CN103174429B - Underground cavity extra-large dome excavating construction method - Google Patents

Underground cavity extra-large dome excavating construction method Download PDF

Info

Publication number
CN103174429B
CN103174429B CN201310065562.XA CN201310065562A CN103174429B CN 103174429 B CN103174429 B CN 103174429B CN 201310065562 A CN201310065562 A CN 201310065562A CN 103174429 B CN103174429 B CN 103174429B
Authority
CN
China
Prior art keywords
dome
excavation
construction method
section
cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310065562.XA
Other languages
Chinese (zh)
Other versions
CN103174429A (en
Inventor
周厚贵
王博
李友华
孙昌忠
黄应军
黄家权
李英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
China Gezhouba Group Three Gorges Construction Engineering Co Ltd
Original Assignee
Hohai University HHU
China Gezhouba Group Three Gorges Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU, China Gezhouba Group Three Gorges Construction Engineering Co Ltd filed Critical Hohai University HHU
Priority to CN201310065562.XA priority Critical patent/CN103174429B/en
Publication of CN103174429A publication Critical patent/CN103174429A/en
Application granted granted Critical
Publication of CN103174429B publication Critical patent/CN103174429B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses an underground cavity extra-large dome excavating construction method. The underground cavity extra-large dome excavating construction method comprises the following steps: first, a dome cavity and a guiding cavity connected with the dome cavity are vertically layered; second, the dome cavity is symmetrically divided into a plurality of areas with the guiding cavity as an axis; third, an upper layer of guiding cavity is excavated and supported, each area is symmetrically excavated with the vertical axis of the dome cavity as an axis in a stagger mode and is gradually away from the vertical axis, and after a single area is excavated, systematic supporting is conducted on a top arch of the dome cavity according to design requirements; and fourth, a lower layer of guiding cavity is excavated and supported, each area is symmetrically excavated with the vertical axis of the dome cavity as an axis in a stagger mode and is gradually away from the vertical axis, and after a single area is excavated, systematic supporting is conducted on a top arch of the dome cavity according to design requirements; and due to the adoption of the steps mentioned above, excavating construction of the extra-large dome of an underground cavity is safely and high efficiently achieved. The simultaneous construction method of layering, area dividing and left-right diagonal staggered area ensures construction quality and construction safety, and meanwhile greatly improves work efficiency and reduces engineering construction cost.

