ding, removable side form moves forward along track, move to design attitude after, stop to draw, removable side form position is finely tuned, and utilize jack that removable side form is pushed up to design elevation, locked;
⑹, repetition above-mentioned steps, the sliding construction of realization Cast-in-situ Beam side form.
CN2013102785223A 2013-07-04 2013-07-04 Cast-in-place box beam lateral die sliding construction device and method Pending CN103352427A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013102785223A CN103352427A (en) 2013-07-04 2013-07-04 Cast-in-place box beam lateral die sliding construction device and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013102785223A CN103352427A (en) 2013-07-04 2013-07-04 Cast-in-place box beam lateral die sliding construction device and method

Publications (1)

Publication Number Publication Date
CN103352427A true CN103352427A (en) 2013-10-16

Family

ID=49308835

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013102785223A Pending CN103352427A (en) 2013-07-04 2013-07-04 Cast-in-place box beam lateral die sliding construction device and method

Country Status (1)

Country Link
CN (1) CN103352427A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669215A (en) * 2013-11-19 2014-03-26 中建三局建设工程股份有限公司 Vertical-horizontal overall-sliding type side mold of fulcrum-few support
CN105464000A (en) * 2016-01-10 2016-04-06 中铁十一局集团第一工程有限公司 Cast-in-place box beam moving formwork
CN105735141A (en) * 2016-05-05 2016-07-06 中铁上海工程局集团有限公司 Gliding device with box beam side template and construction method thereof
CN107245955A (en) * 2017-08-06 2017-10-13 中国水利水电第七工程局成都水电建设工程有限公司 A kind of band translation sliding formwork spirally falls the cast-in-place beam forms of rack supporting device
CN107268448A (en) * 2017-07-28 2017-10-20 中铁十局集团第四工程有限公司 A kind of form removable of support cast-in-place concrete continuous beam and erecting device
CN107542037A (en) * 2017-09-28 2018-01-05 谢晓燕 A kind of new supporting bracket of bridge construction
CN107724250A (en) * 2017-11-28 2018-02-23 中交公局第三工程有限公司 Cast-in-situ box girder mold plate connecting mechanism and cast-in-situ box girder support shuttering
CN112281664A (en) * 2020-10-22 2021-01-29 中铁八局集团第一工程有限公司 Slip form construction method for cast-in-situ of large-span simply supported beam
CN112482781A (en) * 2020-10-21 2021-03-12 中铁大桥局第七工程有限公司 Side mold bent frame system and using method thereof
CN113585736A (en) * 2021-07-26 2021-11-02 中铁一局集团(广州)建设工程有限公司 Cast-in-place case roof beam integral sliding type side form with adjustable it is multidirectional
CN113756191A (en) * 2021-08-12 2021-12-07 中铁上海工程局集团有限公司 Automatic sliding installation construction method for steel side mold
CN114438887A (en) * 2021-12-28 2022-05-06 中铁二十局集团有限公司 Template moving method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000017883A (en) * 1999-12-27 2000-04-06 김근택 Incremental launching method type pc box girder bridge making mold system and segment making method thereof
KR20060008453A (en) * 2004-07-20 2006-01-27 김근택 Bridge construction work method
JP2010018975A (en) * 2008-07-09 2010-01-28 Nippon Steel & Sumikin Metal Products Co Ltd Form timbering and horizontal force processing member for form timbering
CN101922142A (en) * 2009-10-10 2010-12-22 中交二公局第二工程有限公司 Cast-in-situ box beam bracket template integral sliding construction method
CN102140779A (en) * 2011-01-14 2011-08-03 中铁大桥局集团第六工程有限公司 Movable cast-in-situ support and movable construction method of box girder cast-in-situ support
CN202180523U (en) * 2011-08-23 2012-04-04 湖南中铁五新钢模有限责任公司 Outer-side mould traveling mechanism
CN202220327U (en) * 2011-07-20 2012-05-16 中铁十四局集团有限公司 Moving pulley of side web plate of full space support cast-in-place box beam
CN203320425U (en) * 2013-07-04 2013-12-04 中铁十三局集团电务工程有限公司 Cast-in-situ box girder construction apparatus with slidingly movable side mold

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000017883A (en) * 1999-12-27 2000-04-06 김근택 Incremental launching method type pc box girder bridge making mold system and segment making method thereof
KR20060008453A (en) * 2004-07-20 2006-01-27 김근택 Bridge construction work method
JP2010018975A (en) * 2008-07-09 2010-01-28 Nippon Steel & Sumikin Metal Products Co Ltd Form timbering and horizontal force processing member for form timbering
CN101922142A (en) * 2009-10-10 2010-12-22 中交二公局第二工程有限公司 Cast-in-situ box beam bracket template integral sliding construction method
CN102140779A (en) * 2011-01-14 2011-08-03 中铁大桥局集团第六工程有限公司 Movable cast-in-situ support and movable construction method of box girder cast-in-situ support
CN202220327U (en) * 2011-07-20 2012-05-16 中铁十四局集团有限公司 Moving pulley of side web plate of full space support cast-in-place box beam
CN202180523U (en) * 2011-08-23 2012-04-04 湖南中铁五新钢模有限责任公司 Outer-side mould traveling mechanism
CN203320425U (en) * 2013-07-04 2013-12-04 中铁十三局集团电务工程有限公司 Cast-in-situ box girder construction apparatus with slidingly movable side mold

