CN102767379A - Shallow-buried unsymmetrical pressure section tunnel drilling construction method - Google Patents
Shallow-buried unsymmetrical pressure section tunnel drilling construction method Download PDFInfo
- Publication number
- CN102767379A CN102767379A CN201210285678XA CN201210285678A CN102767379A CN 102767379 A CN102767379 A CN 102767379A CN 201210285678X A CN201210285678X A CN 201210285678XA CN 201210285678 A CN201210285678 A CN 201210285678A CN 102767379 A CN102767379 A CN 102767379A
- Authority
- CN
- China
- Prior art keywords
- construction
- hole
- tunnel
- section
- arch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention relates to the field of tunnel construction and particularly relates to a shallow-buried unsymmetrical pressure section tunnel hole-entering construction method. The method can shorten the constriction period. The method comprises the steps of performing temporary tunnel lining of a drilling tunnel opening section, digging construction grooves arranged on two sides of a pipe-roof cover arch and performing inverted slope protection along sides of the construction grooves arranged on the two sides of the pipe-roof cover arch; performing pipe-roof cover arch construction, steel gantry construction and cover arch pouring; performing advanced supporting construction; performing pre-supporting construction of big pipe sheds or advanced small pipes; performing roof backfill back pressure; and performing underground excavation of an upper step and a lower step of a rock-soil body in an open cut tunnel section of an inner tunnel opening during the temporary tunnel lining of the drilling tunnel opening section.
Description
Technical field
The present invention relates to the constructing tunnel field, be specifically related to tunnel, a kind of shallow embedding bias voltage location and advance cavity construction method.
Background technology
Along with developing rapidly of social economy and transportation network, large-scale infrastructure, increasingly high to the construction period index request, still receive the restriction of landform, geological conditions, many road constructions are restricted.
Particularly the tunnel in shallow embedding bias voltage location advances hole when construction, because that the entrance end covering layer buries is more shallow, and crack, rock mass space; When raining, form the hole internal arch part easily and drench with rain, very easily produce roof fall and cave in; Tunnel exit end hillside natural grade is steeper; The hillside gradient is to the lopsidedness bias voltage, and barrel section country rock rank is low, and very easily generation is come down or subsided.
At present; The shallow embedding unsymmetrial loading tunnel enters the hole and generally adopts brush limit, top, hole, and the hole bias part is unloaded, and carries out anchor spray protection then; Carry out the earth and stone digging of portal section kerve again; Also to do advance support, also will build gravity barricade or antislide pile by laying bricks or stones at last, make that the construction period of this job practices is long at the opposite side that is symmetrical in bias voltage to hole bassoon canopy.
Summary of the invention
The present invention provides end tunnel, a kind of shallow embedding bias voltage ground to advance cavity construction method, can effectively shorten construction period.
To achieve these goals, the present invention realizes through following technical scheme:
Tunnel, a kind of shallow embedding bias voltage location advances cavity construction method, and this method may further comprise the steps:
Advance interim lining cutting of hole, hole section and pipe canopy cover arch both sides construction groove excavation, and pipe canopy cover arch both sides construction trough rim is faced upward the slope protection;
The construction of pipe canopy cover arch, the steel arch construction is built the cover arch;
The advance support construction;
Bassoon canopy or leading ductule are paid in advance and are protected construction;
Top, hole backfill back-pressure;
The tunneling of topping bar, get out of a predicament or an embarrassing situation of the open cut tunnel section geotechnical body of entering the inner hole of the interim lining cutting of hole, hole section.
Preferably, the said open cut tunnel section geotechnical body of entering the inner hole of the interim lining cutting of hole, hole section is topped bar, is got out of a predicament or an embarrassing situation after the step of tunneling, further comprises:
Advance hole, hole section inverted arch, inverted arch backfill.
Preferably, after the said step of advancing hole, hole section inverted arch, inverted arch backfill, further comprise:
Carry out short abutment wall construction.
Preferably, after the said step of carrying out the construction of short abutment wall, further comprise:
Advance the open cut tunnel section waterproofing course and the gutter construction of hole, hole section, and the step of open cut tunnel lining construction.
Preferably, saidly advance hole, hole section open cut tunnel section waterproofing course and gutter construction, and after the step of open cut tunnel lining construction, further comprise: the ancillary facility construction.
Preferably, saidly advance interim lining cutting of hole, hole section and pipe canopy cover arch both sides construction groove excavation, and before interim lining cutting faces upward the slope protection with pipe canopy cover arch both sides construction trough rim, comprise that further build catchwater, sloping surface dust is faced upward in finishing.
Preferably, said ancillary facility construction comprises hole jacking row greening recovery.
End tunnel, a kind of shallow embedding bias voltage provided by the invention ground advances cavity construction method, owing to adopt the method for the tunneling of topping bar, get out of a predicament or an embarrassing situation to construct in the open cut tunnel section geotechnical body of entering the inner hole of the interim lining cutting of hole, hole section, can effectively shorten construction period.
Description of drawings
In order to be illustrated more clearly in the embodiment of the invention or technical scheme of the prior art; Below will discuss the accompanying drawing of required use in embodiment or the description of the Prior Art; Obviously, only be some embodiments of the present invention in the technical scheme that combines accompanying drawing to describe, for those of ordinary skills; Under the prerequisite of not paying creative work, can also obtain other embodiment and accompanying drawing thereof according to these accompanying drawing illustrated embodiments.
Fig. 1 is that the end tunnel, a kind of shallow embedding bias voltage ground of the embodiment of the invention 1 advances the cavity construction method flow chart;
Fig. 2 is that the end tunnel, a kind of shallow embedding bias voltage ground of the embodiment of the invention 2 advances the cavity construction method flow chart;
Fig. 3 is that the end tunnel, a kind of shallow embedding bias voltage ground of the embodiment of the invention 3 advances the cavity construction method flow chart.
The specific embodiment
Below will combine accompanying drawing that the technical scheme of various embodiments of the present invention is carried out clear, complete description, obviously, described embodiment only is a part of embodiment of the present invention, rather than whole embodiment.Based on the embodiment described in the present invention, those of ordinary skills are resulting all other embodiment under the prerequisite that does not need creative work, all in the scope that the present invention protected.
Embodiment 1
The tunnel, a kind of shallow embedding bias voltage location that the embodiment of the invention as shown in Figure 1 provides advances cavity construction method, and this method may further comprise the steps:
101, advance interim lining cutting of hole, hole section and pipe canopy cover arch both sides construction groove excavation, and pipe canopy cover arch both sides construction trough rim is faced upward the slope protection;
102, pipe canopy cover arch construction, the steel arch construction is built the cover arch;
103, advance support construction;
104, bassoon canopy or leading ductule are paid in advance and are protected construction;
105, top, hole backfill back-pressure;
106, the tunneling of topping bar, get out of a predicament or an embarrassing situation of the open cut tunnel section geotechnical body of entering the inner hole of the interim lining cutting of hole, hole section.
End tunnel in a kind of shallow embedding bias voltage provided by the invention ground advances cavity construction method, adopts top bar, the get out of a predicament or an embarrassing situation method construction of tunneling of the inner hole of the interim lining cutting of hole, hole section open cut tunnel section geotechnical body, can effectively shorten construction period.
Embodiment 2
The tunnel, a kind of shallow embedding bias voltage location that the embodiment of the invention as shown in Figure 2 provides advances cavity construction method, and this method may further comprise the steps:
201, advance interim lining cutting of hole, hole section and pipe canopy cover arch both sides construction groove excavation, and pipe canopy cover arch both sides construction trough rim is faced upward the slope protection;
202, pipe canopy cover arch construction, the steel arch construction is built the cover arch;
203, advance support construction;
204, bassoon canopy or leading ductule are paid in advance and are protected construction;
205, top, hole backfill back-pressure;
206, the tunneling of topping bar, get out of a predicament or an embarrassing situation of the open cut tunnel section geotechnical body of entering the inner hole of the interim lining cutting of hole, hole section;
207, advance hole, hole section inverted arch, inverted arch backfill.
Embodiment 3
The tunnel, a kind of shallow embedding bias voltage location that is illustrated in figure 3 as the embodiment of the invention advances cavity construction method, and this method may further comprise the steps:
301, advance interim lining cutting of hole, hole section and pipe canopy cover arch both sides construction groove excavation, and pipe canopy cover arch both sides construction trough rim is faced upward the slope protection;
302, pipe canopy cover arch construction, the steel arch construction is built the cover arch;
303, advance support construction;
304, bassoon canopy or leading ductule are paid in advance and are protected construction;
305, top, hole backfill back-pressure;
306, the tunneling of topping bar, get out of a predicament or an embarrassing situation of the open cut tunnel section geotechnical body of entering the inner hole of the interim lining cutting of hole, hole section;
307, advance hole, hole section inverted arch, inverted arch backfill;
308, carry out short abutment wall construction.
Embodiment 4
The difference of embodiments of the invention and embodiment 3 is: after said step of carrying out the construction of short abutment wall, further comprise into hole, hole section open cut tunnel section waterproofing course and gutter construction, and the step of open cut tunnel lining construction.
Embodiment 5
The difference of present embodiment and embodiment 4 is: saidly advance hole, hole section open cut tunnel section waterproofing course and gutter construction, and after the step of open cut tunnel lining construction, further comprise: the ancillary facility construction.
As the preferred embodiment of present embodiment, said ancillary facility construction comprises hole jacking row greening recovery, has protected environment.
Embodiment 6
The difference of present embodiment and embodiment 1 is; Saidly advance interim lining cutting of hole, hole section and pipe canopy cover arch both sides construction groove excavation, and before interim lining cutting faces upward the slope protection with pipe canopy cover arch both sides construction trough rim, further comprise; Build catchwater, sloping surface dust is faced upward in finishing.
Various embodiment provided by the invention can make up with any-mode as required each other, the technical scheme that obtains through this combination, also within the scope of the invention.
Obviously, under the situation that does not break away from the spirit and scope of the present invention, those skilled in the art can carry out various changes and modification to the present invention.Like this, if these changes of the present invention and modification are belonged within the scope of claim of the present invention and equivalent thereof, then the present invention also will comprise these changes and modification.
Claims (7)
1. tunnel, a shallow embedding bias voltage location advances cavity construction method, it is characterized in that this method may further comprise the steps:
Advance interim lining cutting of hole, hole section and pipe canopy cover arch both sides construction groove excavation, and pipe canopy cover arch both sides construction trough rim is faced upward the slope protection;
The construction of pipe canopy cover arch, the steel arch construction is built the cover arch;
The advance support construction;
Bassoon canopy or leading ductule are paid in advance and are protected construction;
Top, hole backfill back-pressure;
The tunneling of topping bar, get out of a predicament or an embarrassing situation of the open cut tunnel section geotechnical body of entering the inner hole of the interim lining cutting of hole, hole section.
2. tunnel, shallow embedding bias voltage location as claimed in claim 1 advances cavity construction method, it is characterized in that, the said open cut tunnel section geotechnical body of entering the inner hole of the interim lining cutting of hole, hole section is topped bar, got out of a predicament or an embarrassing situation after the step of tunneling, further comprises:
Advance hole, hole section inverted arch, inverted arch backfill.
3. tunnel, shallow embedding bias voltage location as claimed in claim 2 advances cavity construction method, it is characterized in that, after the said step of advancing hole, hole section inverted arch, inverted arch backfill, further comprises:
Carry out short abutment wall construction.
4. tunnel, shallow embedding bias voltage location as claimed in claim 3 advances cavity construction method, it is characterized in that, after the said step of carrying out the construction of short abutment wall, further comprises:
Advance the open cut tunnel section waterproofing course and the gutter construction of hole, hole section, and the step of open cut tunnel lining construction.
5. tunnel, shallow embedding bias voltage location as claimed in claim 4 advances cavity construction method, it is characterized in that, saidly advances hole, hole section open cut tunnel section waterproofing course and gutter construction, and after the step of open cut tunnel lining construction, further comprises: the ancillary facility construction.
6. tunnel, shallow embedding bias voltage location as claimed in claim 1 advances cavity construction method; It is characterized in that; Saidly advance interim lining cutting of hole, hole section and pipe canopy cover arch both sides construction groove excavation, and before interim lining cutting faces upward the slope protection with pipe canopy cover arch both sides construction trough rim, further comprise; Build catchwater, sloping surface dust is faced upward in finishing.
7. tunnel, shallow embedding bias voltage location as claimed in claim 5 advances cavity construction method, it is characterized in that, said ancillary facility construction comprises hole jacking row greening recovery.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210285678XA CN102767379A (en) | 2012-08-10 | 2012-08-10 | Shallow-buried unsymmetrical pressure section tunnel drilling construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210285678XA CN102767379A (en) | 2012-08-10 | 2012-08-10 | Shallow-buried unsymmetrical pressure section tunnel drilling construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102767379A true CN102767379A (en) | 2012-11-07 |
Family
ID=47094919
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210285678XA Pending CN102767379A (en) | 2012-08-10 | 2012-08-10 | Shallow-buried unsymmetrical pressure section tunnel drilling construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102767379A (en) |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103206219A (en) * | 2013-05-06 | 2013-07-17 | 浙江省宏途交通建设有限公司 | Holed excavation supporting structure for light and dark junction section of tunnel in bias pressure state and construction method |
CN104234081A (en) * | 2014-09-12 | 2014-12-24 | 中铁五局(集团)有限公司 | Direct entrance construction method for open cut tunnel on valley |
CN104818991A (en) * | 2015-03-30 | 2015-08-05 | 中铁二十四局集团福建铁路建设有限公司 | Construction method of residual slope wash tunnel with shallow cover and unsymmetrical pressure |
CN106321106A (en) * | 2015-06-30 | 2017-01-11 | 中交二公局第六工程有限公司 | Construction method for tunnel-entering of tunnel weak surrounding rock and semi-open and semi-underground bias section portal abutment |
CN106567717A (en) * | 2015-10-10 | 2017-04-19 | 中铁隧道勘测设计院有限公司 | Construction oblique channel structure utilizing subway exit and entrance and construction method |
CN106640096A (en) * | 2017-02-17 | 2017-05-10 | 中铁八局集团第工程有限公司 | Construction method for penetrating through tunnel of backfilling soil section and transition section |
CN106761781A (en) * | 2016-12-12 | 2017-05-31 | 上海市基础工程集团有限公司 | Shield armored concrete open cut tunnel receives construction method |
CN106988760A (en) * | 2017-04-12 | 2017-07-28 | 中铁二院工程集团有限责任公司 | Facility-sliding strata tunnel portal reinforcing construction and construction method |
CN107780941A (en) * | 2017-10-11 | 2018-03-09 | 中交路桥建设有限公司 | A kind of tunnel zero excavation construction method |
CN108661655A (en) * | 2018-05-11 | 2018-10-16 | 中铁四局集团有限公司 | Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine |
CN109209389A (en) * | 2018-08-17 | 2019-01-15 | 中铁十七局集团第三工程有限公司 | Hazy tunnel construction method |
CN110331992A (en) * | 2019-07-03 | 2019-10-15 | 中铁二十五局集团第五工程有限公司 | A kind of hole daguanpeng construction method |
CN111350512A (en) * | 2020-04-16 | 2020-06-30 | 青岛市青排市政工程有限公司 | Transverse hole underground excavation process method |
CN112127900A (en) * | 2020-09-07 | 2020-12-25 | 中国水利水电第十四工程局有限公司 | Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body |
CN112901204A (en) * | 2021-02-25 | 2021-06-04 | 中铁二十五局集团第五工程有限公司 | Safe construction method for cliff tunnel |
CN114086969A (en) * | 2021-11-30 | 2022-02-25 | 广西路桥工程集团有限公司 | Tunnel entering construction method |
CN114251109A (en) * | 2021-12-25 | 2022-03-29 | 中铁二局集团有限公司 | Construction method for karst tunnel earth-rock binary structure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100676914B1 (en) * | 2006-06-13 | 2007-02-01 | 주식회사 무진네오테크 | Excavating method of tunnel with slight vibration |
CN101260806A (en) * | 2008-04-24 | 2008-09-10 | 重庆交通科研设计院 | Preposition type opening construction method |
CN101324072A (en) * | 2008-07-30 | 2008-12-17 | 中国科学院武汉岩土力学研究所 | Construction method of pervious rib type arch beam tunnel |
JP2010053574A (en) * | 2008-08-27 | 2010-03-11 | Kajima Corp | Construction method for tunnel entrance |
CN101725358A (en) * | 2008-10-31 | 2010-06-09 | 中铁四局集团有限公司 | Tunnel ultra-shallow buried uneven weathered stratum excavation construction method |
-
2012
- 2012-08-10 CN CN201210285678XA patent/CN102767379A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100676914B1 (en) * | 2006-06-13 | 2007-02-01 | 주식회사 무진네오테크 | Excavating method of tunnel with slight vibration |
CN101260806A (en) * | 2008-04-24 | 2008-09-10 | 重庆交通科研设计院 | Preposition type opening construction method |
CN101324072A (en) * | 2008-07-30 | 2008-12-17 | 中国科学院武汉岩土力学研究所 | Construction method of pervious rib type arch beam tunnel |
JP2010053574A (en) * | 2008-08-27 | 2010-03-11 | Kajima Corp | Construction method for tunnel entrance |
CN101725358A (en) * | 2008-10-31 | 2010-06-09 | 中铁四局集团有限公司 | Tunnel ultra-shallow buried uneven weathered stratum excavation construction method |
Cited By (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103206219A (en) * | 2013-05-06 | 2013-07-17 | 浙江省宏途交通建设有限公司 | Holed excavation supporting structure for light and dark junction section of tunnel in bias pressure state and construction method |
CN104234081A (en) * | 2014-09-12 | 2014-12-24 | 中铁五局(集团)有限公司 | Direct entrance construction method for open cut tunnel on valley |
CN104234081B (en) * | 2014-09-12 | 2016-09-14 | 中铁五局(集团)有限公司 | At cheuch, barrel open cut tunnel directly enters the construction method in hole |
CN104818991A (en) * | 2015-03-30 | 2015-08-05 | 中铁二十四局集团福建铁路建设有限公司 | Construction method of residual slope wash tunnel with shallow cover and unsymmetrical pressure |
CN106321106B (en) * | 2015-06-30 | 2018-05-15 | 中交二公局第六工程有限公司 | A kind of tunnel weak surrounding rock, hazy bias location hole abutment start tunneling method |
CN106321106A (en) * | 2015-06-30 | 2017-01-11 | 中交二公局第六工程有限公司 | Construction method for tunnel-entering of tunnel weak surrounding rock and semi-open and semi-underground bias section portal abutment |
CN106567717A (en) * | 2015-10-10 | 2017-04-19 | 中铁隧道勘测设计院有限公司 | Construction oblique channel structure utilizing subway exit and entrance and construction method |
CN106567717B (en) * | 2015-10-10 | 2019-03-05 | 中铁第六勘察设计院集团有限公司 | It is a kind of to double as construction access ramp structure and construction method using subway entrance |
CN106761781A (en) * | 2016-12-12 | 2017-05-31 | 上海市基础工程集团有限公司 | Shield armored concrete open cut tunnel receives construction method |
CN106640096A (en) * | 2017-02-17 | 2017-05-10 | 中铁八局集团第工程有限公司 | Construction method for penetrating through tunnel of backfilling soil section and transition section |
CN106988760A (en) * | 2017-04-12 | 2017-07-28 | 中铁二院工程集团有限责任公司 | Facility-sliding strata tunnel portal reinforcing construction and construction method |
CN107780941A (en) * | 2017-10-11 | 2018-03-09 | 中交路桥建设有限公司 | A kind of tunnel zero excavation construction method |
CN108661655A (en) * | 2018-05-11 | 2018-10-16 | 中铁四局集团有限公司 | Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine |
CN108661655B (en) * | 2018-05-11 | 2020-03-17 | 中铁四局集团有限公司 | Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine |
CN109209389A (en) * | 2018-08-17 | 2019-01-15 | 中铁十七局集团第三工程有限公司 | Hazy tunnel construction method |
CN110331992A (en) * | 2019-07-03 | 2019-10-15 | 中铁二十五局集团第五工程有限公司 | A kind of hole daguanpeng construction method |
CN111350512A (en) * | 2020-04-16 | 2020-06-30 | 青岛市青排市政工程有限公司 | Transverse hole underground excavation process method |
CN112127900A (en) * | 2020-09-07 | 2020-12-25 | 中国水利水电第十四工程局有限公司 | Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body |
CN112901204A (en) * | 2021-02-25 | 2021-06-04 | 中铁二十五局集团第五工程有限公司 | Safe construction method for cliff tunnel |
CN114086969A (en) * | 2021-11-30 | 2022-02-25 | 广西路桥工程集团有限公司 | Tunnel entering construction method |
CN114086969B (en) * | 2021-11-30 | 2024-02-20 | 广西路桥工程集团有限公司 | Tunnel entering construction method |
CN114251109A (en) * | 2021-12-25 | 2022-03-29 | 中铁二局集团有限公司 | Construction method for karst tunnel earth-rock binary structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102767379A (en) | Shallow-buried unsymmetrical pressure section tunnel drilling construction method | |
CN106869944B (en) | The extra small clear-distance tunnel construction method in underground interchange intersection under complex environment | |
CN102128035B (en) | Construction method of bilateral biased small-clear distance tunnel | |
CN204419195U (en) | A kind of supporting and protection structure pattern being applicable to tunnel portal section | |
CN103953067B (en) | Foundation pit bracing and underground box type major structure integration structure and construction method thereof | |
CN203308470U (en) | Cover arch structure suitable for large-section unsymmetrical loading tunnel portal section | |
CN104763433A (en) | Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum | |
CN101644157B (en) | Space-time conversion exploitation method for high and steep rock slope stock ground near river | |
CN103883328B (en) | The dark construction method of half lid half of high steep V-type coombe biased segment is worn under separate tunnel | |
CN107060771A (en) | Middle short tunnel is unidirectionally appeared excavation method | |
CN102561402B (en) | Treatment method for construction joint between top plate and wall of individual underground civil air defense project constructed by covered top-down excavation method | |
CN106703044B (en) | One kind stream modeling shape rinse fill soft stratum slope combination supporting method | |
CN109610435B (en) | Loess high fill valley foundation drainage structure and laying method thereof | |
CN105863650A (en) | Tunneling construction method with first wall construction and second tunneling construction | |
CN104847362A (en) | Large-span subway station underground excavation construction method for hard rock stratum | |
CN103939115B (en) | A kind of method of half shallow mining method hangar tunnel and structure | |
CN106988760A (en) | Facility-sliding strata tunnel portal reinforcing construction and construction method | |
CN102808627A (en) | Underground excavation construction method of steel pipe shed | |
CN100513705C (en) | Underground Beam-Pile Frame Structure for Slope Reinforcement | |
CN103726508B (en) | A kind of precast rc slab material loose tool and construction method | |
CN102839980A (en) | Highway tunnel structure and construction method thereof | |
CN208416561U (en) | A kind of Mountain Tunnels half-open and half-hidden structure | |
CN111594168B (en) | Pseudo-goaf-layer supporting and sinking-limiting stoping method formed by matching rock waste with rock waste | |
CN203335089U (en) | Protruding type environment-friendly tunnel portal with supports | |
CN208396718U (en) | A kind of shield arch and ear wall combined type tunnel and high steep bias hole foundation structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20121107 |