Description

The especially big dome excavation construction method of underground chamber
Technical field
The present invention relates to underground cavern excavation construction field, particularly the especially big dome excavation construction method of a kind of underground chamber.
Background technology
In underground excavation engineering, be designed with dome-shaped, i.e. crown curved underground chamber spherical in shape, the surge shaft in such as power station.For middle-size and small-size class dome-shaped cavern, the usual span of arch (i.e. dome diameter) is less than 12m, the construction method at dome position mainly contains pilot tunnel method, cross excavating load, fan-shaped stick method, annular center pillar method etc., but for the dome position of especially big dome-shaped underground chamber, the such as dome of the span of arch more than 20 meters, according to these construction methods, there is working space narrow, each operation is disturbed greatly mutually, it is larger that shot hole explosive payload controls difficulty, the yielding instability of country rock, constructing operation is extremely inconvenient, the shortcomings such as Arch Excavation forming quality is wayward, be difficult to adopt large-scale excavation, support apparatus, therefore work efficiency is low, duration not easily ensures, construction cost is large.
" Chinese Water Conservancy Hydroelectric Project Construction " 2011. first phase 24-27 page describe " Huizhou Pump-storage Plant down stream surge tank dome excavation construction ", have employed the method for circumferentially boring lateral aperture and carry out excavation construction, obtain good excavation molding effect.Such as, but when adopting the method, operating space relative narrowness, is unfavorable for adopting Large Construction facility, bores quick-fried chassis etc., and when the span of arch is larger, such as reach 20m even 30m time, the height of cavern's dome is higher, construction inconvenience, inefficiency.
" Shanxi architecture " January the 3rd in 2008, phase 152-153 page described " blasting construction on silo dome of left bank mixing system of Xiaowan power station ", have employed with the constructure scheme of gallery symmetrical branch piecemeal, Problems existing is, when the diameter of cavern's dome becomes large, such as, when reaching 30 meters, now the height of cavern's dome is higher, and construction is difficulty comparatively, and construction risk increases.
Summary of the invention
Technical problem to be solved by this invention is to provide the especially big dome excavation construction method of a kind of underground chamber, multiple work plane can be realized construct simultaneously, and working space is larger, be suitable for adopting large-scale excavation, support apparatus to construct, reduce difficulty of construction and security risk, and each operation is disturbed mutually little, Arch Excavation forming quality is easy to control, work efficiency is higher, and construction cost is lower.
For solving the problems of the technologies described above, the technical solution adopted in the present invention is: the especially big dome excavation construction method of a kind of underground chamber, comprises the following steps:
One, by dome cavern and the pilot tunnel that is attached thereto by upper lower leaf;
Two, by dome cavern with pilot tunnel for be divided into multiple section axisymmetrically;
Three, excavate the pilot tunnel on upper strata, after pilot drive, by designing requirement, system supporting is carried out to its crown position; With the vertical axis of dome cavern for axisymmetry, and with pilot tunnel axis for each section of the staggered excavation of axis of symmetry symmetry, and progressively away from this vertical axis, after the excavation of single section, by designing requirement, system supporting is carried out to dome crown, in digging process, the location poor to local geological conditions, can take temporary lining measure at random;
Four, excavate the pilot tunnel of lower floor, after pilot drive, by designing requirement, system supporting is carried out to its side wall; With the vertical axis of dome cavern for axisymmetry, and with pilot tunnel axis for each section of the staggered excavation of axis of symmetry symmetry, and progressively away from this vertical axis, after the excavation of each section, by designing requirement, system supporting is carried out to dome crown, in digging process, the location poor to local geological conditions, can take temporary lining measure at random;
The especially big dome excavation construction of underground chamber is realized by above-mentioned steps is safe and efficient.
In step 2, section, the upper strata quantity of division is more than the quantity of lower floor section.
In step 4, be also provided with the topping of annular outside each section and between dome design profile line, topping is constructed after inner section has been excavated again.
In step 3 and four, the work plane of simultaneously constructing must not more than two.
In step 3 and four, adopt the independence explosion of monolithic district during explosion, forbid multiple scope of operation to implement explosion simultaneously.
