CN102867228B - The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling - Google Patents
The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling Download PDFInfo
- Publication number
- CN102867228B CN102867228B CN201210251307.XA CN201210251307A CN102867228B CN 102867228 B CN102867228 B CN 102867228B CN 201210251307 A CN201210251307 A CN 201210251307A CN 102867228 B CN102867228 B CN 102867228B
- Authority
- CN
- China
- Prior art keywords
- month
- plan
- planning unit
- electricity
- tracking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 28
- 230000005611 electricity Effects 0.000 claims abstract description 117
- 238000010248 power generation Methods 0.000 claims description 31
- PEDCQBHIVMGVHV-UHFFFAOYSA-N Glycerine Chemical compound OCC(O)CO PEDCQBHIVMGVHV-UHFFFAOYSA-N 0.000 claims description 24
- 230000005619 thermoelectricity Effects 0.000 claims description 16
- 238000000354 decomposition reaction Methods 0.000 claims description 14
- 238000012423 maintenance Methods 0.000 claims description 11
- 238000010977 unit operation Methods 0.000 claims description 6
- 238000000137 annealing Methods 0.000 claims description 4
- 238000005096 rolling process Methods 0.000 claims description 3
- 238000007689 inspection Methods 0.000 claims 1
- 235000006508 Nelumbo nucifera Nutrition 0.000 description 2
- 240000002853 Nelumbo nucifera Species 0.000 description 2
- 235000006510 Nelumbo pentapetala Nutrition 0.000 description 2
- 230000005540 biological transmission Effects 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 241001269238 Data Species 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009472 formulation Methods 0.000 description 1
- 238000007726 management method Methods 0.000 description 1
- 238000010297 mechanical methods and process Methods 0.000 description 1
- 230000005226 mechanical processes and functions Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention relates to the progress such as a kind of and roll the implementation method of establishment monthly generation scheduling, this implementation method comprises the steps: A, determines generating plan model, establishment target and constraints;B, the calculating planning unit average regulation of annual plan electricity;After C, judgement adjust in proportion, whether planning unit annual plan electricity exceedes its annual maximum generation ability;D, in proportion plan for adjustment unit year generation schedule electricity;E, pre-year-by-year plan dump energy;F, adjust monthly pre-point of result.The method can be simultaneously achieved the effective control to power plant's annual plan completion rate deviation in the hope of rational follow-up month monthly generation scheduling value in unit load rate restriction range.
Description
Technical field
The present invention relates to field of electric power automation, be specifically related to the progress such as a kind of and roll the realization of establishment monthly generation scheduling
Method.
Background technology
Power plant's year generation schedule refers to power plant's year base power generation generation schedule, year base power generation generation schedule be by
Local electricity administrative responsibile institution is according to the formulation of national grid management and running regulations or different recording review and issues, and it may be often
Year middle and late stage is adjusted according to practical situation, and the harmony of year generation schedule completion rate is as the fair weight in examination market
Index extremely electricity power enterprise is wanted to pay close attention to.Monthly generation scheduling is as the monthly decomposition of year generation schedule, and scientific and reasonable is monthly
Generation schedule establishment can not only ensure for the offer of tracing control annual plan performance, the most again can be for arranging short-term with in real time
Generation schedule provides the basic datas such as monthly tracking target.Some preparing methods of monthly generation scheduling at present, such as annual plan
Divide equally, monthly etc. progress, etc. the methods such as the progress such as rate of load condensate and so-called annual plan the most frequent in actual mechanical process
Because of unit maintenance adjust, supply and demand change and the factor impact such as newly conclude the transaction all are not carried out annual plan completion rate deviation
Effectively control.
Summary of the invention
For the deficiencies in the prior art, the present invention provides the progress such as a kind of to roll the realization side of establishment monthly generation scheduling
Method, first the method adjusts generating of each tracking power plant year meter in proportion according to follow-up month system tracking thermoelectricity power generation needs
Draw, then meet annual follow-up month system tracking thermoelectricity power generation needs, unit operation situation and concluded the transaction point considering
After adjusting under the constraintss such as month electricity, the dump energy of annual plan is reasonably allocated to follow-up month, rolls and generates the follow-up moon
Part monthly generation scheduling, and give a kind of adjustment algorithm to the monthly plan being unsatisfactory for rate of load condensate constraint.The method is at unit
Can be simultaneously achieved power plant's annual plan in the hope of rational follow-up month monthly generation scheduling value in rate of load condensate restriction range
Effective control of completion rate deviation.
It is an object of the invention to use following technical proposals to realize:
The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling, and it thes improvement is that, described implementation method
Comprise the steps:
A, determine generating plan model, establishment target and constraints;
B, the calculating planning unit average regulation of annual plan electricity;
After C, judgement adjust in proportion, whether planning unit annual plan electricity exceedes its annual maximum generation ability;
D, in proportion plan for adjustment unit year generation schedule electricity;
E, pre-year-by-year plan dump energy;
F, adjust monthly pre-point of result.
