CN103132456A - Construction method for large span girder with cementation pre-stress - Google Patents

Construction method for large span girder with cementation pre-stress Download PDF

Info

Publication number
CN103132456A
CN103132456A CN2013100875992A CN201310087599A CN103132456A CN 103132456 A CN103132456 A CN 103132456A CN 2013100875992 A CN2013100875992 A CN 2013100875992A CN 201310087599 A CN201310087599 A CN 201310087599A CN 103132456 A CN103132456 A CN 103132456A
Authority
CN
China
Prior art keywords
bellows
steel
presstressed reinforcing
duct
reinforcing steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100875992A
Other languages
Chinese (zh)
Inventor
成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2013100875992A priority Critical patent/CN103132456A/en
Publication of CN103132456A publication Critical patent/CN103132456A/en
Pending legal-status Critical Current

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The invention discloses a construction method for a large span girder with cementation pre-stress. The method includes the steps of steel bar binding, corrugated pipe reservation, pre-stress steel blanking, pre-stress steel piercing, concrete pouring, pre-stress steel stretch-draw, duct grouting, end portion sealing and wrapping and the like. With the construction method for the large span girder with the cementation pre-stress, construction is convenient and safe, construction efficiency is high and construction quality is good.

Description

Large span bonded prestressed beam job practices
Technical field
The present invention relates to a kind of large span bonded prestressed beam job practices.
Background technology
Existing large span bonded prestressed beam construction, method is complicated, has defective at aspects such as efficiency of construction, safety, construction effects, needs further to improve.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, safety, the measured large span bonded prestressed beam of matter job practices.
Technical solution of the present invention is:
A kind of large span bonded prestressed beam job practices, comprise that staying of reinforcing bar binding, bellows established, presstressed reinforcing steel blanking, presstressed reinforcing steel lashing, concreting, tension of prestressed tendon, duct grouting and end envelope wrap up in, it is characterized in that: (one) reinforcing bar binding:
(1) reinforcing bar binding well draws the presstressed reinforcing steel installation curve afterwards on stirrup;
(2) the first assembling reinforcement of Vierendeel girder and stirrup, colligation is carried out in the lacing wire of beam S type again after presstressed reinforcing steel installs;
(3) during assembling reinforcement, guarantee the correct of prestressed pore passage coordinate position;
(4) when colligation post muscle, guarantee that bellows and steel strand can pass through smoothly;
(5) the colligation floor steel bar, when pipeline is installed, must not mobile bellows and the position of steel strand, must not shrivel bellows;
(2) staying of bellows established
(1) bellows is pressed design attitude and installed fixingly, and its process is as follows: topping at the bottom of colligation Vierendeel girder stirrup and beam steel → processing beam → on stirrup is by duct coordinate position spot welding analog bracket → laying and fixing bellows → installation and mooring anchor backing plate → penetrate steel strand → inspect for acceptance;
(2) after first installation frame beam steel protective layer, can begin fixedly bellows; Connect with bigger bellows between bellows, the connection pipe range is 200mm-350mm, and two ends screw in symmetrically and evenly, and wraps up in seam with the adhesive tape envelope;
(3) slurry outlet is arranged on the position of constraint circle, firmly, vertically;
(4) prestressed girder end anchor backing plate is laid smoothly, firm, and the center in its pre-buried anchor plate hole is concentric with the duct center line, and end face is vertical with the duct center line;
(5) duct stays when establishing coordinate position correct, and the control point error of coordinate should be less than ± 20mm, and horizontal position error must not be greater than ± 20 mm; Get 50 mm at the bottom of the minimum thickness beam of presstressed reinforcing steel topping, beam side-draw 40 mm; Corrugated pipe connector place envelope wraps up in tightly, firmly, spillage not;
(3) presstressed reinforcing steel blanking
The presstressed reinforcing steel blanking in time penetrates the duct in order to avoid gets rusty; The cutting length of presstressed reinforcing steel is: the physical length in duct+stretch-draw active length; The active length of stretching end is got 0. 8 m-1. 0 m;
(4) presstressed reinforcing steel lashing
After bellows is fixed substantially, with the steel strands-woven bundle colligation, and penetrating wire rope socket on termination point casing, penetrate by bundle;
(5) concreting
Concrete delamination vibrates, vibration compacting;
(6) tension of prestressed tendon
(1) concrete strength reaches 100% rear and carries out stretch-draw;
(2) stressing sequence of presstressed reinforcing steel is: 0 → 0.1 σ con→ 0.60 σ con→ 1.0 σ conAnchoring;
(3) the tension of prestressed tendon proof stress is σ con=0.75f ptk=0.75 * 1860=1395MPa;
(4) elongation value of stretching is from 0.1 σ con→ 1.0 σ con, minute three measurements, and do on-the-spot record;
(7) duct grouting and end envelope is wrapped up in
