CN103031790A - Road facility capable of enabling vehicles on crossing road of city not to intersecting - Google Patents

Road facility capable of enabling vehicles on crossing road of city not to intersecting Download PDF

Info

Publication number
CN103031790A
CN103031790A CN 201110310957 CN201110310957A CN103031790A CN 103031790 A CN103031790 A CN 103031790A CN 201110310957 CN201110310957 CN 201110310957 CN 201110310957 A CN201110310957 A CN 201110310957A CN 103031790 A CN103031790 A CN 103031790A
Authority
CN
China
Prior art keywords
track
road
cross road
vehicle
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201110310957
Other languages
Chinese (zh)
Inventor
徐晓广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 201110310957 priority Critical patent/CN103031790A/en
Publication of CN103031790A publication Critical patent/CN103031790A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Traffic Control Systems (AREA)

Abstract

The invention discloses a road facility capable of enabling vehicles on a crossing road of a city not to intersecting. The road facility comprises a longitudinal road and a transverse road which are arranged on the crossing road, and a crossing path formed when the longitudinal road and the transverse road intersect, wherein a plurality of vehicular bridges corresponding to driving directions are arranged on the crossing road, a plurality of corresponding connecting roads are arranged under the corresponding vehicular bridges, one ends of the corresponding connecting roads are connected with the corresponding vehicular bridges, the other ends of the connecting roads are connected with running lanes, and isolation belts are arranged on two sides of the corresponding connecting roads. By adopting the technical scheme provided by the invention, the vehicle traffic capacity on each connecting road of the crossing road can be increased several times. The road facility has the advantages and effects of little investment, resource saving, simple technology, no traffic light, no limit of vehicle flow, smoothness without stop, convenience in running and the like, and radically solves the problem of traffic jam in the city.

