CN102867228A - Implementation method for scheduling monthly power generation plan in manner of rolling at equal progress - Google Patents

Implementation method for scheduling monthly power generation plan in manner of rolling at equal progress Download PDF

Info

Publication number
CN102867228A
CN102867228A CN201210251307XA CN201210251307A CN102867228A CN 102867228 A CN102867228 A CN 102867228A CN 201210251307X A CN201210251307X A CN 201210251307XA CN 201210251307 A CN201210251307 A CN 201210251307A CN 102867228 A CN102867228 A CN 102867228A
Authority
CN
China
Prior art keywords
plan
month
monthly
unit
electric weight
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201210251307XA
Other languages
Chinese (zh)
Other versions
CN102867228B (en
Inventor
黄龙达
耿建
龙苏岩
郑亚先
邵平
王高琴
徐骏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Original Assignee
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, China Electric Power Research Institute Co Ltd CEPRI filed Critical State Grid Corp of China SGCC
Priority to CN201210251307.XA priority Critical patent/CN102867228B/en
Publication of CN102867228A publication Critical patent/CN102867228A/en
Application granted granted Critical
Publication of CN102867228B publication Critical patent/CN102867228B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to an implementation method for scheduling a monthly power generation plan in a manner of rolling at equal progress. The implementation method comprises the following steps of: A, determining a power generation plan model, compiling target and constraint conditions; B, calculating the average adjustment rate of plan unit yearly plan electric quantity; C, judging whether the plan unit yearly plan electric quantity which is adjusted in equal proportion exceeds the yearly highest power generation capacity or not; D, adjusting the plan unit yearly plan electric quantity in equal proportion; E, preassigning the yearly plan remaining electric quantity; and F, adjusting the monthly preassigning results. According to the method, reasonable monthly power generation plan values of subsequent months can be acquired within a constraint range of unit load rates, and the deviation of the percentage complete of the yearly plan of power plants is effectively controlled.

