CN103277122B - Method for drilling anchor rod hole and anchoring anchor rod in broken roof - Google Patents

Method for drilling anchor rod hole and anchoring anchor rod in broken roof Download PDF

Info

Publication number
CN103277122B
CN103277122B CN201310207314.4A CN201310207314A CN103277122B CN 103277122 B CN103277122 B CN 103277122B CN 201310207314 A CN201310207314 A CN 201310207314A CN 103277122 B CN103277122 B CN 103277122B
Authority
CN
China
Prior art keywords
rod
drill
drilling
anchor
drilling rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310207314.4A
Other languages
Chinese (zh)
Other versions
CN103277122A (en
Inventor
李青锋
朱川曲
周泽
杨党委
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Funing Longchuang Technology Service Co ltd
Original Assignee
Hunan University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University of Science and Technology filed Critical Hunan University of Science and Technology
Priority to CN201310207314.4A priority Critical patent/CN103277122B/en
Publication of CN103277122A publication Critical patent/CN103277122A/en
Application granted granted Critical
Publication of CN103277122B publication Critical patent/CN103277122B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a method for drilling an anchor rod hole and anchoring an anchor rod in a broken roof. The method includes the following steps that (1) the depth of a drill hole and the length of the anchor rod are determined according to supporting parameters of the anchor rod of broken surrounding rocks, and then two hollow tubular drill rods are connected according to the depth of the drill hole, or a connecting rod is arranged between the threaded ends of the two drill rods in a connected mode to form a combination drill rod; (2) the end, provided with a square inner buckle, of one drill rod is connected with a drill bit in a sleeved mode, and the end, provided with a square inner buckle, of the other drill rod is connected to a drill rig for drilling; (3) the drill rig is dismantled, the drill rods are exposed, and then a cement cartridge is sent to the bottom of a drill rod center hole through the anchor rod; (4) the anchor is pushed into the cement cartridge through the drill rig, the drill rod connected with the drill bit in the sleeved mode is withdrawn, and after 20-30 minutes, an arch supporting plate and a spherical nut are mounted at the end, extending out of the surrounding rocks, of the anchor rod. According to the method, the drill rods and the connecting rod are of a hollow tubular structure, and protective holes of the drill rods and the connecting rod avoid a hole collapse before anchoring the anchor rod; the cement cartridge is used as an anchoring agent, so that the anchoring is prevented from loosing efficacy.