Description

A kind ofly can make the non-intersect road equipment that travels of vehicle on the cross road, city
(1), technical field:
The invention belongs to city traffic lane intersection facility, be specifically related to a kind ofly can make the non-intersect road equipment that travels of vehicle on the cross road, city.
(2), background technology:
The city driving is blocked up, and is the ubiquitous problem in domestic and international flourishing city.Present crossing, track, city, generally adopt traffic light signal to control, oriented vehicle is in the shunting at crossing, because the signal of traffic lights carries out frequent, cause vehicle to wait, in the situation that vehicle flow is large, very easily cause the vehicle congestion phenomenon, relevant city to be taked the broadening track, builds overpass bridge and driving tunnel, is collected the ways such as the expense of blocking up and restricting the number trip in order to address this is that.Facts have proved, can only alleviate traffic congestion, can not fundamentally solve the driving lane problem of blocking up.
(3), summary of the invention:
The object of the present invention is to provide and a kind ofly can make the non-intersect road equipment that travels of vehicle on the cross road, city, comprise that the vertical road on the cross road intersects the mutually dealings that forms with belt road and they, it is characterized in that: described several corresponding row vehicle bridge corresponding with travel direction that are provided with in the cross road, be provided with several corresponding connection roads with corresponding row vehicle bridge corresponding section, a corresponding end that connects the road is connected with the corresponding row vehicle bridge, the other end links to each other with the track that will travel, and the corresponding both sides that connect the road are provided with the isolation strip.
Described corresponding row vehicle bridge is crossed on vertical road on the phase dealings.
Described corresponding row vehicle bridge is crossed on the belt road on the phase dealings.
Described vertical road in both sides, crossing, cross road is respectively equipped with the corresponding row vehicle bridge corresponding with travel direction.
Described belt road in both sides, crossing, cross road is respectively equipped with the corresponding driving sedan-chair corresponding with travel direction.
Several lane auxiliaries are established respectively in the outside in the track, both sides in cross road.
The described corresponding isolation strip that connects the both sides in road is greenbelt or railing or driving shielding wire.
Described both sides at vertical road and the crossing mutually dealings that forms of belt road also are provided with service bridge.
Described intersecting on the mutually dealings that forms at vertically road and belt road also is provided with underground craspedodrome runway.
Described intersecting on the mutually dealings that forms at vertically road and belt road also is provided with the underground runway that turns to.
In technique scheme, be provided with a plurality of corresponding row vehicle bridge corresponding with travel direction in the cross road, below the corresponding row vehicle bridge, be provided with several corresponding roads that connects, a corresponding end that connects the road is connected with the corresponding row vehicle bridge, vertical track, corresponding row vehicle bridge and horizontal track, connect into the non-intersect communication channel that travels.Its effect:
By this way, so that in certain hour, being conducive to accelerate on the connection track of crossroad, at first is vertical track and the horizontal road speed on the track, is conducive to increase the driving quantity on the phase dealings.Such scheme compared with prior art, the present invention has the following advantages:
1, modern design, rational in infrastructure.This programme can make the vehicle at the crossing, cross road in longitudinal vehicle road and horizontal track, without under the traffic lights indications, simultaneously disjoint, drive on other road junction roadways, can eliminate because of red parking, cause the situation of the track wasting of resources and traffic congestion, reach vehicle smooth without hindrance, take their own roads.Be each track up train that crossing, cross road connects, can travel respectively simultaneously, need provides realization condition on other road junction roadway of arrival.This design has obtained beyond thought technique effect, has solved that people thirst for solving always and the difficult problem of blocking up of unsolved Vehicle Driving Cycle all the time.
2, cost is low, and social benefit is large.This programme can take full advantage of existing resource, and cost of investment is low, can make that realize non-intersectly travelling in the crossing of whole road, without hindrance shunting, has accelerated the passage rate of vehicle, has shortened running time, can fundamentally solve the city driving problem of blocking up.
3, have a extensive future.Technical scheme of the present invention can practical application on the intersection of the different kinds of roads of big and medium-sized cities, and range of application is very wide.
(4), description of drawings:
Fig. 1 is a kind of embodiment one structural representation that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Fig. 2 is a kind of embodiment one structural representation that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Fig. 3 is a kind of embodiment two structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Fig. 4 is a kind of embodiment two structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Fig. 5 is a kind of embodiment three structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Fig. 6 is a kind of embodiment three structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Fig. 7 is a kind of embodiment four structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Fig. 8 is a kind of embodiment four structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Fig. 9 is a kind of embodiment five structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Figure 10 is a kind of embodiment five structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Figure 11 is a kind of embodiment six structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Figure 12 is a kind of embodiment six structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Figure 13 is a kind of embodiment seven structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Figure 14 is a kind of embodiment eight structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Figure 15 is a kind of embodiment eight structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Figure 16 is a kind of embodiment nine structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Figure 17 is a kind of embodiment nine structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention;
Figure 18 is a kind of embodiment ten structural representations that can make the non-intersect road equipment that travels of vehicle on the cross road, city of the present invention.
(5), the specific embodiment:
Can make to the present invention is a kind of that the non-intersect road equipment that travels of vehicle is described in further detail on the cross road, city below in conjunction with accompanying drawing.
Embodiment one:
By Fig. 1, Fig. 2 as seen, in the present embodiment: in vertical both sides, cross road, connect respectively the six-lane that vertically travels in opposite directions.In cross road both lateral sides, connect respectively the six-lane that laterally travels in opposite directions.Longitudinally the track of road is provided with corresponding row vehicle bridge 1 on the cross road, is provided with the corresponding road 2 that connects below corresponding row vehicle bridge 1.
On the right of the center line of track, southern side, vertical cross road: be provided with G1, G2, G3 track.On the cross road of G1, the connection of G2 track, be provided with successively the corresponding row vehicle bridge 1 that turns to of crossing over the cross road.On the cross road that connects in the G3 track, be provided with the corresponding row vehicle bridge 1 of the craspedodrome of crossing over the cross road, they successively correspondence be connected to north side, cross road longitudinally on A1, A2, the A3 track.Wherein: in southern side, cross road, be located at the bridge of overhead travelling crane lane length on the G2 track, shorter than the bridge of overhead travelling crane track that arranges on G1, the G3 track, in north side, cross road, extend to bridge of overhead travelling crane lane length on the A1 track by the G1 track, shorter than the bridge of overhead travelling crane track that is extended on A2, the A3 track by G2, G3 track.The left side at above-mentioned track center line: be provided with H1, H2, H3 track, they are connected respectively on the cross road from southern bridge of overhead travelling crane track, wherein: connect the bridge lane length of the corresponding row vehicle bridge 1 that turns in the H1 track, shorter than the bridge of overhead travelling crane track that arranges in H2, H3, G1, G3 track.Below the bridge of overhead travelling crane track in southern side, cross road, from north southward, be provided with successively first, second, third, fourth corresponding road 2 that connects.
On the right in the face of track, north side, vertical cross road center line: be provided with B1, B2, B3 track.On the cross road of B1, the connection of B2 track, be provided with successively and cross over the corresponding row vehicle bridge 1 that the cross road turns to, on the cross road of B3 track connection, be provided with and cross over the corresponding row vehicle bridge 1 of keeping straight in the cross road, they are successively on corresponding H1, the H2 that is connected to southern side, cross road, the H3 track.Wherein: in north side, cross road, be located at the bridge of overhead travelling crane lane length on the B2 track, shorter than the bridge of overhead travelling crane track that arranges in B1, B3 track, in southern side, cross road, extend to bridge of overhead travelling crane lane length on the H1 track by the B1 track, shorter than the bridge of overhead travelling crane track that is extended on H2, the H3 track by B2, B3 track.The left side at above-mentioned track center line: be provided with successively A1, A2, A3 track, they are connected respectively the bridge of overhead travelling crane track from south toward north on the cross road, wherein: connect the bridge lane length of the corresponding row vehicle bridge 1 that turns in the A1 track, shorter than the bridge of overhead travelling crane track that arranges in A2, A3, B1, B3 track.Below the bridge track of north side, cross road, from Nan Wangbei, be provided with successively first, second, the 3rd, the 4th correspondence connects road 2.
The right in the face of track, east side, cross road center line is provided with C1, C2, C3 track successively.On the left side of above-mentioned track center line, be provided with successively E1, E2, E3 track.The right in the face of track, west side, cross road center line is provided with F1, F2, F3 track successively, on the left side of above-mentioned track center line, is provided with successively D1, D2, D3 track.
The below is illustrated the Vehicle Driving Cycle process, for example:
One, when vehicle in the face of on the track, south, cross road:
1, vehicle is in the face of on the G1 track, south, cross road, in the time of turning left to the D2 track, west, cross road:
Vehicle is on the G1 track, to overtake on the corresponding row vehicle bridge 1 that turns to, on the North track in this bridge track, drive to the north, cross road, connect on the road 2 from south toward the 3rd northern correspondence, turn left and connect under the bridge of overhead travelling crane in cross road to the B1 track, under this bridge track, pass, through the B2 track, turn left and connect under the bridge of overhead travelling crane in cross road to the B3 track, under this bridge track, travel southwards, in D2 track, west, cross road and joint, cross road, turning right drives on the D2 track in west, cross road.
2, vehicle is being faced on the G2 track, cross road, in the time of turning right on the E3 track, east, cross road:
Vehicle is on the G2 track, to overtake to south, cross road, from southern the 4th corresponding the connection on the road 2, right travel connects under the bridge of overhead travelling crane in cross road in the G3 track forward, under this bridge track, northwards travel, in E3 track, east, cross road and joint, cross road, turn right, drive on the E3 track in the east, cross road.
3, vehicle is being faced on the G3 track, cross road, keep straight on when sailing on the A3 track, the north, cross road:
Vehicle on the corresponding row vehicle bridge 1 of keeping straight on, drives on the track of this bridge track the North on the G3 track to overtake, drives on the A3 track on the north, cross road.
Two, when vehicle in the face of on the track, the north, cross road:
1, vehicle is in the face of on the B1 track, the north, cross road, in the time of turning left to the cross road in the east on the E2 track:
Vehicle is on the B1 track, to overtake on the corresponding row vehicle bridge 1 that turns to, on the track of this south, bridge track, drive to south, cross road, connect on the road 2 from southern the 3rd correspondence, turn left and connect under the bridge of overhead travelling crane in cross road to the G1 track, under this bridge track, pass, through the G2 track, turn left and connect under the bridge of overhead travelling crane in cross road to the G3 track, under this bridge track, northwards travel, in E2 track, east, cross road and joint, cross road, turning right drives on the E2 track in the east, cross road.
2, vehicle is being faced on the B2 track, the north, cross road, in the time of turning right on the D3 track, west, cross road:
Vehicle is on the B2 track, to the north, cross road, from south toward north the 4th is corresponding to overtake connects on the road 2, right travel connects the corresponding row vehicle bridge 1 time of the craspedodrome in cross road in the B3 track forward, under this bridge track, travel southwards, in D3 track, west, cross road and joint, cross road, turn right, drive on the D3 track in west, cross road.
3, vehicle in the face of on the B3 track, the north, cross road, to keep straight on when sailing on the H3 track, south, cross road:
Vehicle on the corresponding row vehicle bridge 1 of keeping straight on, drives on the track of this south, bridge track on the B3 track to overtake, drives on the H3 track in south, cross road.
Three, when vehicle in the face of cross road in the east on the track:
1, vehicle in the face of the cross road in the east on the C2 track, in the time of will turning left to the H2 track, south, cross road:
Vehicle is on the C2 track, drive under the bridge of overhead travelling crane track in connection cross road, A3 track, the north, cross road, drive to the right on the north, cross road, first the corresponding connection road 2 from south toward north, pass under the connection up vehicle bridge track, cross road in cross road north A2, A1, B1 track, drive on the B2 track, turn left and drive on the corresponding row vehicle bridge 1 that turns on the connection cross road, B2 track, on the track of this south, bridge track, drive on the H2 track in south, cross road.
2, vehicle is in the face of cross road in the east on the C3 track, in the time of turning right on the A1 track on the north, cross road:
Vehicle is on the C3 track, arrive to overtake under the bridge of overhead travelling crane in connection cross road, A3 track, the north, cross road, drive to the north, cross road to the right, connect on the road 2 from south toward second northern correspondence, connect in the A3 track under the bridge of overhead travelling crane track in cross road, northwards left lateral is sailed, and under the bridge of overhead travelling crane track in the cross road that process A2 track connects, northwards left lateral sails on the A1 track, turn right in the A1 track, drive on the A1 track on the north, cross road.
3, vehicle in the face of the cross road in the east on the C1 track, to keep straight on when sailing on the D1 track, west, cross road:
Vehicle on the C1 track, to overtake, on longitudinal crossing cross road, bridge of overhead travelling crane passes under the track, drive on the D1 track that west, cross road connects.
Four, when vehicle in the face of on the track, west, cross road:
1, vehicle is in the face of on the F2 track, west, cross road, in the time of will turning left to the A2 track on the north, cross road:
Vehicle is on the F2 track, arrive to overtake under the bridge of overhead travelling crane track in connection cross road, H3 track, south, cross road, right lateral sails to south, cross road, connects on road 2 from southern first correspondence forward, pass under the bridge of overhead travelling crane track that connect in cross road south H2, H1, G1 track, on the cross road, drive on the G2 track, turn left and drive on the corresponding row vehicle bridge 1 that turns on the connection cross road, G2 track, on the track of this bridge track the North, drive on the A2 track on the north, cross road.
2, vehicle is on facing F3 track, west, cross road, in the time of will turning right on the H1 track, south, cross road:
Vehicle is on the F3 track, arrive to overtake under the bridge of overhead travelling crane in connection cross road, H3 track, south, cross road, drive to south, cross road to the right, connect on the road 2 from southern second correspondence, under this bridge track, left lateral to the south is sailed, and connects through the H2 track under the bridge of overhead travelling crane track in cross road, and left lateral to the south sails on the H1 track, turn right in the H1 track, drive on the H1 track in south, cross road.
3, vehicle in the face of on the F1 track, west, cross road, keep straight on sails to the cross road in the east on the E1 track time:
Vehicle to overtake, passes under the bridge of overhead travelling crane track on the longitudinal crossing cross road on the F1 track, drives on the E1 track that the cross road connects in the east.
In the present embodiment, the corresponding both sides that connect road 2 are provided with the isolation strip, and the isolation strip is railing.
Embodiment two:
By Fig. 3, Fig. 4 as seen, in the present embodiment: in vertical both sides, cross road, connect respectively the six-lane that vertically travels in opposite directions.In cross road both lateral sides, connect respectively the six-lane that laterally travels in opposite directions.Longitudinally the track of road is provided with corresponding row vehicle bridge 1 on the cross road, is provided with the corresponding road 2 that connects below corresponding row vehicle bridge 1.Be provided with lane auxiliary 3 in the outside in track on both sides of the road in vertical road.
On the right in the face of track, southern side, vertical cross road center line: be provided with longitudinally G1, G2, G3 track.On the right, G3 track, be provided with a lane auxiliary 3.On the cross road of G1, the connection of G2 track, be provided with successively the corresponding row vehicle bridge 1 that turns to.On the cross road of G3 track connection, be provided with the corresponding row vehicle bridge 1 of craspedodrome.The left side at above-mentioned track center line: be provided with H1, H2, H3 track.On the left side, H3 track, be provided with a lane auxiliary 3.Below the bridge track in southern side, cross road, from north southward, be provided with successively first, second corresponding road 2 that connects.
On the right of the center line of track, north side, vertical cross road: be provided with longitudinally B1, B2, B3 track.On the right, B3 track, be provided with a lane auxiliary 3.On the cross road of B1, the connection of B2 track, be provided with the corresponding row vehicle bridge 1 that turns to; On the cross road of B3 track connection, be provided with the corresponding row vehicle bridge 1 of craspedodrome.The left side at above-mentioned track center line: be provided with A1, A2, A3 track.On the left side, A3 track, a lane auxiliary 3 is set.Below the bridge track of north side, cross road, from Nan Wangbei, be provided with successively first, second corresponding road 2 that connects.
The right in the face of track, east side, cross road center line is provided with C1, C2, C3 track successively.On the left side of above-mentioned track center line, be provided with successively E1, E2, E3 track.
The right in the face of track, west side, cross road center line is provided with F1, F2, F3 track successively.On the left side of above-mentioned track center line, be provided with successively D1, D2, D3 track.
The below is illustrated the Vehicle Driving Cycle process, for example:
One, when vehicle in the face of on the track, south, cross road:
1, vehicle is in the face of on the G1 track, south, cross road, in the time of turning left to the D2 track, west, cross road:
Vehicle is on the G1 track, to overtake on the corresponding row vehicle bridge 1 that turns to, drive on the North track in this bridge track, drive to the north, cross road, connect on the road 2 from south toward second northern correspondence, under left-hand rotation connects bridge of overhead travelling crane track on the cross road to the B1 track, under this bridge track, pass, through the B2 track, under left-hand rotation connects bridge of overhead travelling crane track on the cross road to the B3 track, under this bridge track, travel southwards, in D2 track, west, cross road and joint, cross road, turning right drives on the D2 track in west, cross road.
2, vehicle is being faced on the G3 track, south, cross road, in the time of turning right on the E3 track, east, cross road:
Vehicle is on the G3 track, and right lateral sails on the lane auxiliary 3 on the right, G3 track forward, northwards travels, and in E3 track, east, cross road and joint, cross road, turns right, and drives on the E3 track in the east, cross road.
3, vehicle is being faced on the G3 track, cross road, keep straight on when sailing on the A3 track, the north, cross road:
Vehicle on the corresponding row vehicle bridge 1 of keeping straight on, drives on the North track in this bridge track on the G3 track to overtake, drives on the A3 track on the north, cross road.
Two, when vehicle in the face of on the track, the north, cross road:
1, vehicle is in the face of on the B1 track, the north, cross road, in the time of turning left to the cross road in the east on the E2 track:
Vehicle is on the B1 track, to overtake on the corresponding row vehicle bridge 1 that turns to, drive on the track, the south in this bridge track, drive to south, cross road, connect on the road 2 from southern second correspondence, under left-hand rotation connects bridge of overhead travelling crane track on the cross road to the G1 track, under this bridge track, pass, through the G2 track, turn left to drive under the bridge of overhead travelling crane track of G3 track connection, under this bridge track, northwards travel, in E2 track, east, cross road and joint, cross road, turning right drives on the E2 track in the east, cross road.
2, vehicle is being faced on the B3 track, the north, cross road, in the time of turning right on the D3 track, west, cross road:
Vehicle is on the B3 track, and right lateral sails on the lane auxiliary 3 on the right, B3 track, travels southwards, in D3 track, west, cross road and joint, cross road, turns right, and drives on the D3 track in west, cross road.
3, vehicle in the face of on the B3 track, the north, cross road, to keep straight on when sailing on the H3 track, south, cross road:
Vehicle on the corresponding row vehicle bridge 1 of keeping straight on, drives on the track, the south in this bridge track on the B3 track to overtake, drives on the H3 track in south, cross road.
Three, when vehicle in the face of cross road in the east on the track:
1, vehicle in the face of the cross road in the east on the C2 track, in the time of will turning left to the H2 track, south, cross road:
Vehicle is on the C2 track, drive under the bridge of overhead travelling crane track in connection cross road, A3 track, the north, cross road, right lateral sails on the north, cross road, first the corresponding connection road 2 from south toward north, under the bridge of overhead travelling crane track on A2, A1, the connection cross road, B1 track, pass, drive on the B2 track, turning left drives on the corresponding row vehicle bridge 1 that turns on the connection cross road, B2 track, drives on the H2 track that connect, south, cross road, this bridge track.
2, vehicle in the face of the cross road in the east on the C3 track, in the time of will turning right on the A3 track on the north, cross road:
Vehicle on the C3 track to overtake, the east that connects the bridge of overhead travelling crane in cross road in A3 track, the north, cross road, in C3 track and lane auxiliary 3 joints of facing the left side, A3 track, the north, cross road, turn right, drive on the lane auxiliary 3 on the left side, A3 track, left lateral sails on the A3 track on the north, cross road forward.
3, vehicle in the face of the cross road in the east on the C1 track, to keep straight on when sailing on the D1 track, west, cross road:
Vehicle on the C1 track to overtake to the cross road, under the bridge of overhead travelling crane track on the longitudinal crossing cross road, pass, drive on the D1 track in west, cross road.
Four, when vehicle in the face of on the track, west, cross road:
1, vehicle is in the face of on the F2 track, in the time of turning left to the A2 track, the north, cross road:
Vehicle is on track, F2 place, drive under the bridge of overhead travelling crane track on the connection cross road, H3 track, south, cross road, right lateral sail to south, cross road, from north first corresponding connection on road 2 southward, under the bridge of overhead travelling crane on H2, H1 track, the connection cross road, G1 track, pass, drive on the G2 track, turning left drives on the corresponding row vehicle bridge 1 on the connection cross road, G2 track, that turn to, drives on the A2 track of this bridge track the North connection, northwards travels.
2, vehicle is on facing F3 track, west, cross road, in the time of will turning right on the H3 track, south, cross road:
Vehicle on the F3 track to overtake, the west that connects the bridge of overhead travelling crane on the cross road in H3 track, south, cross road, turning right drives on the lane auxiliary 3 that arranges in the face of the left side, H3 track, south, cross road, and on this track, left lateral sails on the H3 track in south, cross road forward.
3, vehicle in the face of on the F1 track, west, cross road, keep straight on sails to the cross road in the east on the E1 track time:
Vehicle on the F1 track to overtake to the cross road, under the bridge of overhead travelling crane track on the longitudinal crossing cross road, pass, drive on the E1 track in the east, cross road.
In the present embodiment, the corresponding both sides that connect road 2 are provided with the isolation strip, and the isolation strip is greenbelt.
Embodiment three:
By Fig. 5, Fig. 6 as seen, in the present embodiment: in vertical both sides, cross road, connect respectively the six-lane that vertically travels in opposite directions.In cross road both lateral sides, connect respectively the six-lane that laterally travels in opposite directions.Longitudinally the track of road is provided with corresponding row vehicle bridge 1 on the cross road, is provided with the corresponding road 2 that connects below corresponding row vehicle bridge 1.Be provided with lane auxiliary 3 in the outside in track on both sides of the road in vertical road.
On the right in the face of track, southern side, vertical cross road center line: be provided with G1, G2, G3 track.On the right, G3 track, be provided with a lane auxiliary 3.On the cross road of G1 track connection, be provided with the corresponding row vehicle bridge 1 of craspedodrome; On the cross road of G2, the connection of G3 track, be respectively equipped with the corresponding row vehicle bridge 1 that turns to; Connect the right of the corresponding row vehicle bridge 1 that turns on the cross road in the G3 track, be provided with service bridge 4.The left side at above-mentioned track center line: be provided with H1, H2, H3 track.On the left side, H3 track, be provided with successively first, second lane auxiliary 3.Below the bridge track in southern side, cross road, from north southward, be provided with successively first, second, third, fourth corresponding road 2 that connects.
On the right in the face of track, north side, cross road center line: be provided with B1, B2, B3 track.On the right, B3 track, be provided with a lane auxiliary 3.On the cross road of B1 track connection, be provided with the corresponding row vehicle bridge 1 of craspedodrome; On the cross road of B2, the connection of B3 track, be respectively equipped with the corresponding row vehicle bridge 1 that turns to; Connect the right of the corresponding row vehicle bridge 1 that turns on the cross road in the B3 track, be provided with service bridge 4.The left side at above-mentioned track center line: be provided with A1, A2, A3 track.On the left side, A3 track, be provided with successively first, second lane auxiliary 3.Below the bridge track of north side, cross road, from Nan Wangbei, be provided with successively first, second, third, fourth corresponding road 2 that connects.
The right in the face of track, east side, cross road center line is provided with C1, C2, C3 track.On the left side of above-mentioned track center line, be provided with E1, E2, E3 track.On the left side, E3 track, be provided with successively first, second lane auxiliary 3.
The right in the face of track, west side, cross road center line is provided with F1, F2, F3 track.On the left side of above-mentioned track center line, be provided with D1, D2, D3 track.On the left side, D3 track, be provided with successively first, second lane auxiliary 3.
The below is illustrated the process of Vehicle Driving Cycle, for example:
One, when vehicle in the face of on the track, south, cross road:
1, vehicle is in the face of on the G2 track, south, cross road, in the time of turning left to the D3 track, west, cross road:
Vehicle is on the G2 track, to overtake on the corresponding row vehicle bridge 1 that turns to, on the track of this bridge track the North, drive on the north, cross road, from south on first northern corresponding connection road 2, turn left, pass under the bridge track on cross road north A1, B1, B2, the connection cross road, B3 track, the lane auxiliary 3 through in the face of the right, B3 track, the north, cross road drives on the D3 track in west, cross road.
2, vehicle is being faced on the G3 track, south, cross road, in the time of turning right on the E3 track, east, cross road:
Vehicle is on the G3 track, right lateral sails on the lane auxiliary 3 on the right, northwards travel, with in the face of second left lane auxiliary 3 joints, E3 track in the east, cross road, turn right, drive on second lane auxiliary 3 on the left side, E3 track, left lateral sails on first lane auxiliary 3 on the left side, E3 track, and left lateral sails on the E3 track in the east, cross road.
3, vehicle is being faced on the G1 track, south, cross road, in the time of on the A1 track, the north, cross road of keeping straight on:
Vehicle on the corresponding row vehicle bridge 1 of keeping straight on, on the North track in this bridge track, drives on the A1 track on the north, cross road on the G1 track to overtake.
4, vehicle is being faced on the G3 track in south, cross road, do in the cross road when returning driving:
Vehicle is on the G3 track, to overtake to south, cross road, the 4th correspondence connects on the road 2 southward from north, turn left, under the bridge of overhead travelling crane track on G2, G1, the connection cross road, H1 track, pass, drive on the H2 track, turn left, travel southwards along the H2 track, cause this vehicle can accomplish to return driving.
Two, when vehicle in the face of on the track, the north, cross road:
1, vehicle is in the face of on the B2 track, the north, cross road, in the time of turning left to the cross road in the east on the E3 track:
Vehicle is on the B2 track, to overtake on the corresponding row vehicle bridge 1 that turns to, drive on the track, the south in this bridge track, drive to south, cross road from southern, first corresponding connection road 2, turn left, under the bridge of overhead travelling crane track on cross road south H1, G1, G2, the connection cross road, G3 track, pass, through the lane auxiliary 3 in the face of the right, G3 track, south, cross road, drive on the E3 track in the east, cross road.
2, vehicle is being faced on the B3 track, the north, cross road, in the time of turning right on the D3 track, west, cross road:
Vehicle is on the B3 track, right lateral sails on the lane auxiliary 3 on the right, B3 track, with in the face of second left lane auxiliary 3 joints, D3 track, west, cross road, drive to the right on second lane auxiliary 3 on the left side, B3 track, left lateral sails on first lane auxiliary 3 on the left side, D3 track, and left lateral sails on the D3 track in west, cross road.
3, vehicle is being faced on the B1 track, the north, cross road, in the time of on the H1 track, south, cross road of keeping straight on:
Vehicle on the corresponding row vehicle bridge 1 of keeping straight on, drives on the track, the south in this bridge track on the B1 track to overtake, drives on the H1 track in south, cross road.
4, vehicle is being faced on the B3 track on the north, cross road, do in the cross road when returning driving:
Vehicle is on the B3 track, to overtake on the north, cross road, from south toward northern, the 4th corresponding downlink connection road 2, turn left, under the bridge of overhead travelling crane track on B2, B1, the connection cross road, A1 track, pass, drive on the A2 track, turn left, northwards travel along the A2 track, cause this vehicle can accomplish to return driving.
Three, when vehicle in the face of cross road in the east on the track:
1, vehicle is in the face of cross road in the east on the C3 track, in the time of turning left to the H3 track, south, cross road:
Vehicle westwards travels on the C3 track, with in the face of second lane auxiliary 3 joint on the left side, A3 track, the north, cross road, drive to the right on the lane auxiliary 3 on the left side, A3 track, on this track, right lateral sails on the north, cross road forward, from south toward north, the 3rd corresponding the connection on the road, westwards travel, first lane auxiliary 3 through the left side, A3 track, under the bridge of overhead travelling crane track on the connection cross road, A3 track, pass, through the A2 track, at A1, B1, pass under the bridge of overhead travelling crane track on the connection cross road, B2 track, drive on the B3 track, on this track, turning left drives on the corresponding row vehicle bridge 1 that turns on this connection cross road, track, on the track, the south in this bridge track, drive on the H3 track in south, cross road.
2, vehicle is in the face of C3 track, east, cross road, in the time of will turning right on the A3 track, the north, cross road:
Vehicle westwards travels on the C3 track, with in the face of second lane auxiliary 3 joint on the left side, A3 track, the north, cross road, drive to the right on second lane auxiliary 3 on the left side, A3 track, northwards left lateral is to first lane auxiliary 3 on the left side, A3 track, and northwards left lateral is to the A3 track on the north, cross road.
3, vehicle is on the C1 that faces east, cross road, C2 track, in the time of on keep straight on cross road west D1, the D2 track:
Vehicle to the cross road, passes under the bridge of overhead travelling crane track on the longitudinal crossing cross road on C1, C2 track to overtake, respectively to overtake on the D1 in west, cross road, D2 track.
4, vehicle is being faced on the C3 track, east, cross road, do when returning driving:
Vehicle westwards travels on the C3 track, with in the face of second lane auxiliary 3 joint on the left side, A3 track, the north, cross road, drive to the right on this lane auxiliary 3, on this track, right lateral sails on the north, cross road forward, from south toward north, the 3rd corresponding the connection on the road, westwards travel, first lane auxiliary 3 through the left side, A3 track, under the bridge of overhead travelling crane track on the connection cross road, A3 track, pass, through the A2 track, at A1, B1, pass under the bridge of overhead travelling crane track on the connection cross road, B2 track, drive on the B3 track, on this track, turn left and drive on the corresponding row vehicle bridge 1 that turns on this connection cross road, track, on this bridge of overhead travelling crane track, right lateral sails on the service bridge 4, on the track of service bridge 4 souths connection, drive to south, cross road from southern second corresponding connection on the road 2, turn left, travel eastwards, under the bridge of overhead travelling crane track on the connection cross road, H3 track, pass, through the H2 track, at H1, G1, G2, pass under the bridge of overhead travelling crane track on the connection cross road, G3 track, drive on first lane auxiliary 3 in the face of the left side, E3 track, east, cross road, upper left driving on the E3 track in the east, cross road causes this vehicle can accomplish to return driving in this track.
Four, when vehicle in the face of on the track, west, cross road:
1, vehicle is in the face of on the F3 track, west, cross road, in the time of will turning left to the A3 track, the north, cross road:
Vehicle travels eastwards on the F3 track, with in the face of second lane auxiliary 3 joint on the left side, H3 track, south, cross road, drive to the right on the above-mentioned lane auxiliary 3, on this track, right lateral sails in south, cross road forward, from southern, the 3rd corresponding the connection on the road, travel eastwards, first lane auxiliary 3 through the left side, H3 track, under the bridge of overhead travelling crane track on the connection cross road, H3 track, pass, through the H2 track, at H1, G1, pass under the bridge of overhead travelling crane track on the connection cross road, G2 track, drive on the G3 track, on this track, turning left drives to this track and connects on the corresponding row vehicle bridge 1 that turns on cross road, drives on the A3 track on the north, cross road that this North track, bridge track connects.
2, vehicle is on facing F3 track, west, cross road, in the time of will turning right on the H3 track, south, cross road:
Vehicle travels eastwards on the F3 track, with in the face of second lane auxiliary 3 joint on the left side, H3 track, south, cross road, drive to the right on this lane auxiliary 3, on this track, left lateral to the south is to first lane auxiliary 3 on the left side, H3 track, and left lateral sails on the H3 track in south, cross road forward.
3, vehicle is on the F1 that faces west, cross road, F2 track, in the time of on keep straight on east, cross road E1, the E2 track:
Vehicle to the cross road, passes under the bridge of overhead travelling crane track in longitudinal crossing cross road on F1, F2 track to overtake, respectively to overtake in the east E1 of cross road, E2 track.
4, vehicle is being faced on the F3 track, west, cross road, do when returning driving:
Vehicle travels eastwards on the F3 track, with in the face of second lane auxiliary 3 joint on the left side, H3 track, south, cross road, drive to the right on the above-mentioned lane auxiliary 3, on this track, right lateral sails in south, cross road forward, from southern, the 3rd corresponding the connection on the road, travel eastwards, first lane auxiliary 3 through the left side, H3 track, under the bridge of overhead travelling crane track on the connection cross road, H3 track, pass, through the H2 track, at H1, G1, pass under the bridge of overhead travelling crane track on the connection cross road, G2 track, drive on the G3 track, on this track, turn left and drive on the corresponding row vehicle bridge 1 that turns on this connection cross road, track, on this bridge track, right lateral sails on the service bridge 4, on the track that service bridge 4 the Norths connect, drive to the north, cross road, second corresponding connection on the road 2 from south toward north, turn left, westwards travel, under the bridge of overhead travelling crane track on the connection cross road, A3 track, pass, through the A2 track, at A1, B1, B2, pass under the bridge of overhead travelling crane track on the connection cross road, B3 track, drive on the lane auxiliary 3 in west, B3 track, drive in the face of on first lane auxiliary 3 on the left side, D3 track, west, cross road, on this track, left lateral sails on the D3 track, west, cross road, causes this vehicle can accomplish to return driving.
In the present embodiment, the corresponding both sides that connect road 2 are provided with the driving shielding wire.
Embodiment four:
By Fig. 7, Fig. 8 as seen, in the present embodiment: in vertical both sides, cross road, connect respectively the six-lane that vertically travels in opposite directions.In cross road both lateral sides, connect respectively the six-lane that laterally travels in opposite directions.Longitudinally the track of road is provided with corresponding row vehicle bridge 1 on the cross road, is provided with the corresponding road 2 that connects below corresponding row vehicle bridge 1.Outside at the runway on four limits, cross road is respectively equipped with lane auxiliary 3.There are respectively vertical road of certain distance and belt road to be provided with service bridge 4 at four sides, distance cross road.
On the right in the face of track, south, vertical cross road center line: be provided with G1, G2, G3 track.On the right, G3 track, be provided with successively first, second, third lane auxiliary 3.On the cross road of G1 track connection, be provided with the corresponding row vehicle bridge 1 that turns to; On the cross road of G2, the connection of G3 track, be provided with the corresponding row vehicle bridge 1 of craspedodrome; On the cross road that first lane auxiliary 3 on the right of the G3 track connects, be provided with again a corresponding row vehicle bridge 1 that turns to.Be arranged on the bridge lane length of the corresponding row vehicle bridge 1 on G2, G3 and the above-mentioned lane auxiliary, than the bridge track of the corresponding row vehicle bridge 1 that arranges on the G1 track, in south, cross road, will grow at least two more than the track.Under the bridge track on G2, G3 and the above-mentioned lane auxiliary, from north southward, be provided with successively first, second corresponding road 2 that connects.The left side at above-mentioned track center line: be provided with H1, H2, H3 track.On the left side, H3 track, be provided with successively first, second, third lane auxiliary 3.Having on the track of a segment distance with south, cross road, on second lane auxiliary 3 on the left side, H3 track to first lane auxiliary 3 on G3 track the right, be provided with service bridge 4.
On the right in the face of track, the north, cross road center line: be provided with B1, B2, B3 track.On the right, B3 track, be provided with successively first, second, third lane auxiliary 3.On the cross road of B1 track connection, be provided with the corresponding row vehicle bridge 1 that turns to; On the cross road of B2, the connection of B3 track, be provided with the track of the corresponding row vehicle bridge 1 of craspedodrome; On the cross road that first lane auxiliary 3 on the right of the B3 track connects, be provided with again a corresponding row vehicle bridge 1 that turns to.Be arranged on the bridge lane length of the corresponding row vehicle bridge 1 on B2, B3 and the above-mentioned lane auxiliary, than the bridge track of the corresponding row vehicle bridge 1 that arranges on the B1 track, on the north, cross road, will grow at least two more than the track.Establish under the bridge track of making at B2, B3 and above-mentioned lane auxiliary, from Nan Wangbei, be provided with successively first, second corresponding road 2 that connects.The left side at above-mentioned track center line: be provided with A1, A2, A3 track.On the left side, A3 track, be provided with successively first, second, the 3rd lane auxiliary 3.Having on the track of a segment distance with the north, cross road, at second lane auxiliary 3 on the left side, A3 track, to first lane auxiliary 3 on the right, B3 track, be provided with service bridge 4.
On the right in the face of track, east, cross road center line: be provided with C1, C2, C3 track.On the right, C3 track, be provided with successively first, second lane auxiliary 3.The left side at above-mentioned track center line: be provided with E1, E2, E3 track.On the left side, E3 track, be provided with successively first, second lane auxiliary 3.Having in the east on the track of a segment distance with the cross road, on first lane auxiliary 3 to C3 tracks on the left side, E3 track, be provided with service bridge 4.
On the right in the face of track, west, cross road center line: be provided with F1, F2, F3 track.On the right, F3 track, be provided with successively first, second lane auxiliary 3.The left side at above-mentioned track center line: be provided with D1, D2, D3 track.On the left side, D3 track, be provided with successively first, second lane auxiliary 3.Having on the track of a segment distance with west, cross road, on first lane auxiliary 3 to F3 tracks on the left side, D3 track, be provided with service bridge 4.
The below is illustrated the process of Vehicle Driving Cycle, for example:
One, when vehicle in the face of on the track, south, cross road:
1, vehicle is in the face of on the G1 track, south, cross road, in the time of turning left to the D3 track in west, cross road:
Vehicle is on the G1 track, drive to south, cross road, from southern second corresponding connection on the road 2, turn right and travel, at G2, G3, and first lane auxiliary 3 connections on the right, G3 track, pass under the bridge of overhead travelling crane on the cross road, drive on second lane auxiliary 3 on the right, G3 track, northwards travel, with in the face of first lane auxiliary 3 joints on the left side, E3 track in the east, cross road, turn right, drive on first lane auxiliary 3 on the left side, E3 track, drive in this track on the bridge road, the south of service bridge 4, northwards travel along this bridge road, on the C3 track that this bridge road the North connects, westwards travel, under the bridge of overhead travelling crane track in longitudinal crossing cross road, pass, drive on the D3 track in west, cross road.
2, vehicle is being faced on the G3 track, south, cross road, in the time of turning right on the E3 track, east, cross road:
Vehicle is on the G3 track, right lateral is to first, second, third lane auxiliary 3 on the right, G3 track forward, northwards travel, with in the face of second lane auxiliary 3 joint on the left side, E3 track in the east, cross road, turn right and drive on second lane auxiliary 3 on the left side, E3 track, left lateral sails on first lane auxiliary 3 on the left side, E3 track forward, and left lateral sails on the E3 track in the east, cross road forward.
When 3, vehicle is in the face of cross road south G2, G3 track, on will keep straight on cross road north A2, the A3 track:
Vehicle to overtake to connecting respectively on the corresponding row vehicle bridge 1 of keeping straight on the cross road, on the North track in bridge track, drives to respectively on the A2, A3 track on the north, cross road on G2, G3 track.
Two, when vehicle in the face of on the track, the north, cross road:
1, vehicle is in the face of on the B1 track, the north, cross road, in the time of turning left to the E3 track in the east, cross road:
Vehicle is on the B1 track, drive to the north, cross road, second corresponding connection on the road 2 from south toward north, turn right and travel, at B2, first lane auxiliary 3 on B3 and the right, B3 track connects, pass under the bridge of overhead travelling crane track on the cross road, drive on second lane auxiliary 3 on the right, B3 track, travel southwards, with in the face of first left lane auxiliary 3 joints, D3 track, west, cross road, turn right and drive on this lane auxiliary 3, drive in this track on the North bridge road of service bridge 4, travel southwards along this bridge road, on the F3 track of this south, bridge track connection, travel eastwards, under the bridge of overhead travelling crane track in longitudinal crossing cross road, pass, to overtake to the track of cross road E3 in the east.
2, vehicle is in the face of on the B3 track, the north, cross road, in the time of turning right on the D3 track in west, cross road:
Vehicle is on the B3 track, right lateral sails on first, second, third lane auxiliary 3 on B3 track the right and travels southwards forward, with in the face of second lane auxiliary 3 joint on the left side, D3 track, west, cross road, turn right and drive on second lane auxiliary 3 on the left side, D3 track, left lateral sails on first lane auxiliary 3 on the left side, D3 track forward, and left lateral sails on the D3 track in west, cross road forward.
3, vehicle is in the face of on the cross road north B2, B3 track, on the H2 in the south, cross road of will keeping straight on, H3 track the time:
Vehicle to overtake to connecting respectively on the corresponding row vehicle bridge 1 of keeping straight on the cross road, on the track, the south in this bridge track, drives to respectively on the H2, H3 track in south, cross road on B2, B3 track.
Three, when vehicle in the face of cross road in the east on the track:
1, in this programme, illustrating of two kinds of left-hand rotation modes done in the driving on the track, east, cross road.
The first, when vehicle in the cross road C3 track in the east, in the time of turning left to the H1 track in south, cross road:
Vehicle is on the C3 track, right lateral sails on first lane auxiliary 3 on the right, C3 track forward, westwards travel under the bridge track of on crossing over cross road corresponding row vehicle bridge 1 the North outside the north side, travel outside north side, cross road, at C3, on the lane auxiliary 3 that arranges outside the north side, D3 track, under the bridge of overhead travelling crane track of west, cross road ragged edge, turning right, drive to the north, cross road, from south toward first corresponding connection on the road 2 in north, at first lane auxiliary 3 in the face of the right, B3 track, the north, cross road, and B3, pass under the bridge of overhead travelling crane track in connection cross road, B2 track, turn right, drive on the corresponding row vehicle bridge 1 that turns on the connection cross road, B1 track, drive to southwards along this bridge track on the H1 track in south, cross road.
The second, when vehicle in the cross road C3 track in the east, in the time of turning left to the H3 track in south, cross road:
Vehicle is on the C3 track, right lateral sails on first lane auxiliary 3 on the right, C3 track forward, in this track and in the face of second left lane auxiliary 3 joints, A3 track, the north, cross road, turn right, drive to the left side, A3 track second lane auxiliary 3 on, drive on the east bridge track of service bridge 4, drive to this bridge west end place, bridge track, on first lane auxiliary 3 in the face of the right, B3 track, the north, cross road, drive on the corresponding row vehicle bridge 1 that turns on these lane auxiliary 3 connection cross roads, on the track, the south in this bridge track, drive to southwards on first lane auxiliary 3 in the face of the left side, H3 track, south, cross road, left lateral sails on the H3 track in south, cross road forward.
2, vehicle is in the face of C3 track in the east, cross road, in the time of turning right on the A3 track on the north, cross road:
Vehicle is on the C3 track, right lateral sails on first, second lane auxiliary 3 on the right, C3 track forward, with in the face of the 3rd lane auxiliary 3 joints on the left side, A3 track, the north, cross road, turn right, drive on the 3rd lane auxiliary 3 on the left side, A3 track, northwards left lateral sail to the left side, A3 track second, on first lane auxiliary 3, northwards left lateral sails on the A3 track on the north, cross road.
3, vehicle is being faced cross road in the east C1, C2 track, on keep straight on cross road west D1, the D2 track:
Vehicle drives to respectively forward on the cross road on C1, C2 track, passes under the bridge of overhead travelling crane track in longitudinal crossing cross road, drives to respectively on the D1, D2 track in west, cross road.
Four, when vehicle in the face of on the track, west, cross road:
1, in this programme, illustrating of two kinds of left-hand rotation modes done in the driving on the track, west, cross road.
The first, when vehicle in F3 track, west, cross road, in the time of turning left to the A1 track on the north, cross road:
Vehicle is on the F3 track, right lateral sails on first lane auxiliary 3 on the right, F3 track forward, travel eastwards under the bridge track of on crossing over cross road corresponding row vehicle bridge 1 south outside the southern side, travel outside southern side, cross road, at F3, on the lane auxiliary 3 that arranges outside the north side, E3 track, under the bridge of overhead travelling crane track of east, cross road ragged edge, turning right, drive to south, cross road, from southern first corresponding connection on the road 2, at first lane auxiliary 3 in the face of the right, G3 track, south, cross road, and G3, pass under the bridge of overhead travelling crane track on the connection cross road, G2 track, turn right, drive on the corresponding row vehicle bridge 1 that turns on the connection cross road, G1 track, northwards drive to along this bridge track on the A1 track on the north, cross road.
The second, when vehicle in F3 track, west, cross road, in the time of will turning left to the A3 track on the north, cross road:
Vehicle is on the F3 track, right lateral sails on first lane auxiliary 3 on the right, F3 track forward, in this track and in the face of second left lane auxiliary 3 joints, H3 track, south, cross road, turn right, drive to the left side, H3 track second lane auxiliary 3 on, drive on the end bridge road, west of service bridge 4, drive to this east place, bridge road, on first lane auxiliary 3 in the face of the right, G3 track, south, cross road, drive on the corresponding row vehicle bridge 1 that turns on these lane auxiliary 3 connection cross roads, on the North track in this bridge track, northwards drive on first lane auxiliary 3 in the face of the left side, A3 track, the north, cross road, left lateral sails on the A3 track on the north, cross road forward.
2, vehicle is in the face of F3 track, west, cross road, in the time of turning right on the H3 track in south, cross road:
Vehicle is on the F3 track, right lateral sails on first, second lane auxiliary 3 on the right, F3 track forward, with in the face of the left side, H3 track, south, cross road, the 3rd lane auxiliary 3 joints, turn right, drive on the 3rd lane auxiliary 3 on the left side, H3 track, left lateral to the south sail to the H3 track second, on first lane auxiliary 3, left lateral to the south sails on the H3 track in south, cross road.
3, vehicle is being faced cross road west F1, F2 track, on keep straight on east, cross road E1, the E2 track:
Vehicle on the cross road that travels respectively forward, passes under the bridge of overhead travelling crane track in longitudinal crossing cross road on F1, F2 track, drives to respectively in the east E1 of cross road, the E2 track.
In the present embodiment, the corresponding both sides that connect road 2 are provided with the isolation strip, and the isolation strip is the driving shielding wire.
Embodiment five:
By Fig. 9, Figure 10 as seen, in the present embodiment: in vertical both sides, cross road, connect respectively the six-lane that vertically travels in opposite directions.In cross road both lateral sides, connect respectively the six-lane that laterally travels in opposite directions.Longitudinally the track of road is provided with corresponding row vehicle bridge 1 on the cross road, is provided with the corresponding road 2 that connects below corresponding row vehicle bridge 1.Outside at the runway on four limits, cross road is respectively equipped with lane auxiliary 3.Also be provided with the ground downlink track 5 of craspedodrome on vertically road and belt road intersect on the cross road that forms the track of road longitudinally, the phase dealings of the top in the ground downlink track 5 of craspedodrome is made as horizontal craspedodrome road.
On the right in the face of track, southern side, cross road center line: be provided with G1, G2, G3 track.The right in the G3 track is provided with first, second lane auxiliary 3.Under the cross road of G1, the connection of G2 track, be provided with the ground downlink track 5 of the craspedodrome of from south to north, passing the cross road.On G3 and G3 the right first, on the cross road that lane auxiliary 3 connects, be respectively equipped with the corresponding row vehicle bridge 1 that turns to.The left side at above-mentioned track center line: be provided with H1, H2, H3 track.On the left side, H3 track, be provided with successively first, second lane auxiliary 3.H1, H2 track connect respectively the ground downlink track 5 of the craspedodrome of passing the cross road from north to south.H3 and H3 first left, lane auxiliary 3, connect respectively the corresponding row vehicle bridge 1 that turns to that from north to south, strides across the cross road.Below the bridge track in southern side, cross road and above the underground track, from north to south, be provided with successively first, second corresponding road 2 that connects.
On the right in the face of track, north side, cross road center line: be provided with B1, B2, B3 track.The right in the B3 track is provided with first, second lane auxiliary 3.On the cross road of B1, the connection of B2 track, be provided with the ground downlink track 5 of the craspedodrome of from north to south, passing the cross road.On the cross road of B3 and first lane auxiliary 3 connections of B3 the right, be respectively equipped with the corresponding row vehicle bridge 1 that turns to.The left side at above-mentioned track center line: be provided with A1, A2, A3 track.On the left side, A3 track, be provided with successively first, second lane auxiliary 3.A1, A2 track connect respectively the ground downlink track 5 of the craspedodrome of passing the cross road from south to north.The lane auxiliary 3 of A3 and A3 first left connects respectively the corresponding row vehicle bridge 1 that turns to that strides across the cross road from south to north.Below the bridge track of north side, cross road and above the underground track, from south to north, be provided with successively first, second disjoint corresponding road 2 that connects.
The right in the face of track, east side, cross road center line is provided with C1, C2, C3 track.The right in the C3 track is provided with a lane auxiliary 3.On the left side of above-mentioned track center line, be provided with E1, E2, E3 track.On the left side, E3 track, be provided with a lane auxiliary 3.
The right in the face of track, west side, cross road center line is provided with F1, F2, F3 track.The right in the F3 track is provided with a lane auxiliary 3.On the left side of above-mentioned track center line, be provided with D1, D2, D3 track.On the left side, D3 track, be provided with a lane auxiliary 3.
The below is illustrated the process of Vehicle Driving Cycle, for example:
One, when vehicle in the face of on the track, south, cross road:
1, vehicle is in the face of on the G3 track, south, cross road, in the time of turning left to the D3 track in west, cross road:
Vehicle is on the G3 track, right lateral sails on first lane auxiliary 3 on the right, G3 track, drive on the corresponding row vehicle bridge 1 that turns on the cross road, the North in this bridge track, drive in the face of on first lane auxiliary 3 on the left side, A3 track, the north, cross road, drive to north side, cross road, from south to north, first corresponding connection on road 2.Turn left and travel, under the bridge of overhead travelling crane track on the connection cross road, A3 track, north side, cross road, pass, turn left drive in the face of the cross road in the east, laterally on the right, cross road of track center line on from the east to the west the ragged edge track, along this lanes to the D3 track in west, cross road.
2, vehicle is being faced on the G3 track, south, cross road, in the time of turning right on the E3 track, east, cross road:
Vehicle is on the G3 track, right lateral sails on first, second lane auxiliary 3 on the right, G3 track, northwards travel, with in the face of lane auxiliary 3 intersections on the left side, E3 track in the east, cross road, turn right, drive on the lane auxiliary 3 on the left side, E3 track, on this track, left lateral sails on the E3 track in the east, cross road forward.
3, vehicle is being faced on cross road south G1, the G2 track, in the time of on keep straight on cross road north A1, the A2 track:
Vehicle passes respectively 5 li in the ground downlink track of the craspedodrome under the cross road to overtake on G1, G2 track, respectively to overtake on the A1 on the north, cross road, A2 track.
Two, when vehicle in the face of on the track, the north, cross road:
1, vehicle is in the face of on the B3 track, the north, cross road, in the time of turning left to the cross road in the east on the track of E3:
Vehicle is on the B3 track, right lateral sails on first lane auxiliary 3 on the right, B3 track, drive on the corresponding row vehicle bridge 1 that turns on the cross road, the south in this bridge track, drive in the face of on first lane auxiliary 3 on the left side, H3 track, south, cross road, drive to southern side, cross road, from north to south, first corresponding connection on road 2.Turn left and travel, under the bridge of overhead travelling crane track on the connection cross road, H3 track, southern side, cross road, pass, turning left drives in the face of west, cross road, laterally on the right, cross road of track center line on the ragged edge track from the west to east, along this lanes to the cross road in the east the E3 track.
2, vehicle is being faced on the B3 track, the north, cross road, in the time of turning right on the D3 track, west, cross road:
Vehicle is on the B3 track, right lateral sail to B3 track the right first, on second lane auxiliary 3, travel southwards, with in the face of lane auxiliary 3 intersections on the left side, D3 track, west, cross road, turn right, drive on the lane auxiliary 3 on the left side, D3 track, on this track, left lateral sails on the D3 track in west, cross road forward.
3, vehicle is being faced on cross road north B1, the B2 track, in the time of on keep straight on cross road south H1, the H2 track:
Vehicle passes respectively 5 li in the ground downlink track of the craspedodrome under the cross road to overtake on B1, B2 track, respectively to overtake on the H1 in south, cross road, H2 track.
Three, when vehicle in the face of cross road in the east on the track:
1, vehicle is in the face of cross road in the east on the C3 track, in the time of turning left to the H3 track, south, cross road:
Vehicle is on the C3 track, right lateral sails on the lane auxiliary 3 on the right, C3 track, to overtake, with in the face of second lane auxiliary 3 intersection on the left side, A3 track, the north, cross road, turn right, drive on second lane auxiliary 3 on the left side, A3 track, on this track, drive on first lane auxiliary 3 on the left side, A3 track, drive to north side, cross road, from south to north, second corresponding connection on the road 2, westwards travel, in A3 track, the north, cross road, connect under the bridge of overhead travelling crane track on the cross road and pass, westwards drive on the B3 track, on this track, turn left, drive on the corresponding row vehicle bridge 1 that turns on the connection cross road, B3 track, on this bridge track, drive to southwards on the H3 track in south, cross road.
2, vehicle is being faced on the C3 track, east, cross road, in the time of turning right on the A3 track, the north, cross road:
Vehicle is on the C3 track, right lateral sails on the lane auxiliary 3 on the right, C3 track, to overtake, with in the face of second lane auxiliary 3 intersection on the left side, A3 track, the north, cross road, turn right, drive on second lane auxiliary 3 on the left side, A3 track, on this track, drive on first lane auxiliary 3 on the left side, A3 track, drive to left on the A3 track on the north, cross road.
3, vehicle is being faced on east, cross road C1, the C2 track, in the time of on keep straight on cross road west D1, the D2 track:
Vehicle to overtake, passes under the bridge track on the longitudinal crossing cross road on C1, C2 track, respectively to overtake on the D1 in west, cross road, D2 track.
Four, when vehicle in the face of on the track, west, cross road,
1, vehicle is on F3 track, west, cross road, in the time of turning left to the A3 track, the north, cross road:
Vehicle is on the F3 track, right lateral is to the lane auxiliary 3 on the right, F3 track, to overtake, with in the face of second lane auxiliary 3 intersection on the left side, H3 track, south, cross road, turn right, drive on second lane auxiliary 3 on the left side, H3 track, on this track, drive on first lane auxiliary 3 on the left side, H3 track, drive to southern side, cross road, second corresponding connection on the road 2 from north to south, travel eastwards, in H3 track, south, cross road, connect under the bridge of overhead travelling crane track on the cross road and pass, drive to eastwards on the G3 track, on this track, turn left, drive on the corresponding row vehicle bridge 1 that turns on the connection cross road, G3 track, on this bridge track, northwards drive on the A3 track on the north, cross road.
2, vehicle is on facing F3 track, west, cross road: in the time of turning right on the H3 track, south, cross road:
Vehicle is on the F3 track, right lateral sails on the lane auxiliary 3 on the right, F3 track, to overtake, with in the face of second lane auxiliary 3 intersection on the left side, H3 track, south, cross road, turn right, drive on second lane auxiliary 3 on the left side, H3 track, on this track, drive on first lane auxiliary 3 on the left side, H3 track, drive to left on the H3 track in south, cross road.
3, when vehicle in the face of the F1 in west, cross road, F2 track, in the time of on keep straight in the east E1 of cross road, the E2 track:
Vehicle to overtake, passes under the bridge of overhead travelling crane track on the longitudinal crossing cross road on F1, F2 track, respectively to overtake in the east E1 of cross road, E2 track.
In the present embodiment, the corresponding both sides that connect road 2 are provided with the isolation strip, and the isolation strip is the driving shielding wire.
Embodiment six:
By Figure 11, Figure 12 as seen, in the present embodiment: in vertical both sides, cross road, connect respectively the Four-Lane Road that vertically travels in opposite directions.In cross road both lateral sides, connect respectively the Four-Lane Road that laterally travels in opposite directions.Longitudinally the track of road is provided with corresponding row vehicle bridge 1 in the cross road, is provided with the corresponding road 2 that connects below corresponding row vehicle bridge 1, is provided with lane auxiliary 3 at vertical road in cross road and the outside in belt road track.Vertical road that certain distance is arranged and belt road in distance cross road are provided with service bridge 4.Longitudinally also be provided with the ground downlink track 6 that turns on the track of road on the cross road.
On longitudinal surface the right to track, south, cross road center line: be provided with G1, G2 track.On the right, G2 track, be provided with successively first, second, third lane auxiliary 3.On the cross road of G1 track connection, be provided with the bridge track of the corresponding row vehicle bridge 1 of craspedodrome.On the cross road of G2 track connection, be provided with the bridge track of the corresponding row vehicle bridge 1 that turns to.On the cross road that second lane auxiliary 3 on the right of the G2 track connects, be provided with the bridge track of the corresponding row vehicle bridge 1 that turns to, on the left side of above-mentioned track center line: be provided with H1, H2 track.On the left side, H2 track, be provided with successively first, second, third lane auxiliary 3.Second lane auxiliary 3 on H1, H2 track and the left side, H2 track, respectively with cross over the cross road from the corresponding connection in southern bridge track.South in the cross road, have on the track of a segment distance, on first lane auxiliary 3 on the right of the G2 track on the H2 track, be provided with the ground downlink track 6 that first turns to, have on the track of a segment distance in above-mentioned genuine south, on second lane auxiliary 3 on the right of the G2 track on first lane auxiliary 3 on the left side, H2 track, be provided with second ground downlink track 6 that turns to.South in the cross road: at first lane auxiliary 3 on G2 track the right, be provided with corresponding connection road 2 with connection road in the face of first lane auxiliary 3 on the left side, E2 track, east, cross road.At first lane auxiliary 3 on the left side, H2 track, be provided with corresponding connection road 2 with connection road in the face of F2 track, west, cross road.
On longitudinal surface the right to track, the north, cross road center line: be provided with B1, B2 track.On the right, B2 track, be provided with first, second, third lane auxiliary 3.On the cross road of B1 track connection, be provided with the track of the corresponding row vehicle bridge 1 of craspedodrome.On the cross road of B2 track connection, be provided with the corresponding row vehicle bridge 1 that turns to.On the cross road that second lane auxiliary 3 on the right of the B2 track connects, be provided with the corresponding row vehicle bridge 1 that turns to.The left side at above-mentioned track center line: be provided with A1, A2 track.On the left side, A2 track, be provided with first, second, third lane auxiliary 3.Second lane auxiliary 3 on A1, A2 track and the left side, A2 track, the bridge track with the corresponding row vehicle bridge 1 from south toward north of crossing over the cross road is connected respectively.The north in the cross road has on the track of a segment distance, on first lane auxiliary 3 on A2 track and the right, B2 track, is provided with the ground downlink track 6 that first turns to.Have on the track of a segment distance on the above-mentioned genuine north, on second lane auxiliary 3 of first lane auxiliary 3 on the right of the B2 track on the left side, A2 track, be provided with second ground downlink track 6 that turns to.The north in the cross road: at first lane auxiliary 3 on B2 track the right, be provided with corresponding connection road 2 with the connection road of first lane auxiliary 3 of facing the left side, D2 track, west, cross road.First lane auxiliary 3 on the left side, A2 track, be provided with corresponding connection road 2 in the connection road in C2 track in the east in the face of the cross road.
On the right in the face of track, east, cross road center line: be provided with C1, C2 track.The left side at above-mentioned track center line: be provided with E1, E2 track.On the left side, E2 track, be provided with successively first, second lane auxiliary 3.
On the right in the face of track, west, cross road center line: be provided with F1, F2 track.The left side at above-mentioned track center line: be provided with D1, D2 track.On the left side, D2 track, be provided with successively first, second lane auxiliary 3.
The below is illustrated the process of Vehicle Driving Cycle, for example:
One, when vehicle in the face of on the track, south, cross road:
1, vehicle is in the face of on the G2 track in south, cross road, in the time of turning left to the D2 track in west, cross road:
Vehicle is on the G2 track, drive on the corresponding row vehicle bridge 1 that turns to, on the track of this bridge track the North, drive to 6 li in first ground downlink track of turning to, the north, cross road, on first lane auxiliary 3 in the face of the right, B2 track, the north, cross road, entrance to a tunncl from this track rolls away from, drive to southwards corresponding the connection on the road 2, with in the face of first lane auxiliary 3 joints on the left side, D2 track, west, cross road, turn right, under the bridge of overhead travelling crane track in longitudinal crossing cross road, pass, drive on first lane auxiliary 3 on the left side, D2 track, on this track, left lateral sails on the D2 track in west, cross road forward.
2, vehicle is being faced on the G2 track in south, cross road, in the time of turning right on the E2 track in the east, cross road:
Vehicle is on the G2 track, right lateral is to first, second, third lane auxiliary 3 on the right, G2 track, with in the face of second lane auxiliary 3 joint on the left side, E2 track in the east, cross road, turn right, drive on second lane auxiliary 3 on the left side, E2 track, on this track, left lateral sails on first lane auxiliary 3 on the left side, E2 track forward, and left lateral sails on the E2 track in the east, cross road forward.
3, vehicle is on the G1 track in south, cross road, in the time of on the A1 track on the north, cross road of keeping straight on:
Vehicle drives on the corresponding row vehicle bridge 1 of craspedodrome on the G1 track, and the North in this bridge track drives on the A1 track on the north, cross road.
Two, when vehicle in the face of on the track, the north, cross road:
1, vehicle is in the face of on the B2 track on the north, cross road, in the time of turning left to the E2 track in the east, cross road:
Vehicle is on the B2 track, drive on the corresponding row vehicle bridge 1 that turns to, on the track of this south, bridge track, drive to 6 li in first ground downlink track of turning to, south, cross road, on first lane auxiliary 3 in the face of the right, G2 track, south, cross road, entrance to a tunncl from this track rolls away from, drive to corresponding the connection on the road 2 northwards, with in the face of first left lane auxiliary 3 joints, E2 track in the east, cross road, turn right, under the bridge of overhead travelling crane track in longitudinal crossing cross road, pass, drive on first lane auxiliary 3 on the left side, E2 track, on this track, left lateral sails on the E2 track in the east, cross road forward.
2, vehicle is in the face of on the B2 track on the north, cross road, in the time of turning right on the D2 track in west, cross road:
Vehicle is on the B2 track, forward right lateral sail to B2 track the right first, second, on the lane auxiliary 3, the 3rd lane auxiliary 3, with in the face of second lane auxiliary 3 joint on the left side, D2 track, west, cross road, turn right, drive on second lane auxiliary 3 on the left side, D2 track, on this track, left lateral sails on first lane auxiliary 3 on the left side, D2 track forward, and left lateral sails on the D2 track in west, cross road forward.
3, vehicle is being faced on the B1 track on the north, cross road, in the time of on the H1 track in the south, cross road of keeping straight on:
Vehicle drives on the corresponding row vehicle bridge 1 of craspedodrome on the B1 track, and the south in this bridge track drives on the H1 track in south, cross road.
Three, when vehicle in the face of cross road in the east on the track:
1, vehicle is in the face of C2 track in the east, cross road, in the time of turning left to the H2 track in south, cross road:
Vehicle travels in the C2 track, under the bridge track of outside, east side on the cross road, pass, forward to the right in the face of north side on the cross road, the left side, A2 track, on first lane auxiliary 3, travel and connect on the road 2 in correspondence, drive to north side on the cross road, 6 li in second ground downlink track that turns on this track, facing north side on the cross road, entrance to a tunncl on second lane auxiliary 3 on the right, B2 track rolls away from, drive to southwards and cross on the cross road, on the corresponding row vehicle bridge 1 that turns to, on the track, the south in this bridge track, drive in the face of second of the left side, H2 track, south, cross road, on first lane auxiliary 3, left lateral sails on the H2 track in south, cross road forward.
