CN102926803A - Water drainage method for simultaneously exploiting water and coals under complicated hydrological condition - Google Patents

Water drainage method for simultaneously exploiting water and coals under complicated hydrological condition Download PDF

Info

Publication number
CN102926803A
CN102926803A CN2012104260140A CN201210426014A CN102926803A CN 102926803 A CN102926803 A CN 102926803A CN 2012104260140 A CN2012104260140 A CN 2012104260140A CN 201210426014 A CN201210426014 A CN 201210426014A CN 102926803 A CN102926803 A CN 102926803A
Authority
CN
China
Prior art keywords
water
drainage
coal
tunnel
water drainage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104260140A
Other languages
Chinese (zh)
Other versions
CN102926803B (en
Inventor
孟凡刚
靖晓颖
李树兴
张显峰
曹守新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kailuan Group Co Ltd Donghuantuo Mining Branch
Original Assignee
Kailuan Group Co Ltd Donghuantuo Mining Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kailuan Group Co Ltd Donghuantuo Mining Branch filed Critical Kailuan Group Co Ltd Donghuantuo Mining Branch
Priority to CN201210426014.0A priority Critical patent/CN102926803B/en
Publication of CN102926803A publication Critical patent/CN102926803A/en
Application granted granted Critical
Publication of CN102926803B publication Critical patent/CN102926803B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a water drainage method for simultaneously exploiting water and coals under a complicated hydrological condition. The method comprises the following steps of: constructing a dedicated water drainage tunnel connected to a working face in a coal layer in a water enrichment region of a coal layer top plate, and constructing a sedimentation pool at the tail end of the water drainage tunnel; forming a water drainage tunnel along a conveying belt tunnel; forming communicating holes for communicating the conveying belt tunnel and the water drainage tunnel in the conveying belt tunnel at intervals, arranging a vibration sieve at the tail end of the water drainage tunnel, and forming another coal conveying tunnel behind the vibration sieve; drilling water drainage holes in the water drainage tunnel for the water enrichment region of the coal layer top plate, so that a part of top plate water can be drained in advance, after the water is drained, draining the water into the sedimentation pool through the water drainage tunnel, and after sedimentation, draining the water into a water bin at the bottom of a well; and after a part of the top plate water is drained in advance, executing working face exploitation when the water is continuously drained. By the method, aiming at the water yield property of the coal layer, the top plate water is drained from the dedicated water drainage tunnel in advance; water drainage and coal exploitation are simultaneously executed, so that pressure of in-advance water drainage and crossheading water drainage are reduced; and the conventional single water drainage mode of the working face is changed.