Description

One bores bolthole and anchor rod anchored method in breaking roof
Technical field
The present invention relates to one in breaking roof, bore bolthole and anchor rod anchored method.
Background technology
Along with the increase of coal mining depth, part mine working presents the features such as large deformation, wall rock loosening ring scope is large, roadway surrounding rock is broken, makes roadway maintenance difficulty; In addition, in ultra close distance coal seam exploitation and separate zone production, its stope drift active workings top board is all more broken, adopts bolt support often to run into boring collapse hole and resin anchoring failure phenomenon in breaking surrounding rock.
Summary of the invention
In order to solve the problems of the technologies described above, the invention provides one and can avoid collapse hole of holing, that fastening invalidation phenomenon can be prevented again to occur bores bolthole and anchor rod anchored method in breaking roof.
The technical solution used in the present invention is: one bores bolthole and anchor rod anchored method in breaking roof, comprises the steps:
1) drilling rod is assembled: according to breaking surrounding rock Bolting Parameters determination drilling depth and rock-bolt length, when drilling depth is less than the length of a drilling rod, connected by adapter sleeve by the end of thread of the drilling rod of the tubular structure of two hollows; When drilling depth is greater than the length of a drilling rod, between the end of thread of two drilling rods, connect a connecting rod by adapter sleeve; Described connecting rod is made up of a connecting rod, or is connected to form by adapter sleeve by many connecting rods, and described connecting rod is the tubular structure of hollow;
2) hole: one end of the square interior button of a drilling rod and drill bit are socketed; One end of the square interior button of another drilling rod connects rig, boring;
3) cement-roll is placed: after boring, the drilling rod unloading rig and be connected with rig, then soaked cement-roll is filled in the centre bore of the drilling rod be socketed with drill bit, then head on anchor pole the cement-roll filled in and be sent to along the centre bore of drilling rod at the bottom of the hole of centre bore together;
4) anchoring: after cement-roll is in place, heads in cement-roll with rig by anchor pole, then slowly exits the drilling rod be socketed with drill bit, waits for 20 ~ 30 minutes, and arch supporting plate and spherical nut are installed in the one end of stretching out country rock at anchor pole, and screw spherical nut.
Compared with prior art, the invention has the beneficial effects as follows: 1. drilling rod of the present invention and connecting rod are the tubular structure of hollow that there is borehole wall-protection and endoporus filling cement-roll and anchor pole function; After boring, owing to having hollow drill pipe and connecting rod guard aperture, ensure that filling cement-roll and smoothly anchor rod anchored, avoid anchor rod anchored front collapse hole.2. drilling rod of the present invention and drill bit take socket mode to be connected, and after fill in cement-roll and anchor rod body in boring, drill bit can uncoupling automatic with drilling rod, is convenient to hollow drill pipe and exits.3. anchor pole press-in cement-roll anchorage style of the present invention, add anchor pole and the cement-roll Anchor Agent compactness in borehole space, Anchor Agent is contacted with country rock tightly, and fill up hole wall circumferential crack, improve the anchor-holding force of anchor bolt of breaking surrounding rock, avoid the fluidity cement in resin anchoring agent run off from hole wall crack and cause fastening invalidation problem.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention.
In figure: 1, country rock, 2, drill bit, 3, drilling rod, 4, adapter sleeve, 5 connecting rods, 51 connecting rods, 6, cement-roll, 7, anchor pole, 8, arch supporting plate, 9, spherical nut.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present invention is described in further detail.
As shown in Figure 1, the present invention includes following steps:
1) drilling rod is assembled: according to breaking surrounding rock 1 Bolting Parameters determination drilling depth and rock-bolt length; When drilling depth is less than the length of a drilling rod 3, the end of thread of the drilling rod 3 of the tubular structure of two hollows is connected by adapter sleeve 4; When drilling depth is greater than the length of a drilling rod 3, between the end of thread of two drilling rods 3, connect a connecting rod 5 by adapter sleeve 4; Described connecting rod 5 is made up of a connecting rod 51, or is connected to form by adapter sleeve 4 by many connecting rods 51, the described tubular structure of connecting rod 51 in hollow.
2) hole: one end of square for drilling rod 3 interior button and drill bit 2 are socketed; One end of the square interior button of another drilling rod 3 connects rig, boring.
3) cement-roll 6 is placed: after boring, the drilling rod unloading rig and be connected with rig, then soaked cement-roll 6 is filled in the centre bore of the drilling rod be socketed with drill bit 2, then head on anchor pole 7 cement-roll 6 filled in and be sent to along the centre bore of drilling rod 3 together at the bottom of the hole of centre bore.
4) anchoring: after cement-roll 6 is in place, heads in cement-roll 6 with rig by anchor pole 7, then slowly exits the drilling rod 3 and connecting rod 5 that are socketed with drill bit 2; Wait for 20 ~ 30 minutes, arch supporting plate 8 and spherical nut 9 are installed in the one end of stretching out country rock 1 at anchor pole 7, and screw the pretightning force that spherical nut 9 provides 30 ~ 50kN.
It is long that every root drilling rod 3 and connecting rod 51 are 1.0m; The internal diameter of drilling rod 3 and connecting rod 51 is 28mm.After boring, owing to having drilling rod 3 and connecting rod 5 guard aperture of hollow, before avoiding anchor pole 7 anchoring collapse hole and because of boring collapse hole cause cement-roll 6 and anchor pole 7 cannot send in hole.Meanwhile, because drilling rod 3 and drill bit 2 are socketed, after filling in cement-roll 6 and anchor pole 7 in the centre bore toward drilling rod 3, drill bit 2 can uncoupling automatic with drilling rod 3, is convenient to exiting of the drilling rod 3 be connected with drill bit 2.If anchor pole 7 adopts hollow bolt, the later stage can also toward slip casting in breaking surrounding rock 1, shutoff crack.The anchor pole 7 that the present invention uses is high-strength screw-thread steel anchor pole or hollow grouting anchor, and cement-roll 6 makes the Anchor Agent of anchor pole 7, and the fluidity cement in resin anchoring agent can be avoided to run off from hole wall crack and cause fastening invalidation.