Wherein, in described step A, described determine that generating plan model includes:
1) arbitrary tracking planning unit is designated i, wherein i ∈ [1, N];If the month of monthly generation scheduling to be worked out is secondary
Month, i.e. the m month, follow-up arbitrary month is t ∈ [m, 12];
2) calendar natural law monthly is D (t);The tracking thermoelectricity power generation needs in secondary month and follow-up month is W (t), wherein W
T () is according to whole society's tracking power consumption aggregate demand, it is considered to purchase between net/province sell, new and renewable sources of energy gives priority in arranging for meter
Draw unit sent out plan electricity, throw annealing group of motors plan and preferred arrangement all kinds of transaction (as entrust outer power transmission conclude the business,
Generation Rights Trade electricity etc.) divide calculated tracking thermoelectricity planning unit generated energy demand after moon electricity;
3) the annual plan total amount of each planning unit is Ey (i), and planning unit i completed annual plan before the m month
Generated energy is Ef (i);
4) planning unit i the plan final result of t month arrangement be R (i, t), the rate of load condensate upper limit set asNegative
Lotus rate lower limit isLr(i,t);Planning unit i t month installed capacity be C (i, t);All kinds of transaction of planning unit i are in the follow-up t month
Transaction component be Eytd (i, t);Planning unit i the t month maintenance, mediate and the natural law that is obstructed add up to Dc (i, t);Dr(i,t)
Represent consider planning unit unit maintenance, be obstructed and mediate after calculated for subsequent month planning unit monthly actual motion natural law, Dr
(i,t)=D(t)-Dc(i,t)。
Wherein, in described step A, when the monthly plan of the rolling establishment m month to December, if there is not tune in planning unit
Exceed the situation of its maximum generation ability during whole annual plan, then planning unit year terminal hour annual plan completion rate deviation is identical,
Then establishment target represents by following 1. formula:
Wherein, i ∈ [1, N], j ∈ [1, N], N are planning unit sum.
Wherein, in described step A, described constraints includes hair electric equilibrium constraints and the transaction point moon of follow-up month
The planning unit rate of load condensate constraint of electricity;
The constraint of described hair electric equilibrium refers to follow-up month, and planning unit plan electricity must is fulfilled for monthly tracking fire
The demand of electricity generated energy, represents by following 2. formula:
②;
Described subsequent transaction divides the planning unit rate of load condensate constraint of moon electricity to refer to for there is monthly transaction component
Planning unit, all kinds of transaction electricity comprised in monthly plan electricity are preferential clearing, and monthly plan electricity must preferentially ensure
This transaction divides completing of moon electricity, represents by following 3. formula:
For the planning unit not run the whole month, i.e. D (t)=Dc (i, t), thenLr(i, t) andIt is disposed as 0.
Wherein, in described step B, the described planning unit average regulation of annual plan electricity represents by following 4. formula:
Wherein, in described step C, plan for adjustment unit annual plan electricity in proportion, and by calculating in residue month
Annual plan dump energy to be allocated whether exceed planning unit follow-up month maximum can generated energy, according to following formula 5. and likes
6. after judging to adjust in proportion planning unit annual plan whether exceed its year maximum generation ability:
Ey ' (i)=Ey (i) * α is 5.;
Wherein: the annual plan total amount of each planning unit after Ey ' (i) expression adjustment in proportion.
Wherein, if planning unit annual plan exceedes its annual maximum generation ability, then plan for adjustment after adjusting in proportion
Unit annual plan can generate electricity electricity sum for actually accomplishing electricity and residue month maximum, and fixing residue monthly plan is monthly
Maximum can generated energy, and 7. 8. recalculate with formula according to following formula planning unit average regulation α of annual plan electricity and time
The tracking thermoelectricity power generation needs in the moon and follow-up month is W (t):
Set E is defined as E={i | and 8. formula is set up };
Directly it is set as maximum generating watt for being not belonging to gather the modular plan value of E, represents by following 9. formula:
Wherein, if planning unit annual plan is not above its annual maximum generation ability after adjusting in proportion, step D is carried out.
Wherein, in described step E, pre-year-by-year plan dump energy comprises the steps:
A, year dump energy divide in advance;
B, monthly plan result adjust balance;
C, annual plan adjust balance.
Wherein, in described step a, first arranging transaction component is that (i, t), in combination with unit operation situation and generating for Eytd
After amount demand, annual plan dump energy is arranged into follow-up month, represents by following 10. formula:
Wherein: (i, after being intended to unit adjustment after t) representing consideration maintenance, monthly transaction electricity and power generation needs factor for Rh
Annual plan dump energy carries out monthly decomposition result.
Wherein, in described step b, divide in advance according to step a electricity ratio plan for adjustment unit transverse decomposition result Rh (i,
T), to meet monthly power generation needs W (t), with followingFormula represents:
Wherein: (i t) represents pre-point of electricity Rh (i, t) ratio plan for adjustment unit longitudinal direction decomposition result to Rv;
Described monthly plan result meets described constraints 2. formula.