In step 3, upper strata excavation adopts and bores the boring of quick-fried chassis cooperation artificial hand air drill, and boring aperture is φ 42 ± 3mm, slotting is taked to excavate, main explosion hole drill lateral aperture, the perimeter hole in contiguous dome crown outline line region, as far as possible along the boring of outline line direction hand air drill, adopts smooth blasting method.
In described smooth blasting, breaking hole pitch-row is with 1 ± 0.1m, and perimeter hole pitch-row is with 0.5 ± 0.05m, and excavation cyclic advance controls at 1.5 ± 0.15m.
In step 4, lower floor's excavation adopts down-the-hole drill boring, coordinates heading blast method.
In step 4, the lower floor's pilot tunnel in dome cavern is also provided with one section of reserved slope, and the exit end wherein near pilot tunnel is higher, and described reserved ramp slope is 12%.
In step 4, the described last excavation construction in reserved slope, or together with the well bore part of bottom, dome cavern excavation construction.
The especially big dome excavation construction method of a kind of underground chamber provided by the invention, compared with prior art has following beneficial effect:
1, cavern surrounding rocks is carried out layering, subregion according to the principle of " breaking the whole up into parts, partial excavation ", thus reduce excavation span, reduce difficulty of construction and security risk.
2, same layer rock mass follows the principle of " left and right diagonally opposing corner wrong cross section simultaneously construct ", and according to the sequencing excavation construction determined, two work planes can operation simultaneously, and each operation is disturbed little mutually, is conducive to improving work efficiency, reducing Construction Cost.
3, be close to the perimeter hole in dome outline line region, adopt along outline line hoop horizontal bore mode, be both conducive to convenient working human users, be also easy to the forming quality ensureing that dome outline line once excavates.
4, after dome lower floor pilot drive completes, because the supporting of upper strata dome completes, during the rock excavation of its both sides, working space is larger, is easy to adopt large-scale excavation supporting equipment, and in conjunction with the construction of heading blast method, is conducive to increasing work efficiency further.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described:
Fig. 1 is the vertical section structure schematic diagram of dome cavern in the present invention.
Fig. 2 is the A-A cross-sectional schematic of Fig. 1, and what show in figure is point section schematic diagram on upper strata.
Fig. 3 is the present invention's sequence of excavation of section and tunneling direction schematic diagram at the middle and upper levels.
Fig. 4 is the schematic diagram of the present invention's pilot drive at the middle and upper levels.
Fig. 5 is the B-B cross-sectional schematic of Fig. 4.
Fig. 6 is the C-C cross-sectional schematic of Fig. 1, and what show in figure is point section schematic diagram of lower floor.
Fig. 7 is the vertical section schematic diagram of lower floor section excavation in the present invention.
Fig. 8 is lower floor section sequence of excavation and tunneling direction schematic diagram in the present invention.
In figure: stratification line 1, pilot tunnel 2, the second layer 3, first floor 4, reserved slope 5, topping 6, system supporting 7, dome cavern 8.
Detailed description of the invention
As in Fig. 1 ~ 8, the especially big dome excavation construction method of a kind of underground chamber, comprises the following steps:
One, by dome cavern 8 and the pilot tunnel 2 that is attached thereto by upper lower leaf; Specifically as shown in fig. 1, in this example, dome cavern 8 and pilot tunnel 2 are divided into two-layer.As shown in Figure 1 with stratification line 1 be boundary first floor 4 and the second layer 3.Sequence of construction in design first excavates first floor 4, then excavate the second layer 3, thus construction height is controlled in the scope of constructability.In this example, upper and lower two layer heights of pilot tunnel 2 are roughly equal.
Two, by dome cavern 8 with pilot tunnel 2 for be divided into multiple section axisymmetrically; Concrete as shown in Fig. 2,6, in Fig. 2, be divided into 9 sections, in Fig. 6, be divided into 6 sections, such as, I-1 ~ I-5' section in Fig. 2, II in Fig. 6-1 ~ II-4' section.As can be seen from the figure, the scheme of optimization, as in step 2, section, the upper strata quantity of division is more than the quantity of lower floor section.This is because when lower floor section and the second layer 3 are constructed, section, upper strata and first floor 4 have excavated and have completed the system supporting 7 of crown, security risk is relatively little, working space is larger, therefore larger section can be divided into, be convenient to adopt down-the-hole drill boring, coordinate heading blast method, with further accelerating construction progress.
Three, the pilot tunnel 2 on upper strata is excavated, the width of pilot tunnel 2 and highly general 1/4 ~ 1/3 control according to the span of value.First excavate upper strata pilot tunnel 2, dome is divided into left and right two parts by pilot tunnel centrally line symmetrically; In pilot drive construction, after face enters dome region, its Arch Excavation line gradually changes along dome design profile line is curved, specifically as shown in Figure 4; After pilot drive, to crown and side wall position, by designing requirement implementation system supporting 7, except the side wall in dome region herein.In digging process, the location poor to local geological conditions, can take temporary lining measure at random, and its working procedure and method are implemented with reference to existing conventional method.