Claims (3)

1. in breaking roof, bore bolthole and an anchor rod anchored method, it is characterized in that, comprise the steps:
1) according to breaking surrounding rock Bolting Parameters determination drilling depth and rock-bolt length, when drilling depth is less than the length of a drilling rod: the end of thread of the drilling rod of the tubular structure of two hollows is connected by adapter sleeve; When drilling depth is greater than the length of a drilling rod: connect connecting rod by adapter sleeve between the end of thread of two drilling rods; Described connecting rod is made up of a connecting rod, or is connected to form by adapter sleeve by many connecting rods, and described connecting rod is the tubular structure of hollow;
2) one end of square for drilling rod interior button and drill bit are socketed; One end of the square interior button of another drilling rod connects rig, boring;
3) after boring, the drilling rod unloading rig and be connected with rig, then fills in soaked cement-roll in the centre bore of the drilling rod be socketed with drill bit, then heads on anchor pole the cement-roll filled in and be sent to along the centre bore of drilling rod at the bottom of the hole of centre bore together;
4) after cement-roll is in place, head in cement-roll with rig by anchor pole, then slowly exit the drilling rod be socketed with drill bit, wait for 20 ~ 30 minutes, arch supporting plate and spherical nut are installed in the one end of stretching out country rock at anchor pole, and screw spherical nut.
2. in breaking roof, bore bolthole and anchor rod anchored method as claimed in claim 1, it is characterized in that: it is long that every root drilling rod and connecting rod are 1.0m; The internal diameter of drilling rod and connecting rod is 28mm.
3. in breaking roof, bore bolthole and anchor rod anchored method as claimed in claim 1, it is characterized in that: described anchor pole is high-strength screw-thread steel anchor pole or hollow grouting anchor.
CN201310207314.4A 2013-05-30 2013-05-30 Method for drilling anchor rod hole and anchoring anchor rod in broken roof Expired - Fee Related CN103277122B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310207314.4A CN103277122B (en) 2013-05-30 2013-05-30 Method for drilling anchor rod hole and anchoring anchor rod in broken roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310207314.4A CN103277122B (en) 2013-05-30 2013-05-30 Method for drilling anchor rod hole and anchoring anchor rod in broken roof

Publications (2)

Publication Number Publication Date
CN103277122A CN103277122A (en) 2013-09-04
CN103277122B true CN103277122B (en) 2015-04-15

Family

ID=49059726

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310207314.4A Expired - Fee Related CN103277122B (en) 2013-05-30 2013-05-30 Method for drilling anchor rod hole and anchoring anchor rod in broken roof

Country Status (1)

Country Link
CN (1) CN103277122B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107035394A (en) * 2017-05-25 2017-08-11 中国矿业大学 A kind of umbrella reed structure anchor pole anchor head assembly and its application method
CN107190743A (en) * 2017-07-26 2017-09-22 山东省城乡建设勘察设计研究院 A kind of composite rod automatic anchor pole and its construction method
CN108049900A (en) * 2017-12-07 2018-05-18 中国矿业大学 A kind of colliery bulky powder coal body armature boring construction method
CN107842384A (en) * 2017-12-18 2018-03-27 中国矿业大学 The synchronous anchor and brill anchor method of a kind of hollow screw anchor pole
CN111322097B (en) * 2020-01-16 2022-06-17 湖北三鑫金铜股份有限公司 Supporting method for coordinating deformation of surrounding rock of roadway
CN111677536A (en) * 2020-06-30 2020-09-18 陕西陕煤韩城矿业有限公司 Method for conveying explosive cartridge anchoring agent in soft coal seam
CN114086999A (en) * 2021-12-03 2022-02-25 武钢资源集团金山店矿业有限公司 Anchoring method of tube seam anchor rod
CN114810171B (en) * 2022-03-30 2023-03-10 西南交通大学 Anchor rod with expandable end

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1727633A (en) * 2005-06-22 2006-02-01 叶迎新 Drill pipe of the center emplacement type jumbolter and construction method
CN1888326A (en) * 2006-07-26 2007-01-03 中冶沈勘工程技术有限公司 Two-purpose boring bar and hole-protecting casing soil anchor bolt boring technology
CN101761350A (en) * 2010-02-08 2010-06-30 河南理工大学 Rapid drilling device of small-bore tunnel bottom plate drill
CN102943681A (en) * 2012-11-21 2013-02-27 天地科技股份有限公司 Method and device for supporting weak adhesion bond soft rock roadway

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6672806B2 (en) * 2000-11-22 2004-01-06 Forasol International Sa Device for drilling and anchoring and process for placing grout anchors

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1727633A (en) * 2005-06-22 2006-02-01 叶迎新 Drill pipe of the center emplacement type jumbolter and construction method
CN1888326A (en) * 2006-07-26 2007-01-03 中冶沈勘工程技术有限公司 Two-purpose boring bar and hole-protecting casing soil anchor bolt boring technology
CN101761350A (en) * 2010-02-08 2010-06-30 河南理工大学 Rapid drilling device of small-bore tunnel bottom plate drill
CN102943681A (en) * 2012-11-21 2013-02-27 天地科技股份有限公司 Method and device for supporting weak adhesion bond soft rock roadway

Also Published As

Publication number Publication date
CN103277122A (en) 2013-09-04

Similar Documents

Publication Publication Date Title
CN103277122B (en) Method for drilling anchor rod hole and anchoring anchor rod in broken roof
CN109236337B (en) Arrow anchor rod anchored by multi-section type clamping grouting and using method thereof
CN103032086B (en) Method for filling resin explosive cartridge in drilled hole of tunnel roof anchor rod
CN103643977A (en) Full-anchor partition pressure transferring grouting anchor rod and application method thereof
CN106368725B (en) A kind of reaming rotation type anchor pole and application method
CN107288671B (en) Construction method of soft crushed coal rock mass drilling, sealing and injecting integrated extendable anchor rod
CN203248178U (en) Downward-hole self-drilling grouting anchor rod
CN103758552A (en) Hole-expanding anchor rod and construction process thereof
CN109578033A (en) Coal mine roadway anchor and its implementation method
CN206592139U (en) A kind of external poured is segmented anchoring rod
CN206468364U (en) In one kind device is pre-installed to deep hole Anchor Agent
CN104533486A (en) Bolting-grouting reinforcement method for remained roadway along goaf by use of self-drilling hollow grouting anchor cable
CN205117379U (en) Let pressure stock from advancing formula large deformation
CN207261027U (en) A kind of Novel threaded anchor pole hangnail device
CN103643976A (en) Recyclable nylon split combination anchor rod and anchor rod installing and recycling method
CN206448830U (en) A kind of self-advancing type Hollow non-metallic screw thread reinforced resin anchor pole
CN204476444U (en) A kind of self-drilling hollow grouting cable anchor
CN114087001A (en) Section steel prestress grouting anchor cable for internally and externally combined reinforcement of fractured surrounding rock and use method
CN208347807U (en) Anchor pole is locked in tensioning
CN2905900Y (en) Self-propelled grouting anchoring-bolt
CN103206222B (en) Method for constructing reinforced surrounding rock inside precast-segment tunnels
CN103498690B (en) A kind of two anchor cable combined locking devices and methods therefor
CN103410542A (en) Device and method for improving hole forming efficiency and anchoring performance of anchor rod and anchor cable of roadway floor
CN207634096U (en) A kind of top plate deep hole Anchor Agent pre-installation device
CN102678145A (en) Efficient novel construction method for resin anchor rod

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201225

Address after: 224400 Room 201, 2nd floor, 556 Macao Road, Funing County, Yancheng City, Jiangsu Province

Patentee after: Funing longchuang Technology Service Co.,Ltd.

Address before: 411201 Taoyuan Road, Yuhu District, Hunan, Xiangtan

Patentee before: Hunan University of Science and Technology

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150415