Description

The roll implementation method of establishment monthly generation scheduling of the progress such as a kind of
Technical field
The present invention relates to the power automation field, be specifically related to the roll implementation method of establishment monthly generation scheduling of the progress such as a kind of.
Background technology
Power plant's year generation schedule refers to power plant's year base power generation generation schedule, annual base power generation generation schedule is to be formulated according to national grid management and running regulations or different recording review and issue by local electricity administrative responsibile institution, it may be adjusted according to actual conditions in the annual middle and later periods, and the harmony of annual generation schedule completion rate is as extremely electricity power enterprise's concern of important indicator of examination market justice.Monthly generation scheduling is as the monthly decomposition of annual generation schedule, scientific and reasonable monthly generation scheduling establishment can not only be given security for tracking control annual plan performance, can provide the basic datas such as monthly tracking target for arranging short-term and real-time generation schedule again simultaneously.Present some preparing methods of monthly generation scheduling, as annual plan divide equally, the progress such as monthly, etc. the methods such as progress such as rate of load condensate and so-called annual plan in actual mechanical process, but often change because of unit maintenance adjustment, supply and demand and the factor affecting such as newly conclude the transaction all not have realization to effective control of annual plan completion rate deviation.
Summary of the invention
For the deficiencies in the prior art, the invention provides the roll implementation method of establishment monthly generation scheduling of the progress such as a kind of, the method is at first adjusted each tracking power plant year generation schedule in proportion according to follow-up month system's tracking thermoelectricity power generation needs, then considering to satisfy annual follow-up month system's tracking thermoelectricity power generation needs, the dump energy of annual plan is reasonably allocated to follow-up month after will adjusting under the constraint conditions such as unit operation situation and minute month electric weight of having concluded the transaction, roll to generate follow-up month monthly generation scheduling, and the monthly plan that does not satisfy the rate of load condensate constraint has been provided a kind of adjustment algorithm.The method can in the hope of rational follow-up month monthly generation scheduling value, realize the effective control to power plant's annual plan completion rate deviation simultaneously in unit load rate restriction range.
The objective of the invention is to adopt following technical proposals to realize:
The roll implementation method of establishment monthly generation scheduling of the progress such as a kind of, its improvements be, described implementation method comprises the steps:
A, determine generating plan model, establishment target and constraint condition;
B, the average regulation of calculating plan unit annual plan electric weight;
Whether plan unit annual plan electric weight surpassed its annual maximum generation ability after C, judgement were adjusted in proportion;
D, in proportion plan for adjustment unit year the generation schedule electric weight;
E, pre-year-by-year plan dump energy;
F, monthly pre-minute result of adjustment.
Wherein, in the described steps A, described definite generating plan model comprises:
1) arbitrary tracking plan unit marks is i, wherein i ∈ [1, N]; If the month of monthly generation scheduling to be worked out is inferior month, i.e. the m month, follow-up arbitrary month is t ∈ [m, 12];
2) per month calendar fate is D (t); The tracking thermoelectricity power generation needs in inferior month and follow-up month is W (t), wherein W (t) is according to whole society's tracking power consumption aggregate demand, consider to purchase between net/provinces sell, sent out plan electric weight that new and renewable sources of energy is given priority in arranging for the plan unit, all kinds of transaction (sending electric transaction, Generation Rights Trade electric weight etc. such as trust outside) of throwing annealing group of motors plan and preferred arrangement divide the tracking thermoelectricity plan unit generated energy demand that calculates behind moon electric weight;
3) the annual plan total amount of each plan unit is Ey (i), and plan unit i finished the annual plan generated energy by m before the month be Ef (i);
4) plan unit i is R (i, t) at the plan net result of t month arrangement, is limited on the rate of load condensate of setting
Figure BDA00001906445600021
Be limited under the rate of load condensate Lr(i, t); Plan unit i is C (i, t) in t month installed capacity; All kinds of transaction of plan unit i are Eytd (i, t) at the component of concluding the business the follow-up t month; Plan unit i in the maintenance of the t month, mediate and the fate that is obstructed adds up to Dc (i, t); The monthly actual motion fate in plan unit of rear calculated for subsequent month, Dr (i, t)=D (t)-Dc (i, t) are overhauled, are obstructed and mediated to Dr (i, t) expression consideration of planning monoblock.
Wherein, in the described steps A, when the monthly plan in the m month to Dec is worked out in rolling, if there is not the situation that surpasses its maximum generation ability when adjusting annual plan in the plan unit, then plan unit year terminal hour annual plan completion rate deviation identical, then work out target and represent with following 1. formula:
Σ t = m t = 12 R ( i , t ) + Ef ( i ) Ey ( i ) = Σ t = m t = 12 R ( j , t ) + Ef ( j ) Ey ( j ) , i ≠ j
Wherein, i ∈ [1, N], j ∈ [1, N], N is plan unit sum.
Wherein, in the described steps A, described constraint condition comprises the plan unit load rate constraint of hair electrobalance constraint condition and transaction of follow-up month minute moon electric weight;
Described hair electrobalance constraint referred to follow-up month, and plan modular plan electric weight must satisfy the demand of monthly tracking thermoelectricity generated energy, represents with following 2. formula:
Figure BDA00001906445600031
Described subsequent transaction divides the plan unit load rate constraint of moon electric weight to refer to for the plan unit that has monthly transaction component, all kinds of transaction electric weight that comprise in the monthly plan electric weight are preferential clearing, the monthly plan electric weight must preferentially guarantee finishing of this transaction minute moon electric weight, represents with following 3. formula:
Lr ‾ ( i , t ) ≤ R ( i , t ) + Eytd ( i , t ) C ( i , t ) × Dr ( i , t ) × 24 ≤ Lr ‾ ( i , t )