Description

Water, coal are with the water discharge method of adopting under the complicated hydrologic condition
Technical field
The invention belongs to the Coal Mining Technology field.
Background technology
About 25,000,000,000 t of coal reserves that China emphasis colliery is threatened by water, nearly 10,000,000,000 t of coal reserves that threatened by the water bodys such as surface water body (river, river, lake, sea etc.), loose aquifer, bedrock aquifer.Affected by the river, just there be more than 200 mine threatened by more than 100 bars size river, and the coalfield of North China, East China, the Northeast is that the unconsolidated formation aquifer covers by Quaternary system and the 3rd generally, causes the relatively best superficial part outcrop area seam mining difficulty of its exploitation benefit.
Coal mine roof plate is permeable to be a very complicated problem that is subjected to various factors, be subject to the impact of geological conditions and structure, hydrogeological conditions and man-made recovery's condition, can be summarized as the co-controlling that is subject to water source, overlying strata stratum, geological structure and 4 kinds of factors of digging activity.Under complicated hydrologic condition, how to realize that the high-yield and high-efficiency exploitation is the great difficult problem that domestic mining circle need to solve.
The control roof water mainly is that top board is arranged drainage boring both at home and abroad at present, roof water is emitted in advance, owing to there is not special drainage channel, generally be from the transportation lane, directly to enter shaft sump, so can not carry out simultaneously with coal mining when discharging water in advance, and roof water to put in advance be a long process, the need that have discharging 2-3 affects continuing of coal-face.
Because roof water can not all be emitted in advance, along with roof caving produces the water guide crack, still have a large amount of roof waters to discharge from work plane during working face mining besides, the water of discharge and the coal dust of exploitation are mixed in together, enter shaft sump from the transportation lane.Therefore, the water that top board is emitted in advance and work plane muddy water enter shaft sump together, cause the coal bunker alluvial, affect retaining, increase and dig clearly workload.For the later on water coal separation of shaft sump has increased difficulty, the draining difficulty strengthens.
Therefore according to the watery of top board, taking the down-hole to replenish drainage measure, is that the realization roof water is put in advance and mined and carry out simultaneously and the prerequisite of safe working.
Summary of the invention
The objective of the invention is to put in advance the problem that can not carry out simultaneously and the effective problem of draining for mining under the complicated hydrologic condition with roof water, propose a kind of water, coal with the water discharge method of adopting, thereby guarantee the safe working in flood coal seam.
Technical scheme of the present invention is:
Water, coal is characterized in that with the water discharge method of adopting under a kind of complicated hydrologic condition:
The first step: before the working face mining, according to hydrogeological detection event, the special-purpose opening for drainage of at first in the coal seam in the rich pool of roof, constructing, the opening for drainage head end connects work plane, and the terminal construction of opening for drainage sedimentation basin connects between sedimentation basin and the wellhole; Drainage trenching in the opening for drainage, and carry out necessary supporting; Opening for drainage head end and work plane junction arrange filter screen;
Second step: along sluicing tunnel of developing, travelling belt lane, the absolute altitude in sluicing tunnel should be lower than the absolute altitude in belt lane, and is designed with certain gravity flow gradient again; The interval is set up and is connected eye in the travelling belt lane, by connecting eye with travelling belt lane and sluicing roadway linking; End in the sluicing tunnel is installed vibrosieve, and vibrosieve is opened up later on a fortune coal road road that is connected with the travelling belt lane again, and the fortune coal road is arranged haulage device in the road;
The 3rd step: in special-purpose opening for drainage, bore the dewatering orifice to the rich pool of roof, a part of roof water is emitted in advance, enter sedimentation basin by opening for drainage after emitting, enter wellhole after the precipitation;
The 4th step: after a part of roof water is emitted in advance, carry out working face mining when continuing to emit, a part of water coal body that roof water forms enters opening for drainage behind strainer filtering, enter sedimentation basin from opening for drainage, enters wellhole after the precipitation; Remaining water coal body leaks into the sluicing tunnel from nearest perforation eye, when the water coal body flow to vibrosieve, granularity obtains filtering greater than the solid particle of sieve gap, filtration coal on the sieve haulage device of packing into, be transported to the travelling belt lane from fortune coal road road, be transported to Bunker with work plane coal by equipment of conveyer again; Black water under the sieve enters shaft sump.
Good effect of the present invention is: for the watery in coal seam, the water of top board is discharged in advance from special-purpose opening for drainage; Mine when discharging water, the water coal body part of work plane enters special-purpose opening for drainage behind strainer filtering, and remainder is diverted to the sluicing tunnel, through vibrosieve from after discharge; Thereby alleviated the pressure that discharges water in advance with the crossheading draining, change the original single discharging mode of work plane, the work plane drainage system has been divided into three parts discharges, improved the drainability of work plane, thereby keep the unimpeded and water of work plane draining, coal to adopt together, and keep safe working.By strainer filtering and vibrosieve from, coal is filtered out, prevent blocking up of opening for drainage, keep the unimpeded of drainage system, realized the in advance purification before black water enters shaft sump, reduced the amount of sludge of shaft sump, guaranteed the water-holding capacity of sump.
Description of drawings
Below in conjunction with description of drawings enforcement of the present invention.
Fig. 1 is the schematic diagram of the embodiment of the invention.
Marginal data, 1-work plane, 2-travelling belt, 3-connect eye, 4-vibrosieve, 5-sluicing tunnel, 7-wellhole, 8-opening for drainage, 9-travelling belt lane, 10 fortune coal road roads, 11-haulage device, 12-filter screen, 13-sedimentation basin, the rich pool of 14-.
The specific embodiment
Work plane water discharge method under a kind of complicated hydrologic condition, as follows:
1, before work plane 1 exploitation, according to hydrogeological detection event, the special-purpose opening for drainage 8 of at first in the coal seam in the rich pool 14 of roof, constructing, opening for drainage 8 head ends connect work plane 1, and terminal construction sedimentation basin 13 connects between sedimentation basin 13 and the wellhole 7; Opening for drainage 8 interior drainage trenchings, and carry out necessary supporting; Opening for drainage 8 head ends and work plane 1 junction arrange filter screen 12;
2, again along the travelling belt lane 9 the developing sluicing tunnel 5, the absolute altitude in sluicing tunnel 5 should be lower than the absolute altitude in belt lane 9, and is designed with certain gravity flow gradient; In travelling belt lane 9, set up at a certain distance to connect eye 3, by connecting eye 3 travelling belt lane 9 and sluicing tunnel 5 are connected; End in sluicing tunnel 5 is installed vibrosieve 4, opens up a fortune coal road road 10 that is connected with travelling belt lane 9 after the vibrosieve 4 again, arranges haulage device 11 in the fortune coal road road 10; Haulage device 11 is connected with travelling belt 2 in the travelling belt lane 9;
3, afterwards, in special-purpose opening for drainage 8, bore the dewatering orifice to the rich pool 14 of roof, a part of roof water is emitted in advance, enter sedimentation basin 13 by opening for drainage 8 after emitting, enter wellhole 7 after the precipitation;
4, after a part of roof water is emitted in advance, when continuing to emit, carry out the exploitation of work plane 1, a part of water coal body that roof water forms enters opening for drainage 8 after filter screen 12 filters, enter sedimentation basin 13 from opening for drainage 8, enters wellhole 7 after the precipitation; Remaining water coal body leaks into sluicing tunnel 5 from nearest perforation eye 3, when the water coal body flow to vibrosieve 4, granularity obtains filtering greater than the solid particle of sieve gap, filtration coal on the sieve haulage device 11 of packing into, be transported to travelling belt lane 9 from fortune coal road road 10, be transported to Bunker 6 with work plane coal by equipment of conveyer 2 again; Black water under the sieve enters shaft sump 7.