(1) be in the milk in complete rear 24 hours until the whole stretch-draw of presstressed reinforcing steel.Be in the milk the previous day, end anchorage place's application of pure cement paste or mortar envelope are wrapped up in the space between anchor clipper, only reserve grout hole or venthole;
(2) Grouting Cement intensity is 42.5 Portland cements, and water/binder ratio is 0.4-0.45, mixes the JM3 expansion agent of 6-8%, and degree of mobilization is 12~17cm, the Grouting Cement mechanical agitation; Once fill equably the duct from the grout hole that stretching end is set, treat emerge underflow rear enclosed bleeding hole, other end ground tackle venthole place, and continue to be pressurized to 0.6MPa rear enclosed grout hole;
(3) the end steel strand adopt machine cuts, expose steel strand and keep 30mm; Ground tackle is wrapped up in to protect with the pea gravel concreten envelope in the end.
Easy construction of the present invention, safety, efficiency of construction is high, and construction quality is good.
The invention will be further described below in conjunction with embodiment.
The specific embodiment
A kind of large span bonded prestressed beam job practices comprises that staying of reinforcing bar binding, bellows established, presstressed reinforcing steel blanking, presstressed reinforcing steel lashing, concreting, tension of prestressed tendon, duct grouting and end envelope wrap up in; (1) reinforcing bar binding:
(1) reinforcing bar binding well draws the presstressed reinforcing steel installation curve afterwards on stirrup;
(2) the first assembling reinforcement of Vierendeel girder and stirrup, colligation is carried out in the lacing wire of beam S type again after presstressed reinforcing steel installs;
(3) during assembling reinforcement, guarantee the correct of prestressed pore passage coordinate position;
(4) when colligation post muscle, guarantee that bellows and steel strand can pass through smoothly;
(5) the colligation floor steel bar, when pipeline is installed, must not mobile bellows and the position of steel strand, must not shrivel bellows;
(2) staying of bellows established
(1) bellows is pressed design attitude and installed fixingly, and its process is as follows: topping at the bottom of colligation Vierendeel girder stirrup and beam steel → processing beam → on stirrup is by duct coordinate position spot welding analog bracket → laying and fixing bellows → installation and mooring anchor backing plate → penetrate steel strand → inspect for acceptance;
(2) after first installation frame beam steel protective layer, can begin fixedly bellows; Connect with bigger bellows between bellows, the connection pipe range is 200mm-350mm, and two ends screw in symmetrically and evenly, and wraps up in seam with the adhesive tape envelope;
(3) slurry outlet is arranged on the position of constraint circle, firmly, vertically;
(4) prestressed girder end anchor backing plate is laid smoothly, firm, and the center in its pre-buried anchor plate hole is concentric with the duct center line, and end face is vertical with the duct center line;
(5) duct stays when establishing coordinate position correct, and the control point error of coordinate should be less than ± 20mm, and horizontal position error must not be greater than ± 20 mm; Get 50 mm at the bottom of the minimum thickness beam of presstressed reinforcing steel topping, beam side-draw 40 mm; Corrugated pipe connector place envelope wraps up in tightly, firmly, spillage not;
(3) presstressed reinforcing steel blanking
The presstressed reinforcing steel blanking in time penetrates the duct in order to avoid gets rusty; The cutting length of presstressed reinforcing steel is: the physical length in duct+stretch-draw active length; The active length of stretching end is got 0. 8 m-1. 0 m;
(4) presstressed reinforcing steel lashing
After bellows is fixed substantially, with the steel strands-woven bundle colligation, and penetrating wire rope socket on termination point casing, penetrate by bundle;
(5) concreting
Concrete delamination vibrates, vibration compacting;
(6) tension of prestressed tendon
(1) concrete strength reaches 100% rear and carries out stretch-draw;
(2) stressing sequence of presstressed reinforcing steel is: 0 → 0.1 σ con→ 0.60 σ con→ 1.0 σ conAnchoring;
(3) the tension of prestressed tendon proof stress is σ con=0.75f ptk=0.75 * 1860=1395MPa;
(4) elongation value of stretching is from 0.1 σ con→ 1.0 σ con, minute three measurements, and do on-the-spot record;
(7) duct grouting and end envelope is wrapped up in
(1) be in the milk in complete rear 24 hours until the whole stretch-draw of presstressed reinforcing steel.Be in the milk the previous day, end anchorage place's application of pure cement paste or mortar envelope are wrapped up in the space between anchor clipper, only reserve grout hole or venthole;
(2) Grouting Cement intensity is 42.5 Portland cements, and water/binder ratio is 0.4-0.45, mixes the JM3 expansion agent of 6-8%, and degree of mobilization is 12~17cm, the Grouting Cement mechanical agitation; Once fill equably the duct from the grout hole that stretching end is set, treat emerge underflow rear enclosed bleeding hole, other end ground tackle venthole place, and continue to be pressurized to 0.6MPa rear enclosed grout hole;
(3) the end steel strand adopt machine cuts, expose steel strand and keep 30mm; Ground tackle is wrapped up in to protect with the pea gravel concreten envelope in the end.