Wherein, in described step c, the ratio predicted according to monthly power generation needs calculates each planning unit monthly to be needed to adjust
Whole electricity, the described electricity monthly needing to adjust is with followingFormula represents:
Wherein: (i t) represents so that annual plan dump energy after residue month monthly plan summation and adjustment σ
LefyEy ' (i) is identical and that be adjusted the monthly plan of every month difference;
LeftEy′(i)=Ey′(i)-Ef(i);
Longitudinal decomposition result is adjusted as follows: R (i, t)=Rv (and i, t)-σ (i, t), i ∈ E;
The planned outcome of described pre-year-by-year plan dump energy meets constraints 2. formula.
Wherein, in described step F, the monthly pre-point of result of described adjustment includes: each planning unit i in traversal E set
Each month t of the m-12 month:
1) if planning unit i is that (i, t) beyond the rate of load condensate upper limit for R in the planned outcome of t month arrangementThen will meter
Draw electricity by the power generation load rate upper limitAnd record adjustment electricity temp;Traveling through other month, lookup can be dissolved
The month t ' of temp electricity;Generated energy ability can travel through residue planning unit j ∈ E from big to small according to remaining the t month, find energy
Enough dissolve temp electricity, and the planning unit j of generation schedule can cut down the t ' moon, perform following operation:
R (i, t)=R (i, t)-tempR (i, t ')=R (i, t ')+temp
R (j, t)=R (j, t)+tempR (j, t ')=R (j, t ')-temp
R (i, t ') represents the unit i monthly plan value at t ';R (j, t ') represents the unit j monthly plan value at t ';
2) if planning unit i is that (i, t) beyond rate of load condensate lower limit for R ' in the planned outcome of t month arrangementLr(i t), then will
Plan electricity increases to power generation load rate lower limitLr(i t), and records adjustment electricity temp;Traveling through other month, lookup can be cut
Subtract follow-up month t ' of temp electricity;Travel through residue planning unit j ∈ E from big to small according to t month generating capacity, finding can
Cut down temp electricity, and at the planning unit j of generation schedule that can dissolve by the t ' moon;Perform to operate as follows:
R (i, t)=R (i, t)-tempR (i, t ')=R (i, t ')+temp
R (j, t)=R (j, t)+tempR (j, t ')=R (j, t ')-temp
3) if the t monthly plan result R ' of unit i (i, t) beyond rate of load condensate bound retrain, then continue traversal, until
All months of the m-12 month are traveled through.
Compared with the prior art, the present invention reaches to provide the benefit that:
1, the present invention provide etc. progress roll the implementation method of establishment monthly generation scheduling, in establishment time month monthly generating
It is no longer limited to a time month month during plan, but is conceived to annual residue month, so permissible when arranging secondary monthly plan
Make overall plans annual situation, more scientific and reasonable.
2, the present invention provide etc. progress roll establishment monthly generation scheduling implementation method, for the unit year that realizes a plan
The progresses such as degree plan, take that to actually accomplish total amount, following power generation needs total amount and total system annual plan according to total system total
Amount calculates the average regulation coefficient of annual plan of planning unit, adjustment unit annual plan electricity in proportion.
3, the present invention provide etc. progress roll establishment monthly generation scheduling implementation method, consider unit adjust the year after next
It is calculated annual plan dump energy after degree plan electricity and the amount of actually accomplishing, divides in advance through annual plan dump energy, the moon
Degree power generation needs leveling, annual plan dump energy leveling and rate of load condensate constraint adjust the scientific and reasonable arrangement of FOUR EASY STEPS time month meter
Draw and follow-up month is pre-planned.
4, the present invention provide etc. progress roll establishment monthly generation scheduling implementation method, solve planning unit year
Completion rate of the plan deviation problems of too, and the most effective.
Accompanying drawing explanation
Fig. 1 be the monthly generation scheduling that provides of the present invention etc. progress roll preparation method schematic flow sheet.
Detailed description of the invention
Below in conjunction with the accompanying drawings the detailed description of the invention of the present invention is described in further detail.
The present invention provide monthly generation scheduling etc. progress roll preparation method flow process as it is shown in figure 1, the method includes
Following step:
A, determine generating plan model, establishment target and constraints;
(1) generating plan model includes:
1) arbitrary tracking planning unit is designated i, wherein i ∈ [1, N];If the month of monthly generation scheduling to be worked out is secondary
Month, i.e. the m month, follow-up arbitrary month is t ∈ [m, 12];
2) calendar natural law monthly is D (t);The tracking thermoelectricity power generation needs in secondary month and follow-up month is W (t), wherein W
T () is according to whole society's tracking power consumption aggregate demand, it is considered to purchase between net/province sell, new and renewable sources of energy gives priority in arranging for meter
Draw unit sent out plan electricity, throw annealing group of motors plan and give priority in arranging for all kinds of transaction (as entrust outer power transmission conclude the business,
Generation Rights Trade electricity etc.) divide calculated tracking thermoelectricity planning unit generated energy demand after moon electricity;
3) the annual plan total amount of each planning unit is Ey (i), and planning unit i completed annual plan before the m month
Generated energy is Ef (i);
4) planning unit i the plan final result of t month arrangement be R (i, t), the rate of load condensate upper limit set asNegative
Lotus rate lower limit isLr(i,t);Planning unit i t month installed capacity be C (i, t);All kinds of transaction of planning unit i are in the follow-up t month
Transaction component be Eytd (i, t);Planning unit i the t month maintenance, mediate and the natural law that is obstructed add up to Dc (i, t);Dr(i,t)
Represent consider planning unit unit maintenance, be obstructed and mediate after calculated for subsequent month planning unit monthly actual motion natural law, Dr
(i,t)=D(t)-Dc(i,t)。
(2) establishment target:
When the monthly plan of the rolling establishment m month to December, if exceeded when planning unit does not exist adjustment annual plan
The situation of its maximum generation ability, then planning unit year terminal hour annual plan completion rate deviation is identical, then establishment target is with following
1. formula represents:
Wherein, i ∈ [1, N], j ∈ [1, N], N are planning unit sum.
(3) constraints:
This method mainly considers the constraint of hair electric equilibrium, considers the planning unit rate of load condensate of transaction point of follow-up month moon electricity
Constraint.
The constraint of hair electric equilibrium refers to follow-up month, and planning unit plan electricity must is fulfilled for monthly tracking thermoelectricity and sends out
The demand of electricity, represents by following 2. formula:
②;
Subsequent transaction divides the planning unit rate of load condensate constraint of moon electricity to refer to the plan for there is monthly transaction component
Unit, all kinds of transaction electricity comprised in monthly plan electricity are preferential clearing, and monthly plan electricity must preferentially ensure this friendship
Easily divide completing of moon electricity, represent by following 3. formula:
For the planning unit not run the whole month, i.e. D (t)=Dc (i, t), thenLr(i, t) andIt is disposed as 0.
B, the calculating planning unit average regulation of annual plan electricity;
The average regulation of planning unit annual plan electricity represents by following 4. formula:
After C, judgement adjust in proportion, whether planning unit annual plan electricity exceedes its annual maximum generation ability;
Plan for adjustment unit annual plan electricity on year-on-year basis, and remain by calculating the annual plan residue month is to be allocated
Electricity whether exceed unit follow-up month maximum can generated energy, verify in proportion adjust after annual plan the most exceeded its year
Degree maximum generation ability,
Ey ' (i)=Ey (i) * α is 5.;
Wherein: the annual plan total amount of each planning unit after Ey ' (i) expression adjustment in proportion.
If planning unit annual plan exceedes its annual maximum generation ability, then plan for adjustment unit year after adjusting in proportion
Degree plan can generate electricity electricity sum for actually accomplishing electricity and residue month maximum, and fixing residue monthly plan is that monthly maximum can
Generated energy, and 7. 8. recalculate with formula according to following formula planning unit average regulation α of annual plan electricity and time month and
The tracking thermoelectricity power generation needs in follow-up month is W (t), if set E element number be N; perform step E, otherwise according to
Following formula recalculates factor alpha and adjusts W (t):
Set E is defined as E={i | and 8. formula is set up };
Directly it is set as maximum generating watt for being not belonging to gather the modular plan value of E, represents by following 9. formula:
If planning unit annual plan is not above its annual maximum generation ability after adjusting in proportion, carry out step D.
D, in proportion plan for adjustment unit year generation schedule electricity.
Ey ' (i)=Ey (i) * α
E, pre-year-by-year plan dump energy;
Pre-year-by-year plan dump energy comprises the steps:
A, year dump energy divide in advance;First arrange transaction component be Eytd (i, t), in combination with unit operation situation and send out
After electrical demand, annual plan dump energy is arranged into follow-up month, represents by following 10. formula:
Wherein: (i, after being intended to unit adjustment after t) representing consideration maintenance, monthly transaction electricity and power generation needs factor for Rh
Annual plan dump energy carries out monthly decomposition result.
B, monthly plan result adjust balance;Electricity ratio plan for adjustment unit transverse decomposition result is divided in advance according to step a
(i, t), to meet monthly power generation needs W (t), with following for RhFormula represents:
Wherein: (i t) represents pre-point of electricity Rh (i, t) ratio plan for adjustment unit longitudinal direction decomposition result to Rv;
Monthly plan result meets described constraints 2. formula.
C, annual plan adjust balance;Mathematically proveIt is apparent from, because
Both withUnanimously.Due to month distributions such as different planning unit unit operation situations and transaction point moon electricity not exclusively
Unanimously, causeThe most identical with Ey ' (i)-Ef (i), i ∈ E.The ratio predicted according to monthly power generation needs
Calculating the electricity that each planning unit monthly needs to adjust, the described electricity monthly needing to adjust is with followingFormula represents:
Wherein: (i t) represents so that annual plan dump energy after residue month monthly plan summation and adjustment σ
LeftEy ' (i) is identical and that be adjusted the monthly plan of every month difference;
LeftEy′(i)=Ey′(i)-Ef(i)
Longitudinal decomposition result is adjusted as follows: R (i, t)=Rv (and i, t)-σ (i, t), i ∈ E;
The planned outcome of pre-year-by-year plan dump energy meets constraints 2. formula.