Claims (1)

1. water, coal is characterized in that with the water discharge method of adopting under the complicated hydrologic condition:
The first step: before the working face mining, according to hydrogeological detection event, the special-purpose opening for drainage of at first in the coal seam in the rich pool of roof, constructing, the opening for drainage head end connects work plane, and the terminal construction of opening for drainage sedimentation basin connects between sedimentation basin and the wellhole; Drainage trenching in the opening for drainage, and carry out supporting; Opening for drainage head end and work plane junction arrange filter screen;
Second step: along sluicing tunnel of developing, travelling belt lane, the absolute altitude in sluicing tunnel should be lower than the absolute altitude in belt lane, and is designed with the gravity flow gradient again; The interval is set up and is connected eye in the travelling belt lane, by connecting eye with travelling belt lane and sluicing roadway linking; End in the sluicing tunnel is installed vibrosieve, and vibrosieve is opened up later on a fortune coal road road that is connected with the travelling belt lane again, and the fortune coal road is arranged haulage device in the road;
The 3rd step: in special-purpose opening for drainage, bore the dewatering orifice to the rich pool of roof, a part of roof water is emitted in advance, enter sedimentation basin by opening for drainage after emitting, enter wellhole after the precipitation;
The 4th step: after a part of roof water is emitted in advance, carry out working face mining when continuing to emit, a part of water coal body that roof water forms enters opening for drainage behind strainer filtering, enter sedimentation basin from opening for drainage, enters wellhole after the precipitation; Remaining water coal body leaks into the sluicing tunnel from nearest perforation eye, when the water coal body flow to vibrosieve, granularity obtains filtering greater than the solid particle of sieve gap, filtration coal on the sieve haulage device of packing into, be transported to the travelling belt lane from fortune coal road road, be transported to Bunker with work plane coal by equipment of conveyer again; Black water under the sieve enters shaft sump.
CN201210426014.0A 2012-10-30 2012-10-30 Water drainage method for simultaneously exploiting water and coals under complicated hydrological condition Expired - Fee Related CN102926803B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210426014.0A CN102926803B (en) 2012-10-30 2012-10-30 Water drainage method for simultaneously exploiting water and coals under complicated hydrological condition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210426014.0A CN102926803B (en) 2012-10-30 2012-10-30 Water drainage method for simultaneously exploiting water and coals under complicated hydrological condition