With the vertical axis of dome cavern 8 be shaft staggered symmetry excavation each section, and progressively away from this vertical axis, be specially sequence of excavation as shown in Figure 3 and tunneling direction, construct I-2 and I-2 successively simultaneously ', I-3 and I-3 ', I-4 and I-4 ' and I-5 and I-5 '.Namely staggered symmetrical with vertical axis or be called and similarly construct with rotational symmetric two sections of vertical axis simultaneously, wrong cross interlocks construction method thus, and guarantee that two sections of simultaneously constructing do not interfere with each other, especially construction equipment and transport do not interfere with each other.Adopt progressively away from the form of construction work of the form of construction work cooperation stage excavation of vertical axis, further ensure that excavation construction safety, and efficiency of construction is high, is especially convenient to the scheduling of engineering truck.
The work plane of simultaneously constructing must not more than two, to excavate when preorder section and after system supporting is carried out by designing requirement to dome crown, in digging process, the location poor to local geological conditions, temporary lining measure can be taked at random, to construct successively follow-up section, until dome first floor 4 all construction is complete.
In step 3, upper strata excavation adopts and bores the boring of quick-fried chassis cooperation artificial hand air drill, and boring aperture is φ 42 ± 3mm, slotting is taked to excavate, main explosion hole drill lateral aperture, the perimeter hole in contiguous dome crown outline line region, as far as possible along the boring of outline line direction hand air drill, adopts smooth blasting method.
In described smooth blasting, preferred breaking hole pitch-row is advisable with 1 ± 0.1m, continuously dress diameter phi 32mm emulsification powder stick; Perimeter hole pitch-row is advisable with 0.5 ± 0.05m, and select φ 25mm emulsification powder stick, spaced loading, line density is preferably advisable with 110 ~ 130g/m, or actual blasting parameter can be determined further according to on-the-spot explosion bulge test.As in Fig. 3, arrow points is preferred tunneling direction, and excavation cyclic advance controls at 1.5 ± 0.15m.
Four, excavate the pilot tunnel 2 of lower floor, and extend in dome, after the pilot tunnel 2 of lower floor has excavated, by designing requirement, supporting is carried out to the side wall of pilot tunnel 2, except the side wall in dome region herein.
With the vertical axis of dome cavern 8 be shaft staggered symmetry excavation each section, and progressively away from this vertical axis, be specially the sequence of excavation shown in Fig. 8 and tunneling direction, construct II-2 and II-2 successively ', II-3 and II-3 ' simultaneously, namely construct with the vertical axis symmetrical Liang Ge district that interlocks, the work plane of simultaneously constructing must not more than two simultaneously.
Each section adopts down-the-hole drill boring, and boring aperture is φ 90 ± 9mm, and pitch of holes is advisable with 2 ± 0.2m; Adopt heading blast method, the preferred diameter phi 70mm of dress continuously emulsification powder stick, or actual blasting parameter can be determined according to on-the-spot explosion bulge test.
In this step; the scheme optimized, is also provided with II-4 section in reserved topping 6(and Fig. 6 of annular outside each section and between dome design profile line), reserved topping 6 is constructed after inner section excavation is complete again; scheme thus, is beneficial to the shaping of crown curved-surface structure.In step 4, lower floor's pilot tunnel 2 in dome cavern 8 is also provided with one section of reserved slope 5, namely as shown in Figure 7 II-5, exit end wherein near pilot tunnel 2 is higher, described reserved slope 5 gradient is 12%, the setting on reserved slope 5, has both been conducive to plant equipment and has passed through, also reduce the projected depth of pilot tunnel, save the open excavation amount of pilot tunnel.II-4, II-5 district implements with reference to the quick-fried method of brill described in step 3 and smooth blasting method, and wherein said reserved slope 5 i.e. II-5 last excavation construction in section, or together with the well bore part of bottom, dome cavern 8 excavation construction.
After reserved topping 6 excavates, carry out system supporting to dome crown by designing requirement, in digging process, the location poor to local geological conditions, can take temporary lining measure at random.
The especially big dome excavation construction of underground chamber is realized by above-mentioned steps is safe and efficient.
Especially should be noted that, in step 3 and four, the independence explosion of monolithic district should be adopted during explosion, forbid multiple scope of operation to implement explosion simultaneously, further, each bursting work face is also take pilot tunnel as the operation of axis of symmetry individual interleaving, and to guarantee construction safety further, such as, preferred blasting sequence shown in Fig. 5 is (1) → (2) ... (18).

