CN103216102A - Construction method for tremie guiding pouring inside steel pipe column - Google Patents

Construction method for tremie guiding pouring inside steel pipe column Download PDF

Info

Publication number
CN103216102A
CN103216102A CN2013101566159A CN201310156615A CN103216102A CN 103216102 A CN103216102 A CN 103216102A CN 2013101566159 A CN2013101566159 A CN 2013101566159A CN 201310156615 A CN201310156615 A CN 201310156615A CN 103216102 A CN103216102 A CN 103216102A
Authority
CN
China
Prior art keywords
steel pipe
pipe column
concrete
conduit
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101566159A
Other languages
Chinese (zh)
Inventor
陈长正
庞永祥
王小培
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU HUAJIANG CONSTRUCTION GROUP CO Ltd
Original Assignee
JIANGSU HUAJIANG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU HUAJIANG CONSTRUCTION GROUP CO Ltd filed Critical JIANGSU HUAJIANG CONSTRUCTION GROUP CO Ltd
Priority to CN2013101566159A priority Critical patent/CN103216102A/en
Publication of CN103216102A publication Critical patent/CN103216102A/en
Pending legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention provides a construction method for tremie guiding pouring inside a steel pipe column, and relates to the technical field of construction of pouring concrete inside the steep pipe column of high-rise buildings. After the steel pipe column is erected, cement is poured from bottom to top layer by layer. The construction method for tremie guiding pouring inside the steel pipe column is characterized in that a plurality of inner clapboards are respectively fixed inside the steel pipe column, a through hole used for allowing a tube to insert is formed in the center of each clapboard, in the process of pouring, the tube is inserted in the steel pipe column, the outlet end of the tube is located between two adjacent inner clapboards, vibration is conducted after pouring of the steel pipe column between the two adjacent inner clapboards is finished, and then the tube is lifted upwards, and pouring of a steel pipe column between a former set of two adjacent inner clapboards is conducted. The construction method for tremie guiding pouring inside the steel pipe column has the advantages of improving pouring quality of cement inside the steel pipe column, increasing whole intensity of a steel structure, and saving funds. The phenomena that the measures that the steel pipe column is scraped or the cement inside the steel pipe column is reinforced are adopted due to the fact that incompact quality of the cement inside the steel pipe column and insufficient intensity is eliminated.