Publications (2)

Publication Number Publication Date
CN102926803A true CN102926803A (en) 2013-02-13
CN102926803B CN102926803B (en) 2014-12-10

Family

ID=47641715

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210426014.0A Expired - Fee Related CN102926803B (en) 2012-10-30 2012-10-30 Water drainage method for simultaneously exploiting water and coals under complicated hydrological condition

Country Status (1)

Country Link
CN (1) CN102926803B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103742145A (en) * 2013-12-24 2014-04-23 山东新阳能源有限公司 Water control method for abnormal water-enriched region of coal mine
CN106285777A (en) * 2016-10-28 2017-01-04 河北钢铁集团矿业有限公司 The method that flood mine mineral building discharges water in advance
CN107740707A (en) * 2017-08-13 2018-02-27 煤炭科学技术研究院有限公司 Thick coal-layer mining water damage prevention and controls under a kind of deep high artesian
CN108590754A (en) * 2018-04-24 2018-09-28 中煤西安设计工程有限责任公司 Concentrate sluicing lane method for arranging in a kind of monocline coal seam exploiting field
CN113107595A (en) * 2021-03-23 2021-07-13 河南理工大学 Rich water roof face-up mining face drainage system based on gob entry
CN113863978A (en) * 2021-09-24 2021-12-31 国家能源集团宁夏煤业有限责任公司 Face-up mining working face roadway system and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2293819C1 (en) * 2005-08-26 2007-02-20 Василий Витаутасович Сенкус Method to recover hydrological regime of mining facility
CN101050709A (en) * 2006-04-03 2007-10-10 郭国政 High water pressure releasing and blocking mining method for mining area
CN101387204A (en) * 2007-09-12 2009-03-18 河南理工大学 Coal dehydration technology under hole for coal mine
CN102505963A (en) * 2011-11-11 2012-06-20 山西晋城无烟煤矿业集团有限责任公司 Stope face roof water pre-drainage construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2293819C1 (en) * 2005-08-26 2007-02-20 Василий Витаутасович Сенкус Method to recover hydrological regime of mining facility
CN101050709A (en) * 2006-04-03 2007-10-10 郭国政 High water pressure releasing and blocking mining method for mining area
CN101387204A (en) * 2007-09-12 2009-03-18 河南理工大学 Coal dehydration technology under hole for coal mine
CN102505963A (en) * 2011-11-11 2012-06-20 山西晋城无烟煤矿业集团有限责任公司 Stope face roof water pre-drainage construction method