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陆国清: "侧模滑移在膺架现浇施工中的应用", 《黑龙江科技信息》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669215A (en) * 2013-11-19 2014-03-26 中建三局建设工程股份有限公司 Vertical-horizontal overall-sliding type side mold of fulcrum-few support
CN105464000A (en) * 2016-01-10 2016-04-06 中铁十一局集团第一工程有限公司 Cast-in-place box beam moving formwork
CN105735141A (en) * 2016-05-05 2016-07-06 中铁上海工程局集团有限公司 Gliding device with box beam side template and construction method thereof
CN107268448A (en) * 2017-07-28 2017-10-20 中铁十局集团第四工程有限公司 A kind of form removable of support cast-in-place concrete continuous beam and erecting device
CN107245955A (en) * 2017-08-06 2017-10-13 中国水利水电第七工程局成都水电建设工程有限公司 A kind of band translation sliding formwork spirally falls the cast-in-place beam forms of rack supporting device
CN107542037B (en) * 2017-09-28 2018-12-04 谢志坚 A kind of supporting bracket of bridge construction
CN107542037A (en) * 2017-09-28 2018-01-05 谢晓燕 A kind of new supporting bracket of bridge construction
CN107724250A (en) * 2017-11-28 2018-02-23 中交公局第三工程有限公司 Cast-in-situ box girder mold plate connecting mechanism and cast-in-situ box girder support shuttering
CN112482781A (en) * 2020-10-21 2021-03-12 中铁大桥局第七工程有限公司 Side mold bent frame system and using method thereof
CN112281664A (en) * 2020-10-22 2021-01-29 中铁八局集团第一工程有限公司 Slip form construction method for cast-in-situ of large-span simply supported beam
CN113585736A (en) * 2021-07-26 2021-11-02 中铁一局集团(广州)建设工程有限公司 Cast-in-place case roof beam integral sliding type side form with adjustable it is multidirectional
CN113756191A (en) * 2021-08-12 2021-12-07 中铁上海工程局集团有限公司 Automatic sliding installation construction method for steel side mold
CN113756191B (en) * 2021-08-12 2024-05-17 中铁上海工程局集团有限公司 Automatic sliding installation construction method for steel side mold
CN114438887A (en) * 2021-12-28 2022-05-06 中铁二十局集团有限公司 Template moving method

Similar Documents

Publication Publication Date Title
CN103352427A (en) Cast-in-place box beam lateral die sliding construction device and method
CN203320425U (en) Cast-in-situ box girder construction apparatus with slidingly movable side mold
CN103334381B (en) Full-bracket track-bogie bearing and moving device and construction method for installing steel box girders
CN100547225C (en) A kind of tunnel overhead arch mould plate trolley with floating type traffic under carriage
CN204662279U (en) Tumbling-type concrete box girder bridge rotator construction with protection system closes up hanger device
CN102094392A (en) Lower supported hanging basket in bridge construction and application thereof
CN103669215A (en) Vertical-horizontal overall-sliding type side mold of fulcrum-few support
CN202707081U (en) Walk-through type closed conduit pouring template trolley
CN102134832B (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN103194977B (en) Integration of transporting and building formula Bridge Erector sets up first hole case beam front launching nose machine installation method
CN101885206B (en) Hydraulic internal mold truss type walking track system of high speed railway prefabricating box girder
CN201080597Y (en) Multifunctional cast-in-situ cantilever plate construction bracket
CN106192761B (en) A kind of method for disassembling mobile formwork in the narrow short transition time section of bridge tunnel
CN106285019A (en) A kind of overhead traveling crane installation method under confined space
CN201776835U (en) Hydraulic mechanism for fitting hydraulic internal mold in precast box-girder for high-speed railway
CN201972099U (en) Through type hanging basket in bridge construction
CN203769791U (en) Small curvature radius steering sliding device for shield train equipment
CN209178828U (en) A kind of cast-in-situ box girder outer steel formwork board mounting assembly
CN209836697U (en) Long steel rail cross-track shifting device
CN103194978B (en) Erecting method for last three-span box girders in railway bridging
CN204266129U (en) Steel box-girder installs the auxiliary bridge of the nose
CN202595630U (en) Template construction trolley for steel-frame bridge crossing business line
CN205189885U (en) Simple and easy backing plate that is unearthed
CN207108292U (en) Novel U-shaped erection equipment
CN201460908U (en) Tunnel high side wall concrete lining trolley

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 300150 Tianjin city Hebei District Zhicheng Daocheng of No. 41

Applicant after: CR13G ELECTRIC ENGINEERING CO., LTD.

Address before: 300150 Tianjin city Hebei District Zhicheng Daocheng of No. 41

Applicant before: CR13G Electric Engineering Co., Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: CHINA RAILWAY 13TH BUREAU GROUP ELECTRICAL SERVICE ENGINEERING CO., LTD. TO: CHINA RAILWAY CONSTRUCTION BRIDGE ENGINEERING GROUP ELECTRIFICAYTION ENGINEERING CO., LTD.

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131016