Claims (10)

1. the especially big dome excavation construction method of underground chamber, is characterized in that comprising the following steps:
One, by dome cavern (8) and the pilot tunnel (2) that is attached thereto by upper lower leaf;
Two, by dome cavern (8) with pilot tunnel (2) for be divided into multiple section axisymmetrically;
Three, excavate the pilot tunnel (2) on upper strata, after pilot tunnel (2) excavation, by designing requirement, system supporting is carried out to its crown position; With the vertical axis of dome cavern (8) for axisymmetry, and be each section of the staggered excavation of axis of symmetry symmetry with pilot tunnel (2) axis, and progressively away from this vertical axis, after the excavation of single section, by designing requirement, system supporting is carried out to dome crown, in digging process, the location poor to local geological conditions, can take temporary lining measure at random;
Four, excavate the pilot tunnel (2) of lower floor, after pilot tunnel (2) excavation, by designing requirement, system supporting is carried out to its side wall; With the vertical axis of dome cavern (8) for axisymmetry, and be each section of the staggered excavation of axis of symmetry symmetry with pilot tunnel (2) axis, and progressively away from this vertical axis, after the excavation of each section, by designing requirement, system supporting is carried out to dome crown, in digging process, the location poor to local geological conditions, can take temporary lining measure at random;
The especially big dome excavation construction of underground chamber is realized by above-mentioned steps is safe and efficient.
2. the especially big dome excavation construction method of a kind of underground chamber according to claim 1, is characterized in that: in step 2, and section, the upper strata quantity of division is more than the quantity of lower floor section.
3. the especially big dome excavation construction method of a kind of underground chamber according to claim 1; it is characterized in that: in step 4; also be provided with the reserved topping (6) of annular outside each section and between dome design profile line, reserved topping (6) is constructed after inner section has been excavated again.
4. the especially big dome excavation construction method of a kind of underground chamber according to claim 1, is characterized in that: in step 3 and four, and the work plane of simultaneously constructing must not more than two.
5. the especially big dome excavation construction method of a kind of underground chamber according to claim 1, is characterized in that: in step 3 and four, adopts the independence explosion of monolithic district, forbid multiple scope of operation to implement explosion simultaneously during explosion.
6. the especially big dome excavation construction method of a kind of underground chamber according to claim 1, it is characterized in that: in step 3, upper strata excavation adopts and bores the boring of quick-fried chassis cooperation artificial hand air drill, boring aperture is φ 42 ± 3mm, slotting is taked to excavate, main explosion hole drill lateral aperture, the perimeter hole in contiguous dome outline line region, as far as possible along the boring of outline line direction hand air drill, adopts smooth blasting method.
7. the especially big dome excavation construction method of a kind of underground chamber according to claim 6, is characterized in that: in described smooth blasting, and breaking hole pitch-row is with 1 ± 0.1m, and perimeter hole pitch-row is with 0.5 ± 0.05m, and excavation cyclic advance controls at 1.5 ± 0.15m.
8. the especially big dome excavation construction method of a kind of underground chamber according to claim 1, is characterized in that: in step 4, and lower floor's excavation adopts down-the-hole drill boring, coordinates heading blast method.
9. the especially big dome excavation construction method of a kind of underground chamber according to claim 1, it is characterized in that: in step 4, lower floor's pilot tunnel (2) in dome cavern (8) is also provided with one section of reserved slope (5), exit end wherein near pilot tunnel (2) is higher, and described reserved slope (5) gradient is 12%.
10. the especially big dome excavation construction method of a kind of underground chamber according to claim 9, is characterized in that: in step 4, the last excavation construction in described reserved slope (5), or together with the well bore part of dome cavern (8) bottom excavation construction.
CN201310065562.XA 2013-03-01 2013-03-01 Underground cavity extra-large dome excavating construction method Active CN103174429B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310065562.XA CN103174429B (en) 2013-03-01 2013-03-01 Underground cavity extra-large dome excavating construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310065562.XA CN103174429B (en) 2013-03-01 2013-03-01 Underground cavity extra-large dome excavating construction method

Publications (2)

Publication Number Publication Date
CN103174429A CN103174429A (en) 2013-06-26
CN103174429B true CN103174429B (en) 2015-05-20

Family

ID=48634562

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310065562.XA Active CN103174429B (en) 2013-03-01 2013-03-01 Underground cavity extra-large dome excavating construction method

Country Status (1)

Country Link
CN (1) CN103174429B (en)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103953368B (en) * 2014-05-14 2015-11-11 山东黄金矿业(莱州)有限公司三山岛金矿 Three layers of associating tunneling construction method of especially big elevator chamber
CN104061007B (en) * 2014-06-13 2016-06-15 长江勘测规划设计研究有限责任公司 Super-span dome reserved center, a kind of nuclear reactor cavern, underground rock pillar construction technology
CN104806252B (en) * 2015-04-28 2017-03-01 中铁工程设计咨询集团有限公司 Underground dome excavation construction arrangement and excavation method
CN105201532B (en) * 2015-09-11 2017-09-22 中铁九局集团第二工程有限公司 The Ring Cutting construction method of underground Long span spherical crown shape dome under weak surrounding rock
CN105821817A (en) * 2016-03-24 2016-08-03 中国电建集团华东勘测设计研究院有限公司 Method for excavating semicircular dome of giant cylindrical surge chamber
CN107060775B (en) * 2017-05-11 2023-09-12 中国电建集团华东勘测设计研究院有限公司 Double-layer simultaneous and homodromous excavation deep-buried tunnel rock burst releasing structure and application thereof
CN109488309A (en) * 2018-10-22 2019-03-19 中国水利水电第七工程局有限公司 High-ground stress, basalt underground power house cavern con struction method
CN110685698B (en) * 2019-10-29 2021-04-27 中铁(贵州)市政工程有限公司 Climbing reverse construction method for newly building large-section tunnel in existing cavern side direction
CN111550249B (en) * 2020-05-14 2021-10-22 中国水利水电第五工程局有限公司 Method for excavating hyperbolic inverted suspension dome in vertical shaft
CN112145185A (en) * 2020-09-23 2020-12-29 中铁四局集团有限公司 Hyperboloid cave depot dome excavation method
CN112065470B (en) * 2020-09-23 2022-03-15 中铁四局集团有限公司 Cave depot tank body excavation method
CN112127921B (en) * 2020-09-28 2022-05-17 中电建十一局工程有限公司 Construction method of buried grit chamber
CN112267887A (en) * 2020-10-20 2021-01-26 黄河勘测规划设计研究院有限公司 Excavation construction method for extra-large section tunnel with city gate hole
CN112412502A (en) * 2020-12-16 2021-02-26 中铁四局集团有限公司 Excavation method for one-step blasting forming of cave depot tank body
CN113047835B (en) * 2021-02-24 2022-04-15 中南大学 Deep well thick and large ore body mining method integrating emptying, caving and filling
CN113027469B (en) * 2021-04-13 2023-08-01 中国水利水电第六工程局有限公司 Construction method for multilayer underground space excavation supporting
CN113250696B (en) * 2021-05-24 2023-05-12 中国水利水电第六工程局有限公司 Method for arranging blasting holes in large-diameter vertical shaft excavation blasting
CN114109449B (en) * 2021-11-22 2023-08-08 中国电建集团成都勘测设计研究院有限公司 Large-span underground cavern dome supporting structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704939A (en) * 2012-06-26 2012-10-03 中国建筑第五工程局有限公司 Combined steel temporary supporting excavation method for tunnel with extra-large section

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09125867A (en) * 1995-11-02 1997-05-13 Kenki Eng:Kk Excavation method of tunnel
KR20020024912A (en) * 2000-09-27 2002-04-03 고순방 Method of construct a tunnel

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704939A (en) * 2012-06-26 2012-10-03 中国建筑第五工程局有限公司 Combined steel temporary supporting excavation method for tunnel with extra-large section

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
小湾电站左岸拌合***料仓竖井穹顶***施工;向科铭等;《山西建筑》;20080120;第34卷(第3期);第152-153页 *
糯扎渡水电站尾水调压室穹顶开挖支护施工技术;邓拥军等;《云南水力发电》;20121015;第28卷(第5期);第66-69页 *
长河坝电站进风洞空调机房上挑式穹顶开挖法施工;杨福蓉等;《四川水力发电》;20101015;第29卷(第5期);第144-147页 *

Also Published As

Publication number Publication date
CN103174429A (en) 2013-06-26

Similar Documents

Publication Publication Date Title
CN103174429B (en) Underground cavity extra-large dome excavating construction method
CN100582386C (en) Construction method of pervious rib type arch beam tunnel
CN103993892B (en) A kind of supporting method for weak broken uneven strata constructing tunnel
CN102134998B (en) Construction method for wind-blown sand tunnel
CN103277106A (en) Highway tunnel three-step five-procedure excavation construction method
CN102979531B (en) Reinforce construction method and the structure of large-scale rock slope deep weak structural plane
CN103256053B (en) Excavation and construction method of underground cavity ball coronary dome
CN110685698B (en) Climbing reverse construction method for newly building large-section tunnel in existing cavern side direction
CN101368812B (en) Nuclear island negative excavation ring corridor presplit blasting method
CN102758642A (en) Long-span tunnel overlapping carrying arch structure for upper-soft and lower-hard stratum and construction method thereof
CN103726858A (en) Underground large-scale cave depot project sphere-cylinder combination excavation method
CN105821817A (en) Method for excavating semicircular dome of giant cylindrical surge chamber
CN102678126A (en) Method for excavating mountain tunnels in weak surrounding rock-fractured zones or shallow covered slope sections
CN107965341A (en) A kind of large-section underground pipe canopy pipe network concrete support method
CN110924974A (en) Construction method of branch tunnel
CN110924952B (en) Construction method for three-step seven-step normal medium rock pillar method conversion of super-large section tunnel
CN106194223A (en) The excavation method of large-scale down stream surge-chamber dome under a kind of complex geological condition
CN104863591A (en) Method for controlling caving and earth surface filling treatment in goaf
CN102692164A (en) Stress unloading, water injecting and drilling and blasting method for longitudinal structure surface structural strong rockburst regions
CN102261249A (en) Creasing-type sill-pillar-free stage caving stopping method based on steel structured artificial top
CN109707388A (en) The method of surface collapse when preventing shield launching from wearing existing shield tunnel down
CN109184704A (en) A kind of small-clear-distance tunnel excavation and middle folder rock reinforcement technique
CN104612725B (en) A kind of underground cavern middle level changes the outfit construction method
CN116658178B (en) Ultra-small clear distance tunnel subsection differential blasting vibration reduction and isolation construction method
CN109594995B (en) Weak surrounding rock tunnel perturbation motive machinery subsection tunneling construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: CHINA GEZHOUBA GROUP THREE GORGES CONSTRUCTION ENG

Free format text: FORMER OWNER: CHINA GEZHOUBA GROUP CO., LTD.;SANXIA UNIVERSITY

Effective date: 20140618

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20140618

Address after: Nanjing City, Jiangsu province 210098 Xikang Road No. 1

Applicant after: HOHAI University

Applicant after: CHINA GEZHOUBA GROUP THREE GORGES CONSTRUCTION ENGINEERING Co.,Ltd.

Address before: Nanjing City, Jiangsu province 210098 Xikang Road No. 1

Applicant before: HOHAI University

Applicant before: CHINA GEZHOUBA GROUP Co.,Ltd.

C14 Grant of patent or utility model
GR01 Patent grant