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
付辉: "崔家寨煤矿 E11510工作面防治水技术", 《煤炭科学技术》, vol. 37, no. 3, 31 March 2009 (2009-03-31) *
周学智: "综采工作面治理水方法与实践", 《煤炭技术》, vol. 20, no. 12, 31 December 2001 (2001-12-31) *
王建洲等: "WL-I型煤矿井下水煤分离***的改进设计", 《煤矿机械》, vol. 33, no. 1, 31 January 2012 (2012-01-31) *
王永申: "补连塔煤矿 2211 工作面防治水措施", 《水力采煤与管道运输》, no. 2, 30 June 2001 (2001-06-30) *
董尚根: "寺河二号井15号煤层的回采实践", 《科技情报开发与经济》, vol. 21, no. 27, 31 December 2011 (2011-12-31) *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103742145A (en) * 2013-12-24 2014-04-23 山东新阳能源有限公司 Water control method for abnormal water-enriched region of coal mine
CN106285777A (en) * 2016-10-28 2017-01-04 河北钢铁集团矿业有限公司 The method that flood mine mineral building discharges water in advance
CN106285777B (en) * 2016-10-28 2018-05-08 河北钢铁集团矿业有限公司 The method that flood mine mineral building discharges water in advance
CN107740707A (en) * 2017-08-13 2018-02-27 煤炭科学技术研究院有限公司 Thick coal-layer mining water damage prevention and controls under a kind of deep high artesian
CN108590754A (en) * 2018-04-24 2018-09-28 中煤西安设计工程有限责任公司 Concentrate sluicing lane method for arranging in a kind of monocline coal seam exploiting field
CN113107595A (en) * 2021-03-23 2021-07-13 河南理工大学 Rich water roof face-up mining face drainage system based on gob entry
CN113107595B (en) * 2021-03-23 2023-09-26 河南理工大学 Gob-side entry retaining-based water-rich roof upward mining surface drainage system
CN113863978A (en) * 2021-09-24 2021-12-31 国家能源集团宁夏煤业有限责任公司 Face-up mining working face roadway system and construction method thereof
CN113863978B (en) * 2021-09-24 2023-10-03 国家能源集团宁夏煤业有限责任公司 Face upward mining roadway system and construction method thereof

Also Published As

Publication number Publication date
CN102926803B (en) 2014-12-10

Similar Documents

Publication Publication Date Title
CN102926803B (en) Water drainage method for simultaneously exploiting water and coals under complicated hydrological condition
CN102913280B (en) Method for draining roof water in flood mine
CN101176400B (en) New process for recultivating glebe in mine subsidence area
CN107448176A (en) A kind of non-diagenesis gas hydrates mechanical jet unitized production method and device of sea-bottom shallow
EA030263B1 (en) Mining method for gassy and low permeability coal seams
CN109441450A (en) A kind of double resource pit mining modes of lower coal water of overlying strata hydrogeologic condition disturbance
CN207686763U (en) Screening system is crossed in goaf
CN101915118A (en) Method for progressive gas drainage in high gas medium-hard coal seam
CN102926802B (en) Method for reducing silt coal by using underground water drainage tunnel of coal mine
CN206987885U (en) Getting working face drain discharge corollary apparatus
CN107152309B (en) A kind of coal seam is the high water level and high-speed drainage water damage control method of Main aquifer
CN102943691B (en) Method for reducing silt coal slime in underground water sump of large water coal mine
RU2441167C1 (en) Method for draining out of gases in superimposed seam
CN112302715B (en) Soft sandstone aquifer dredging and lowering method
CN111749694B (en) Collaborative mining method capable of mining under pressure
RU2299986C1 (en) Method for well hydro-extraction of mineral resources
RU2003130110A (en) METHOD FOR PREVENTING EDUCATION OF landslides
CN105604605B (en) The complicated anti-broke-out diseases device of flood mine underground mine
Różkowski et al. Participation of quaternary aquifers in groundwater inflow to mines in the Upper Silesian Coal Basin (USCB)
CN104018459B (en) A kind of dredging method of coal mine underground reservoir
Barnes Treatment of the gravity minewater discharge at Deerplay Mine, Burnley, UK
CN115584957B (en) Method for mining salt lake mineral products in segmented and progressive linkage mode
SU1139802A1 (en) Drainage for soil area
SU898072A1 (en) Method of preventing accidental burst-through of floating earth into mine workings
Straskraba et al. Konkola Mine dewatering study

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141210

Termination date: 20151030

EXPY Termination of patent right or utility model