F, adjust monthly pre-point of result;
Adjust monthly pre-point of result to include:
Each month t of the m-12 month of each planning unit i in traversal E set:
1) if planning unit i is that (i, t) beyond the rate of load condensate upper limit for R in the planned outcome of t month arrangementThen will meter
Draw electricity by the power generation load rate upper limitAnd record adjustment electricity temp;Traveling through other month, lookup can be dissolved
The month t ' of temp electricity;Generated energy ability can travel through residue planning unit j ∈ E from big to small according to remaining the t month, find energy
Enough dissolve temp electricity, and the planning unit j of generation schedule can cut down the t ' moon, perform following operation:
R (i, t)=R (i, t)-tempR (i, t ')=R (i, t ')+temp
R (j, t)=R (j, t)+tempR (j, t ')=R (j, t ')-temp
R (i, t ') represents the unit i monthly plan value at t ';R (j, t ') represents the unit j monthly plan value at t ';
2) if planning unit i is that (i, t) beyond rate of load condensate lower limit for R ' in the planned outcome of t month arrangementLr(i t), then will
Plan electricity increases to power generation load rate lower limitLr(i t), and records adjustment electricity temp;Traveling through other month, lookup can be cut
Subtract follow-up month t ' of temp electricity;Travel through residue planning unit j ∈ E from big to small according to t month generating capacity, finding can
Cut down temp electricity, and at the planning unit j of generation schedule that can dissolve by the t ' moon;Perform to operate as follows:
R (i, t)=R (i, t)-tempR (i, t ')=R (i, t ')+temp
R (j, t)=R (j, t)+tempR (j, t ')=R (j, t ')-temp
3) if the t monthly plan result R ' of unit i (i, t) beyond rate of load condensate bound retrain, then continue traversal, until
All months of the m-12 month are traveled through.
The present invention provide etc. progress roll establishment monthly generation scheduling implementation method, work out monthly plan time not only
It is confined to secondary month, but it is complete to combine the residue power generation needs in all months, unit operation situation and transaction point moon electricity arrangement
The monthly generation schedulings in year all residue months, the so also follow-up institute of rolling amendment while establishment time month monthly generation scheduling
Having the pre-planned of month, the planning influence factor being thus likely to occur future considers early.
In order to realize a plan, unit annual plan completion rate deviation is identical, adjusts unit annual plan electricity in proportion.
Actually accomplish total amount, following power generation needs total amount and total system annual plan total amount according to total system and calculate the year of planning unit
Plan average regulation coefficient, so achieve all planning unit annual plans under conditions of annual plan after completing to adjust
The Synchronization Control of completion rate deviation (for except the planning unit that cannot adjust in proportion because of self generating scarce capacity).
Annual plan dump energy after adjusting according to unit, divides in advance through annual plan dump energy, monthly power generation needs
Leveling, annual plan dump energy leveling and rate of load condensate constraint adjust the scientific and reasonable arrangement of FOUR EASY STEPS time monthly plan and follow-up
Month is pre-planned.The method of the present invention can be in the hope of monthly generating of rational follow-up month meter in unit load rate restriction range
Draw value, be simultaneously achieved the effective control to power plant's annual plan completion rate deviation.
Finally should be noted that: above example is only in order to illustrate that technical scheme is not intended to limit, to the greatest extent
The present invention has been described in detail by pipe with reference to above-described embodiment, and those of ordinary skill in the field are it is understood that still
The detailed description of the invention of the present invention can be modified or equivalent, and any without departing from spirit and scope of the invention
Amendment or equivalent, it all should be contained in the middle of scope of the presently claimed invention.
Claims (5)
1. the progress such as a kind rolls the implementation method of establishment monthly generation scheduling, it is characterised in that under described implementation method includes
State step:
A, determine generating plan model, establishment target and constraints;
B, the calculating planning unit average regulation of annual plan electricity;
After C, judgement adjust in proportion, whether planning unit annual plan electricity exceedes its annual maximum generation ability;
D, in proportion plan for adjustment unit year generation schedule electricity;
E, pre-year-by-year plan dump energy;
F, adjust monthly pre-point of result;
In described step A, described determine that generating plan model includes:
1) tracking planning unit is i, wherein i ∈ [1, N];If the month of monthly generation scheduling to be worked out is secondary month, i.e. the m month, after
Continuous arbitrary month is t ∈ [m, 12];
2) calendar natural law monthly is D (t);The tracking thermoelectricity power generation needs in secondary month and follow-up month is W (t), wherein W (t)
For according to whole society's tracking power consumption aggregate demand, it is considered to purchase between net/province sell, the new and renewable sources of energy plan of giving priority in arranging for single
The sent out plan electricity of unit, throw calculated tracking thermoelectricity plan after anneal group of motors plan and all kinds of transaction divide moon electricity
Unit generated energy demand;
3) the annual plan total amount of each tracking planning unit is Ey (i), and tracking planning unit i completed year before the m month
Plan generated energy is Ef (i);
4) tracking planning unit i the plan final result of t month arrangement be R (i, t), the rate of load condensate upper limit set as
Rate of load condensate lower limit isLr(i,t);Tracking planning unit i t month installed capacity be C (i, t);All kinds of friendships of tracking planning unit i
Easily component of concluding the business the follow-up t month be Eytd (i, t);Tracking planning unit i the t month maintenance, mediate and the natural law that is obstructed adds up to
Dc(i,t);Dr (i, t) represent consider planning unit unit maintenance, be obstructed and mediate after calculated for subsequent month planning unit monthly
Actual motion natural law, and Dr (i, t)=D (t)-Dc (i, t);
In described step B, the described tracking planning unit average regulation of annual plan electricity represents by following 4. formula:
In described step C, plan for adjustment unit annual plan electricity in proportion, and by calculating in residue year to be allocated in month
Degree plan dump energy whether exceed tracking planning unit follow-up month maximum can generated energy, 5. 6. judge with formula according to following formula
In proportion adjust after tracking planning unit annual plan whether exceed its year maximum generation ability:
Ey'(i)=Ey (i) * α is 5.;
The annual plan total amount of each planning unit after wherein: Ey'(i) expression adjusts in proportion;
If tracking planning unit annual plan exceedes its annual maximum generation ability after adjusting in proportion, then adjust tracking plan list
Unit's annual plan can generate electricity electricity sum for actually accomplishing electricity and residue month maximum, fixing remain monthly plan be monthly
Greatly can generated energy, and 7. 8. recalculate arbitrary tracking planning unit average regulation of annual plan electricity with formula according to following formula
α is W (t) with the tracking thermoelectricity power generation needs of secondary month and follow-up month:
Tracking planning unit set E is defined as Ε={ i | 8. formula set up };
Directly it is set as maximum generating watt for being not belonging to gather the modular plan value of Ε, represents by following 9. formula:
If tracking planning unit annual plan is not above its annual maximum generation ability after adjusting in proportion, carry out step D.
2. the progress such as claimed in claim 1 rolls the implementation method of establishment monthly generation scheduling, it is characterised in that described step
In rapid A, when the monthly plan of the rolling establishment m month to December, if tracking planning unit does not exist during adjustment annual plan super
Cross the situation of its maximum generation ability, then tracking planning unit year terminal hour annual plan completion rate deviation is identical, then work out target
Represent by following 1. formula:
Wherein, i ∈ [1, N], j ∈ [1, N], N are tracking planning unit sum.
3. the progress such as claimed in claim 1 rolls the implementation method of establishment monthly generation scheduling, it is characterised in that described step
In rapid A, described constraints includes hair electric equilibrium constraints and the tracking planning unit of transaction point of follow-up month moon electricity
Rate of load condensate retrains;
The constraint of described hair electric equilibrium refers to follow-up month, and tracking planning unit plan electricity must is fulfilled for monthly tracking fire
The demand of electricity generated energy, represents by following 2. formula:
Described subsequent transaction divides the tracking planning unit rate of load condensate constraint of moon electricity to refer to for there is monthly transaction component
Planning unit, all kinds of transaction electricity comprised in monthly plan electricity are preferential clearing, and monthly plan electricity must preferentially ensure
This transaction divides completing of moon electricity, represents by following 3. formula:
For the tracking planning unit not run the whole month, i.e. D (t)=D c (i, t), thenLr(i, t) andIt is disposed as 0.
4. the progress such as claimed in claim 1 rolls the implementation method of establishment monthly generation scheduling, it is characterised in that described step
In rapid E, pre-year-by-year plan dump energy comprises the steps:
A, year dump energy divide in advance;
B, monthly plan result adjust balance;
C, annual plan adjust balance;
In described step a, first arrange transaction component be Eytd (i, t), after unit operation situation and generated energy demand,
Annual plan dump energy is arranged into follow-up month, represents by following 10. formula:
Wherein: (i is intended to after unit adjusts year to Rh after t) representing consideration maintenance, monthly transaction electricity and power generation needs factor
Plan dump energy carries out monthly decomposition result;I is tracking planning unit, wherein i ∈ [1, N];M is for waiting to work out monthly generating meter
In the month drawn, the most secondary month, t was follow-up arbitrary month, t ∈ [m, 12];W (t) sends out for the tracking thermoelectricity of secondary month and follow-up month
Electricity demand, wherein W (t) is according to whole society's tracking power consumption aggregate demand, it is considered to purchase between net/province sell, new forms of energy and renewable energy
Give priority in arranging for after the plan the sent out electricity of planning unit, throwing annealing group of motors plan and all kinds of transaction divide moon electricity and calculate in source
The tracking thermoelectricity planning unit generated energy demand arrived;Ef (i) is that tracking planning unit i completed annual plan before the m month and sends out
