CN103141252A CN2013100689166A CN201310068916A CN103141252A CN 103141252 A CN103141252 A CN 103141252A CN 2013100689166 A CN2013100689166 A CN 2013100689166A CN 201310068916 A CN201310068916 A CN 201310068916A CN 103141252 A CN103141252 A CN 103141252A
Authority
CN
China
Prior art keywords
slope
water
virescence
clay
grass
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100689166A
Other languages
Chinese (zh)
Inventor
毛若卿
张海林
张艺林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SANYA NEWDAXING LANDSCAPE CO Ltd
Original Assignee
SANYA NEWDAXING LANDSCAPE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SANYA NEWDAXING LANDSCAPE CO Ltd filed Critical SANYA NEWDAXING LANDSCAPE CO Ltd
Priority to CN2013100689166A priority Critical patent/CN103141252A/en
Publication of CN103141252A publication Critical patent/CN103141252A/en
Pending legal-status Critical Current

Links

Landscapes

  • Cultivation Of Plants (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Revetment (AREA)

Abstract

The invention relates to a material for slope fixing and virescence and application thereof. The slope fixing and virescence material comprises a skeleton material, a pouring material and a virescence material, wherein the skeleton material is paved at the engineering part to be constructed, the pouring material is used for pouring after condensation, and maintenance is performed to form the slope fixing material; and the virescence material is paved on the surface of the slope fixing material and watering maintenance is performed until the plant root system penetrates the slope fixing material. The slope protecting and fixing materials with certain mechanical strength are combined with the phase with a network structure through scientific and reasonable constitution and proportioning, so that the side slope can be maintained, the plant root system can grow and develop in the slope fixing material, virescence is realized, and ecological restoration is promoted. The slope fixing and virescence material has the characteristics of good slope fixing and protecting effects, and can be widely applied to slope fixing and virescence of water edge, a road and a railway roadbed as well as ecological restoration of bare rock on two sides of the road and the railway and abandoned mines.

Description

A kind of material and application for the Gu Po greening
Technical field
The invention belongs to the Materials Science and Engineering field, be specifically related to a kind of material and application for the Gu Po greening.
Background technology
Bank protection refers to as preventing that side slope from being washed away, and the various general designations of paving and planting of doing on domatic comprise dyke strengthening flood control, grid bank protection, massif ecological recovery etc.
At first, dyke strengthening flood control is China's important process in every year always, and along with the development of national economy and the people raising to environmental requirement, the Ecological Construction of dykes and dams becomes people's common recognition day by day.At present the Gu Po of water bank has following several mode, and 1, stone is built by laying bricks or stones or the casting concrete plate, this way does not have greening function, and the globality that stone is built by laying bricks or stones is very poor; 2, use concrete net lattice beam Gu Po, the greening of banketing in grid, its afforestation effect is limited, and the ability of opposing flood is inadequate; 3, normal concrete Gu Po, reserving hole in concrete, greening in the cavity, diameter and the ratio in cavity are excessive, affect solid slope effect, diameter and the too small afforestation effect that affects of ratio in cavity.Highway, railway exceed the larger roadbed bank protection of ground level, basically use above-mentioned several mode, Gu Po and two effects of greening are difficult to get both.
Next is the bank protection that adopts for the massif that highway, railway bank are opened up when building the road, at present mainly use stone or normal concrete to carry out the grid bank protection in the part of soft clay, but revegetation is relatively poor, the rock part is substantially exposed, easily cause the natural calamities such as landslide, realize its greening and recover ecological significant.
The massif ecological recovery of various abandoned mines again.ecotope is the basis of human social economy's sustainable development, good ecology is one of necessary condition of human survival and life, mining makes the massif surface exposure, had a strong impact on ecotope, cause the ecosystem to suffer in various degree destruction, seriously restricted the sustainable development of human social economy, even jeopardize mankind itself's safety, therefore, ecological recovery has become the basic premise of mining, exposed massif after mining mainly adopts the mode of artificial planting trees to recover vegetation at present, but the time is long, and easily cause water and soil loss because of rain drop erosion.
Summary of the invention
The purpose of this invention is to provide a kind of material and application for the Gu Po greening, by scientific and reasonable composition and proportioning, to have the bank protection of certain mechanical strength, solid slope material combines with the phase with network structure, both can carry out maintenance to side slope, the root system of plant is grown in the material of solid slope, grow, realize that greening promotes its ecological recovery, has the characteristics of good integrity.
The technical solution adopted in the present invention:
A kind of material for the Gu Po greening, comprise framework material, pouring material and green material application, described framework material is formed by aggregate, Binder Materials, additive and water mixing, and wherein the parts by weight of each component are by weight: aggregate 800~1700, Binder Materials 160~210, additive 0.010~0.080, water 72~100; Described aggregate refers to build stone, haydite, slag or concrete disintegrating screening particle; Described Binder Materials refers to the Binder Materials of cement or alkali-slag system; Described additive refers to a class high molecular weight water soluble polymer, Binder Materials-water slurry body is under the prerequisite that this base polymer exists, when its water-cement ratio (weight ratio of water and Binder Materials) changes in a big way, the rheological behavior kept stable of slurry, the Typical Representative of this base polymer has: methylcellulose, cellulose ether, xanthans.Described pouring material is that its water-solid ratio (weight ratio of water and clay, fertilizer sum) is between 100:30~40 with the slurry of clay, nutritious fertilizer and water preparation.Described green material application is to be formed by clay, nutritious fertilizer and grass-seed mixing, and its weight ratio is: clay: nutritious fertilizer: grass-seed=100:0.5~30:0.5~1.5.
The particle diameter of described aggregate between 20~30mm, simple grain level grating.
Described cement refers to portland cement, Portland cement, pulverized fuel ash cement, pozzolan cement, slag cements or complex cement.
Described nutritious fertilizer refers to the conventional nutritious fertilizer that uses of agricultural or gardens.
Described grass-seed is the various grass-seeds that Landscape Industry uses.
The present invention also provides the application of a kind of above-mentioned solid slope green material application, and its concrete steps are as follows:
1, by proportioning, aggregate, Binder Materials, additive and water mixing are obtained framework material, then be layed in the engineering position (as side slope) that needs construction, thickness obtains having the skeleton of linked hole network structure at 10~15cm after condensing, its porosity is between 25~30%.
2, press proportioning with clay, nutritious fertilizer and water mixing, prepare the pulpous state pouring material, then be filled in the skeleton that condenses, have the linked hole network structure, sprinkle water maintenance after 14 days, more than its overall mechanical strength reaches 4MPa, form a relative closely knit solid slope material that is formed by hard skeleton structure and the soft network system.
3, by proportioning, clay, nutritious fertilizer and grass-seed mixing are obtained green material application, then be routed to the surface of the solid slope material that framework material after condensing and pouring material form, thickness is 1~3cm, and the maintenance of sprinkling water, until root system of plant penetrates solid slope material.
For the greening of bare rock, can lay in advance at rock surface the argillic horizon of 10-15cm, construct by above-mentioned engineering method again after compacting.For the gradient more greatly, highly higher rock, can put muscle on rock, tie up when laying solid slope green material application and put horizontal bar.
For the Gu Pos greening of the gradient greater than 60 degree, can when skeleton structure is in the milk, grass-seed be sneaked into slurry, the watering maintenance.
A kind of material and application for the Gu Po greening provided by the invention, its advantage is: 1, material monolithic large tracts of land laying, whole sclerosis, Gu the slope globality is strong, due to the protection of networking sclerotic bone shelf structure, Gu the anti-flood erosion of slope material, Gu Po, protection effect are good; 2, owing to having the network system that is fit to plant growth in material, Gu the slope material surface can be obtained good afforestation effect, existing solid slope mode can not be compared; 3, for tall and big, precipitous rock greening, by bar planting in rock, in the solid slope material that the colligation horizontal bar solidifies, security performance is high; 4, have wide range of applications, can be widely used in the Gu Po greening of water (river, lake, ocean) bank, highway and railway bed, the ecological recovery of highway and railway both sides bare rock, abandoned mine.
Embodiment
Below in conjunction with embodiment, the specific embodiment of the present invention is described in further detail.Following examples are used for explanation the present invention, but are not used for limiting the scope of the invention.The experimental technique of unreceipted actual conditions in the following example, usually according to normal condition, or the condition of advising according to manufacturer.
Embodiment one, riverbank Gu Po greening
1, raw material
Aggregate: lime stone building stone, 25mm simple grain level grating;
Binder Materials: P.O42.4 class g cement;
Water: running water;
Additive: cellulose ether;
Clay: construction site discarded slurry;
Fertilizer: gardens company uses Nutrition Soil;
Grass-seed: paspalum notatum grass-seed.
2, match ratio
Framework material match ratio (weight ratio): stone: cement: water: additive=1500:180:82:2.5;
Grouting material match ratio (weight ratio): water: clay: Nutrition Soil=100:25:10;
Green material application match ratio (weight ratio): clay: Nutrition Soil: grass-seed=100:30: 1;
3, framework material preparation
Agitator uses 3 cubic metres of double-horizontal axle concrete-mixers, feeds intake 2 cubic metres at every turn, mixing time 150 seconds, and dump truck is adopted in transportation.
4, lay
Material is transported to the building site by dump truck, and truck slowly is discharged into material in a pin-connected panel chute, and human assistance promotes material to laying the position, laying depth 12cm, 17 meters of riverbank lengths of grade are laid 5 meters of width at every turn, both sides arrange masterplate, lay complete rear artificial levelling compacting.
5, grouting
Material was laid after 24 hours, mud and Nutrition Soil are entered in container with paddle together, after adjustment moisture stirs, the skeleton that laying is condensed with slush pump is in the milk, repeatedly for several times, until fill, form a relative closely knit solid slope material that is formed by hard skeleton structure and the soft network system.
6, greening
The solid slope material watering maintenance that framework material and pouring material form is after 14 days, and its actual mechanical strength reaches 5.2MPa, with the mixture of clay, Nutrition Soil and grass-seed, after uniform spreading was located at its surperficial 1cm, the watering maintenance was after 25 days, root system penetrates solid slope material, completes the Gu Po greening on riverbank.
Embodiment two, bare rock greening
1, raw material:
Aggregate: broken slag, 30mm simple grain level grating;
Binder Materials: 42.5 grades of pozzolan cements;
Water: running water;
Additive: methylcellulose;
Clay: fetch earth in the farmland;
Fertilizer: agricultural composite fertilizer;
Grass-seed: Hawaii grass.
2, match ratio
Framework material match ratio (weight ratio): stone: cement: water: additive=1520:190:81:2.7;
Grouting material match ratio (weight ratio): water: clay: composite fertilizer=100:30:1.5;
Green material application match ratio (weight ratio): clay: composite fertilizer: grass-seed=100:1.0: 1.0;
3, framework material preparation
Agitator uses 3 cubic metres of double-horizontal axle concrete-mixers, feeds intake 2 cubic metres at every turn, mixing time 150 seconds, and dump truck is adopted in transportation.
4, rock surface earthing
Cover the 10cm argillic horizon at rock surface, and the compacting of manually watering.
5, lay
Material is transported to the building site by dump truck, manually transports material to laying the position, laying depth 15cm, and 3 meters of rock lengths of grade are laid 5 meters of width at every turn, and both sides arrange masterplate, lay complete rear artificial levelling compacting.
6, grouting
Material was laid after 24 hours, clay and composite fertilizer are entered in container with paddle together, after adjustment moisture stirs, the skeleton that laying is condensed with slush pump is in the milk, repeatedly for several times, until fill, form a relative closely knit solid slope material that is formed by hard skeleton structure and the soft network system.
7, greening
The solid slope material watering maintenance that framework material and pouring material form is after 14 days, its actual mechanical strength reaches 6MPa, mixture with clay, composite fertilizer and grass-seed, after uniform spreading is located at solid slope material surface 2cm, the watering maintenance, after 35 days, root system penetrates solid slope material, completes the greening of bare rock.
Embodiment three, road massif slope protection greening
1, raw material:
Aggregate: 1000 kilograms of unit weight haydites, 20mm simple grain level grating;
Binder Materials: waterglass (sodium silicate), S95 slag powders;
Water: running water;
Additive: xanthans;
Clay: fetch earth in the farmland;
Fertilizer: urea;
Grass-seed: Bermuda grass grass-seed.
2, match ratio
The framework material respective outer side edges is than (weight ratio): haydite: breeze: sodium silicate: water: additive=980:180:20:76:2.2;
Grouting material match ratio (weight ratio): water: clay: urea=100:30:3.0;
Green material application match ratio (weight ratio): clay: urea: grass-seed=100:2:1;
3, framework material preparation
Agitator uses 200 liters of vertical shaft concrete mixers, feeds intake 200 liters, mixing time 5 minutes, manual cleaning at every turn.
4, lay
Material is transported to the building site by dump truck, and truck slowly is discharged into material in a pin-connected panel chute, and human assistance promotes material to laying the position, laying depth 13cm, 11 meters of massif lengths of grade are laid 5 meters of width at every turn, both sides arrange masterplate, lay complete rear artificial levelling compacting.
5, grouting
Material was laid after 24 hours, clay and urea are entered in container with paddle together, after adjustment moisture stirs, the skeleton that laying is condensed with slush pump is in the milk, repeatedly for several times, until fill, form a relative closely knit solid slope material that is formed by hard skeleton structure and the soft network system.
6, greening
The solid slope material watering maintenance that framework material and pouring material form is after 14 days, its actual mechanical strength reaches 6.5MPa, mixture with clay, urea and grass-seed, after uniform spreading is located at its surperficial 3cm, the watering maintenance, after 25 days, root system penetrates solid slope material, completes the Gu Po greening of the massif that the highway bank opens up when building the road.
The above is only the preferred embodiment of the present invention; should be pointed out that for those skilled in the art, under the prerequisite that does not break away from the technology of the present invention principle; can also make some improvements and modifications, these improvements and modifications also should be considered as protection scope of the present invention.

Claims (6)

1. a material that is used for the Gu Po greening, is characterized in that: comprise framework material, pouring material and green material application; Described framework material is formed by aggregate, Binder Materials, additive and water mixing, and wherein the parts by weight of each component are by weight: aggregate 800~1700, Binder Materials 160~210, additive 0.010~0.080, water 72~100; Described aggregate refers to build stone, haydite, slag or concrete disintegrating screening particle; Described Binder Materials refers to the Binder Materials of cement or alkali-slag system; Described additive refers to methylcellulose, cellulose ether or xanthans; Described pouring material is that its water-solid ratio is between 100:30~40 with the slurry of clay, nutritious fertilizer and water preparation; Described green material application is to be formed by clay, nutritious fertilizer and grass-seed mixing, and its weight ratio is: clay: nutritious fertilizer: grass-seed=100:0.5~30:0.5~1.5.
2. material according to claim 1 is characterized in that: the particle diameter of described aggregate between 20~30mm, simple grain level grating.
3. material according to claim 1, it is characterized in that: described cement refers to portland cement, Portland cement, pulverized fuel ash cement, pozzolan cement, slag cements or complex cement.
4. material according to claim 1 is characterized in that: described nutritious fertilizer refers to the conventional nutritious fertilizer that uses of agricultural or gardens.
5. material according to claim 1 is characterized in that: described grass-seed is the various grass-seeds that Landscape Industry uses.
6. the application of a solid slope claimed in claim 1 green material application, its concrete steps are as follows:
1), by proportioning, aggregate, Binder Materials, additive and water mixing are obtained framework material, then be layed in the engineering position that needs construction, thickness obtains having the skeleton of linked hole network structure at 10~15cm after condensing, and its porosity is between 25~30%;
2), press proportioning with clay, nutritious fertilizer and water mixing, prepare the pulpous state pouring material, then be filled in the skeleton that condenses, have the linked hole network structure, sprinkle water maintenance after 14 days, more than its overall mechanical strength reaches 4MPa, form solid slope material;
3), by proportioning, clay, nutritious fertilizer and grass-seed mixing are obtained green material application, then be routed to the surface of the solid slope material that framework material after condensing and pouring material form, thickness is 1~3cm, and the maintenance of sprinkling water, until root system of plant penetrates solid slope material.
CN2013100689166A 2013-03-04 2013-03-04 Material for slope fixing and virescence and application thereof Pending CN103141252A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100689166A CN103141252A (en) 2013-03-04 2013-03-04 Material for slope fixing and virescence and application thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100689166A CN103141252A (en) 2013-03-04 2013-03-04 Material for slope fixing and virescence and application thereof

Publications (1)

Publication Number Publication Date
CN103141252A true CN103141252A (en) 2013-06-12

Family

ID=48539813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100689166A Pending CN103141252A (en) 2013-03-04 2013-03-04 Material for slope fixing and virescence and application thereof

Country Status (1)

Country Link
CN (1) CN103141252A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103650972A (en) * 2013-12-30 2014-03-26 上海申迪园林投资建设有限公司 Structure soil for planting bed and production method thereof
CN106522164A (en) * 2017-01-04 2017-03-22 广州华隧威预制件有限公司 Shrub planting type ecological concrete component and preparing method thereof
CN114158456A (en) * 2021-11-26 2022-03-11 中冶南方都市环保工程技术股份有限公司 Heavy metal mine side slope spray-seeding material and preparation method and application thereof

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10136775A (en) * 1996-11-11 1998-05-26 Raito Kogyo Co Ltd Bag body for greening and greening method
JPH10168884A (en) * 1996-12-05 1998-06-23 Rontai Kk Vegetation sheet
CN1669975A (en) * 2005-03-10 2005-09-21 毛鑫 Concrete for plant growth
CN1768569A (en) * 2005-09-29 2006-05-10 上海大学 Vegetation ecological concrete precast block and preparation method thereof
CN101037598A (en) * 2007-03-30 2007-09-19 成都理工大学 Ecological slope protection substrate
CN101538135A (en) * 2008-03-19 2009-09-23 深圳市海川实业股份有限公司 Vegetation form cellular concrete and method for preparing same
CN101897289A (en) * 2010-07-05 2010-12-01 桂林矿产地质研究院 Plant-growing type eco-concrete and preparation method thereof
CN102060604A (en) * 2010-11-11 2011-05-18 华南理工大学 Suitable material special for plant-growing type porous concrete and filling method
CN102359113A (en) * 2011-07-20 2012-02-22 上海嘉洁环保工程有限公司 Integrally-cast cement pervious concrete ecological protection slope and construction method thereof
CN102518139A (en) * 2011-12-31 2012-06-27 董发达 Manufacture method for ecological vegetated protective slope

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10136775A (en) * 1996-11-11 1998-05-26 Raito Kogyo Co Ltd Bag body for greening and greening method
JPH10168884A (en) * 1996-12-05 1998-06-23 Rontai Kk Vegetation sheet
CN1669975A (en) * 2005-03-10 2005-09-21 毛鑫 Concrete for plant growth
CN1768569A (en) * 2005-09-29 2006-05-10 上海大学 Vegetation ecological concrete precast block and preparation method thereof
CN101037598A (en) * 2007-03-30 2007-09-19 成都理工大学 Ecological slope protection substrate
CN101538135A (en) * 2008-03-19 2009-09-23 深圳市海川实业股份有限公司 Vegetation form cellular concrete and method for preparing same
CN101897289A (en) * 2010-07-05 2010-12-01 桂林矿产地质研究院 Plant-growing type eco-concrete and preparation method thereof
CN102060604A (en) * 2010-11-11 2011-05-18 华南理工大学 Suitable material special for plant-growing type porous concrete and filling method
CN102359113A (en) * 2011-07-20 2012-02-22 上海嘉洁环保工程有限公司 Integrally-cast cement pervious concrete ecological protection slope and construction method thereof
CN102518139A (en) * 2011-12-31 2012-06-27 董发达 Manufacture method for ecological vegetated protective slope

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103650972A (en) * 2013-12-30 2014-03-26 上海申迪园林投资建设有限公司 Structure soil for planting bed and production method thereof
CN106522164A (en) * 2017-01-04 2017-03-22 广州华隧威预制件有限公司 Shrub planting type ecological concrete component and preparing method thereof
CN114158456A (en) * 2021-11-26 2022-03-11 中冶南方都市环保工程技术股份有限公司 Heavy metal mine side slope spray-seeding material and preparation method and application thereof

Similar Documents

Publication Publication Date Title
US10913894B1 (en) Construction method for ecologically protecting expansive soil slope by combining phosphogypsum with microbial mineralization
CN104402339B (en) The constructional method of pervious concrete
CN107963838B (en) Ecological spray anchor slope protection structure and method
CN101796913B (en) Alien soil for slope protection of loess slope plants
CN103866776B (en) A kind of building waste gabion wall ecological bank protecting method
CN105970979A (en) Ecological slope protection method based on sludge solidification soil
CN101486555A (en) Cast-in-situ invert filter type pervious ecological concrete and method for constructing slope protection thereof
CN101684038A (en) Curing agent and construction method of weak soil
CN101696574A (en) Ecological protection method for high steep side slope
CN102359113A (en) Integrally-cast cement pervious concrete ecological protection slope and construction method thereof
CN101897289A (en) Plant-growing type eco-concrete and preparation method thereof
CN105165325A (en) Ecological protecting method for low liquid limit powdery clay side slope
CN104944892B (en) A kind of eco-concrete for greening side slope and preparation method thereof
CN102409637A (en) Ecological restoration method of hydro-fluctuation belt
CN101684409A (en) Soil chemical stabilizer formula and application
CN101089299A (en) Cement slope ecological recovery method
CN107698213A (en) Restoring vegetation concrete component and its preparation method and application
CN204898694U (en) Living concrete member is planted to prefabricated chain formula
CN103141252A (en) Material for slope fixing and virescence and application thereof
AU2020100940A4 (en) Method For Protecting Soil Slope From Shallow Landslide By Using Phosphogypsum
CN107129208A (en) A kind of bioactivity, porous gap coarse aggregate ecological revetment matrix engineering material
CN207749380U (en) Vegetation type eco-concrete
AU2021104437A4 (en) Construction method for slope ecologically restoration using phosphogypsum and microbial mineralization technology
CN110066159A (en) A kind of purified water type greening brick and preparation method thereof applied to ecological slope protection
CN105239532A (en) Ecological concrete building block similar to sponge and preparation method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130612