2, vehicle is in the face of C2 track in the east, cross road, in the time of turning right on the A2 track on the north, cross road:
Vehicle is on the C2 track, arrive to overtake the cross road in the east, with in the face of north side, the left side, A2 track on the cross road, the 3rd lane auxiliary 3 joints, turn right, drive on this lane auxiliary 3, left lateral sails on second of the left side, A2 track, first lane auxiliary 3 forward, and left lateral sails on the A2 track on the north, cross road forward.
3, vehicle is being faced C1 track in the east, cross road, in the time of on the D1 track, west, cross road of keeping straight on:
Vehicle is on the C1 track, and keeping straight on forward sails on the cross road, passes under the bridge of overhead travelling crane track in longitudinal crossing cross road, and keeping straight on sails on the D1 track in west, cross road.
Four, on vehicle is in the face of track, west, cross road:
1, vehicle is in the face of F2 track, west, cross road, in the time of turning left to the A2 track on the north, cross road:
Vehicle on the F2 track to overtake, under the bridge track of outside, west side on the cross road, pass, forward to the right in the face of southern side on the cross road, the left side, H2 track, on first lane auxiliary 3, travel and connect on the road 2 in correspondence, drive to southern side on the cross road, 6 li in second ground downlink track that turns on this track, facing southern side on the cross road, entrance to a tunncl on second lane auxiliary 3 on the right, G2 track rolls away from, driving to this track northwards connects on the leap cross road, on the corresponding row vehicle bridge 1 that turns to, on the North track in this bridge track, drive in the face of second of the left side, A2 track, the north, cross road, on first lane auxiliary 3, left lateral sails on the A2 track on the north, cross road forward.
2, vehicle is in the face of F2 track, west, cross road, in the time of turning right on the H2 track in south, cross road:
Vehicle is on the F2 track, arrive to overtake west, cross road, with in the face of southern side, the left side, H2 track on the cross road, the 3rd lane auxiliary 3 joints, turn right, drive on this lane auxiliary 3, left lateral sails on second of the left side, H2 track, first lane auxiliary 3 forward, and left lateral sails on the H2 track in south, cross road forward.
3, vehicle is being faced F1 track, west, cross road, in the time of on the E1 track, east, cross road of keeping straight on:
Vehicle is on the F1 track, and keeping straight on forward sails on the cross road, passes under the bridge of overhead travelling crane track in longitudinal crossing cross road, and keeping straight on sails on the E1 track in the east, cross road.
In the present embodiment, the corresponding both sides that connect road 2 are provided with the isolation strip, and the isolation strip is the driving shielding wire.
Embodiment seven:
As seen from Figure 13, in the present embodiment: in vertical both sides, cross road, connect respectively the six-lane that vertically travels in opposite directions.In cross road both lateral sides, connect respectively the six-lane that laterally travels in opposite directions.On the cross road of the vertically crossing formation of road and belt road: longitudinally the track of road is provided with corresponding row vehicle bridge 1; Be provided with the ground downlink track 6 that turns to; On the cross road, be provided with the ground downlink track 5 of craspedodrome along belt road; Longitudinally road is connected with belt road and is provided with the ground downlink track 6 that turns to and lane auxiliary 3 and the corresponding road 2 that connects on the cross road.
The right in the face of track, south, cross road center line is provided with G1, G2, G3 runway successively.Track center line the right on above-mentioned cross road is provided with successively and is connected with above-mentioned track: the corresponding row vehicle bridge 1 that turns to; The corresponding row vehicle bridge 1 of keeping straight on; The corresponding row vehicle bridge 1 that turns to.On the North track in the bridge of overhead travelling crane track that connects in the G1 track, be provided with the genuine import of turning left in this track.On the right, G3 track, be provided with successively first, second, third, fourth ground downlink track 6 that turns to.Wherein: first above-mentioned tunnel, on the G3 track of the south, bridge of overhead travelling crane track that connects in the G3 track, be provided with a genuine outlet, its car tunnel that advances is second above-mentioned tunnel, this tunnel joins with the tunnel that F3 track, west, cross road is connected.On the G3 track in above-mentioned genuine outlet south, establish a genuine import, it and above-mentioned the 4th genuine connection, its outlet is located on second lane auxiliary 3 on the left side, E3 track, east, cross road.The center line left side, track above-mentioned is provided with H1, H2, H3 track successively, and they connect on the cross road successively from southern bridge of overhead travelling crane track.On the H1 track, be provided with a genuine import, the ground downlink track 6 that turns to that it connects, be horizontally through G1, G2, G3 track and first, second above-mentioned tunnel, join with the 3rd above-mentioned tunnel, its outlet is located on first lane auxiliary 3 on the left side, E3 track, east, cross road.The left side in the H3 track is provided with the ground downlink track 6 that turns to that joins with F3 track, west, cross road, in its exit, is provided with lane auxiliary 3, on this track, is provided with the corresponding road 2 that connects.
In the face of the right of track, the north, cross road center line, be provided with successively B1, B2, B3 runway, center line the right, track on above-mentioned cross road is provided with successively and is connected with above-mentioned track: the corresponding row vehicle bridge 1 that turns to; The corresponding row vehicle bridge 1 of keeping straight on; The corresponding row vehicle bridge 1 that turns to.On the track, the south in the bridge of overhead travelling crane track that connects in the B1 track, be provided with the genuine import of turning left in this track, on the right, B3 track, be provided with successively first, second, third, fourth ground downlink track 6 that turns to.Wherein: first above-mentioned tunnel, on the B3 track of the bridge of overhead travelling crane track the North that connects in the B3 track, be provided with a genuine outlet, its car tunnel that advances is second above-mentioned tunnel, this tunnel joins with the tunnel that C3 track, east, cross road is connected.On the B3 track on the above-mentioned genuine outlet north, be provided with a genuine import, it is connected with above-mentioned the 4th tunnel, and its outlet is located on second lane auxiliary 3 on the left side, D3 track, west, cross road.On the left side of above-mentioned track center line, be provided with successively A1, A2, A3 track, they connect successively the phase dealings and get on the bus the center line left side from south toward northern bridge of overhead travelling crane track.On the A1 track, be provided with a genuine import, the ground downlink track 6 that turns to that it connects, be horizontally through B1, B2, B3 track and first, second above-mentioned tunnel, join with the 3rd above-mentioned tunnel, its outlet is located on first lane auxiliary 3 on the left side, D3 track, west, cross road.The left side in the A3 track is provided with a ground downlink track 6 that joins and turn to C3 track, east, cross road, in its exit, is provided with lane auxiliary 3, on this track, is provided with the corresponding road 2 that connects.
The right in the face of track, east, cross road center line is provided with C1, C2, C3 runway successively.Get on the bus at above-mentioned phase dealings the right of center line is provided with successively: be connected the ground downlink track 5 of keeping straight on C1, C2 track, be connected the ground downlink track 6 that turns to the C3 track, in C3 track and joint, A3 track, the north, cross road, in the tunnel of C3 track connection, and along the east side in A3 track, be provided with the tunnel of turning right to the north, cross road in a C3 track.
On the left side of above-mentioned track center line, be provided with successively E1, E2, E3 runway.Above-mentioned runway, the ground downlink track in cross road is passed in connection from the west to east, the left side in the E3 track, be provided with first, second ground downlink track 6 that turns to and genuine outlet, in two above-mentioned genuine exits, be provided with first, second lane auxiliary 3, on above-mentioned two lane auxiliaries 3, be respectively equipped with the corresponding road 2 that connects.
The right in the face of track, west, cross road center line is provided with F1, F2, F3 runway successively.Get on the bus at above-mentioned phase dealings the right of center line is provided with successively: be connected the ground downlink track 5 of keeping straight on F1, F2 track, be connected the ground downlink track 6 that turns to the F3 track, in F3 track and joint, H3 track, south, cross road, in the tunnel of F3 track connection, and along the west side in H3 track, be provided with the tunnel of turning right to south, cross road in a F3 track.On the left side of above-mentioned track center line, be provided with successively D1, D2, D3 runway.Above-mentioned runway, connect the ground downlink track of passing from the east to the west the cross road, the left side in the D3 track, be provided with first, second ground downlink track 6 that turns to and genuine outlet, in above-mentioned exit, two ground downlink tracks, be provided with first, second lane auxiliary 3, on above-mentioned two lane auxiliaries 3, be respectively equipped with the corresponding road 2 that connects.
The below is illustrated the process of Vehicle Driving Cycle, for example:
One, on vehicle is in the face of track, south, cross road:
1, vehicle is in the face of G1 track, south, cross road, in the time of turning left to the D3 track, west, cross road:
Vehicle is on the G1 track, drive on the bridge track of the corresponding row vehicle bridge 1 that turns to, on the track of this bridge track the North, travel and enter the import in the ground downlink track 6 that turns to, travel along this tunnel, in this exit, tunnel, drive on first lane auxiliary 3 in the face of the left side, D3 track, west, cross road, left lateral sails on the D3 track in west, cross road.
2, vehicle is being faced G3 track, south, cross road, in the time of turning right on the E3 track, east, cross road:
Vehicle travels in the G3 track, turn right and enter 6 li in the ground downlink track that turns to that the G3 track connects, along this tunnel to overtake, in this exit, tunnel, drive on second lane auxiliary 3 in the face of the left side, E3 track, east, cross road, left lateral sails on first lane auxiliary 3 on the left side, above-mentioned E3 track forward, and left lateral sails on the E3 track in the east, cross road forward.
3, vehicle is being faced G2 track, south, cross road, in the time of on the A2 track, the north, cross road of keeping straight on:
Vehicle drives on the bridge track of corresponding row vehicle bridge 1 of craspedodrome on the G2 track, on the track of this bridge track the North, drives on the A2 track on the north, cross road.
Two, when vehicle in the face of on the track, the north, cross road:
1, vehicle is in the face of B1 track, the north, cross road, in the time of turning left to the cross road in the east on the E3 track:
Vehicle is on the B1 track, drive on the bridge track of the corresponding row vehicle bridge 1 that turns to, on the track of this bridge track the North, travel and enter the import in the ground downlink track 6 that turns to, along this underground track to overtake, in this exit, underground track, drive on first lane auxiliary 3 in the face of the left side, E3 track, east, cross road, left lateral sails on the E3 track in the east, cross road forward.
2, vehicle is being faced B3 track, the north, cross road, in the time of turning right on the D3 track, west, cross road:
Vehicle travels in the B3 track, turn right and enter the B3 track and connect 6 li in the ground downlink track turn to, travel along this tunnel, in this exit, tunnel, drive in the face of on second lane auxiliary 3 on the left side, D3 track, west, cross road, left lateral sails on first lane auxiliary 3 on the left side, above-mentioned D3 track, and left lateral sails on the D3 track in west, cross road.
3, vehicle is being faced B2 track, the north, cross road, keep straight on to when facing on the H2 track, south, cross road:
Vehicle drives on the bridge track of corresponding row vehicle bridge 1 of craspedodrome on the B2 track, on the track that connects in this south, bridge track, drives on the H2 track that south, cross road connects.
Three, when vehicle in the face of cross road in the east on the track:
1, vehicle is in the face of C3 track in the east, cross road, in the time of turning left to the H3 track, south, cross road:
Vehicle travels in the C3 track, 6 li in the ground downlink track that enter under the cross road, turns to overtake, in west, phase dealings, the right-hand rotation entering surface to B3 track, the north, cross road the right, 6 li in second ground downlink track that turns to, drive in this exit, tunnel on the B3 track on the north, cross road, turning right drives on the corresponding row vehicle bridge 1 that turns to of B3 track connection, on the track, the south in this bridge track, drives on the H3 track in south, cross road.
2, vehicle in the face of the cross road in the east the C3 track, in the time of will turning right on the A3 track, the north, cross road:
Vehicle on the C3 track to overtake, enter 6 li in the ground downlink track that turns to that the C3 track connects the cross road, in the cross road in the east, turn right, drive to 6 li in the ground downlink track that the C3 track turns to A3 track, the north, cross road, along this tunnel to overtake, in this exit, tunnel, drive in the face of on second lane auxiliary 3 on the left side, A3 track, the north, cross road, left lateral sails on first lane auxiliary 3 on the left side, above-mentioned A3 track forward, and left lateral sails on the A3 track on the north, cross road forward.
3, vehicle is being faced on east, cross road C1, the C2 track, when westwards travelling on keep straight on cross road west D1, the D2 track:
Vehicle is on C1, C2 track, and travelling respectively enters 5 li in the ground downlink track that is connected with C1, C2 track, keep straight under the cross road, behind the above-mentioned tunnel that travels out respectively, drives to respectively on the D1, D2 track in west, cross road.
Four, when vehicle in the face of on the track, west, cross road:
1, vehicle is in the face of F3 track, west, cross road, in the time of turning left to the A3 track, the north, cross road:
Vehicle travels in the F3 track, 6 li in the ground downlink track that enter under the cross road, turns to overtake, at the phase dealings in the east, the right-hand rotation entering surface to G3 track, south, cross road the right, 6 li in second ground downlink track that turns to, in this exit, tunnel, drive on the G3 track in south, cross road, turn right, on the bridge track of the corresponding row vehicle bridge 1 that drive on the connection phase dealings, G3 track, turns to, to overtake to the A3 track on the north, cross road.
2, when vehicle on F3 track, west, cross road, in the time of will turning right on the H3 track, south, cross road:
Vehicle travels in the F3 track, enter 6 li in the ground downlink track that turns to that the F3 track connects, turn right in west, cross road, drive to 6 li in the ground downlink track that the F3 track turns to H3 track, south, cross road, travel along this tunnel, in this exit, tunnel, drive in the face of on H3 track, south, the cross road second left lane auxiliary 3, drive to left on first lane auxiliary 3 on the left side, above-mentioned H3 track, left lateral sails on the H3 track in south, cross road forward.
3, on vehicle is in the face of cross road west F1, F2 track, to keep straight on when sailing to the cross road and travelling eastwards on E1, the E2 track in the east:
Vehicle is on F1, F2 track, and travelling respectively enters 5 li in the ground downlink track that is connected with F1, F2 track, keep straight under the cross road, behind the above-mentioned tunnel that travels out respectively, drives to respectively the cross road in the east on E1, the E2 track.
In the present embodiment, the corresponding both sides that connect road 2 are provided with the isolation strip, and the isolation strip is the driving shielding wire.
The mode of travelling by this programme, make on the cross road and do not had Vehicle Driving Cycle, so that can be cross road construction adult walking along the street, fundamentally both solved the city driving problem of blocking up, fundamentally solved again the human and vehicle shunting trip problem of urban traffic.
Embodiment eight:
By Figure 14, Figure 15 as seen, in the present embodiment: in vertical both sides, cross road, connect respectively the six-lane that vertically travels in opposite directions.In cross road both lateral sides, connect respectively the six-lane that laterally travels in opposite directions.Vertical road in both sides, crossing, cross road is respectively equipped with the longitudinally corresponding row vehicle bridge 1 of road, is provided with the corresponding road 2 that connects below corresponding row vehicle bridge 1, is provided with lane auxiliary 3 in the outside in track on both sides of the road in vertical road.Longitudinally the track of road is provided with corresponding row vehicle bridge 1 on the cross road,
On the right in the face of track, southern side, cross road center line: be provided with longitudinally G1, G2, G3 track.On the right, G3 track, be provided with first, second lane auxiliary 3.On the left side in the face of track, southern side, cross road center line: be provided with H1, H2, H3 track.On the left side, H3 track, be provided with first, second lane auxiliary 3.The center line both sides, track in southern side on the cross road: be provided with the corresponding row vehicle bridge 1 that turns in G1, H1, H3 track, on G2, H2 track, be provided with the corresponding row vehicle bridge 1 of craspedodrome; Establish the length in two bridge of overhead travelling crane tracks of making in G1, G2 track, than establishing three bridge of overhead travelling crane tracks of making on H1, H2, the H3 track, will grow at least one more than the track in south, cross road.Establish under the bridge track of making in H1, H2, H3, G1, G2 track: from north southward, be provided with successively first, second corresponding road 2 that connects; Establish under the bridge track of making in G1, G2 track, be provided with a corresponding road 2 that connects.On the cross road of G1, G2, the connection of G3 track: on G1, G3 track, be provided with the corresponding row vehicle bridge 1 that turns to; On the G2 track, be provided with the corresponding row vehicle bridge 1 of craspedodrome.
On the right in the face of track, north side, cross road center line: be provided with B1, B2, B3 track.On B3 track the right, be provided with first, second lane auxiliary 3.The left side at above-mentioned track center line: be provided with A1, A2, A3 track.On the left side, A3 track, be provided with first, second lane auxiliary 3.Center line both sides, track in north side, cross road: on B1, A1, A3 track, be provided with the corresponding row vehicle bridge 1 that turns to.At B2, on the A2 track, be provided with the corresponding row vehicle bridge 1 of craspedodrome; Establish the length in two bridge tracks of making in B1, B2 track, than establish three bridge tracks of making in A1, A2, A3 track, will grow at least one more than the track on the north, cross road.Establish under the bridge track of making in A1, A2, A3, B1, B2 track: from Nan Wangbei, be provided with successively first, second corresponding road 2 that connects; Establish under the bridge track of making in B1, B2 track, be provided with a corresponding road 2 that connects.On the cross road of B1, B2, the connection of B3 track: on B1, B3 track, be provided with the corresponding row vehicle bridge 1 that turns to; On the B2 track, be provided with the corresponding row vehicle bridge 1 of craspedodrome.
On the right in the face of track, east side, cross road center line: be provided with C1, C2, C3 track.On the left side in the face of track, east side, cross road center line: be provided with E1, E2, E3 track.
On the right in the face of track, west side, cross road center line: be provided with F1, F2, F3 track.On the left side in the face of track, west side, cross road center line: be provided with D1, D2, D3 track.
The below is illustrated the process of Vehicle Driving Cycle, for example:
One, when vehicle in the face of on the track, south, cross road:
1, vehicle is in the face of G1 track, south, cross road, in the time of turning left to the D2 track, west, cross road:
Vehicle is on the G1 track, drive on the corresponding row vehicle bridge 1 that turns in south, cross road, on the corresponding row vehicle bridge 1 that turns on the cross road, on the corresponding row vehicle bridge 1 that turns on the north, cross road, on the track of this bridge track the North, turn left to arrive at B1, under two bridge of overhead travelling crane tracks on the B2 track, travel and connect on the road 2 in correspondence, drive to the B3 track, and on first lane auxiliary 3 in the face of the right, B3 track, the north, cross road, drive on second lane auxiliary 3 on the right, B3 track, travel southwards, in D2 track and the joint, cross road in west, cross road, turning right drives on the D2 track in west, cross road.
2, vehicle is being faced G3 track, south, cross road, in the time of turning right on the E3 track, east, cross road:
Vehicle is on the G3 track, and right lateral sails on first, second lane auxiliary 3 on G3 track the right, northwards travel, with joint, E3 track in the east, cross road, turning right drives on the E3 track in the east, cross road.
3, vehicle in the face of G2 track, south, cross road, to keep straight on when sailing on the A2 track, the north, cross road:
Vehicle is on the G2 track, to overtake on the corresponding row vehicle bridge 1 of the craspedodrome in south, cross road, on the track of the corresponding row vehicle bridge 1 of keeping straight on the cross road, on the corresponding row vehicle bridge 1 of the craspedodrome on the north, cross road, drive on the A2 track on the north, cross road.
Two, when vehicle in the face of on the track, the north, cross road:
1, vehicle is in the face of B1 track, the north, cross road, in the time of turning left to the cross road in the east on the E2 track:
Vehicle is on the B1 track, drive on the corresponding row vehicle bridge 1 that turns on the north, cross road, drive on the corresponding row vehicle bridge 1 that turns on the cross road, drive on the corresponding row vehicle bridge 1 that turns in south, cross road, on the track of this south, bridge track, turn left to G1, under two bridge of overhead travelling crane tracks on the G2 track, travel and connect on the road 2 in correspondence, drive to the G3 track, and on first lane auxiliary 3 in the face of the right, G3 track, south, cross road, drive on second lane auxiliary 3 on the right, G3 track, northwards travel, E2 track and joint, cross road in east, cross road, turning right drives on the E2 track in the east, cross road.
2, vehicle is being faced B3 track, the north, cross road, in the time of turning right on the D3 track, west, cross road:
Vehicle is on the B3 track, and right lateral sails on first, second lane auxiliary 3 on B3 track the right, travel southwards, with joint, D3 track, west, cross road, turning right drives on the D3 track in west, cross road.
3, vehicle in the face of B2 track, the north, cross road, to keep straight on when sailing on the H2 track, south, cross road:
Vehicle is on the B2 track, on the corresponding row vehicle bridge 1 of the craspedodrome in south, cross road, drive on the H2 track in south, cross road to overtake on the corresponding row vehicle bridge 1 of the craspedodrome on the corresponding row vehicle bridge 1 of the craspedodrome on the north, cross road, on the cross road.
Three, when vehicle in the face of cross road in the east on the track:
1, vehicle in the face of the cross road in the east on the C2 track, in the time of will turning left to the H3 track, south, cross road:
Vehicle on the C2 track to overtake, with in the face of first lane auxiliary 3 joints on the left side, A3 track, the north, cross road, turn right and drive on this lane auxiliary 3, northwards travel, the east of the bridge of overhead travelling crane that connects in A3 track, the north, cross road, turn left, travel at the A3 on the north, cross road, A2, A1, B1, under the bridge of overhead travelling crane track that the B2 track connects, the correspondence of travelling under above line vehicle bridge track connects on the road 2, westwards travel, turn left in the B3 track, on the corresponding row vehicle bridge 1 that turns on the cross road that connects in the B3 track of travelling, travel southwards on the corresponding row vehicle bridge 1 that turns to that the H3 track that drives to south, cross road connects, drive on the H3 track in south, cross road.
2, vehicle in the face of the cross road in the east on the C3 track, in the time of will turning right on the A3 track on the north, cross road:
Vehicle on the C3 track to overtake, with in the face of second left lane auxiliary 3 joints, A3 track, the north, cross road, turning right drives on this lane auxiliary 3, and left lateral sails on first lane auxiliary 3 on the left side, A3 track forward, and left lateral sails on the A3 track on the north, cross road forward.
3, vehicle in the face of the cross road in the east on the C1 track, to keep straight on when sailing on the D1 track, west, cross road:
Vehicle on the C1 track to overtake to the cross road, under the bridge of overhead travelling crane track in longitudinal crossing cross road, pass, drive on the D1 track in west, cross road.
Four, when vehicle in the face of on the track, west, cross road:
1, vehicle is in the face of on the F2 track, west, cross road, in the time of will turning left to the A3 track, the north, cross road:
Vehicle on the F2 track to overtake, with in the face of first left lane auxiliary 3 joints, H3 track, south, cross road, turn right and drive on this lane auxiliary 3, travel southwards, the west of the bridge of overhead travelling crane that connects in H3 track, south, cross road, turn left, travel at the H3 in south, cross road, H2, H1, G1, under the bridge of overhead travelling crane track that the G2 track connects, the correspondence of travelling under above line vehicle bridge track connects on the road 2, travel eastwards, turn left in the G3 track, on the corresponding row vehicle bridge 1 that turns on the cross road that connects in the G3 track of travelling, northwards travel on the corresponding row vehicle bridge 1 that turns to that the A3 track that drives to the north, cross road connects, drive on the A3 track on the north, cross road.
2, vehicle is on facing F3 track, west, cross road, in the time of will turning right on the H3 track, south, cross road:
Vehicle on the F3 track to overtake, with in the face of second lane auxiliary 3 joint on the left side, H3 track, south, cross road, turning right drives on this lane auxiliary 3, and left lateral sails on the lane auxiliary 3 of H3 track first left forward, and left lateral sails on the H3 track in south, cross road forward.
3, vehicle in the face of on the F1 track, west, cross road, keep straight on sails to the cross road in the east on the E1 track time:
Vehicle on the F1 track to overtake to the cross road, under the bridge of overhead travelling crane track in longitudinal crossing cross road, pass, drive on the D1 track in the east, cross road.
In the present embodiment, the corresponding both sides that connect road 2 are provided with the isolation strip, and the isolation strip is the driving shielding wire.
Embodiment nine:
By Figure 16, Figure 17 as seen, in the present embodiment: in vertical both sides, cross road, be connected with respectively the six-lane that vertically travels in opposite directions.In cross road both lateral sides, be connected with respectively the six-lane that laterally travels in opposite directions.Longitudinally road is respectively equipped with the corresponding row vehicle bridge 1 corresponding with travel direction in the both sides, crossing in cross road, is provided with the corresponding road 2 that connects below corresponding row vehicle bridge 1, is provided with lane auxiliary 3 in the outside in track on both sides of the road in vertical road.
On the right in the face of track, southern side, cross road center line: be provided with longitudinally G1, G2, G3 track.On the right, G3 track, be provided with first, second, third lane auxiliary 3.The left side at above-mentioned track center line: be provided with H1, H2, H3 track.On the left side, H3 track, be provided with first, second, third lane auxiliary 3.Center line both sides, track in southern side, cross road: be provided with the corresponding row vehicle bridge 1 that turns in G1, H1, H3 track; Be provided with the corresponding row vehicle bridge 1 of craspedodrome in G2, H2 track; Establish the bridge lane length of two bridge of overhead travelling cranes making in G1, G2 track, than the bridge track of establishing three bridge of overhead travelling cranes making on H1, H2, the H3 track, will grow at least one more than the track in south, cross road.Establish under the bridge track of making in H1, H2, H3, G1, G2 track: be provided with successively southward first, second corresponding road 2 that connects from north; Establish under the bridge track of making in G1, G2 track, be provided with a corresponding road 2 that connects.
On the right in the face of track, north side, cross road center line: be provided with B1, B2, B3 track.On the right, B3 track, be provided with first, second, third lane auxiliary 3.The left side at above-mentioned track center line: be provided with A1, A2, A3 track.On the left side, A3 track, be provided with first, second, third lane auxiliary 3.
On center line both sides, track, north side, cross road: on B1, A1, A3 track, be provided with the corresponding row vehicle bridge 1 that turns to, on B2, A2 track, be provided with the corresponding row vehicle bridge 1 of craspedodrome; Establish the bridge lane length of two bridge of overhead travelling cranes making in B1, B2 track, than the bridge track of establishing three bridge of overhead travelling cranes making on A1, A2, the A3 track, will grow at least one more than the track on the north, cross road.Establish under the bridge track of making in A1, A2, A3, B1, B2 track: the correspondence that is provided with successively first, second from Nan Wangbei connects road 2; Establish under the bridge track of making in B1, B2 track, be provided with a corresponding road 2 that connects.
On the right of the center line of track, east side, cross road: be provided with C1, C2, C3 track.On the above-mentioned center line left side, track: be provided with E1, E2, E3 track.
On the right of the center line of track, west side, cross road: be provided with F1, F2, F3 track.On the above-mentioned center line left side, track: be provided with D1, D2, D3 track.
The below is illustrated the process of Vehicle Driving Cycle, for example:
One, when vehicle in the face of on the track, south, cross road:
1, vehicle is in the face of G1 track, south, cross road, in the time of turning left to the D2 track, west, cross road:
Vehicle is on the G1 track, to overtake on the corresponding row vehicle bridge 1 that turns to, drive on the direct lane on the connection cross road, G1 track, drive on the corresponding row vehicle bridge 1 that turns on the A1 track, the north, cross road, on the track of this bridge track the North, turn left to B1, below two bridge tracks on the B2 track, travel and connect on the road 2 in correspondence, under two above-mentioned bridge tracks, pass, through the B3 track, and first lane auxiliary 3 of facing the right, B3 track, the north, cross road, drive on second the lane auxiliary 3 on the right, B3 track, travel southwards, in D2 track and the joint, cross road in west, cross road, turning right drives on the D2 track in west, cross road.
2, vehicle is being faced G3 track, south, cross road, in the time of turning right on the E3 track, east, cross road:
Vehicle is on the G3 track, and right lateral sails on first, second, third lane auxiliary 3 on G3 track the right, northwards travel, with joint, E3 track in the east, cross road, turning right drives on the E3 track in the east, cross road.
3, vehicle in the face of G2 track, south, cross road, to keep straight on when sailing on the A2 track, the north, cross road:
Vehicle is on the G2 track, to overtake on the corresponding row vehicle bridge 1 of keeping straight on, drive on the direct lane on the connection cross road, G2 track, drive on the corresponding row vehicle bridge 1 of the craspedodrome on the A2 track, the north, cross road, on the track of this bridge track the North, drive on the A2 track on the north, cross road.
Two, when vehicle in the face of on the track, the north, cross road:
1, vehicle is in the face of B1 track, the north, cross road, in the time of turning left to the cross road in the east on the E2 track:
Vehicle is on the B1 track, to overtake on the corresponding row vehicle bridge 1 that turns to, drive on the direct lane on the connection cross road, B1 track, drive on the corresponding row vehicle bridge 1 that turns on the H1 track, south, cross road, on the track of this south, bridge track, turn left to G1, below two bridge tracks on the G2 track, travel and connect on the road 2 in correspondence, under two above-mentioned bridge tracks, pass, through the G3 track, and first lane auxiliary 3 of facing the right, G3 track, south, cross road, drive on second lane auxiliary 3 on the right, G3 track, travel southwards, E2 track and joint, cross road in east, cross road, turning right drives on the E2 track in the east, cross road.
2, vehicle is being faced B1 track, the north, cross road, in the time of turning right on the D3 track, west, cross road:
Vehicle is on the G3 track, and right lateral sails on first, second, third lane auxiliary 3 on B3 track the right, travels southwards, with joint, D3 track, west, cross road, turning right drives on the D3 track in west, cross road.
3, vehicle in the face of B2 track, the north, cross road, to keep straight on when sailing on the H2 track, south, cross road:
Vehicle is on the B2 track, to overtake on the corresponding row vehicle bridge 1 of keeping straight on, drive on the direct lane on the connection cross road, B2 track, drive on the corresponding row vehicle bridge 1 of keeping straight on the H2 track, south, cross road, on the track of this south, bridge track, drive on the H2 track in south, cross road.
Three, when vehicle in the face of cross road in the east on the track:
1, vehicle in the face of the cross road in the east on the C1 track, in the time of will turning left to the H3 track, south, cross road:
Vehicle on the C1 track to overtake, with in the face of first lane auxiliary 3 joints on the left side, A3 track, the north, cross road, turn right, northwards travel, the east of the bridge of overhead travelling crane that connects in the A3 track, turn left, travel at the A3 on the north, cross road, A2, A1, B1, under the bridge of overhead travelling crane track that the B2 track connects, travel on the north, cross road, first correspondence connects on the road 2 toward north from south, westwards travel, turn left in the B3 track, drive on the direct lane on the connection cross road, B3 track, drive to southwards on the corresponding row vehicle bridge 1 that turns on the H3 track, south, cross road, drive on the H3 track in the south, cross road that this bridge track connects.
2, vehicle in the face of the cross road in the east on the C3 track, in the time of will turning right on the A3 track on the north, cross road:
Vehicle travels in the C3 track, with in the face of the 3rd lane auxiliary 3 joints on the left side, A3 track, the north, cross road, turn right and drive on the 3rd lane auxiliary 3, left lateral sails on second, the 3rd lane auxiliary 3 on the left side, A3 track forward, on the 3rd lane auxiliary 3, left lateral sails on the A3 track on the north, cross road forward.
3, vehicle in the face of the cross road in the east on the C2 track, to keep straight on when sailing on the D1 track, west, cross road:
Vehicle on the C2 track to overtake, with in the face of second lane auxiliary 3 joint on the left side, A3 track, the north, cross road, turning right drives on this second lane auxiliary 3,, northwards left lateral sails on first lane auxiliary 3 on the left side, A3 track.The east of the bridge of overhead travelling crane that connects in the A3 track, turn left, travel under the bridge of overhead travelling crane track that connects in A3, the A2 on the north, cross road, A1, B1, B2 track, the correspondence of travelling on the north, cross road, from south toward second in north connects on the road 2, westwards travels, through the B3 track, drive on first lane auxiliary 3 in the face of the right, B3 track, the north, cross road, turn left, travel southwards, with joint, D1 track, west, cross road, turn right, westwards drive on the D1 track in west, cross road.
Four, when vehicle in the face of on the track, west, cross road:
1, vehicle is in the face of on the F1 track, west, cross road, in the time of will turning left to the A3 track, the north, cross road:
Vehicle on the F1 track to overtake, with in the face of first lane auxiliary 3 joints on the left side, H3 track, south, cross road, turn right and drive on this first lane auxiliary 3, travel southwards, the west of the bridge of overhead travelling crane that connects in the H3 track, turn left, travel at the H3 in south, cross road, H2, H1, G1, under the bridge of overhead travelling crane track that the G2 track connects, travel in south, cross road, first correspondence connects on the road 2 southward from north, travel eastwards, turn left in the G3 track, drive on the direct lane on the connection cross road, G3 track, northwards drive on the corresponding row vehicle bridge 1 that turns to that A3 track, the north, cross road connects, drive on the A3 track on the north, cross road that this bridge track connects.
2, vehicle is on facing F3 track, west, cross road, in the time of will turning right on the H3 track, south, cross road:
Vehicle on the F3 track to overtake, in this track and the 3rd lane auxiliary 3 joints facing the left side, H3 track, south, cross road, turn right, travel southwards, on the 3rd above-mentioned lane auxiliary 3, left lateral is sailed on second lane auxiliary 3 through the left side, H3 track forward, arrive on the 3rd the lane auxiliary 3 on the left side, H3 track, on this track, left lateral sails on the H3 track in south, cross road forward.
3, vehicle in the face of on the F2 track, west, cross road, keep straight on sails to the cross road in the east on the E1 track time:
Vehicle on the F2 track to overtake, in this track and second lane auxiliary 3 joint facing the left side, H3 track, south, cross road, turn right and drive on this second lane auxiliary 3, left lateral to the south sails on first the lane auxiliary 3 on the left side, H3 track, the west of the bridge of overhead travelling crane that connects in the H3 track, turn left, travel at the H3 in south, cross road, H2, H1, G1, under the bridge of overhead travelling crane track that the G2 track connects, travel in south, cross road, second correspondence connects on the road 2 southward from north, travel eastwards, through the G3 track, drive on first lane auxiliary 3 in the face of the right, G3 track, south, cross road, turn left, northwards travel, in this track and joint, E1 track, east, cross road, turn right, drive to eastwards on the E1 track, east, cross road.
In the present embodiment, the corresponding both sides that connect road 2 are provided with the isolation strip, and the isolation strip is the driving shielding wire.
Embodiment ten:
As seen from Figure 18, in the present embodiment: in vertical both sides, cross road, connect respectively the six-lane that vertically travels in opposite directions.In cross road both lateral sides, connect respectively the six-lane that laterally travels in opposite directions.Longitudinally the track is provided with corresponding row vehicle bridge 1 on the cross road, and the track on the cross road is made as horizontal craspedodrome road.Be provided with lane auxiliary 3 in the outside in track on both sides of the road in vertical road, have at the two ends of corresponding row vehicle bridge 1 on vertical track of a segment distance, be respectively equipped with the ground downlink track 5 of craspedodrome and the ground downlink track 6 that turns to.In the ground downlink track 5 of keeping straight on be provided with corresponding connection road 2 above the ground downlink track 6 that is connected.
On the right in the face of track, southern side, cross road center line: be provided with longitudinally G1, G2, G3 track.On the right, G3 track, be provided with first, second lane auxiliary 3.The left side at above-mentioned track center line: be provided with H1, H2, H3 track.On the left side, H3 track, be provided with first, second lane auxiliary 3.Center line both sides, track in southern side, cross road: on G1, H1, H3 track, be provided with the ground downlink track 6 that turns to, on G2, H2 track, be provided with the ground downlink track 5 of craspedodrome; Establish two genuine length making in G1, G2 track, than establishing three tunnels making on H1, H2, the H3 track, will grow at least one more than the track in south, cross road.Divide into above the tunnel of making in H1, H2, H3, G1, G2 track: be provided with a corresponding road 2 that connects.Divide into above the tunnel of making in G1, G2 track, be provided with a corresponding road 2 that connects.Connect on the cross road in G1, G2, G3 track: on G1, G3 track, be provided with the corresponding row vehicle bridge 1 that turns to; On the G2 track, be provided with the corresponding row vehicle bridge 1 of craspedodrome.
On the right in the face of track, north side, cross road center line: be provided with B1, B2, B3 track.On the right, B3 track, be provided with first, second lane auxiliary 3.The left side at above-mentioned track center line: be provided with A1, A2, A3 track.On the left side, A3 track, be provided with first, second lane auxiliary 3.Center line both sides, track in north side, cross road: on B1, A1, A3 track, be provided with the ground downlink track 6 that turns to; On B2, A2 track, be provided with the ground downlink track 5 of craspedodrome; Establish two genuine length making in B1, B2 track, than establishing three tunnels making on A1, A2, the A3 track, will grow at least one more than the track in south, cross road.Establish above the tunnel of making in A1, A2, A3, B1, B2 track: be provided with a corresponding road 2 that connects.Establish above the tunnel of making in B1, B2 track, be provided with a corresponding road 2 that connects.On the cross road of B1, B2, the connection of B3 track: be provided with the corresponding row vehicle bridge 1 that turns in B1, B3 track; Be provided with the corresponding row vehicle bridge 1 of craspedodrome in the B2 track.
On the center line the right, track in the face of east side, cross road: be provided with C1, C2, C3 track.On the above-mentioned center line left side, track: be provided with E1, E2, E3 track.
On the center line the right, track in the face of west side, cross road: be provided with F1, F2, F3 track.On the above-mentioned center line left side, track: be provided with D1, D2, D3 track.
The below is illustrated the process of Vehicle Driving Cycle, for example:
One, when vehicle in the face of on the track, south, cross road:
1, vehicle is in the face of G1 track, south, cross road, in the time of turning left to the D2 track, west, cross road:
Vehicle is on the G1 track, to overtake to 6 li in the ground downlink track that turns to, after going out this tunnel, drive on the corresponding row vehicle bridge 1 that turns to, drive to 6 li in the ground downlink track that turns on this north, bridge track, after going out this tunnel, turn left under B1, B2 track two above the tunnel, travel and connect on the road 2 in correspondence, drive on B3 track and first lane auxiliary 3 in the face of the right, B3 track, the north, cross road, travel southwards, in D2 track and the joint, cross road in west, cross road, turning right drives on the D2 track in west, cross road.
2, vehicle is being faced G3 track, south, cross road, in the time of turning right on the E3 track, east, cross road:
Vehicle is on the G3 track, and right lateral sails on first, second lane auxiliary 3 on G3 track the right, northwards travel, with joint, E3 track in the east, cross road, turning right drives on the E3 track in the east, cross road.
3, vehicle in the face of G2 track, south, cross road, to keep straight on when sailing on the A2 track, the north, cross road:
Vehicle is on the G2 track, to overtake to 5 li in the ground downlink track of keeping straight on, go out this tunnel after, drive on the corresponding row vehicle bridge 1 of craspedodrome, drive to 5 li in the ground downlink track of the craspedodrome on the north, bridge track, after going out this tunnel, drive on the A2 track on the north, cross road.
Two, when vehicle in the face of on the track, the north, cross road:
1, vehicle is in the face of B1 track, the north, cross road, in the time of turning left to the cross road in the east on the E2 track:
Vehicle is on the B1 track, to overtake to 6 li in the ground downlink track that turns to, after going out this tunnel, drive on the corresponding row vehicle bridge 1 that turns to, drive to 6 li in the ground downlink track that turns in this south, bridge track, after going out this tunnel, turn left to two under G1, G2 track above the tunnel, travel and connect on the road 2 in correspondence, drive on G3 track and first lane auxiliary 3 in the face of the right, G3 track, south, cross road, northwards travel, E2 track and joint, cross road in east, cross road, turning right drives on the E2 track in the east, cross road.
2, vehicle is being faced B1 track, the north, cross road, in the time of turning right on the D3 track, west, cross road:
Vehicle is on the B3 track, and right lateral sails on first, second lane auxiliary 3 on B3 track the right, travel southwards, with joint, D3 track, west, cross road, turning right drives on the D3 track in west, cross road.
3, vehicle in the face of B2 track, the north, cross road, to keep straight on when sailing on the H2 track, south, cross road:
Vehicle arrives 5 li in the ground downlink track of keeping straight on to overtake on the B2 track, go out this tunnel after, drive on the corresponding row vehicle bridge 1 of craspedodrome, drive to 5 li in the ground downlink track of the craspedodrome in this south, bridge track, go out this tunnel after, drive on the H2 track in south, cross road.
Three, when vehicle in the face of cross road in the east on the track:
1, vehicle in the face of the cross road in the east on the C2 track, in the time of will turning left to the H3 track, south, cross road:
Vehicle travels in the C2 track, in the cross road in the east, with in the face of first lane auxiliary 3 joints on the left side, A3 track, the north, cross road, turn right, northwards travel, what connect in the A3 track is in the east genuine, turn left, travel at the A3 on the north, cross road, A2, A1, B1, the correspondence that the B2 track connects on the tunnel connects on the road 2, westwards travel, turn left in the B3 track, driving to the B3 track connects on the corresponding row vehicle bridge 1 that turns to of crossing on the cross road, drive to southwards 6 li in the ground downlink track that turns on the H3 track, south, cross road, go out this tunnel after, drive on the H3 track in south, cross road.
2, vehicle in the face of the cross road in the east on the C3 track, in the time of will turning right on the A3 track on the north, cross road:
Vehicle on the C3 track to overtake, with in the face of second lane auxiliary 3 joint on the left side, A3 track, the north, cross road, turn right, northwards travel, on second lane auxiliary 3 on the left side, A3 track, left lateral sails on first lane auxiliary 3 on the left side, A3 track forward, and left lateral sails on the A3 track on the north, cross road forward.
3, vehicle in the face of the cross road in the east on the C1 track, to keep straight on when sailing on the D1 track, west, cross road:
Vehicle on the C1 track to overtake to the cross road, under the bridge of overhead travelling crane track in longitudinal crossing cross road, pass, drive on the D1 track in west, cross road.
Four, when vehicle in the face of on the track, west, cross road:
1, vehicle is in the face of on the F2 track, west, cross road, in the time of will turning left to the A3 track, the north, cross road:
Vehicle travels in the F2 track, in west, cross road, in F2 track and first lane auxiliary 3 joints of facing the left side, H3 track, south, cross road, turn right, travel southwards, the genuine west that connects in the H3 track, turn left, travel at the H3 in south, cross road, H2, H1, G1, the correspondence that the G2 track connects on the tunnel connects on the road 2, travel eastwards, turn left in the G3 track, drive to the G3 track and connect to cross on the corresponding row vehicle bridge 1 that turns on the cross road, drive to 6 li in the ground downlink track that turns on the A3 track, the north, cross road northwards, after going out this tunnel, drive on the A3 track on the north, cross road.
2, vehicle is on facing F3 track, west, cross road, in the time of will turning right on the H3 track, south, cross road:
Vehicle on the F3 track to overtake, with in the face of second lane auxiliary 3 joint on the left side, H3 track, south, cross road, turn right, travel southwards, on second above-mentioned lane auxiliary 3, left lateral sails on first lane auxiliary 3 on the left side, H3 track forward, and left lateral sails on the H3 track in south, cross road forward.
3, vehicle in the face of on the F1 track, west, cross road, keep straight on sails to the cross road in the east on the E1 track time:
Vehicle on the F1 track to overtake to the cross road, under the bridge of overhead travelling crane track in longitudinal crossing cross road, pass, drive on the D1 track in west, cross road.
In the present embodiment, the corresponding both sides that connect road 2 are provided with the isolation strip, and the isolation strip is the driving shielding wire.
Implement this programme, can make track, vertical both sides on the cross road, city and the vehicle on the both lateral sides track, can accomplish that disjoint, checkless left-hand rotation drives on other road junction roadway that need to arrive, disjoint, the checkless right-hand rotation of vehicle on the road intersection mouth is travelled and craspedodrome sails on other road junction roadway.

Claims (10)

1. one kind can make the non-intersect road equipment that travels of vehicle on the cross road, city, comprise that the vertical road on the cross road intersects the mutually dealings that forms with belt road and they, it is characterized in that: described several corresponding row vehicle bridge (1) corresponding with travel direction that be provided with in the cross road, be provided with several corresponding connection roads (2) with corresponding row vehicle bridge (1) corresponding section, a corresponding end that connects road (2) is connected with corresponding row vehicle bridge (1), and the other end links to each other with the track that will travel.
2. according to claim 1ly a kind ofly can make the non-intersect road equipment that travels of vehicle on the urban road cross road, it is characterized in that: described corresponding row vehicle bridge (1) is crossed on vertical road on the phase dealings.
3. according to claim 1ly a kind ofly can make the non-intersect road equipment that travels of vehicle on the urban road cross road, it is characterized in that: described corresponding row vehicle bridge (1) is crossed on the belt road on the phase dealings.
4. according to claim 1ly a kind ofly can make the non-intersect road equipment that travels of vehicle on the urban road cross road, it is characterized in that: described vertical road in both sides, crossing, cross road is respectively equipped with the corresponding row vehicle bridge (1) corresponding with travel direction.
5. according to claim 1ly a kind ofly can make the non-intersect road equipment that travels of vehicle on the urban road cross road, it is characterized in that: described belt road in both sides, crossing, cross road is respectively equipped with the corresponding row vehicle bridge (1) corresponding with travel direction.
6. according to claim 1ly a kind ofly can make the non-intersect road equipment that travels of vehicle on the urban road cross road, it is characterized in that: several lane auxiliaries (3) are established respectively in the outside in the track, both sides in cross road.
7. according to claim 1ly a kind ofly can make the non-intersect road equipment that travels of vehicle on the urban road cross road, it is characterized in that: the isolation strip is established in the both sides that connect road (2) in correspondence, and described isolation strip is greenbelt or railing or driving shielding wire.
8. according to claim 1ly a kind ofly can make the non-intersect road equipment that travels of vehicle on the urban road cross road, it is characterized in that: described both sides of intersecting the mutually dealings that forms at vertically road and belt road also are provided with service bridge (4).
9. according to claim 1ly a kind ofly can make the non-intersect road equipment that travels of vehicle on the urban road cross road, it is characterized in that: be described vertically road and belt road intersect the ground downlink track (5) that also is provided with craspedodrome on the mutually dealings that forms.
10. according to claim 1ly a kind ofly can make the non-intersect road equipment that travels of vehicle on the urban road cross road, it is characterized in that: described intersecting on the mutually dealings that forms at vertically road and belt road also is provided with the ground downlink track (6) that turns to.
CN 201110310957 2011-10-07 2011-10-07 Road facility capable of enabling vehicles on crossing road of city not to intersecting Pending CN103031790A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110310957 CN103031790A (en) 2011-10-07 2011-10-07 Road facility capable of enabling vehicles on crossing road of city not to intersecting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110310957 CN103031790A (en) 2011-10-07 2011-10-07 Road facility capable of enabling vehicles on crossing road of city not to intersecting

Publications (1)

Publication Number Publication Date
CN103031790A true CN103031790A (en) 2013-04-10

Family

ID=48019153

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110310957 Pending CN103031790A (en) 2011-10-07 2011-10-07 Road facility capable of enabling vehicles on crossing road of city not to intersecting

Country Status (1)

Country Link
CN (1) CN103031790A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108961758A (en) * 2018-08-03 2018-12-07 东华理工大学 A kind of crossing broadening lane detection method promoting decision tree based on gradient

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108961758A (en) * 2018-08-03 2018-12-07 东华理工大学 A kind of crossing broadening lane detection method promoting decision tree based on gradient
CN108961758B (en) * 2018-08-03 2021-02-02 东华理工大学 Road junction widening lane detection method based on gradient lifting decision tree

Similar Documents

Publication Publication Date Title
CN101463582B (en) The more newly-installed crossing of means of transportation
CN103046444B (en) Intersection with optimized settings and traffic control method of the intersection
CN103233403B (en) Convenient counter-bottleneck mode traffic at level crossing for longitudinally and transversely interacted pedestrians, vehicles and buses
CN201634978U (en) Road intersection system of T-shaped junction
CN104074112A (en) Tidal lane of upstream and downstream intersection of urban road and design method of tidal lane
CN207073044U (en) Bridge tunnel composite cross crossing road
CN200985480Y (en) Non-obstacle crossroad road structure
CN202809421U (en) Checkless overpass
CN102787541A (en) Crossroad traffic system with no traffic light
WO2015055006A1 (en) Level crossing having five-direction complementary and vertically and horizontally interactive traffic at level crossing
CN102787540B (en) One passes unimpeded overpass bridge
CN105625127B (en) A kind of intersection of Chinese knot-type viaduct
CN102383350A (en) U-shaped combined passageway for crossroad
CN209602887U (en) A kind of no red light overpass at crossroads
CN202298397U (en) Road facility capable of keeping vehicles on urban cross road smooth
CN202744915U (en) Intersection traffic system without traffic light
CN202298396U (en) Road facility capable of making vehicles on urban cross road run in nonintersecting way
CN202766940U (en) Road facility for enabling vehicles on lanes to run in non-intersected mode
CN102234965B (en) Right-hand rotation is full unblocked cross composite bridge in the crossroad in outside
CN103031790A (en) Road facility capable of enabling vehicles on crossing road of city not to intersecting
CN202247566U (en) Lane facility capable of smoothly separating vehicles at urban lane intersection
CN203890822U (en) Continuous interchange T-shaped overpass
CN202247567U (en) Road facility enabling vehicles of urban crossroad to be smoothly shunted
CN102864709A (en) Road facility capable of smoothly shunting vehicles at crossroads of urban roads
CN106065551A (en) A kind of without waiting for quickly through crossroad

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130410