Electricity;(i is t) that tracking planning unit i is in t month installed capacity to C;(i t) represents consideration arbitrary tracking planning unit unit inspection to Dr
Calculated for subsequent month tracking planning unit monthly actual motion natural law after repairing, be obstructed and mediating, Dr (i, t)=D (t)-Dc (i,
t);Dc (i, t) be tracking planning unit i the t month maintenance, mediate and the natural law that is obstructed amounts to;D (t) is calendar natural law monthly;
(i is t) that all kinds of transaction of tracking planning unit i are at component of concluding the business the follow-up t month to Eytd;Ey'(i) after expression adjusts in proportion often
The annual plan total amount of individual planning unit;E is tracking planning unit set;
In described step b, divide electricity ratio to adjust horizontal decomposition result Rh of tracking planning unit in advance (i, t), with full according to step a
Mature degree power generation needs W (t), with followingFormula represents:
Wherein: (i t) represents that (i, t) ratio adjusts tracking planning unit longitudinal direction decomposition result to pre-point of electricity Rh to Rv;
Described monthly plan result meets described constraints 2. formula, i.e.Right
In described step c, the ratio predicted according to monthly power generation needs calculates each tracking planning unit monthly needs adjustment
Electricity, the described electricity monthly needing to adjust is with followingFormula represents:
Wherein: (i t) represents so that annual plan dump energy after residue month monthly plan summation and adjustment σ
LeftEy'(i) identical and that the monthly plan of every month is adjusted difference;
LeftEy'(i)=Ey'(i)-Ef (i);
Longitudinal decomposition result is adjusted as follows: R (i, t)=Rv (and i, t)-σ (i, t), i ∈ Ε;
The planned outcome of described pre-year-by-year plan dump energy meets constraints 2. formula;That is:
Wherein: i is tracking planning unit, wherein i ∈ [1, N];M is the month of monthly generation scheduling to be worked out, the most secondary month, and t is
Follow-up arbitrary month, t ∈ [m, 12];W (t) is secondary month and the tracking thermoelectricity power generation needs in follow-up month, and wherein W (t) is root
According to whole society's tracking power consumption aggregate demand, it is considered to purchase between net/province sell, new and renewable sources of energy gives priority in arranging for planning unit
Calculated tracking thermoelectricity planning unit after plan electricity, throwing annealing group of motors plan and all kinds of transaction divide moon electricity can be sent out
Generated energy demand;Ef (i) is that tracking planning unit i completed annual plan generated energy before the m month;Ey'(i) represent in proportion
The annual plan total amount of each planning unit after adjustment;E is tracking planning unit set;Rv (i, t) represent pre-point of electricity Rh (i,
T) ratio adjusts tracking planning unit longitudinal direction decomposition result.
5. the progress such as claimed in claim 1 rolls the implementation method of establishment monthly generation scheduling, it is characterised in that described step
In rapid F, the monthly pre-point of result of described adjustment includes: the m-12 month of each tracking planning unit i in traversal Ε set each
Month t:
1) if tracking planning unit i is that (i, t) beyond the rate of load condensate upper limit for R in the planned outcome of t month arrangementThen will meter
Draw electricity by the power generation load rate upper limitAnd record adjustment electricity temp;Traveling through other month, lookup can be dissolved
The month t' of temp electricity;Travel through residue planning unit j ∈ Ε according to t month surplus generation ability from big to small, find energy
Enough dissolve temp electricity, and the tracking planning unit j of generation schedule can cut down the t' month, perform following operation:
R (i, t)=R (i, t)-tempR (i, t')=R (i, t')+temp
R (j, t)=R (j, t)+tempR (j, t')=R (j, t')-temp
R (i, t') represents the tracking planning unit i monthly plan value at t';R (j, t') represents the tracking planning unit j moon at t'
Degree planned value;
2) if tracking planning unit i is R'(i in the planned outcome of t month arrangement, t) beyond rate of load condensate lower limitLr(i t), then will
Plan electricity increases to power generation load rate lower limitLr(i t), and records adjustment electricity temp;Traveling through other month, lookup can be cut
Subtract follow-up month t' of temp electricity;Travel through residue tracking planning unit j ∈ Ε according to t month generating capacity from big to small, search
To cutting down temp electricity, and at the tracking planning unit j of generation schedule that can dissolve the t' month;Perform to operate as follows:
R (i, t)=R (i, t)-tempR (i, t')=R (i, t')+temp
R (j, t)=R (j, t)+tempR (j, t')=R (j, t')-temp
3) if t monthly plan result R'(i of tracking planning unit i, t) do not retrain beyond rate of load condensate bound, then continue traversal,
Until having traveled through all months of the m-12 month;E is tracking planning unit set.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210251307.XA CN102867228B (en) | 2012-07-19 | 2012-07-19 | The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210251307.XA CN102867228B (en) | 2012-07-19 | 2012-07-19 | The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102867228A CN102867228A (en) | 2013-01-09 |
CN102867228B true CN102867228B (en) | 2016-08-10 |
Family
ID=47446091
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210251307.XA Active CN102867228B (en) | 2012-07-19 | 2012-07-19 | The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102867228B (en) |
Families Citing this family (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105678394B (en) * | 2014-11-07 | 2020-04-14 | 国家电网公司 | Multi-source multi-cycle power generation plan making method |