For the plan unit that does not all move the whole month, i.e. D (t)=Dc (i, t), then Lr(i, t) and All be set to 0.Wherein, among the described step B, annual plan electric weight average regulation in described plan unit represents with following 4. formula:
α = Σ t = m t = 12 W ( t ) + Σ i = 1 i = N Ef ( i ) Σ i = 1 i = N Ey ( i )
Wherein, among the described step C, plan for adjustment unit annual plan electric weight in proportion, but and by calculate residue month annual plan dump energy to be allocated whether surpass plan maximum generated energy of follow-up month of unit, according to following formula 5. with formula 6. judge adjust in proportion after plan unit annual plan whether surpass its annual maximum generation ability:
Ey′(i)=Ey(i)*α ⑤;
Ey ′ ( i ) - Ef ( i ) ≤ Σ t = m t = 12 Dr ( i , t ) * C ( i , t ) * 24 * Lr ‾ ( i , t ) - Eytd ( i , t ) )
Wherein: Ey ' (i) represents that each plans the annual plan total amount of unit afterwards in proportion adjustment.
Wherein, if plan unit annual plan surpasses its annual maximum generation ability after adjusting in proportion, then plan for adjustment unit annual plan is actual electric weight and the residue month maximum electric weight sum of can generating electricity finished, but fixing residue monthly plan is monthly maximum generated energy, and according to following formula 7. with formula 8. recomputate the average regulation α of plan unit annual plan electric weight and time month and the tracking thermoelectricity power generation needs in follow-up month be W (t):
α = Σ t = m t = 12 W ( t ) - Σ i ∉ E ( Ey ′ ( i ) - Ef ( i ) ) + Σ i ∈ E Ef ( i ) Σ i ∈ E Ey ( i )
W ( t ) = W ( t ) - Σ i ∉ E ( Dr ( i , t ) * C ( i , t ) * 24 * Lr ‾ ( i , t ) - Eytd ( i , t ) )
Set E is defined as 8. formula establishment of E={i| };
Directly be set as maximum generating watt for not belonging to the modular plan value of gathering E, represent with following 9. formula:
R ( i , t ) = Dr ( i , t ) * C ( i , t ) * 24 * Lr ‾ ( i , t ) - Eytd ( i , t ) , i ∉ E
Wherein, if plan unit annual plan does not surpass its annual maximum generation ability after adjusting in proportion, carry out step D.
Wherein, in the described step e, pre-year-by-year plan dump energy comprises the steps:
A, annual dump energy divide in advance;
B, monthly plan result adjust balance;
C, annual plan are adjusted balance.
Wherein, among the described step a, arranging first the transaction component is Eytd (i, t), simultaneously in conjunction with after unit operation situation and the generated energy demand, the annual plan dump energy is arranged into follow-up month, represents with following 10. formula:
Rh ( i , t ) = W ( t ) × ( Dr ( i , t ) - Eytd ( i , t ) C ( i , t ) × 24 ) Σ t = m t = 12 ( Dr ( i , t ) - Eytd ( i , t ) C ( i , t ) × 24 ) × W ( t ) × ( E y ′ ( i ) - Ef ( i ) ) , i ∈ E
Wherein: the annual plan dump energy carries out monthly decomposition result after will planning the unit adjustment after Rh (i, t) expression consideration maintenance, monthly transaction electric weight and the power generation needs factor.
Wherein, among the described step b, divide in advance electric weight ratio plan for adjustment unit transverse decomposition result Rh (i, t) according to step a, to satisfy monthly power generation needs W (t), with following
Figure BDA00001906445600043
Formula represents:
Figure BDA00001906445600044
Wherein: the pre-minute vertical decomposition result in electric weight Rh (i, t) ratio plan for adjustment unit of Rv (i, t) expression;
Described monthly plan result satisfies 2. formula of described constraint condition.
Wherein, among the described step c, calculate the per month electric weight of needs adjustment of each plan unit according to the ratio of monthly power generation needs prediction, the described electric weight that needs per month to adjust is with following
Figure BDA00001906445600045
Formula represents:
Figure BDA00001906445600046
Wherein: σ (i, t) expression for so that residue month monthly plan summation with adjust (i) identical and difference that the monthly plan of every month is adjusted of rear annual plan dump energy LefyEy ';
LeftEy′(i)=Ey′(i)-Ef(i);
Vertical decomposition result is carried out following adjustment: R (i, t)=Rv (i, t)-σ (i, t), i ∈ E;
The planned outcome of described pre-year-by-year plan dump energy satisfies 2. formula of constraint condition.
Wherein, in the described step F, described adjustment is monthly pre-minute result comprise: each month t of the m-12 month of each the plan unit i in the traversal E set:
1) if plan unit i is that R (i, t) exceeds the rate of load condensate upper limit in the planned outcome of t month arrangement
Figure BDA00001906445600051
Then will plan electric weight by the power generation load rate upper limit And electric weight temp adjusted in record; Travel through other month, search the month t ' of the temp electric weight of can dissolving; But travel through from big to small residue plan unit j ∈ E according to remaining the generated energy ability t month, find the temp electric weight of can dissolving, and can cut down the plan unit j of generation schedule the t ' moon, carry out following operation:
R(i,t)=R(i,t)-temp
Figure BDA00001906445600053
R(i,t′)=R(i,t′)+temp
Figure BDA00001906445600054
R(j,t)=R(j,t)+temp
Figure BDA00001906445600055
R(j,t′)=R(j,t′)-temp
R (i, t ') expression unit i is in the monthly plan value of t '; R (j, t ') expression unit j is in the monthly plan value of t ';
2) if plan unit i is that R ' (i, t) exceeds the rate of load condensate lower limit in the planned outcome of t month arrangement Lr(i, t) then will plan electric weight and increase to the power generation load rate lower limit Lr(i, t), and electric weight temp adjusted in record; Travel through other month, search the follow-up month t ' that can cut down the temp electric weight; Travel through from big to small residue plan unit j ∈ E according to t month generating capacity, find and can cut down the temp electric weight, and at the plan unit j of generation schedule that can dissolve by the t ' moon; Carry out following operation:
R(i,t)=R(i,t)-temp
Figure BDA00001906445600057
R(i,t′)=R(i,t′)+temp
Figure BDA00001906445600058
R(j,t)=R(j,t)+temp
Figure BDA00001906445600059
R(j,t′)=R(j,t′)-temp
Figure BDA000019064456000510
3) if the t monthly plan of unit i as a result R ' (i, t) do not exceed rate of load condensate bound constraint, then continue traversal, until traveled through all months of the m-12 month.
Compared with the prior art, the beneficial effect that reaches of the present invention is:
1, the progress such as the provided by the invention implementation method of establishment monthly generation scheduling of rolling, when inferior month monthly generation schedule of establishment, no longer be confined to a time month month, but be conceived to annual residue month, and the annual situation of when arranging inferior monthly plan, can making overall plans like this, more scientific and reasonable.
2, the progress such as the provided by the invention implementation method of establishment monthly generation scheduling of rolling, for progresses such as the unit annual plans that realizes a plan, taked on average to adjust coefficient according to the actual annual plan of finishing total amount, following power generation needs total amount and total system annual plan calculation of total plan unit of total system, in proportion adjustment unit annual plan electric weight.
3, the progress such as the provided by the invention implementation method of establishment monthly generation scheduling of rolling, calculating the annual plan dump energy after annual plan electric weight and the actual performance after the consideration unit adjustment, divide in advance through the annual plan dump energy, monthly power generation needs leveling, the leveling of annual plan dump energy and rate of load condensate constraint adjustment FOUR EASY STEPS scientific and reasonable arrangement time monthly plan and follow-up month are pre-planned.
4, the progress such as the provided by the invention implementation method of establishment monthly generation scheduling of rolling has solved plan unit annual plan completion rate deviation problems of too, and effectively simple.
Description of drawings
Fig. 1 be monthly generation scheduling provided by the invention etc. progress rolling preparation method schematic flow sheet.
Embodiment
Below in conjunction with accompanying drawing the specific embodiment of the present invention is described in further detail.
Monthly generation scheduling provided by the invention etc. progress rolling preparation method flow process as shown in Figure 1, the method comprises the steps:
A, determine generating plan model, establishment target and constraint condition;
(1) generating plan model comprises:
1) arbitrary tracking plan unit marks is i, wherein i ∈ [1, N]; If the month of monthly generation scheduling to be worked out is inferior month, i.e. the m month, follow-up arbitrary month is t ∈ [m, 12];
2) per month calendar fate is D (t); The tracking thermoelectricity power generation needs in inferior month and follow-up month is W (t), wherein W (t) is according to whole society's tracking power consumption aggregate demand, considers to purchase between net/provinces to sell, sent out plan electric weight that new and renewable sources of energy is given priority in arranging for the plan unit, throw annealing group of motors plan and all kinds of transaction (sending electric transaction, Generation Rights Trade electric weight etc. such as trust outside) of giving priority in arranging for divide the tracking thermoelectricity plan unit generated energy demand that calculates behind moon electric weight;
3) the annual plan total amount of each plan unit is Ey (i), and plan unit i finished the annual plan generated energy by m before the month be Ef (i);
4) plan unit i is R (i, t) at the plan net result of t month arrangement, is limited on the rate of load condensate of setting
Figure BDA00001906445600061
Be limited under the rate of load condensate Lr(i, t); Plan unit i is C (i, t) in t month installed capacity; All kinds of transaction of plan unit i are Eytd (i, t) at the component of concluding the business the follow-up t month; Plan unit i in the maintenance of the t month, mediate and the fate that is obstructed adds up to Dc (i, t); The monthly actual motion fate in plan unit of rear calculated for subsequent month, Dr (i, t)=D (t)-Dc (i, t) are overhauled, are obstructed and mediated to Dr (i, t) expression consideration of planning monoblock.
(2) establishment target:
When rolling the monthly plan in the establishment m month to Dec, if there is not the situation that surpasses its maximum generation ability when adjusting annual plan in the plan unit, then plan unit year terminal hour annual plan completion rate deviation identical, then work out target and represent with following 1. formula:
Σ t = m t = 12 R ( i , t ) + Ef ( i ) Ey ( i ) = Σ t = m t = 12 R ( j , t ) + Ef ( j ) Ey ( j ) , i ≠ j
Wherein, i ∈ [1, N], j ∈ [1, N], N is plan unit sum.
(3) constraint condition:
This method is mainly considered the constraint of hair electrobalance, is considered the plan unit load rate constraint of follow-up month transaction minute moon electric weight.
The constraint of hair electrobalance referred to follow-up month, and plan modular plan electric weight must satisfy the demand of monthly tracking thermoelectricity generated energy, represents with following 2. formula:
Figure BDA00001906445600072
Subsequent transaction divides the plan unit load rate constraint of moon electric weight to refer to for the plan unit that has monthly transaction component, all kinds of transaction electric weight that comprise in the monthly plan electric weight are preferential clearing, the monthly plan electric weight must preferentially guarantee finishing of this transaction minute moon electric weight, represents with following 3. formula:
Lr ‾ ( i , t ) ≤ R ( i , t ) + Eytd ( i , t ) C ( i , t ) × Dr ( i , t ) × 24 ≤ Lr ‾ ( i , t )
For the plan unit that does not all move the whole month, i.e. D (t)=Dc (i, t), then Lr(i, t) and
Figure BDA00001906445600074
All be set to 0.
B, the average regulation of calculating plan unit annual plan electric weight;
The average regulation of plan unit annual plan electric weight represents with following 4. formula:
α = Σ t = m t = 12 W ( t ) + Σ i = 1 i = N Ef ( i ) Σ i = 1 i = N Ey ( i )
Whether plan unit annual plan electric weight surpassed its annual maximum generation ability after C, judgement were adjusted in proportion;
Plan for adjustment unit annual plan electric weight on year-on-year basis, but and by calculate residue month annual plan dump energy to be allocated whether surpass maximum generated energy of follow-up month of unit, verify whether adjust in proportion rear annual plan has surpassed its annual maximum generation ability
Ey′(i)=Ey(i)*α ⑤;
Ey ′ ( i ) - Ef ( i ) ≤ Σ t = m t = 12 Dr ( i , t ) * C ( i , t ) * 24 * Lr ‾ ( i , t ) - Eytd ( i , t ) )
Wherein: Ey ' (i) represents that each plans the annual plan total amount of unit afterwards in proportion adjustment.
If plan unit annual plan surpasses its annual maximum generation ability after adjusting in proportion, then plan for adjustment unit annual plan is actual electric weight and the residue month maximum electric weight sum of can generating electricity finished, but fixing residue monthly plan is monthly maximum generated energy, and according to following formula 7. with formula 8. recomputate plan unit annual plan electric weight average regulation α and time month and the tracking thermoelectricity power generation needs in follow-up month be W (t), get final product if set E element number is N then execution in step E, otherwise recomputate factor alpha and adjustment W (t) according to following formula:
α = Σ t = m t = 12 W ( t ) - Σ i ∉ E ( Ey ′ ( i ) - Ef ( i ) ) + Σ i ∈ E Ef ( i ) Σ i ∈ E Ey ( i )
W ( t ) = W ( t ) - Σ i ∉ E ( Dr ( i , t ) * C ( i , t ) * 24 * Lr ‾ ( i , t ) - Eytd ( i , t ) )
Set E is defined as 8. formula establishment of E={i| };
Directly be set as maximum generating watt for not belonging to the modular plan value of gathering E, represent with following 9. formula:
R ( i , t ) = Dr ( i , t ) * C ( i , t ) * 24 * Lr ‾ ( i , t ) - Eytd ( i , t ) , i ∉ E
If plan unit annual plan does not surpass its annual maximum generation ability after adjusting in proportion, carry out step D.
D, in proportion plan for adjustment unit year the generation schedule electric weight.
Ey′(i)=Ey(i)*α
E, pre-year-by-year plan dump energy;
Pre-year-by-year plan dump energy comprises the steps:
A, annual dump energy divide in advance; Arranging first the transaction component is Eytd (i, t), simultaneously in conjunction with after unit operation situation and the generated energy demand, the annual plan dump energy is arranged into follow-up month, represents with following 10. formula:
Rh ( i , t ) = W ( t ) × ( Dr ( i , t ) - Eytd ( i , t ) C ( i , t ) × 24 ) Σ t = m t = 12 ( Dr ( i , t ) - Eytd ( i , t ) C ( i , t ) × 24 ) × W ( t ) × ( Ey ′ ( i ) - Ef ( i ) ) , i ∈ E
Wherein: the annual plan dump energy carries out monthly decomposition result after will planning the unit adjustment after Rh (i, t) expression consideration maintenance, monthly transaction electric weight and the power generation needs factor.
B, monthly plan result adjust balance; Divide in advance electric weight ratio plan for adjustment unit transverse decomposition result Rh (i, t) according to step a, to satisfy monthly power generation needs W (t), with following
Figure BDA00001906445600092
Formula represents:
Figure BDA00001906445600093
Wherein: the pre-minute vertical decomposition result in electric weight Rh (i, t) ratio plan for adjustment unit of Rv (i, t) expression;
The monthly plan result satisfies 2. formula of described constraint condition.
C, annual plan are adjusted balance; Prove at mathematics
Figure BDA00001906445600094
Apparent because the two all with
Figure BDA00001906445600095
Unanimously.Because it is not quite identical that different plan monoblock ruuning situations and transaction minute moon electric weight etc. distribute in month, causes
Figure BDA00001906445600096
And Ey ' (i)-Ef (i), i ∈ E is not necessarily identical.Calculate the per month electric weight of needs adjustment of each plan unit according to the ratio of monthly power generation needs prediction, the described electric weight that needs per month to adjust is with following
Figure BDA00001906445600097
Formula represents:
Figure BDA00001906445600098
Wherein: σ (i, t) expression for so that residue month monthly plan summation with adjust (i) identical and difference that the monthly plan of every month is adjusted of rear annual plan dump energy LeftEy ';
LeftEy′(i)=Ey′(i)-Ef(i)
Vertical decomposition result is carried out following adjustment: R (i, t)=Rv (i, t)-σ (i, t), i ∈ E;
The planned outcome of pre-year-by-year plan dump energy satisfies 2. formula of constraint condition.
F, monthly pre-minute result of adjustment;
Adjusting monthly pre-minute result comprises:
Each month t of the m-12 month of each plan unit i in the traversal E set:
1) if plan unit i is that R (i, t) exceeds the rate of load condensate upper limit in the planned outcome of t month arrangement
Figure BDA00001906445600101
Then will plan electric weight by the power generation load rate upper limit And electric weight temp adjusted in record; Travel through other month, search the month t ' of the temp electric weight of can dissolving; But travel through from big to small residue plan unit j ∈ E according to remaining the generated energy ability t month, find the temp electric weight of can dissolving, and can cut down the plan unit j of generation schedule the t ' moon, carry out following operation:
R(i,t)=R(i,t)-temp R(i,t′)=R(i,t′)+temp
Figure BDA00001906445600104
R(j,t)=R(j,t)+temp
Figure BDA00001906445600105
R(j,t′)=R(j,t′)-temp
Figure BDA00001906445600106
R (i, t ') expression unit i is in the monthly plan value of t '; R (j, t ') expression unit j is in the monthly plan value of t ';
2) if plan unit i is that R ' (i, t) exceeds the rate of load condensate lower limit in the planned outcome of t month arrangement Lr(i, t) then will plan electric weight and increase to the power generation load rate lower limit Lr(i, t), and electric weight temp adjusted in record; Travel through other month, search the follow-up month t ' that can cut down the temp electric weight; Travel through from big to small residue plan unit j ∈ E according to t month generating capacity, find and can cut down the temp electric weight, and at the plan unit j of generation schedule that can dissolve by the t ' moon; Carry out following operation:
R(i,t)=R(i,t)-temp
Figure BDA00001906445600107
R(i,t′)=R(i,t′)+temp
Figure BDA00001906445600108
R(j,t)=R(j,t)+temp
Figure BDA00001906445600109
R(j,t′)=R(j,t′)-temp
3) if the t monthly plan of unit i as a result R ' (i, t) do not exceed rate of load condensate bound constraint, then continue traversal, until traveled through all months of the m-12 month.
The roll implementation method of establishment monthly generation scheduling of the progress such as provided by the invention, when the establishment monthly plan, not only be confined to inferior month, but divide moon electric weight to arrange the monthly generation scheduling in annual all residue months in conjunction with power generation needs, unit operation situation and the transaction in all months of residue, also follow-up all months of rolling amendment pre-planned in establishment time month monthly generation schedule considered early to the planning influence factor that may occur future thus like this.
Unit annual plan completion rate deviation is identical in order to realize a plan, and unit annual plan electric weight is adjusted in proportion.On average adjust coefficient according to the actual annual plan of finishing total amount, following power generation needs total amount and total system annual plan calculation of total plan unit of total system, like this finish realized under the condition of annual plan after adjusting to the synchro control (except the plan unit that can't adjust in proportion because of the self generating scarce capacity) of planned unit annual plan completion rate deviation.
According to annual plan dump energy after the unit adjustment, to divide in advance through the annual plan dump energy, monthly power generation needs leveling, the leveling of annual plan dump energy and rate of load condensate constraint adjustment FOUR EASY STEPS scientific and reasonable arrangement time monthly plan and follow-up month are pre-planned.Method of the present invention can in the hope of rational follow-up month monthly generation scheduling value, realize the effective control to power plant's annual plan completion rate deviation simultaneously in unit load rate restriction range.
Should be noted that at last: above embodiment is only in order to illustrate that technical scheme of the present invention is not intended to limit, although with reference to above-described embodiment the present invention is had been described in detail, those of ordinary skill in the field are to be understood that: still can make amendment or be equal to replacement the specific embodiment of the present invention, and do not break away from any modification of spirit and scope of the invention or be equal to replacement, it all should be encompassed in the middle of the claim scope of the present invention.

Claims (13)

1. the progress such as kind implementation method of establishment monthly generation scheduling of rolling is characterized in that, described implementation method comprises the steps:
A, determine generating plan model, establishment target and constraint condition;
B, the average regulation of calculating plan unit annual plan electric weight;
Whether plan unit annual plan electric weight surpassed its annual maximum generation ability after C, judgement were adjusted in proportion;
D, in proportion plan for adjustment unit year the generation schedule electric weight;
E, pre-year-by-year plan dump energy;
F, monthly pre-minute result of adjustment.
2. the progress such as the as claimed in claim 1 implementation method of establishment monthly generation scheduling of rolling is characterized in that, in the described steps A, described definite generating plan model comprises:
1) arbitrary tracking plan unit marks is i, wherein i ∈ [1, N]; If the month of monthly generation scheduling to be worked out is inferior month, i.e. the m month, follow-up arbitrary month is t ∈ [m, 12];
2) per month calendar fate is D (t); The tracking thermoelectricity power generation needs in inferior month and follow-up month is W (t), wherein W (t) is according to whole society's tracking power consumption aggregate demand, consider to purchase between net/provinces sell, the group of motors plan is annealed in sent out plan electric weight, throwing that new and renewable sources of energy is given priority in arranging for the plan unit and all kinds of transaction divides the tracking thermoelectricity plan unit that calculates behind moon electric weight generated energy demand;
3) the annual plan total amount of each plan unit is Ey (i), and plan unit i finished the annual plan generated energy by m before the month be Ef (i);
4) plan unit i is R (i, t) at the plan net result of t month arrangement, is limited on the rate of load condensate of setting Be limited to Lr (i, t) under the rate of load condensate; Plan unit i is C (i, t) in t month installed capacity; All kinds of transaction of plan unit i are Eytd (i, t) at the component of concluding the business the follow-up t month; Plan unit i in the maintenance of the t month, mediate and the fate that is obstructed adds up to Dc (i, t); The monthly actual motion fate in plan unit of rear calculated for subsequent month, Dr (i, t)=D (t)-Dc (i, t) are overhauled, are obstructed and mediated to Dr (i, t) expression consideration of planning monoblock.
3. the progress such as the as claimed in claim 1 implementation method of establishment monthly generation scheduling of rolling, it is characterized in that, in the described steps A, when the monthly plan in the m month to Dec is worked out in rolling, if there is not the situation that surpasses its maximum generation ability when adjusting annual plan in the plan unit, then plan unit year terminal hour annual plan completion rate deviation identical, then work out target and represent with following 1. formula:
Figure FDA00001906445500021
Wherein, i ∈ [1, N], j ∈ [1, N], N is plan unit sum.
4. the progress such as the as claimed in claim 1 implementation method of establishment monthly generation scheduling of rolling is characterized in that, in the described steps A, described constraint condition comprises the plan unit load rate constraint of hair electrobalance constraint condition and transaction of follow-up month minute moon electric weight;
Described hair electrobalance constraint referred to follow-up month, and plan modular plan electric weight must satisfy the demand of monthly tracking thermoelectricity generated energy, represents with following 2. formula:
Figure FDA00001906445500022
Described subsequent transaction divides the plan unit load rate constraint of moon electric weight to refer to for the plan unit that has monthly transaction component, all kinds of transaction electric weight that comprise in the monthly plan electric weight are preferential clearing, the monthly plan electric weight must preferentially guarantee finishing of this transaction minute moon electric weight, represents with following 3. formula:
Figure FDA00001906445500023
For the plan unit that does not all move the whole month, i.e. D (t)=Dc (i, t), then Lr (i, t) and
Figure FDA00001906445500024
All be set to 0.
5. the progress such as the as claimed in claim 1 implementation method of establishment monthly generation scheduling of rolling is characterized in that, among the described step B, annual plan electric weight average regulation in described plan unit represents with following 4. formula:
6. the progress such as the as claimed in claim 1 implementation method of establishment monthly generation scheduling of rolling, it is characterized in that, among the described step C, plan for adjustment unit annual plan electric weight in proportion, but and by calculate residue month annual plan dump energy to be allocated whether surpass plan maximum generated energy of follow-up month of unit, according to following formula 5. with formula 6. judge adjust in proportion after plan unit annual plan whether surpass its annual maximum generation ability:
Ey′(i)=Ey(i)*α ⑤;
Figure FDA00001906445500026
Wherein: Ey ' (i) represents that each plans the annual plan total amount of unit afterwards in proportion adjustment.
7. the progress such as the as claimed in claim 6 implementation method of establishment monthly generation scheduling of rolling, it is characterized in that, if plan unit annual plan surpasses its annual maximum generation ability after adjusting in proportion, then plan for adjustment unit annual plan is actual electric weight and the residue month maximum electric weight sum of can generating electricity finished, but fixing residue monthly plan is monthly maximum generated energy, and according to following formula 7. with formula 8. recomputate the average regulation α of plan unit annual plan electric weight and time month and the tracking thermoelectricity power generation needs in follow-up month be W (t):
Figure FDA00001906445500031
Figure FDA00001906445500032
Set E is defined as 8. formula establishment of E={i| };
Directly be set as maximum generating watt for not belonging to the modular plan value of gathering E, represent with following 9. formula:
Figure FDA00001906445500033
8. the progress such as the as claimed in claim 6 implementation method of establishment monthly generation scheduling of rolling is characterized in that, if plan unit annual plan does not surpass its annual maximum generation ability after adjusting in proportion, carries out step D.
9. the progress such as the as claimed in claim 1 implementation method of establishment monthly generation scheduling of rolling is characterized in that, in the described step e, pre-year-by-year plan dump energy comprises the steps:
A, annual dump energy divide in advance;
B, monthly plan result adjust balance;
C, annual plan are adjusted balance.
10. the progress such as the as claimed in claim 9 implementation method of establishment monthly generation scheduling of rolling, it is characterized in that, among the described step a, arranging first the transaction component is Eytd (i, t), in conjunction with after unit operation situation and the generated energy demand, the annual plan dump energy is arranged into follow-up month simultaneously, represents with following 10. formula:
Wherein: the annual plan dump energy carries out monthly decomposition result after will planning the unit adjustment after Rh (i, t) expression consideration maintenance, monthly transaction electric weight and the power generation needs factor.
The implementation method of establishment monthly generation scheduling is characterized in that, among the described step b 11. the progress such as claimed in claim 9 is rolled, divide in advance electric weight ratio plan for adjustment unit transverse decomposition result Rh (i according to step a, t), to satisfy monthly power generation needs W (t), with following
Figure FDA00001906445500041
Formula represents:
Figure FDA00001906445500042
Wherein: the pre-minute vertical decomposition result in electric weight Rh (i, t) ratio plan for adjustment unit of Rv (i, t) expression;
Described monthly plan result satisfies 2. formula of described constraint condition.
The implementation method of establishment monthly generation scheduling 12. the progress such as claimed in claim 9 is rolled, it is characterized in that, among the described step c, calculate the per month electric weight of needs adjustment of each plan unit according to the ratio of monthly power generation needs prediction, the described electric weight that needs per month to adjust is with following
Figure FDA00001906445500043
Formula represents:
Figure FDA00001906445500044
Wherein: σ (i, t) expression for so that residue month monthly plan summation with adjust (i) identical and difference that the monthly plan of every month is adjusted of rear annual plan dump energy LeftEy ';
LeftEy′(i)=Ey′(i)-Ef(i);
Vertical decomposition result is carried out following adjustment: R (i, t)=Rv (i, t)-σ (i, t), i ∈ E;
The planned outcome of described pre-year-by-year plan dump energy satisfies 2. formula of constraint condition.
The implementation method of establishment monthly generation scheduling is characterized in that 13. the progress such as claimed in claim 1 is rolled, and in the described step F, described adjustment is monthly pre-minute result comprise: each month t of the m-12 month of each the plan unit i in the traversal E set:
1) if plan unit i is that R (i, t) exceeds the rate of load condensate upper limit in the planned outcome of t month arrangement
Figure FDA00001906445500045
Then will plan electric weight by the power generation load rate upper limit
Figure FDA00001906445500046
And electric weight temp adjusted in record; Travel through other month, search the month t ' of the temp electric weight of can dissolving; But travel through from big to small residue plan unit j ∈ E according to remaining the generated energy ability t month, find the temp electric weight of can dissolving, and can cut down the plan unit j of generation schedule the t ' moon, carry out following operation:
R(i,t)=R(i,t)-temp
Figure FDA00001906445500047
R(i,t′)=R(i,t′)+temp
Figure FDA00001906445500048
R(j,t)=R(j,t)+temp
Figure FDA00001906445500051
R(j,t′)=R(j,t′)-temp
Figure FDA00001906445500052
R (i, t ') expression unit i is in the monthly plan value of t '; R (j, t ') expression unit j is in the monthly plan value of t ';
2) if plan unit i is that R ' (i, t) exceeds the rate of load condensate lower limit in the planned outcome of t month arrangement Lr(i, t) then will plan electric weight and increase to the power generation load rate lower limit Lr(i, t), and electric weight temp adjusted in record; Travel through other month, search the follow-up month t ' that can cut down the temp electric weight; Travel through from big to small residue plan unit j ∈ E according to t month generating capacity, find and can cut down the temp electric weight, and at the plan unit j of generation schedule that can dissolve by the t ' moon; Carry out following operation:
R(i,t)=R(i,t)-temp
Figure FDA00001906445500053
R(i,t′)=R(i,t′)+temp
Figure FDA00001906445500054
R(j,t)=R(j,t)+temp
Figure FDA00001906445500055
R(j,t′)=R(j,t′)-temp
Figure FDA00001906445500056
3) if the t monthly plan of unit i as a result R ' (i, t) do not exceed rate of load condensate bound constraint, then continue traversal, until traveled through all months of the m-12 month.
CN201210251307.XA 2012-07-19 2012-07-19 The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling Active CN102867228B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210251307.XA CN102867228B (en) 2012-07-19 2012-07-19 The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210251307.XA CN102867228B (en) 2012-07-19 2012-07-19 The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling

Publications (2)

Publication Number Publication Date
CN102867228A true CN102867228A (en) 2013-01-09
CN102867228B CN102867228B (en) 2016-08-10

Family

ID=47446091

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210251307.XA Active CN102867228B (en) 2012-07-19 2012-07-19 The progress such as a kind of rolls the implementation method of establishment monthly generation scheduling

Country Status (1)

Country Link
CN (1) CN102867228B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104484772A (en) * 2014-12-30 2015-04-01 广东电网有限责任公司电力调度控制中心 Power plan feasibility check method and system
CN104517199A (en) * 2015-01-16 2015-04-15 国家电网公司 New energy power generation online monitoring method based on real time data
CN104616069A (en) * 2015-01-13 2015-05-13 国电南瑞科技股份有限公司 Annual power generation plan rolled decomposition optimization method taking balance between plan finishing rate and load rate into consideration
CN105678394A (en) * 2014-11-07 2016-06-15 国家电网公司 Multi-source and multi-cycle generation schedule formulation method
CN106779297A (en) * 2016-11-23 2017-05-31 青岛鹏海软件有限公司 A kind of method for realizing target Rolling Planning and execution
CN107590559A (en) * 2017-09-04 2018-01-16 广东电网有限责任公司电力调度控制中心 A kind of monthly electricity regulation and control method of cogeneration power plant
CN108182506A (en) * 2017-12-05 2018-06-19 中国电力科学研究院有限公司 A kind of step-by-step optimization method and apparatus of monthly generation scheduling
CN108388968A (en) * 2018-03-20 2018-08-10 云南电网有限责任公司玉溪供电局 Generation schedule based on pre- bid deviation electric quantity balancing mechanism rolls method of adjustment
CN109325878A (en) * 2018-08-16 2019-02-12 国网浙江省电力有限公司绍兴供电公司 Generation schedule optimization method is rolled based on three public scheduling years two stages
CN109978398A (en) * 2019-04-01 2019-07-05 南京师范大学 A kind of electric power medium and long-term transaction contract rolling method
CN113627724A (en) * 2021-07-02 2021-11-09 江苏能电科技有限公司 Method and device for reasonably distributing electric quantity, storage medium and solar street lamp equipment
CN118014319A (en) * 2024-04-09 2024-05-10 国网浙江省电力有限公司宁波供电公司 Associated collaborative management method, device, equipment and medium for comprehensive power grid plan

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102156815A (en) * 2011-04-07 2011-08-17 国电南瑞科技股份有限公司 Method for optimizing power generation plan in mode of tracing scheduling of annual electric quantity progress
CN102509176A (en) * 2011-11-10 2012-06-20 山东电力集团公司德州供电公司 Decision method for rolling optimization of wind and light storage cooperative scheduling

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102156815A (en) * 2011-04-07 2011-08-17 国电南瑞科技股份有限公司 Method for optimizing power generation plan in mode of tracing scheduling of annual electric quantity progress
CN102509176A (en) * 2011-11-10 2012-06-20 山东电力集团公司德州供电公司 Decision method for rolling optimization of wind and light storage cooperative scheduling

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
韩家辉: "节能减排约束下的发电单元年度电能计划编制方法", 《中国优秀硕士学位论文全文数据库工程科技II辑》 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105678394B (en) * 2014-11-07 2020-04-14 国家电网公司 Multi-source multi-cycle power generation plan making method
CN105678394A (en) * 2014-11-07 2016-06-15 国家电网公司 Multi-source and multi-cycle generation schedule formulation method
CN104484772A (en) * 2014-12-30 2015-04-01 广东电网有限责任公司电力调度控制中心 Power plan feasibility check method and system
CN104484772B (en) * 2014-12-30 2017-10-20 广东电网有限责任公司电力调度控制中心 The feasibility method of calibration and system of electricity plan
CN104616069A (en) * 2015-01-13 2015-05-13 国电南瑞科技股份有限公司 Annual power generation plan rolled decomposition optimization method taking balance between plan finishing rate and load rate into consideration
CN104616069B (en) * 2015-01-13 2017-11-10 国电南瑞科技股份有限公司 A kind of annual generation schedule rolls decomposition optimization
CN104517199A (en) * 2015-01-16 2015-04-15 国家电网公司 New energy power generation online monitoring method based on real time data
CN106779297A (en) * 2016-11-23 2017-05-31 青岛鹏海软件有限公司 A kind of method for realizing target Rolling Planning and execution
CN107590559A (en) * 2017-09-04 2018-01-16 广东电网有限责任公司电力调度控制中心 A kind of monthly electricity regulation and control method of cogeneration power plant
CN107590559B (en) * 2017-09-04 2020-09-25 广东电网有限责任公司电力调度控制中心 Monthly electric quantity regulation and control method for cogeneration power plant
CN108182506A (en) * 2017-12-05 2018-06-19 中国电力科学研究院有限公司 A kind of step-by-step optimization method and apparatus of monthly generation scheduling
CN108182506B (en) * 2017-12-05 2021-08-27 中国电力科学研究院有限公司 Step-by-step optimization method and device for monthly power generation plan
CN108388968A (en) * 2018-03-20 2018-08-10 云南电网有限责任公司玉溪供电局 Generation schedule based on pre- bid deviation electric quantity balancing mechanism rolls method of adjustment
CN108388968B (en) * 2018-03-20 2022-03-11 云南电网有限责任公司玉溪供电局 Power generation plan rolling adjustment method based on pre-bidding deviation electric quantity balance mechanism
CN109325878A (en) * 2018-08-16 2019-02-12 国网浙江省电力有限公司绍兴供电公司 Generation schedule optimization method is rolled based on three public scheduling years two stages
CN109978398A (en) * 2019-04-01 2019-07-05 南京师范大学 A kind of electric power medium and long-term transaction contract rolling method
CN113627724A (en) * 2021-07-02 2021-11-09 江苏能电科技有限公司 Method and device for reasonably distributing electric quantity, storage medium and solar street lamp equipment
CN113627724B (en) * 2021-07-02 2024-04-05 江苏能电科技有限公司 Method and device for reasonably distributing electric quantity, storage medium and solar street lamp equipment
CN118014319A (en) * 2024-04-09 2024-05-10 国网浙江省电力有限公司宁波供电公司 Associated collaborative management method, device, equipment and medium for comprehensive power grid plan

Also Published As

Publication number Publication date
CN102867228B (en) 2016-08-10

Similar Documents

Publication Publication Date Title
CN102867228A (en) Implementation method for scheduling monthly power generation plan in manner of rolling at equal progress
Wu et al. GENCO's risk-based maintenance outage scheduling
Bao et al. A multi time-scale and multi energy-type coordinated microgrid scheduling solution—Part II: Optimization algorithm and case studies
Pandžić et al. Near-optimal method for siting and sizing of distributed storage in a transmission network
EP2408082B1 (en) Integrated demand response for energy utilization
Banshwar et al. Market-based participation of energy storage scheme to support renewable energy sources for the procurement of energy and spinning reserve
Lynch et al. Optimal interconnection and renewable targets for north-west Europe
Blake et al. Optimization of distributed energy resources in an industrial microgrid
CN104616069A (en) Annual power generation plan rolled decomposition optimization method taking balance between plan finishing rate and load rate into consideration
CN105528466A (en) Wind power optimal planning modeling method considering adaptability and economy of power system
Liang et al. Robust optimization based bidding strategy for virtual power plants in electricity markets
CN112909933B (en) Intraday rolling optimization scheduling method containing pumped storage unit under spot market environment
Ntomaris et al. Optimal bidding of hybrid power stations in insular power systems
Geiger Strategic power plant investment planning under fuel and carbon price uncertainty
de Sousa Oliveira et al. Maintenance schedule optimization applied to large hydroelectric plants: Towards a methodology encompassing regulatory aspects
Meyer Federal Regulatory Barriers to Grid-Deployed Energy Storage
Khani et al. A real-time multistep optimization-based model for scheduling of storage-based large-scale electricity consumers in a wholesale market
Kumar et al. Stochastic profit‐based unit commitment problem considering renewable energy sources with battery storage systems and plug‐in hybrid electric vehicles
KR20210014616A (en) Operating system and method for integrated demand response resource
CN106780123A (en) A kind of Transaction algorithm decision-making technique for considering power constraint
CN111242438A (en) Evaluation method and system for flexibility adjustment capability of power generation and utilization resources of self-contained power plant
Makarov et al. Analysis methodology for balancing authority cooperation in high penetration of variable generation
Khorsand et al. Stochastic wind-thermal generation scheduling considering emission reduction: A multiobjective mathematical programming approach
JP2019149870A (en) Hybrid system connection system and linked free frame matching system
Hong et al. Electricity market and operations reliability

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant