CN103309782A - Burning and testing integrated system - Google Patents

Burning and testing integrated system Download PDF

Info

Publication number
CN103309782A
CN103309782A CN2013102710142A CN201310271014A CN103309782A CN 103309782 A CN103309782 A CN 103309782A CN 2013102710142 A CN2013102710142 A CN 2013102710142A CN 201310271014 A CN201310271014 A CN 201310271014A CN 103309782 A CN103309782 A CN 103309782A
Authority
CN
China
Prior art keywords
test
burning
module
microcontroller chip
pair matcher
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013102710142A
Other languages
Chinese (zh)
Inventor
詹明东
郑耀彬
于士坤
陈晓峰
谢琨
王佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Shiyuan Electronics Thecnology Co Ltd
Original Assignee
Guangzhou Shiyuan Electronics Thecnology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Shiyuan Electronics Thecnology Co Ltd filed Critical Guangzhou Shiyuan Electronics Thecnology Co Ltd
Priority to CN2013102710142A priority Critical patent/CN103309782A/en
Publication of CN103309782A publication Critical patent/CN103309782A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Arrangements For Transmission Of Measured Signals (AREA)

Abstract

The invention relates to the field of communication, and discloses a burning and testing integrated system, which comprises: computer console, operation panel, little control chip, pairing device. The computer console is connected with the micro control chip through a universal serial bus; the micro control chip is connected with the operation table through a serial peripheral device bus; the operating platform is provided with a first groove for accommodating a module to be burned and tested; the pairing device is connected with the micro control chip and is used for pairing with the module to be burned and tested and transmitting test data during data transmission test. By applying the technical scheme, data transmission test can be performed immediately after software burning of the ZigBee communication module, so that the workload is reduced, and the working efficiency is improved.

Description

A kind of burning and test integrated system
Technical field
The present invention relates to the communications field, particularly a kind of burning and test integrated system.
Background technology
Development along with society, ZigBee technology is as the simple short-distance wireless communication technology of a kind of framework, application at Internet of Things is increasing, just more and more causes attracting attention of industry in the application of automation field, such as fields such as intelligent grid, intelligent transportation, Smart Homes.And when producing the ZigBee wireless module, need to carry out the burning of software and the test of data transmission to the ZigBee module, to guarantee the performance of ZigBee module.
In carrying out research process of the present invention, the inventor finds that there is following defective at least in prior art:
Burning and data transmission test can not carry out at same equipment, need first transmitter module or receiver module to be carried out the software burning, and switching device carries out data transmission test again, and when the ZigBee module was produced in batches, workload was loaded down with trivial details, and work efficiency is lower.In addition, when a plurality of platforms or a plurality of module are tested simultaneously, can cause interference each other, need in specific shielding house, to test.
Summary of the invention
The purpose of the embodiment of the invention is to provide a kind of burning and test integrated system, uses this technical scheme and can followed by carrying out data transmission test, reduce workload after the burning of ZigBee communication module software, increases work efficiency.
First aspect the invention provides a kind of burning and test integrated system, comprising: computer control platform, operator's console, microcontroller chip, pair matcher;
Described computer control platform is connected with described microcontroller chip by USB (universal serial bus);
Described microcontroller chip is connected with described operator's console by the serial peripheral equipment bus;
Described operator's console is provided with the first groove, and described the first groove is used for settling the module for the treatment of burning and test;
Described pair matcher is connected with described microcontroller chip, is used for when data transmission test, matching mutually with described burning and the test module treated, and transmitting test data.
In conjunction with first aspect, under the first implementation, described pair matcher is connected with described microcontroller chip, is specially:
In described USB (universal serial bus), minute draw generic serial port, described pair matcher with by described generic serial port, be connected with described microcontroller chip.
In conjunction with the first implementation of first aspect, under the second implementation, describedly treat that the module of burning and test is the ZigBee transmitter module;
Described pair matcher is used for and described ZigBee transmitter module pairing, and receives test data for receiving pair matcher.
In conjunction with first aspect, under the third implementation, described pair matcher is connected with described microcontroller chip, is specially:
Described pair matcher is installed in the second groove of described operator's console, by described serial peripheral equipment bus, is connected with described microcontroller chip.
In conjunction with the third implementation of first aspect, under the 4th kind of implementation, describedly treat that the module of burning and test is the ZigBee receiver module;
Described pair matcher is the emission pair matcher, is used for and described ZigBee receiver module pairing, and the transmission test data.
In conjunction with first to fourth arbitrary implementation of first aspect or first aspect, under the 5th kind of implementation, described integral system also comprises: radome;
Described microcontroller chip, described pair matcher and described operator's console all are arranged in the described radome.
Therefore, use the present embodiment technical scheme, the ZigBee communication module for the treatment of burning and test is placed in the first groove on the operator's console, computer control platform is connected with the microcontroller chip by USB (universal serial bus), carry out mutual communication, computer control platform starts the burning of software to microcontroller chip sending controling instruction.The microcontroller chip is by the serial peripheral equipment bus, is connected with the ZigBee module of test with the burning for the treatment of on the operator's console, this ZigBee module is carried out burning.After burning is finished, computer control platform is followed by sending instruction to the microcontroller chip, the microcontroller chip sends data transfer instruction to the ZigBee module, the pair matcher of ZigBee module and system is matched, and carry out data transmission, computer control platform shows this transmission of data, finishes the transmission of data test to ZigBee.In prior art, need to carry out burning and data transmission test at distinct device, adopt technical solution of the present invention can reduce a large amount of workloads, improve and produce and work efficiency.In addition, during test, the software on the computer control platform is analyzed the transmission of data, can show intuitively record burning, test result and percent of pass.
Further, if this treats that the module of burning and test is the ZigBee transmitter module, pair matcher is for receiving pair matcher.Receive pair matcher by dividing the generic serial port that extracts in the USB (universal serial bus), be connected respectively with microcontroller chip and computer control platform.When the ZigBee transmitter module was finished burning and carried out data transmission test, transmitter module matched with the reception pair matcher.After the successful matching, receive pair matcher and receive the test the transmission of data that transmitter module sends, this test the transmission of data passes to computer control platform through USB (universal serial bus), by the software of computer control platform the test the transmission of data is analyzed, and the most backward user presents test result.As seen, the employing the technical program can be integrated to the realization burning of ZigBee transmitter module and test transmission, increases work efficiency.
Further, if this treats that the module of burning and test is the ZigBee receiver module, pair matcher is the emission pair matcher.The emission pair matcher is installed in the second groove of operator's console, by the serial peripheral equipment bus, is connected with the microcontroller chip.When the ZigBee receiver module is finished burning and is tested, the microcontroller chip is controlled module to be measured and transmission pair matcher, this module to be measured is matched with the emission pair matcher, the emission pair matcher sends to the test the transmission of data on the module to be measured by wireless, this test is transmitted data after module to be measured receives, pass to the microcontroller chip by the serial peripheral equipment bus, pass to computer control platform by USB (universal serial bus) again, by the software analysis of computer control platform and present test result.As seen, the employing the technical program can be integrated to the realization burning of ZigBee receiver module and test transmission, increases work efficiency.
Further, this integral system also comprises: radome.This microcontroller chip, pair matcher, operator's console all are arranged in this radome.Cause interference each other when adopting this technical scheme can avoid a plurality of platforms or a plurality of module to test simultaneously, improve the practicality of integral system
Description of drawings
In order to be illustrated more clearly in the embodiment of the invention or technical scheme of the prior art, the below will do to introduce simply to the accompanying drawing of required use in embodiment or the description of the Prior Art, apparently, accompanying drawing in the following describes only is some embodiments of the present invention, for those of ordinary skills, under the prerequisite of not paying creative work, can also obtain according to these accompanying drawings other accompanying drawing.
A kind of burning that Fig. 1 provides for the embodiment of the invention and the structural representation of test integrated system;
The optional structural representation of burning and test integrated system that Fig. 2 provides for the embodiment of the invention;
The optional structural representation of burning and test integrated system that Fig. 3 provides for the embodiment of the invention;
The optional structural representation of burning and test integrated system that Fig. 4 provides for the embodiment of the invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the invention, the technical scheme in the embodiment of the invention is clearly and completely described, obviously, described embodiment only is the present invention's part embodiment, rather than whole embodiment.Based on the embodiment among the present invention, those of ordinary skills belong to the scope of protection of the invention not making the every other embodiment that obtains under the creative work prerequisite.
Embodiment:
Referring to Fig. 1, the present embodiment provides a kind of burning and test integrated system, and this system is used for software burning and the data transmission test of ZigBee communication module.This system comprises: computer control platform 101, microcontroller chip 102, operator's console 103, pair matcher 104.
Syndeton and the principle of work of each parts are as follows:
Computer control platform 101 is connected with microcontroller chip 102 by USB (universal serial bus) (USB), is used for to microcontroller chip sending controling instruction, and presents burning, test result and percent of pass to the user.
In the present embodiment, the universal serial bus wherein public mouth of A type of an end links to each other with computer control platform 101, and the Type B public access mouth of the other end is connected with microcontroller chip 102, so that console computer 101 carries out communication with control chip 102.
Microcontroller chip 102 is connected with operator's console 103 by serial peripheral equipment bus (SPI).
In the present embodiment, this microcontroller chip 102 can be the MCU chip.Microcontroller chip 102 is controlled burning and the data transmission test of ZigBee module according to the steering order that issues of computer control platform 101.The serial peripheral equipment bus of microcontroller chip, link to each other with the thimble bottom in the operator's console upper groove, these stitch be one by one to should treating each interface of burning and test module, such as GND (), VCC(power supply), NRST (reset mouthful), DEBUG_DC (debugging interface), DEBUG_DD (debugging interface), RX(fetch interface), the TX(transmission interface), EN(dormancy awakening interface), SPI0_MISO, SPI0_MOSI, the interfaces such as SPI0_SSN, SPI0_CLK.
Be provided with the first groove 105 on the operator's console 103, be used for placing the module for the treatment of burning and test.Be provided with a plurality of thimbles in the first groove 105, connect one to one with this each port for the treatment of burning and test module.Because operator's console 103 is connected with microcontroller chip 102 by spi bus, when the module for the treatment of burning and test is installed in the first groove 105, this module is connected with microcontroller chip 102 by spi bus.
Pair matcher 104 is connected with microcontroller chip 102, is used for when data transmission test, matching with this module for the treatment of burning and test, and transmitting test data.
Specific works principle of the present invention is as follows:
Place the module for the treatment of burning and test in the first groove 105, computer control platform 101 treats that to this burning and test module carry out the software burning to microcontroller chip 102 sending controling instructions, and in computer control platform, shows the burning progress, and completion status.After burning was complete, computer control platform 101 sent matched order to microcontroller chip 102, and microcontroller chip 102 these modules to be measured of control and pair matcher 104 are matched.After the successful matching, issue test instruction by computer control platform 101, microcontroller 102 these modules to be measured of control and pair matcher 104 are carried out data transmission, and this paired data passes to computer control platform 101, software by computer control platform 101 is analyzed, and test result and percent of pass are offered the user.
Optionally, referring to Fig. 2, if this treats that burning and transport module are the ZigBee transmitter module, then pair matcher is for receiving pair matcher 204, and pair matcher 204 divides the generic serial port (USB Hub) of drawing to be connected with microcontroller chip 102 by USB (universal serial bus).In when test, computer control platform 101 sends matched orders for microcontroller chip 102, and this moment, transmitter module can match with the pair matcher 204 that is inserted in USB Hub place and is used for test.If successful matching, software on the computer control platform 101 can show the information of pairing, then computer sends data transfer instruction for microcontroller chip 102 again, the control transmitter module by Radio Transmission Technology to receiving pair matcher 204 the transmission of datas, demonstrate the data of transmission this moment at display, finish the test of transmitter module pairing and the transmission of data.
Optionally, referring to Fig. 3, if this treats that burning and transport module are the ZigBee receiver module, then pair matcher is emission pair matcher 304.Be provided with the second groove 306 in the operator's console 303, emission pair matcher 304 is installed in the second groove 306, is connected with this microcontroller chip 102 by spi bus.In when test, computer control platform 101 sends matched orders for microcontroller chip 102, this moment module to be measured can with the second groove 306 in be used for pair matcher 304 pairings of test.If successful matching, software on the computer control platform 101 can show the information of pairing, then computer control platform 101 sends data transfer instruction for microcontroller chip 102 again, control sends pair matcher 304 to module transmitting data to be measured, after module to be measured receives transmitting test data, data are passed to microcontroller chip 102 pass to again computer control platform 101, demonstrate the data that receive at display this moment, computer control platform is analyzed the transmitting test data that receives, and finishes the test of receiver module pairing and receive data.
Optionally, referring to Fig. 4, this integral system also comprises radome 401.Microcontroller chip 102, operator's console 103 and pair matcher 104 all are arranged in the described radome, in the time of avoiding a plurality of platforms or a plurality of module to test, cause interference each other.
Therefore, use the present embodiment technical scheme, the ZigBee communication module for the treatment of burning and test is placed in the first groove 105 on the operator's console 103, computer control platform 101 is connected with microcontroller chip 102 by USB (universal serial bus), carry out mutual communication, computer control platform 101 starts the burning of software to microcontroller chip 102 sending controling instructions.Microcontroller chip 102 is by the serial peripheral equipment bus, is connected with the ZigBee module of test with the burning for the treatment of on the operator's console 103, this ZigBee module is carried out burning.After burning is finished, computer control platform 101 is followed by sending instruction to microcontroller chip 102, microcontroller chip 102 sends data transfer instruction to the ZigBee module, the pair matcher 104 of ZigBee module and system is matched, and carry out data transmission, computer control platform 101 shows this transmission of data, finishes the transmission of data test to ZigBee.In prior art, need to carry out burning and data transmission test at distinct device, adopt technical solution of the present invention can reduce a large amount of workloads, improve and produce and work efficiency.In addition, during test, the software on the computer control platform is analyzed the transmission of data, can show intuitively record burning, test result and percent of pass.
Further, referring to Fig. 2, if this treats that the module of burning and test is the ZigBee transmitter module, pair matcher is for receiving receiver 204.Reception, is connected respectively with microcontroller chip 102 and computer control platform 101 by dividing the generic serial port that extracts in the USB (universal serial bus) device 204.When the ZigBee transmitter module is finished burning and is carried out data transmission test, transmitter module matches with reception pair matcher 204, after the successful matching, receive pair matcher 204 and receive the test the transmission of data that transmitter module sends, this test the transmission of data passes to computer control platform 101 through USB (universal serial bus), presents test result by the software analysis of computer control platform 101 and to the user.As seen, the employing the technical program can be integrated to the realization burning of ZigBee transmitter module and test transmission, increases work efficiency.
Further, referring to Fig. 3, if this treats that the module of burning and test is the ZigBee receiver module, pair matcher is emission pair matcher 304.Emission pair matcher 304 is installed in the second groove 306 of operator's console, by the serial peripheral equipment bus, is connected with microcontroller chip 102.When the ZigBee receiver module is finished burning and is tested, 102 pairs of modules to be measured of microcontroller chip and generation pair matcher 304 are controlled, this module to be measured and pair matcher 304 are matched, the emission pair matcher sends to the test the transmission of data on the module to be measured by wireless, these data are after module to be measured receives, pass to microcontroller chip 102 by the serial peripheral equipment bus, pass to computer control platform 101 by USB (universal serial bus) again, by the software analysis of computer control platform 101 and present test result.As seen, the employing the technical program can be integrated to the realization burning of ZigBee receiver module and test transmission, increases work efficiency.
Further, referring to Fig. 4, this integral system also comprises: radome 401.This microcontroller chip 102, pair matcher 104, operator's console 103 all are arranged in this radome.Cause interference each other when adopting this technical scheme can avoid a plurality of platforms or a plurality of module to test simultaneously, improve the practicality of integral system.
Device embodiment described above only is schematic, wherein said unit as the separating component explanation can or can not be physically to separate also, the parts that show as the unit can be or can not be physical locations also, namely can be positioned at a place, perhaps also can be distributed on a plurality of network element.Can select according to the actual needs wherein some or all of module to realize the purpose of the present embodiment scheme.Those of ordinary skills namely can understand and implement in the situation that do not pay performing creative labour.
Through the above description of the embodiments, those skilled in the art can be well understood to each embodiment and can realize by the mode that software adds essential general hardware platform, can certainly pass through hardware.Based on such understanding, the part that technique scheme contributes to prior art in essence in other words can embody with the form of software product, this computer software product can be stored in the computer-readable recording medium, such as ROM/RAM, magnetic disc, CD etc., comprise that some instructions are with so that a computer equipment (can be personal computer, server, perhaps network equipment etc.) carry out the described method of some part of each embodiment or embodiment.
Above-described embodiment does not consist of the restriction to this technical scheme protection domain.Any at above-mentioned embodiment spirit and principle within do modification, be equal to and replace and improvement etc., all should be included within the protection domain of this technical scheme.

Claims (6)

1. a burning and test integrated system is characterized in that, comprising: computer control platform, operator's console, microcontroller chip, pair matcher;
Described computer control platform is connected with described microcontroller chip by USB (universal serial bus);
Described microcontroller chip is connected with described operator's console by the serial peripheral equipment bus;
Described operator's console is provided with the first groove, and described the first groove is used for settling the module for the treatment of burning and test;
Described pair matcher is connected with described microcontroller chip, is used for when data transmission test, matching mutually with described burning and the test module treated, and transmitting test data.
2. burning according to claim 1 and test integrated system is characterized in that,
Described pair matcher is connected with described microcontroller chip, is specially:
In described USB (universal serial bus), minute draw generic serial port, described pair matcher with by described generic serial port, be connected with described microcontroller chip.
3. burning according to claim 2 and test integrated system is characterized in that,
Describedly treat that the module of burning and test is the ZigBee transmitter module;
Described pair matcher is used for and described ZigBee transmitter module pairing, and receives test data for receiving pair matcher.
4. burning according to claim 1 and test integrated system is characterized in that,
Described pair matcher is connected with described microcontroller chip, is specially:
Described pair matcher is installed in the second groove of described operator's console, by described serial peripheral equipment bus, is connected with described microcontroller chip.
5. burning according to claim 4 and test integrated system is characterized in that,
Describedly treat that the module of burning and test is the ZigBee receiver module;
Described pair matcher is the emission pair matcher, is used for and described ZigBee receiver module pairing, and the transmission test data.
6. according to claim 1 to 5 arbitrary described burning and test integrated systems, it is characterized in that, also comprise: radome;
Described microcontroller chip, described pair matcher and described operator's console all are arranged in the described radome.
CN2013102710142A 2013-06-28 2013-06-28 Burning and testing integrated system Pending CN103309782A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013102710142A CN103309782A (en) 2013-06-28 2013-06-28 Burning and testing integrated system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013102710142A CN103309782A (en) 2013-06-28 2013-06-28 Burning and testing integrated system

Publications (1)

Publication Number Publication Date
CN103309782A true CN103309782A (en) 2013-09-18

Family

ID=49135033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013102710142A Pending CN103309782A (en) 2013-06-28 2013-06-28 Burning and testing integrated system

Country Status (1)

Country Link
CN (1) CN103309782A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105573743A (en) * 2015-11-19 2016-05-11 深圳市芯海科技有限公司 Chip burning system and method and electronic equipment
CN106611578A (en) * 2015-10-27 2017-05-03 华为终端(东莞)有限公司 Fool-proof testing device
CN111679942A (en) * 2020-06-09 2020-09-18 深圳酷宅科技有限公司 Burning test method, system and computer readable storage medium
CN112418788A (en) * 2020-11-17 2021-02-26 广州易而达科技股份有限公司 Module production processing system and method
CN115079601A (en) * 2022-06-10 2022-09-20 宁波奥克斯电气股份有限公司 Control method for displaying program information and production information, controller and household appliance

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202033659U (en) * 2011-01-10 2011-11-09 宁波伊士通技术股份有限公司 Novel automatic testboard for injection machine master control board
CN102394105A (en) * 2011-12-14 2012-03-28 华容电子(昆山)有限公司 EEPROM on-line burner and on-line burning method
CN102455972A (en) * 2010-10-25 2012-05-16 英业达股份有限公司 Programming device
CN102709253A (en) * 2012-05-14 2012-10-03 奈电软性科技电子(珠海)有限公司 Process for manufacturing integrated circuit board

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102455972A (en) * 2010-10-25 2012-05-16 英业达股份有限公司 Programming device
CN202033659U (en) * 2011-01-10 2011-11-09 宁波伊士通技术股份有限公司 Novel automatic testboard for injection machine master control board
CN102394105A (en) * 2011-12-14 2012-03-28 华容电子(昆山)有限公司 EEPROM on-line burner and on-line burning method
CN102709253A (en) * 2012-05-14 2012-10-03 奈电软性科技电子(珠海)有限公司 Process for manufacturing integrated circuit board

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106611578A (en) * 2015-10-27 2017-05-03 华为终端(东莞)有限公司 Fool-proof testing device
CN105573743A (en) * 2015-11-19 2016-05-11 深圳市芯海科技有限公司 Chip burning system and method and electronic equipment
CN111679942A (en) * 2020-06-09 2020-09-18 深圳酷宅科技有限公司 Burning test method, system and computer readable storage medium
CN111679942B (en) * 2020-06-09 2024-03-22 深圳酷宅科技有限公司 Burn-in test method, system and computer readable storage medium
CN112418788A (en) * 2020-11-17 2021-02-26 广州易而达科技股份有限公司 Module production processing system and method
WO2022105170A1 (en) * 2020-11-17 2022-05-27 广州易而达科技股份有限公司 Production treatment system and method for module
CN115079601A (en) * 2022-06-10 2022-09-20 宁波奥克斯电气股份有限公司 Control method for displaying program information and production information, controller and household appliance
CN115079601B (en) * 2022-06-10 2024-05-10 宁波奥克斯电气股份有限公司 Control method, controller and household appliance for displaying program information and production information

Similar Documents

Publication Publication Date Title
CN103309782A (en) Burning and testing integrated system
CN107907814B (en) Method for improving mass production test efficiency of chips
CN103154905B (en) Apparatus and method for the automated analysis of combination application
CN204044811U (en) The switching device shifter of the direct-connected line of a kind of serial ports and cross spider
CN103412836B (en) Hot plug processing method, device and system
CN104468260A (en) Recognition method, device and system for mobile terminal device
CN104104436A (en) Electricity meter data acquisition apparatus with infrared upgrade function and upgrade method thereof
CN103839398A (en) Remote controller key value information processing method, control apparatus and remote controller
CN204117134U (en) A kind of electric-controlled plate wireless transmission programmer
CN103369711A (en) Communication connection establishment method and terminal device
CN204480239U (en) A kind of USB turns serial port control circuit
CN103034501A (en) Function calling method and function calling device for linux platform
CN203838596U (en) Card computer system and device
CN207504888U (en) Multichannel vehicle-mounted CAN Note data analyzers
CN202331915U (en) Wireless teaching robot development system
CN104571962A (en) Implementation method of firmware in USBKEY suitable for batch production
CN104699644B (en) A method of driving NFC modules under Android platform
CN106339048A (en) Serial port server with terminal-type interface
CN203117963U (en) Debugging system and device for providing graphical pin interface
CN106897479A (en) A kind of array antenna emulation mode and server
CN207096970U (en) A kind of code cd-rom recorder applied to T CON plates
CN102567202A (en) Double-interface intelligent card simulator based on field programmable gata array (FPGA)
CN105630730A (en) Information processing method and electronic equipment
CN206378852U (en) A kind of Multifunctional test equipment
CN108924613A (en) The method of set-top-box system and the set-top-box system of derivative different product form

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130918