CN104484772B (en) * | 2014-12-30 | 2017-10-20 | 广东电网有限责任公司电力调度控制中心 | The feasibility method of calibration and system of electricity plan |
CN104616069B (en) * | 2015-01-13 | 2017-11-10 | 国电南瑞科技股份有限公司 | A kind of annual generation schedule rolls decomposition optimization |
CN104517199A (en) * | 2015-01-16 | 2015-04-15 | 国家电网公司 | New energy power generation online monitoring method based on real time data |
CN106779297A (en) * | 2016-11-23 | 2017-05-31 | 青岛鹏海软件有限公司 | A kind of method for realizing target Rolling Planning and execution |
CN107590559B (en) * | 2017-09-04 | 2020-09-25 | 广东电网有限责任公司电力调度控制中心 | Monthly electric quantity regulation and control method for cogeneration power plant |
CN108182506B (en) * | 2017-12-05 | 2021-08-27 | 中国电力科学研究院有限公司 | Step-by-step optimization method and device for monthly power generation plan |
CN108388968B (en) * | 2018-03-20 | 2022-03-11 | 云南电网有限责任公司玉溪供电局 | Power generation plan rolling adjustment method based on pre-bidding deviation electric quantity balance mechanism |
CN109325878A (en) * | 2018-08-16 | 2019-02-12 | 国网浙江省电力有限公司绍兴供电公司 | Generation schedule optimization method is rolled based on three public scheduling years two stages |
CN109978398A (en) * | 2019-04-01 | 2019-07-05 | 南京师范大学 | A kind of electric power medium and long-term transaction contract rolling method |
CN113627724B (en) * | 2021-07-02 | 2024-04-05 | 江苏能电科技有限公司 | Method and device for reasonably distributing electric quantity, storage medium and solar street lamp equipment |
CN118014319A (en) * | 2024-04-09 | 2024-05-10 | 国网浙江省电力有限公司宁波供电公司 | Associated collaborative management method, device, equipment and medium for comprehensive power grid plan |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102156815A (en) * | 2011-04-07 | 2011-08-17 | 国电南瑞科技股份有限公司 | Method for optimizing power generation plan in mode of tracing scheduling of annual electric quantity progress |
CN102509176A (en) * | 2011-11-10 | 2012-06-20 | 山东电力集团公司德州供电公司 | Decision method for rolling optimization of wind and light storage cooperative scheduling |
-
2012
- 2012-07-19 CN CN201210251307.XA patent/CN102867228B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102156815A (en) * | 2011-04-07 | 2011-08-17 | 国电南瑞科技股份有限公司 | Method for optimizing power generation plan in mode of tracing scheduling of annual electric quantity progress |
CN102509176A (en) * | 2011-11-10 | 2012-06-20 | 山东电力集团公司德州供电公司 | Decision method for rolling optimization of wind and light storage cooperative scheduling |
Non-Patent Citations (1)
Title |
---|
节能减排约束下的发电单元年度电能计划编制方法;韩家辉;《中国优秀硕士学位论文全文数据库工程科技II辑》;20120515(第5期);第41-45页 * |
Also Published As
Publication number | Publication date |
---|---|
CN102867228A (en) | 2013-01-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102867228B (en) | The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling | |
Wu et al. | GENCO's risk-based maintenance outage scheduling | |
de Quevedo et al. | Impact of electric vehicles on the expansion planning of distribution systems considering renewable energy, storage, and charging stations | |
Bao et al. | A multi time-scale and multi energy-type coordinated microgrid scheduling solution—Part II: Optimization algorithm and case studies | |
Chen et al. | Economic optimization of operations for hybrid energy systems under variable markets | |
JP4435101B2 (en) | Design evaluation method for small-scale power system | |
Volpato et al. | General guidelines for the optimal economic aggregation of prosumers in energy communities | |
CN105528466A (en) | Wind power optimal planning modeling method considering adaptability and economy of power system | |
CN107784410A (en) | Regional Energy internet integrated system and the method for optimizing its configuration and operation | |
CN109103914A (en) | The micro-capacitance sensor energy storage Optimal Configuration Method of consideration source lotus storage synthetic operation | |
CN103617453A (en) | Electric system medium and long term transaction operation plan obtaining method taking wind electricity harmonic absorption into consideration | |
Kapsali et al. | Investigating the techno-economic perspectives of high wind energy production in remote vs interconnected island networks | |
Sanchis et al. | The Corridors of Power: A Pan-European\" Electricity Highway\" System for 2050 | |
Li et al. | A coordinated peak shaving strategy using neural network for discretely adjustable energy-intensive load and battery energy storage | |
Ntomaris et al. | Optimal bidding of hybrid power stations in insular power systems | |
CN110021932B (en) | Bilateral participation peak shaving auxiliary service capacity selection and economic model construction method | |
CN105244874B (en) | A kind of meter and failure risk and the power distribution network Optimal reactive power model of cost | |
Ratner et al. | Scenario forecast for wind turbine manufacturing in Russia | |
CN106548266A (en) | A kind of unit operation mode decision method for considering hydro thermal coordination | |
CN107611968B (en) | The active distribution network economical operation method of distributed energy interaction consumption | |
CN106780123A (en) | A kind of Transaction algorithm decision-making technique for considering power constraint | |
CN105894161A (en) | Medium-and-long term generation scheduling compilation method of transverse rolling and vertical leveling in 'fair-and-square' mode | |
CN106651136A (en) | Day-ahead power generation plan compilation method of bilateral transaction and apparatus thereof | |
Short et al. | Modeling the long-term market penetration of wind in the United States | |
CN106169770A (en) | A kind of electric power energy Optimal Configuration Method for water power enrichment area |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |