CN102758486B - Anti-seepage method for building engineering - Google Patents

Anti-seepage method for building engineering Download PDF

Info

Publication number
CN102758486B
CN102758486B CN201210240246.7A CN201210240246A CN102758486B CN 102758486 B CN102758486 B CN 102758486B CN 201210240246 A CN201210240246 A CN 201210240246A CN 102758486 B CN102758486 B CN 102758486B
Authority
CN
China
Prior art keywords
concrete
construction
wall
test
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210240246.7A
Other languages
Chinese (zh)
Other versions
CN102758486A (en
Inventor
成军
冯惠青
丁云文
张红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Xinqi Cultural Tourism Co ltd
Original Assignee
ZHENHUA GROUP (KUNSHAN) CONSTRUCTION ENGINEERING CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHENHUA GROUP (KUNSHAN) CONSTRUCTION ENGINEERING CO LTD filed Critical ZHENHUA GROUP (KUNSHAN) CONSTRUCTION ENGINEERING CO LTD
Priority to CN201210240246.7A priority Critical patent/CN102758486B/en
Publication of CN102758486A publication Critical patent/CN102758486A/en
Application granted granted Critical
Publication of CN102758486B publication Critical patent/CN102758486B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses an anti-leakage method for building engineering, which comprises the steps of roof concrete floor anti-leakage construction, parapet and roof stairwell bottom anti-leakage construction, outer wall anti-leakage construction, kitchen and toilet anti-leakage construction, basement anti-leakage construction and engineering data management. The invention has convenient construction and good effect and ensures the anti-seepage quality.

Description

The Antiseep method of construction work
Technical field
The present invention relates to a kind of Antiseep method of construction work.
Background technology
The antiseep of architectural process is a very important engineering, and existing method ubiquity defective is difficult to ensure the quality of products or construct complexity.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, the Antiseep method of the construction work that construction quality is good.
Technical solution of the present invention is:
A kind of Antiseep method of construction work, comprise roofing concrete floor anti-seepage construction, parapet and go out roofing staircase bottom anti-seepage construction, outer wall impermeable leakage construction, lavatory, kitchen anti-seepage construction, Basement Anti-seepage Construction, Engineering documents Management, it is characterized in that:
(1) roofing concrete floor anti-seepage construction
Roofing concrete intensity is not less than C30, and the expansion agent of mixing the 5-30% percentage by weight makes expansive concrete, and concrete is played from waterproof action; Use the double-layer double-direction steel mesh reinforcement, increase radiation anticracking reinforcing bar at the plate angle that easily produces the crack; Roof drainage 〉=2%, leveling layer in length and breadth every 6m are established dividing joint, stitch wide 20mm;
(2) parapet and go out roofing staircase bottom anti-seepage construction
For the double-layer double-direction reinforcing bar that the cast-in-situ concrete parapet is joined φ 8@150, thickness of slab 〉=100mm; When brick up parapet or staircase body of wall, except corner arranges the cast-in-situ concrete constructional column, set up the cast-in-situ concrete constructional column in the body of wall middle part, spacing≤3m, the building wall mortar strength is not less than M7.5; Flashing place waterproof height is stretched over below the bearing down on one of parapet;
(3) outer wall impermeable leaks construction
It mainly is at construction link that outer wall impermeable leaks, and for pertusate place, wants the wetting brick body on every side of first trickle when shutoff, then closely knit with the pea gravel concreten pouring, meets loosening fragment of brick and should heavily build; The frame wall filled with masonry dome brick is left to more than the 7d builds by laying bricks or stones again, and Shang Xia Wedged is tight when building by laying bricks or stones, and the slit between brick wall and the frame column is filled up with mortar;
When the exterior wall decoration construction, motar uses the cement mortar that is not less than 1:3, and the thickness of plastering is not less than 20mm, and the position of thickness low LCL or outstanding metope is chipping in advance; At the position that is prone to the crack, set up gauze wire cloth in the floated coat, floated coat is done waterproofing work; Adopt special pointing packing real around the window frame, encapsulation process is done at the girth seam place of aluminum alloy outer frame;
When outer walling uses concrete hollow block, reinforced concrete pillar is set, body of wall and concrete structure binding site arrange the anti-cracking structure measure; Windowsill arranges pea gravel concreten and bears down on one; What exterior wall had air-conditioning or other facilities arranges support shelf and hole, avoids or reduces the user in the punching of exterior wall cutter eye;
(4) lavatory, kitchen anti-seepage construction
Casting and compacting of concrete is closely knit; Lavatory, kitchen peripheral flanging concrete exceeds at least 120mm of flooring, and builds simultaneously with floor concrete, does not take secondary to build way; After form removable around the hole, lavatory, smear the 1:2 waterproofing mortar and do leveling layer, and plastering and removed first dust, greasy dirt and swabbing gray scale in the basic unit before levelling is that the plain-water slurry of 1:2 is closely knit to guarantee to be combined with basic unit, mortar laminated compacting, and surface layer is smooth, thickness is not less than 20mm, the height of plastering is smeared to floor face around the wall of hole, and fillet is made at the negative and positive angle, and the hole wall should be finished simultaneously with the end, hole and not stay constuction joint, answer the water filling maintenance after plastering construction is complete, the time is no less than 7 round the clock;
Concrete cushion after the heavy hole backfill in lavatory adopts pea gravel concreten to water puddling in fact, and thickness is not less than 40mm; Concrete cushion must not have the slit with the joint that reaches closet all around, thereby forms waterproof barrier one, prevents that effectively the water on surface from infiltrating the end, hole, requires equally every layer to accomplish that joint is tight when next doing leveling layer and finish coat, does not form the slit.So just form complete from level to level waterproof system from top to bottom;
The floor in lavatory, kitchen and flange adopt self-waterproof concrete, to reduce the formation in concrete self crack; Plaster and adopt waterproofing mortar with levelling; The floor in lavatory, kitchen is done 2mm thick waterproof coating layer and topping, and waterproofing course exceeds at least 300mm of floor face, and kitchen surface is lower than outside ground 40mm~50mm;
(5) Basement Anti-seepage Construction
Before the concreting, spread first the thick and concrete cement mortar in proportion of 50mm~100mm, striking time is 14d, to avoid structure crack or to be vibrated in advance; Basic unit's swabbing gray scale is 0.5 cement slurry, and smooth basic unit also does in advance texturing and processes, and floated coat is combined firmly with basic unit.
(6) Engineering documents Management
Roofing is done for the first time pouring water test after finishing leveling layer, test figure should be write drainage grade, water-sprinkling time exactly; At the bottom of the inspection plate, pipeline infiltration and ponding situation, after the heat insulation construction of roof heat insulation is complete, do for the second time pouring water test or do the retaining test, the retaining test should be drawn plan view, dated pipeline location and draining, water outlet direction on the figure;
The lavatory, kitchen finish plaster with leveling layer, waterproofing course after respectively do retaining test, require exhaustive test; The most shallow 25mm that is not less than of the retaining degree of depth, and be no more than the sleeve pipe height; What the pipeline plug receptacle was low will stop up, and storage time is not less than 24h; Also do water injection test after surface construction is complete one time, also increase has or not seeping phenomenon after indicating draining specifically;
Exterior wall is done water pouring test one time when plastering maintenance, do the secondary water pouring test after facing is complete, and paints elevation.
Easy construction of the present invention, effective, guarantee the antiseep quality.
The invention will be further described below in conjunction with embodiment.
The specific embodiment
A kind of Antiseep method of construction work comprises roofing concrete floor anti-seepage construction, parapet and goes out roofing staircase bottom anti-seepage construction, outer wall impermeable leakage construction, lavatory, kitchen anti-seepage construction, Basement Anti-seepage Construction, Engineering documents Management,
(1) roofing concrete floor anti-seepage construction
Roofing concrete intensity is not less than C30, and the expansion agent of mixing the 5-30% percentage by weight makes expansive concrete, and concrete is played from waterproof action; Use the double-layer double-direction steel mesh reinforcement, increase radiation anticracking reinforcing bar at the plate angle that easily produces the crack; Roof drainage 〉=2%, leveling layer in length and breadth every 6m are established dividing joint, stitch wide 20mm;
(2) parapet and go out roofing staircase bottom anti-seepage construction
For the double-layer double-direction reinforcing bar that the cast-in-situ concrete parapet is joined φ 8@150, thickness of slab 〉=100mm; When brick up parapet or staircase body of wall, except corner arranges the cast-in-situ concrete constructional column, set up the cast-in-situ concrete constructional column in the body of wall middle part, spacing≤3m, the building wall mortar strength is not less than M7.5; Flashing place waterproof height is stretched over below the bearing down on one of parapet;
(3) outer wall impermeable leaks construction
It mainly is at construction link that outer wall impermeable leaks, and for pertusate place, wants the wetting brick body on every side of first trickle when shutoff, then closely knit with the pea gravel concreten pouring, meets loosening fragment of brick and should heavily build; The frame wall filled with masonry dome brick is left to more than the 7d builds by laying bricks or stones again, and Shang Xia Wedged is tight when building by laying bricks or stones, and the slit between brick wall and the frame column is filled up with mortar;
When the exterior wall decoration construction, motar uses the cement mortar that is not less than 1:3, and the thickness of plastering is not less than 20mm, and the position of thickness low LCL or outstanding metope is chipping in advance; At the position that is prone to the crack, set up gauze wire cloth in the floated coat, floated coat is done waterproofing work; Adopt special pointing packing real around the window frame, encapsulation process is done at the girth seam place of aluminum alloy outer frame;
When outer walling uses concrete hollow block, reinforced concrete pillar is set, body of wall and concrete structure binding site arrange the anti-cracking structure measure; Windowsill arranges pea gravel concreten and bears down on one; What exterior wall had air-conditioning or other facilities arranges support shelf and hole, avoids or reduces the user in the punching of exterior wall cutter eye;
(4) lavatory, kitchen anti-seepage construction
Casting and compacting of concrete is closely knit; Lavatory, kitchen peripheral flanging concrete exceeds at least 120mm of flooring, and builds simultaneously with floor concrete, does not take secondary to build way; After form removable around the hole, lavatory, smear the 1:2 waterproofing mortar and do leveling layer, and plastering and removed first dust, greasy dirt and swabbing gray scale in the basic unit before levelling is that the plain-water slurry of 1:2 is closely knit to guarantee to be combined with basic unit, mortar laminated compacting, and surface layer is smooth, thickness is not less than 20mm, the height of plastering is smeared to floor face around the wall of hole, and fillet is made at the negative and positive angle, and the hole wall should be finished simultaneously with the end, hole and not stay constuction joint, answer the water filling maintenance after plastering construction is complete, the time is no less than 7 round the clock;
Concrete cushion after the heavy hole backfill in lavatory adopts pea gravel concreten to water puddling in fact, and thickness is not less than 40mm; Concrete cushion must not have the slit with the joint that reaches closet all around, thereby forms waterproof barrier one, prevents that effectively the water on surface from infiltrating the end, hole, requires equally every layer to accomplish that joint is tight when next doing leveling layer and finish coat, does not form the slit.So just form complete from level to level waterproof system from top to bottom;
The floor in lavatory, kitchen and flange adopt self-waterproof concrete, to reduce the formation in concrete self crack; Plaster and adopt waterproofing mortar with levelling; The floor in lavatory, kitchen is done 2mm thick waterproof coating layer and topping, and waterproofing course exceeds at least 300mm of floor face, and kitchen surface is lower than outside ground 40mm~50mm;
(5) Basement Anti-seepage Construction
Before the concreting, spread first the thick and concrete cement mortar in proportion of 50mm~100mm, striking time is 14d, to avoid structure crack or to be vibrated in advance; Basic unit's swabbing gray scale is 0.5 cement slurry, and smooth basic unit also does in advance texturing and processes, and floated coat is combined firmly with basic unit.
(6) Engineering documents Management
Roofing is done for the first time pouring water test after finishing leveling layer, test figure should be write drainage grade, water-sprinkling time exactly; At the bottom of the inspection plate, pipeline infiltration and ponding situation, after the heat insulation construction of roof heat insulation is complete, do for the second time pouring water test or do the retaining test, the retaining test should be drawn plan view, dated pipeline location and draining, water outlet direction on the figure;
The lavatory, kitchen finish plaster with leveling layer, waterproofing course after respectively do retaining test, require exhaustive test; The most shallow 25mm that is not less than of the retaining degree of depth, and be no more than the sleeve pipe height; What the pipeline plug receptacle was low will stop up, and storage time is not less than 24h; Also do water injection test after surface construction is complete one time, also increase has or not seeping phenomenon after indicating draining specifically;
Exterior wall is done water pouring test one time when plastering maintenance, do the secondary water pouring test after facing is complete, and paints elevation.

Claims (1)

1. the Antiseep method of a construction work, comprise roofing concrete floor anti-seepage construction, parapet and go out roofing staircase bottom anti-seepage construction, outer wall impermeable leakage construction, lavatory, kitchen anti-seepage construction, Basement Anti-seepage Construction, Engineering documents Management, it is characterized in that:
(1) roofing concrete floor anti-seepage construction
Roofing concrete intensity is not less than C30, and the expansion agent of mixing the 5-30% percentage by weight makes expansive concrete, and concrete is played from waterproof action; Use the double-layer double-direction steel mesh reinforcement, increase radiation anticracking reinforcing bar at the plate angle that easily produces the crack; Roof drainage 〉=2%, leveling layer in length and breadth every 6m are established dividing joint, stitch wide 20mm;
(2) parapet and go out roofing staircase bottom anti-seepage construction
For the double-layer double-direction reinforcing bar that the cast-in-situ concrete parapet is joined φ 8@150, thickness of slab 〉=100mm; When brick up parapet or staircase body of wall, except corner arranges the cast-in-situ concrete constructional column, set up the cast-in-situ concrete constructional column in the body of wall middle part, spacing≤3m, the building wall mortar strength is not less than M7.5; Flashing place waterproof height is stretched over below the bearing down on one of parapet;
(3) outer wall impermeable leaks construction
It mainly is at construction link that outer wall impermeable leaks, and for pertusate place, wants the wetting brick body on every side of first trickle when shutoff, then closely knit with the pea gravel concreten pouring, meets loosening fragment of brick and should heavily build; The frame wall filled with masonry dome brick is left to more than the 7d builds by laying bricks or stones again, and embedding is tight up and down when building by laying bricks or stones, and the slit between brick wall and the frame column is filled up with mortar;
When the exterior wall decoration construction, motar uses the cement mortar that is not less than 1:3, and the thickness of plastering is not less than 20mm, and the position of outstanding metope is chipping in advance; At the position that is prone to the crack, set up gauze wire cloth in the floated coat, floated coat is done waterproofing work; Adopt the pointing packing real around the window frame, encapsulation process is done at the girth seam place of aluminum alloy outer frame;
When outer walling uses concrete hollow block, reinforced concrete pillar is set, body of wall and concrete structure binding site arrange the anti-cracking structure measure; Windowsill arranges pea gravel concreten and bears down on one; What exterior wall had air-conditioning or other facilities arranges support shelf and hole, avoids or reduces the user in the punching of exterior wall cutter eye;
(4) lavatory, kitchen anti-seepage construction
Casting and compacting of concrete is closely knit; Lavatory, kitchen peripheral flanging concrete exceeds at least 120mm of flooring, and builds simultaneously with floor concrete, does not take secondary to build way; After form removable around the hole, lavatory, smear the 1:2 waterproofing mortar and do leveling layer, and plastering and removed first dust, greasy dirt and swabbing gray scale in the basic unit before levelling is that the plain-water slurry of 1:2 is closely knit to guarantee to be combined with basic unit, mortar laminated compacting, and surface layer is smooth, thickness is not less than 20mm, the height of plastering is smeared to floor face around the wall of hole, and fillet is made at the negative and positive angle, and the hole wall should be finished simultaneously with the end, hole and not stay constuction joint, answer the water filling maintenance after plastering construction is complete, the time is no less than 7 round the clock;
Concrete cushion after the heavy hole backfill in lavatory adopts pea gravel concreten to water puddling in fact, and thickness is not less than 40mm; Concrete cushion must not have the slit with the joint that reaches closet all around, thereby form waterproof barrier one, the water that effectively prevents the surface infiltrates the end, hole, require equally every layer to accomplish that joint is tight when next doing leveling layer and finish coat, do not form the slit, so just form complete from level to level waterproof system from top to bottom;
The floor in lavatory, kitchen and flange adopt self-waterproof concrete, to reduce the formation in concrete self crack; Plaster and adopt waterproofing mortar with levelling; The floor in lavatory, kitchen is done 2mm thick waterproof coating layer and topping, and waterproofing course exceeds at least 300mm of floor face, and kitchen surface is lower than outside ground 40mm~50mm;
(5) Basement Anti-seepage Construction
Before the concreting, spread first the thick and concrete cement mortar in proportion of 50mm~100mm, striking time is 14d, to avoid structure crack or to be vibrated in advance; Basic unit's swabbing gray scale is 0.5 cement slurry, and smooth basic unit also does in advance texturing and processes, and floated coat is combined with basic unit firmly;
(6) Engineering documents Management
Roofing is done for the first time pouring water test after finishing leveling layer, test figure should be write drainage grade, water-sprinkling time exactly; At the bottom of the inspection plate, pipeline infiltration and ponding situation, after the heat insulation construction of roof heat insulation is complete, do for the second time pouring water test or do the retaining test, the retaining test should be drawn plan view, dated pipeline location and draining, water outlet direction on the figure;
The lavatory, kitchen finish plaster with leveling layer, waterproofing course after respectively do retaining test, require exhaustive test; The most shallow 25mm that is not less than of the retaining degree of depth, and be no more than the sleeve pipe height; What the pipeline plug receptacle was low will stop up, and storage time is not less than 24h; Also do water injection test after surface construction is complete one time, also increase has or not seeping phenomenon after indicating draining specifically;
Exterior wall is done water pouring test one time when plastering maintenance, do the secondary water pouring test after facing is complete, and paints elevation.
CN201210240246.7A 2012-07-12 2012-07-12 Anti-seepage method for building engineering Active CN102758486B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210240246.7A CN102758486B (en) 2012-07-12 2012-07-12 Anti-seepage method for building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210240246.7A CN102758486B (en) 2012-07-12 2012-07-12 Anti-seepage method for building engineering

Publications (2)

Publication Number Publication Date
CN102758486A CN102758486A (en) 2012-10-31
CN102758486B true CN102758486B (en) 2013-05-29

Family

ID=47053118

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210240246.7A Active CN102758486B (en) 2012-07-12 2012-07-12 Anti-seepage method for building engineering

Country Status (1)

Country Link
CN (1) CN102758486B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102936954A (en) * 2012-11-28 2013-02-20 深圳市鹏城建筑集团有限公司 Method and structure for plugging pipeline floor hole
CN104179263A (en) * 2014-09-01 2014-12-03 中启胶建集团有限公司 Building exterior wall external thermal insulation system waterproof and drainage construction method
CN106677355A (en) * 2017-02-27 2017-05-17 中国冶集团有限公司 Floor slab hole plugging device and method
CN108755983B (en) * 2018-06-01 2020-09-08 湖南吉米防水科技有限公司 Waterproof process

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3969861A (en) * 1974-06-17 1976-07-20 Hanlon Edward J O Leakproof roof and method of constructing same
CN87102845A (en) * 1987-04-22 1988-11-02 马铭锋 Concrete work leak-prevention treatment and repair material and technologies such as roofing
CN1109130A (en) * 1994-03-25 1995-09-27 郭玉民 Method for preventing water leakage of roof or floor
CN2876207Y (en) * 2006-03-15 2007-03-07 刘丹 Water leakage proof structure of floor surface or roof surface deformed seam
CN201474099U (en) * 2009-08-11 2010-05-19 北京城建集团有限责任公司 Three-layer waterproof structure for deformation joint
CN202124949U (en) * 2011-06-28 2012-01-25 天津天一建设集团有限公司 Equal height type waterproof expansion joint of roof parapet wall

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3969861A (en) * 1974-06-17 1976-07-20 Hanlon Edward J O Leakproof roof and method of constructing same
CN87102845A (en) * 1987-04-22 1988-11-02 马铭锋 Concrete work leak-prevention treatment and repair material and technologies such as roofing
CN1109130A (en) * 1994-03-25 1995-09-27 郭玉民 Method for preventing water leakage of roof or floor
CN2876207Y (en) * 2006-03-15 2007-03-07 刘丹 Water leakage proof structure of floor surface or roof surface deformed seam
CN201474099U (en) * 2009-08-11 2010-05-19 北京城建集团有限责任公司 Three-layer waterproof structure for deformation joint
CN202124949U (en) * 2011-06-28 2012-01-25 天津天一建设集团有限公司 Equal height type waterproof expansion joint of roof parapet wall

Also Published As

Publication number Publication date
CN102758486A (en) 2012-10-31

Similar Documents

Publication Publication Date Title
CN107227813B (en) Steel structure keel masonry brick outer curtain wall system and construction method thereof
CN103266767B (en) Construction method for preventing and treating cracks between concrete structure and filler wall
CN101818527B (en) Assembled integral shear wall structure system and construction method thereof
CN104358341B (en) Building brickwork and masonry construction method of building brickwork
CN111519665A (en) Gapless filling method for foundation post-cast strip
CN201280725Y (en) Post-casting construction precast slab for basement of buildings
CN104032771B (en) Anti-cracking construction method for additionally arranging induction joint on underground structure
CN204435404U (en) The additional elevator foundation structure of a kind of old house
CN203625942U (en) Basement outer wall post-cast strip ahead water stopping structure
CN103352537B (en) Overall load bearing heat preserving wallboard and production construction process thereof
CN102758486B (en) Anti-seepage method for building engineering
CN101949207A (en) Method for constructing subsided rest room
CN208933989U (en) A kind of tower-crane foundation structure
CN103410173A (en) Construction method for vertical post pouring belt plugging of underground structural outer wall
CN106812219A (en) Filling wall top stuff up a crack construction method
CN102653946A (en) Waterproof construction method for setting rubber waterstop at bottom of reinforced concrete raft foundation
CN103306497B (en) Shock prevention and strengthening construction method for existing brickwork dwelling house fabricated structure
CN101761287A (en) Reinforced concrete windowsill coping adverse construction method
CN209555958U (en) A kind of pile-raft foundation structure based on the adaptive deformation adjustment device of stake top
CN204645093U (en) Basement outer wall post-cast strip advanced treatment structure
CN103590508A (en) Composite thermal insulating wall structure and construction method thereof
CN102535493B (en) Method for constructing inverted type foundation beam
CN102535847B (en) Method for constructing gypsum self-insulation outer wall block masonry
CN213773865U (en) Precast concrete reversed bank
CN209412856U (en) A kind of assembled integral basement structure meeting stability against floating requirement

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 215300 No. 1158 Xiao Li Road, Kunshan, Jiangsu, Suzhou

Patentee after: Zhenhua Group (Kunshan) construction Limited by Share Ltd

Address before: 215300 No. 1158 Xiao Li Road, Kunshan, Jiangsu, Suzhou

Patentee before: ZHENHUA GROUP (KUNSHAN) CONSTRUCTION ENGINEERING CO., LTD.

TR01 Transfer of patent right

Effective date of registration: 20201201

Address after: 538000 Chengxi Industrial Zone, Shangsi County, Fangchenggang City, Guangxi Zhuang Autonomous Region

Patentee after: Guangxi Shangsi Hualin forest products industry Co., Ltd

Address before: 215300 No. 1158 Xiao Li Road, Kunshan, Jiangsu, Suzhou

Patentee before: Zhenhua Group (Kunshan) Construction Engineering Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210513

Address after: 294 zhongzi street, Sishui County, Jining City, Shandong Province

Patentee after: Zhang Fei

Address before: 538000 Chengxi Industrial Zone, Shangsi County, Fangchenggang City, Guangxi Zhuang Autonomous Region

Patentee before: Guangxi Shangsi Hualin forest products industry Co., Ltd

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211217

Address after: 273500, 500m southwest of Liuzhuang village, Chengqian Town, Zoucheng City, Jining City, Shandong Province

Patentee after: Shandong Mencius ecological agriculture Limited by Share Ltd.

Address before: 294 zhongzi street, Sishui County, Jining City, Shandong Province

Patentee before: Zhang Fei

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220506

Address after: 273500 No. 517, merchants Road, Gangshan street, Zoucheng City, Jining City, Shandong Province (North Gate of Xinqi farmers' market)

Patentee after: Shandong Xinqi Cultural Tourism Co.,Ltd.

Address before: 273500, 500m southwest of Liuzhuang village, Chengqian Town, Zoucheng City, Jining City, Shandong Province

Patentee before: Shandong Mencius ecological agriculture Limited by Share Ltd.

PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Anti leakage method of building engineering

Effective date of registration: 20220518

Granted publication date: 20130529

Pledgee: Zou Cheng Branch of industrial and Commercial Bank of China Ltd.

Pledgor: Shandong Xinqi Cultural Tourism Co.,Ltd.

Registration number: Y2022980005702

PE01 Entry into force of the registration of the contract for pledge of patent right