Claims (1)

1. large span bonded prestressed beam job practices, comprise that staying of reinforcing bar binding, bellows established, presstressed reinforcing steel blanking, presstressed reinforcing steel lashing, concreting, tension of prestressed tendon, duct grouting and end envelope wrap up in, it is characterized in that: (one) reinforcing bar binding:
(1) reinforcing bar binding well draws the presstressed reinforcing steel installation curve afterwards on stirrup;
(2) the first assembling reinforcement of Vierendeel girder and stirrup, colligation is carried out in the lacing wire of beam S type again after presstressed reinforcing steel installs;
(3) during assembling reinforcement, guarantee the correct of prestressed pore passage coordinate position;
(4) when colligation post muscle, guarantee that bellows and steel strand can pass through smoothly;
(5) the colligation floor steel bar, when pipeline is installed, must not mobile bellows and the position of steel strand, must not shrivel bellows;
(2) staying of bellows established
(1) bellows is pressed design attitude and installed fixingly, and its process is as follows: topping at the bottom of colligation Vierendeel girder stirrup and beam steel → processing beam → on stirrup is by duct coordinate position spot welding analog bracket → laying and fixing bellows → installation and mooring anchor backing plate → penetrate steel strand → inspect for acceptance;
(2) after first installation frame beam steel protective layer, can begin fixedly bellows; Connect with bigger bellows between bellows, the connection pipe range is 200mm-350mm, and two ends screw in symmetrically and evenly, and wraps up in seam with the adhesive tape envelope;
(3) slurry outlet is arranged on the position of constraint circle, firmly, vertically;
(4) prestressed girder end anchor backing plate is laid smoothly, firm, and the center in its pre-buried anchor plate hole is concentric with the duct center line, and end face is vertical with the duct center line;
(5) duct stays when establishing coordinate position correct, and the control point error of coordinate should be less than ± 20mm, and horizontal position error must not be greater than ± 20 mm; Get 50 mm at the bottom of the minimum thickness beam of presstressed reinforcing steel topping, beam side-draw 40 mm; Corrugated pipe connector place envelope wraps up in tightly, firmly, spillage not;
(3) presstressed reinforcing steel blanking
The presstressed reinforcing steel blanking in time penetrates the duct in order to avoid gets rusty; The cutting length of presstressed reinforcing steel is: the physical length in duct+stretch-draw active length; The active length of stretching end is got 0. 8 m-1. 0 m;
(4) presstressed reinforcing steel lashing
After bellows is fixed substantially, with the steel strands-woven bundle colligation, and penetrating wire rope socket on termination point casing, penetrate by bundle;
(5) concreting
Concrete delamination vibrates, vibration compacting;
(6) tension of prestressed tendon
(1) concrete strength reaches 100% rear and carries out stretch-draw;
(2) stressing sequence of presstressed reinforcing steel is: 0 → 0.1 σ con→ 0.60 σ con→ 1.0 σ conAnchoring;
(3) the tension of prestressed tendon proof stress is σ con=0.75f ptk=0.75 * 1860=1395MPa;
(4) elongation value of stretching is from 0.1 σ con→ 1.0 σ con, minute three measurements, and do on-the-spot record;
(7) duct grouting and end envelope is wrapped up in
(1) be in the milk in complete rear 24 hours until the whole stretch-draw of presstressed reinforcing steel.Be in the milk the previous day, end anchorage place's application of pure cement paste or mortar envelope are wrapped up in the space between anchor clipper, only reserve grout hole or venthole;
(2) Grouting Cement intensity is 42.5 Portland cements, and water/binder ratio is 0.4-0.45, mixes the JM3 expansion agent of 6-8%, and degree of mobilization is 12~17cm, the Grouting Cement mechanical agitation; Once fill equably the duct from the grout hole that stretching end is set, treat emerge underflow rear enclosed bleeding hole, other end ground tackle venthole place, and continue to be pressurized to 0.6MPa rear enclosed grout hole;
(3) the end steel strand adopt machine cuts, expose steel strand and keep 30mm; Ground tackle is wrapped up in to protect with the pea gravel concreten envelope in the end.
CN2013100875992A 2013-03-19 2013-03-19 Construction method for large span girder with cementation pre-stress Pending CN103132456A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100875992A CN103132456A (en) 2013-03-19 2013-03-19 Construction method for large span girder with cementation pre-stress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100875992A CN103132456A (en) 2013-03-19 2013-03-19 Construction method for large span girder with cementation pre-stress

Publications (1)

Publication Number Publication Date
CN103132456A true CN103132456A (en) 2013-06-05

Family

ID=48492865

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100875992A Pending CN103132456A (en) 2013-03-19 2013-03-19 Construction method for large span girder with cementation pre-stress

Country Status (1)

Country Link
CN (1) CN103132456A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410329A (en) * 2013-08-30 2013-11-27 南通八建集团有限公司 Large-span basement concrete roof structure flat tube bonded prestressing force construction method
CN106522561A (en) * 2016-11-02 2017-03-22 中建八局第三建设有限公司 Long-span concrete frame beam bonded prestressed post-cast strip inside stretching construction method
CN109898546A (en) * 2019-03-25 2019-06-18 五冶集团上海有限公司 A kind of raw material mill vertical prestressing steel strand wires bellows mounting and fixing support
CN112647706A (en) * 2020-07-28 2021-04-13 安宜建设集团有限公司 Construction method for long-span concrete beam slow-bonding prestress
CN112942444A (en) * 2021-02-02 2021-06-11 金华职业技术学院 Self-cracking-resistant rigid landfill reinforced concrete bottom plate and construction process thereof
CN113107129A (en) * 2021-04-20 2021-07-13 中国建筑第七工程局有限公司 Super high-rise post-tensioning method bonded prestressed beamless floor construction method
CN115262626A (en) * 2022-06-24 2022-11-01 中铁第四勘察设计院集团有限公司 Construction method of underground space prestress steel reinforced concrete top cover under super-large span heavy load
CN116695566A (en) * 2023-05-12 2023-09-05 中建八局第三建设有限公司 Tensioning construction process of prestressed concrete beam

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101775903A (en) * 2010-01-22 2010-07-14 北京首钢建设集团有限公司 Construction method for pouring after settlement of reinforced concrete continuous beam with cohesive pre-stress
CN101798875A (en) * 2010-03-16 2010-08-11 南通华荣建设集团有限公司 Construction method for stretching and drawing high-span crossbeam with bonding prestress at single side
KR20110017066A (en) * 2009-08-13 2011-02-21 지에스건설 주식회사 Psc girder bridge making method with closed section member between upper flanges
CN102213022A (en) * 2010-04-09 2011-10-12 上海市第七建筑有限公司 Construction method of prestress beam
KR101180989B1 (en) * 2010-03-02 2012-09-07 방정연 Curved prestress concrete girder and bridge with the same

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110017066A (en) * 2009-08-13 2011-02-21 지에스건설 주식회사 Psc girder bridge making method with closed section member between upper flanges
CN101775903A (en) * 2010-01-22 2010-07-14 北京首钢建设集团有限公司 Construction method for pouring after settlement of reinforced concrete continuous beam with cohesive pre-stress
KR101180989B1 (en) * 2010-03-02 2012-09-07 방정연 Curved prestress concrete girder and bridge with the same
CN101798875A (en) * 2010-03-16 2010-08-11 南通华荣建设集团有限公司 Construction method for stretching and drawing high-span crossbeam with bonding prestress at single side
CN102213022A (en) * 2010-04-09 2011-10-12 上海市第七建筑有限公司 Construction method of prestress beam

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘忠: "大跨度预应力梁的施工工作总结", 《山西建筑》, vol. 32, no. 15, 20 August 2006 (2006-08-20), pages 113 - 114 *
袁建国: "某工程500mm×1900mm有粘结预应力梁施工", 《山西建筑》, vol. 34, no. 15, 20 May 2008 (2008-05-20), pages 132 - 133 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410329A (en) * 2013-08-30 2013-11-27 南通八建集团有限公司 Large-span basement concrete roof structure flat tube bonded prestressing force construction method
CN103410329B (en) * 2013-08-30 2015-04-15 南通八建集团有限公司 Large-span basement concrete roof structure flat tube bonded prestressing force construction method
CN106522561A (en) * 2016-11-02 2017-03-22 中建八局第三建设有限公司 Long-span concrete frame beam bonded prestressed post-cast strip inside stretching construction method
CN106522561B (en) * 2016-11-02 2018-12-14 中建八局第三建设有限公司 Stretch-draw construction method in large-span concrete Vierendeel girder bonded prestress post-cast strip
CN109898546A (en) * 2019-03-25 2019-06-18 五冶集团上海有限公司 A kind of raw material mill vertical prestressing steel strand wires bellows mounting and fixing support
CN112647706A (en) * 2020-07-28 2021-04-13 安宜建设集团有限公司 Construction method for long-span concrete beam slow-bonding prestress
CN112942444A (en) * 2021-02-02 2021-06-11 金华职业技术学院 Self-cracking-resistant rigid landfill reinforced concrete bottom plate and construction process thereof
CN113107129A (en) * 2021-04-20 2021-07-13 中国建筑第七工程局有限公司 Super high-rise post-tensioning method bonded prestressed beamless floor construction method
CN115262626A (en) * 2022-06-24 2022-11-01 中铁第四勘察设计院集团有限公司 Construction method of underground space prestress steel reinforced concrete top cover under super-large span heavy load
CN115262626B (en) * 2022-06-24 2023-12-01 中铁第四勘察设计院集团有限公司 Construction method of underground space prestress steel reinforced concrete top cover under ultra-large span heavy load
CN116695566A (en) * 2023-05-12 2023-09-05 中建八局第三建设有限公司 Tensioning construction process of prestressed concrete beam
CN116695566B (en) * 2023-05-12 2024-04-09 中建八局第三建设有限公司 Tensioning construction process of prestressed concrete beam

Similar Documents

Publication Publication Date Title
CN103132456A (en) Construction method for large span girder with cementation pre-stress
CN107119574B (en) A kind of Cantilever Construction Method of arch rib bridge girder
CN106522561B (en) Stretch-draw construction method in large-span concrete Vierendeel girder bonded prestress post-cast strip
US8931236B2 (en) System for anchoring a load
CN106498950B (en) Anchor head is placed in the implementation method of the Pile-Anchor Supporting for Deep Excavation system of pile body
CN109281250B (en) Arch ring linearity and prestress control construction method for deck type external cable multi-arch bridge
CN108677743A (en) A kind of concrete cast-in-situ box girder construction method of viaduct
CN205917838U (en) Balcony board installation node
CN108104121B (en) Structure and method for improving compressive strength of pressure type anchor cable cement grouting body
CN104976424B (en) Anchor cable construction method for rectangular top pipe joint connecting and strengthening
CN108004925B (en) Prestress reinforced concrete circular arch tower construction method
JP6427045B2 (en) Reinforcement structure and reinforcement method of existing concrete structure
CN109837895A (en) A kind of big pressure dispersing anchorage cable construction of depth
KR20110111907A (en) Saddle assembly
CN109653511A (en) Large-span bidirectional mixing prestressing force complete construction method
CN107090777A (en) A kind of T beam manufacture methods for reducing blibbing
CN105714819B (en) A kind of outer anchor head multi-protective device of prestress anchorage cable and its fixing means
KR20130136847A (en) End continuing method of wire truss decks
CN110184948A (en) A kind of Bridge beam construction method
CN111501517A (en) Novel external prestressed assembly of prestressed box girder
CN101798875B (en) Construction method for stretching and drawing high-span crossbeam with bonding prestress at single side
CN101550724A (en) Construction method of large-span post-tensioned prestressed longitudinal and transverse frame beams
CN108360821A (en) A kind of construction method of beam
CN108978870A (en) Fold-line-shaped girder steel and concrete combined structure construction method
CN108756243A (en) Girder steel and concrete ring beam, the structure-integrated construction of concrete floor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130605