Description

Steel pipe column inner concrete conduit imports the job practices of building
Technical field
The present invention relates to the construction technology of highrise building, particularly the technical field of construction of concreting in steel pipe column.
Background technology
The method of concreting mainly contains in the steel pipe column in the construction work: pumping, jacking pouring method, a high position leave without vibration method, segmentation pouring method and artificial manual paragraph by paragraph pouring method successively etc.Because the steel pipe column of highrise building is welded to each other by many steel pipes and forms, in order to add intensity through steel pipe column, usually in steel pipe column, be provided with the horizontal dividing plate of multiple tracks, and concrete is from topmost building downwards, so, more than the total defective of existing each method be: the concrete after the pouring, particularly the concrete compactness in bottom is poor, this exists high potential safety hazard for highrise building.
Summary of the invention
The present invention seeks to propose a kind of steel pipe column inner concrete conduit that can effectively improve the cement concrete compactness after the pouring and import the job practices of building.
After the present invention earlier erects steel pipe column, after concreting layer by layer from bottom to top, characteristics are: be fixed with the multiple tracks internal partition in the described steel pipe column respectively, the center of every dividing plate is offered and is used for interting the through hole of conduit; When building, insert conduit in steel pipe column, the port of export that makes conduit vibrates after finishing the building of steel pipe column between two adjacent internal partitions between two adjacent internal partitions, upwards promote conduit then, again the steel pipe column between last one group of two adjacent internal partition is built.
The present invention has made full use of the former internal partition that is used to reinforce steel pipe column, make every layer internal partition carry out weight supporting to the concrete on it, can realize that building of steel pipe column inner concrete is fully closely knit, control concrete compaction below the steel pipe column internal partition to the full extent well, concrete below the internal partition is not produced drowns oneself, detect by the intensity of ultrasonic wave to the steel pipe inner concrete, concrete compactness reaches code requirement, and the phenomenon of drowning oneself does not appear in tubing string internal partition below.Improved the pouring quality of steel pipe column inner concrete, increased the steel work bulk strength, reduced, and taked steel pipe column to scrap or the steel pipe column inner concrete is taked the measure of reinforcement aspect, saved fund because of tubing string inner concrete quality leakiness, insufficient strength.
In addition, the present invention sets out pore on each internal partition, and described venthole is positioned at the outside of through hole.Be convenient to increase concrete exhaust, airing function, in time discharge because of building the air that brings, the layer of concrete of just building is compactness more.
For the concrete compaction of controlling well below the steel pipe column internal partition, surface concrete is not produced drown oneself, internal partition of the present invention is funnel-form, and described through hole is positioned at the foot on internal partition plane, and the angle of internal partition sidewall and center line is 45~60 °.
Also when the steel pipe column between two adjacent internal partitions of each group was built, concreting 10cm place below the lastblock internal partition of this group gave over to and builds next time in the present invention,
Purpose is to allow concrete self shrink earlier, so just can prevent better that concrete from occurring drowning oneself below internal partition and produce the gap.The end that of conduit was positioned at the following 20cm of the concrete horizontal face place that built last time when built next time.Concrete will by conduit downwards around overflow, avoided concrete in injection process, a large amount of air to be contained in steel pipe column, the density of building with raising.
In addition, drown oneself in order to prevent that concrete from producing, the time interval of adjacent twice concreting is 30 minutes.
When vibrating, vibrating head is inserted into 10~20cm place below the layer of concrete of building previously, the concrete of two-step pouring can be combined well.
Concreting in steel pipe column when the capital, and vibrate finish after, the concrete of 30cm height above in the steel pipe column is removed, treat to build again after 30 minutes and vibrate.Because when the steel pipe capital was arrived in concreting, cement paste was upwards general, the ratio of coarse aggregate reduces, and in order to guarantee the intensity of steel pipe column inner concrete, the concrete of upper part in the steel pipe capital is removed, and builds again.
Earlier directly in steel pipe column, build the high concrete of 1.9~2.3m, then conduit is inserted in the concrete degree of depth and reach and carry out first time intubate more than the 20cm and build.By progressively promoting, make conduit can not expose the concrete face, prevent to produce bubble.
The specific embodiment
Case engineering: Xi'an research and development centre, underground two-layer, 24 layers on the ground (highly being 93.25 meters on the ground), 40338 square metres of building areas.This project is a frame construction, designs 576 of steel box columns altogether, and underground two layers is (two segmented columns), and the post height is 10.34 meters; More than three layers and three layers (three segmented columns), the standard column height is 11.4 meters on the ground, all adopts pouring concrete in the square shaped pipe post.
The interior sectional dimension of square shaped pipe post is 650mm * 650mm, 550mm*550mm, and concrete placing adopts C35, C40, C45, C50 concrete in the square shaped pipe post, about total irrigation amount 750m3.Be welded with 6 road rectangle internal partitions respectively by rib in each square shaped pipe post of this project, internal partition is of a size of 650mm*650mm, and central through hole is Φ 300mm, four jiaos of air-vents that four Φ 25mm are set.Internal partition is funnel-form, and central through hole is positioned at the foot on internal partition plane, and the angle of internal partition sidewall and center line is 45~60 °.
Conduit can adopt Ф 150 welded steel pipes, and its external diameter is convenient to increase concrete exhaust, airing function less than the central through hole diameter of internal partition.
The commodity in use concrete adds a certain amount of micro-expanding agent in concrete, make concreting after micro-expanding agent reach closely knit with compensate for shrinkage; Suitable reduction cement consumption increases the admixture materials.Mix suitable water reducing agent; Increase the proportion of fines, improve aggregate grading (sand should use in coarse grain directly, the rubble of stone employing 5~25mm); Suitably increase the consumption of Admixture (pumping admixture, water reducing agent).Match ratio is joined definite by test room's examination, and provides the concrete mix list.
Each concreting 10cm place below dividing plate gives over to and builds next time, and just in time to inject tubing string inner concrete 20cm dark for conduit when built next time.
Key points for operation:
Steel pipe column is erect firm after, in steel pipe column, inject the high concrete of 1.9~2.3m earlier, again conduit is inserted that the degree of depth reaches more than the 20cm in the concrete, then concreting layer by layer from bottom to top.
When building, in steel pipe column, insert conduit, the port of export that makes conduit is between two adjacent internal partitions, after finishing the building of steel pipe column between two adjacent internal partitions, vibrate, upwards promote conduit then, but can not expose the concreting surface layer,, again the steel pipe column between last one group of two adjacent internal partition be built in order to avoid outside air enters in the concrete.
When the steel pipe column between two adjacent internal partitions of each group is built, concreting 10cm place below the lastblock internal partition of this group gives over to and builds next time, and the end that of conduit was positioned at the following 20cm of the concrete horizontal face place that built last time when built next time.
The time interval of adjacent twice concreting is 30 minutes.
When vibrating, vibrating head is inserted into 10~20cm place below the layer of concrete of building previously.
Concreting in steel pipe column when the capital, and vibrate finish after, the concrete of 30cm height above in the steel pipe column is removed, treat to build again after 30 minutes and vibrate.
The winter construction insulation adopts cotton felt to be bundled on the steel pipe column, and assurance steel pipe column inner concrete is not endured cold.
Summer, maintenance was bundled in above the steel pipe column with gunnysack, watered the water for cooling maintenance, and each watered water in two hours one time.
Notice in the time of maintenance that temperature difference between inside and outside concrete must not be greater than 25 degree.
Detect by the intensity of ultrasonic wave to the steel pipe inner concrete, concrete compactness reaches code requirement, and the phenomenon of drowning oneself does not appear in tubing string internal partition below, and the slit in the 30~45 of steel pipe column internal partition below narrows down in the allowed band simultaneously.This technology is on probation on this project, has obtained success.

Claims (8)

1. steel pipe column inner concrete conduit imports the job practices of building, earlier steel pipe column is erect, concreting layer by layer from bottom to top is characterized in that being fixed with respectively in the described steel pipe column multiple tracks internal partition then, and the center of every dividing plate is offered and is used for interting the through hole of conduit; When building, insert conduit in steel pipe column, the port of export that makes conduit vibrates after finishing the building of steel pipe column between two adjacent internal partitions between two adjacent internal partitions, upwards promote conduit then, again the steel pipe column between last one group of two adjacent internal partition is built.
2. import the job practices of building according to the described steel pipe column inner concrete of claim 1 conduit, it is characterized in that setting out pore on each internal partition, described venthole is positioned at the outside of through hole.
3. import the job practices of building according to the described steel pipe column inner concrete of claim 1 conduit, it is characterized in that internal partition is funnel-form, described through hole is positioned at the foot on internal partition plane, and the angle of internal partition sidewall and center line is 45~60 °.
4. import the job practices of building according to claim 1 or 2 or 3 described steel pipe column inner concrete conduits, it is characterized in that when the steel pipe column between two adjacent internal partitions of each group is built, concreting 10cm place below the lastblock internal partition of this group gives over to and builds next time, and the end that of conduit was positioned at the following 20cm of the concrete horizontal face place that built last time when built next time.
5. import the job practices of building according to claim 1 or 2 or 3 described steel pipe column inner concrete conduits, the time interval that it is characterized in that adjacent twice concreting is 30 minutes.
6. import the job practices of building according to claim 1 or 2 or 3 described steel pipe column inner concrete conduits, it is characterized in that when vibrating, vibrating head is inserted into 10~20cm place below the layer of concrete of building previously.
7. import the job practices of building according to claim 1 or 2 or 3 described steel pipe column inner concrete conduits, it is characterized in that concreting in steel pipe column is when the capital, and vibrate finish after, the concrete of 30cm height above in the steel pipe column is removed, treat to build again after 30 minutes and vibrate.
8. import the job practices of building according to claim 1 or 2 or 3 described steel pipe column inner concrete conduits, it is characterized in that earlier directly in steel pipe column, building the high concrete of 1.9~2.3m, then conduit is inserted in the concrete degree of depth and reach and carry out first time intubate more than the 20cm and build.
CN2013101566159A 2013-05-02 2013-05-02 Construction method for tremie guiding pouring inside steel pipe column Pending CN103216102A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101566159A CN103216102A (en) 2013-05-02 2013-05-02 Construction method for tremie guiding pouring inside steel pipe column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101566159A CN103216102A (en) 2013-05-02 2013-05-02 Construction method for tremie guiding pouring inside steel pipe column

Publications (1)

Publication Number Publication Date
CN103216102A true CN103216102A (en) 2013-07-24

Family

ID=48814222

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101566159A Pending CN103216102A (en) 2013-05-02 2013-05-02 Construction method for tremie guiding pouring inside steel pipe column

Country Status (1)

Country Link
CN (1) CN103216102A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105332511A (en) * 2015-11-16 2016-02-17 上海建工二建集团有限公司 Huge concrete filled steel tubular column core grouting pouring and tamping device and method
CN105756348A (en) * 2016-03-23 2016-07-13 中冶建工集团有限公司 Concrete pouring construction method in steel pipe column of core cylinder beam column
CN105804402A (en) * 2016-03-23 2016-07-27 中冶建工集团有限公司 Feeding pouring method for concrete in steel pipe column of core tube beam column
CN108049496A (en) * 2017-12-20 2018-05-18 佛山市万科置业有限公司 Complete cast-in-place exterior wall high residential building interts construction and puies forward efficacious prescriptions method entirely
CN108049495A (en) * 2017-12-20 2018-05-18 佛山市万科置业有限公司 Complete cast-in-place exterior wall high residential building escalator, staircase intert construction and put forward efficacious prescriptions method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201330470Y (en) * 2008-11-06 2009-10-21 广东省建筑工程集团有限公司 Inner gusset plate, square steel tube and square steel tube concrete column
JP2010209601A (en) * 2009-03-11 2010-09-24 Chiyoda Soiltech Inc Apparatus for constructing concrete pile, and method for constructing cast-in-place concrete pile using the same
CN101845889A (en) * 2009-12-24 2010-09-29 上海市第七建筑有限公司 Concrete casting and tamping method of steel tube concrete structure column
CN102535746A (en) * 2011-12-30 2012-07-04 宁波建工股份有限公司 Concrete-filled steel tube column and casting method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201330470Y (en) * 2008-11-06 2009-10-21 广东省建筑工程集团有限公司 Inner gusset plate, square steel tube and square steel tube concrete column
JP2010209601A (en) * 2009-03-11 2010-09-24 Chiyoda Soiltech Inc Apparatus for constructing concrete pile, and method for constructing cast-in-place concrete pile using the same
CN101845889A (en) * 2009-12-24 2010-09-29 上海市第七建筑有限公司 Concrete casting and tamping method of steel tube concrete structure column
CN102535746A (en) * 2011-12-30 2012-07-04 宁波建工股份有限公司 Concrete-filled steel tube column and casting method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
胡伯杭: "方钢管混凝土柱施工工艺的应用", 《山西建筑》, vol. 36, no. 33, 20 November 2010 (2010-11-20) *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105332511A (en) * 2015-11-16 2016-02-17 上海建工二建集团有限公司 Huge concrete filled steel tubular column core grouting pouring and tamping device and method
CN105756348A (en) * 2016-03-23 2016-07-13 中冶建工集团有限公司 Concrete pouring construction method in steel pipe column of core cylinder beam column
CN105804402A (en) * 2016-03-23 2016-07-27 中冶建工集团有限公司 Feeding pouring method for concrete in steel pipe column of core tube beam column
CN105756348B (en) * 2016-03-23 2018-05-15 中冶建工集团有限公司 A kind of Core Walls Structure beam column steel pipe column interior concrete pouring construction method
CN108049496A (en) * 2017-12-20 2018-05-18 佛山市万科置业有限公司 Complete cast-in-place exterior wall high residential building interts construction and puies forward efficacious prescriptions method entirely
CN108049495A (en) * 2017-12-20 2018-05-18 佛山市万科置业有限公司 Complete cast-in-place exterior wall high residential building escalator, staircase intert construction and put forward efficacious prescriptions method

Similar Documents

Publication Publication Date Title
CN103821364B (en) The construction method of reinforced concrete water pond
CN101906768B (en) Panel construction method of concrete faced rock-fill dam
CN103615110B (en) Random oblique netted nine-squares beam Hyperbolic Roof construction method
CN103321421B (en) The one-time formed construction method of a kind of concrete water pool wall
CN106437142A (en) Construction method and double-layer formwork structure for cast-in-situ slope roof
CN102392549B (en) Construction working method for seamless prestressed-concrete self-waterproof clean water reservoir
CN105040970A (en) High formwork system of comprehensive gymnasium and construction method thereof
CN101956458A (en) Construction method of overlong and superhigh single-side fair-faced concrete wall
CN102116061A (en) Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN103216102A (en) Construction method for tremie guiding pouring inside steel pipe column
CN103410269B (en) Prestressing without bondn cast-in-place reinforced concrete hollow slab constructing structure and construction method
CN105275209A (en) Special-shaped spatial curved surface water concrete construction method
CN104213717B (en) Multi-storey building integration transformation method of construction
CN102877486A (en) Integral cast-in-situ construction method for cable ducts
CN102587663A (en) Concrete construction process of steel tube columns of super-high-rise building
CN108265623A (en) A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct
CN107476567A (en) It is a kind of to control the pitched roof gradient and the construction method and track-type facilities of thickness
CN207363251U (en) A kind of track-type facilities for being used to control the pitched roof gradient and thickness
CN106351376A (en) Construction method of garage roof
CN104846745B (en) Urban high-pier support-free formwork turnover construction method
CN206245730U (en) A kind of cast-in-place pitched roof double template structure
CN105821895A (en) Raft board foundation steel reinforcement support frame water-proof treatment construction process
CN202689240U (en) Stone wall body
CN112012762A (en) Construction method of double-layer secondary lining multi-arch tunnel structure
CN107586068B (en) Upright column concrete and construction method of concrete upright column

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130724