CN102704495A - 顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法 - Google Patents

顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法 Download PDF

Info

Publication number
CN102704495A
CN102704495A CN201210225937XA CN201210225937A CN102704495A CN 102704495 A CN102704495 A CN 102704495A CN 201210225937X A CN201210225937X A CN 201210225937XA CN 201210225937 A CN201210225937 A CN 201210225937A CN 102704495 A CN102704495 A CN 102704495A
Authority
CN
China
Prior art keywords
excavation
soil body
purlin
island
excavating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210225937XA
Other languages
English (en)
Inventor
龚剑
朱毅敏
周虹
耿涛
薛永申
孙晓鸣
张常庆
陈康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction Group Co Ltd
Shanghai Construction No 1 Group Co Ltd
Original Assignee
Shanghai Construction Group Co Ltd
Shanghai Construction No 1 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction Group Co Ltd, Shanghai Construction No 1 Group Co Ltd filed Critical Shanghai Construction Group Co Ltd
Priority to CN201210225937XA priority Critical patent/CN102704495A/zh
Publication of CN102704495A publication Critical patent/CN102704495A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

本发明公开了顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法,包括如下步骤:首先上层土体采用岛式开挖,先行施工上层环边土体,后开挖中部土体,及时施工该层环形围檩;如上层环形围檩已达到设计强度,应率先开挖下层环边土体,及时施工下道环形围檩,之后开挖下层中部土体;如上层环形围檩未形成或达到设计强度,在满足基坑变形控制要求的前提下,率先开挖下层中部土体,后开挖环边土体;最后开挖该层剩余土体。本发明采用岛盆结合的施工方法,形成与围护结构施工紧密衔接的岛盆结合的开挖作业方式。加快基坑开挖进度,减少基坑暴露时间,有利于围护结构变形控制及周边环境保护。

Description

顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法
技术领域
本发明属于建筑地下工程技术领域,涉及一种基坑土方开挖方法,具体是一种顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法。
背景技术
在采用顺作法施工的大直径圆形基坑中,由于其在工程中应用实例较少,此类基坑的开挖一般遵循岛式开挖的施工方法,即先开挖环边土体,形成环形围檩,待环形围檩达到一定强度后,方能开挖基坑下层土体。受环形围檩施工及养护时间制约,整个基坑的开挖工作会出现间歇性等待,基坑的暴露时间增加,围护结构变形增大。
发明内容
本发明所要解决的技术问题是提供一种作业进度快、经济性好有利于围护结构变形控制及周边环境保护的顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法,以克服现有技术存在的上述缺陷。
本发明解决技术问题的技术方案如下:
一种顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法,其特征在于,包括如下步骤:
(1)上层土体采用岛式开挖,先行施工上层环边土体,后开挖中部土体,及时施工该层环形围檩;
(2)如上层环形围檩已达到设计强度,应率先开挖下层环边土体,及时施工下道环形围檩,之后开挖下层中部土体;
(3)如上层环形围檩未形成或达到设计强度,可根据开挖深度预留一定的环边土体,在满足基坑变形控制要求的前提下,率先开挖下层中部土体,后开挖环边土体;如监测数据反映围护结构变形超出正常范围或有异常波动时,应立即停止中部土方开挖,待上层环形围檩达到设计强度后,转而开挖环边土体,及时施工下道环形围檩,最后开挖该层剩余土体。
由以上公开的技术方案可知,本发明顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法,通过将环形围檩的形成时间作为基坑开挖控制的关键线路,对每层土方的环边土体和中部土体进行细致划分,从而灵活安排各层土方的开挖。本发明基于传统的岛式开挖施工方法,融入盆式开挖的优点,采用岛盆结合的施工方法,形成与围护结构施工紧密衔接的岛盆结合的开挖作业方式。在对应开挖层的环形围檩未行成或养护强度未到设计要求的情况下,紧跟上层土体的开挖,继续开挖下层中部土体,保留环边土体,以形成连续施工,加快基坑开挖进度,减少基坑暴露时间,有利于围护结构变形控制及周边环境保护。
本发明有益效果如下:
1、摆脱单一的岛式开挖施工方法,采用更为机动的岛盆结合土方施工方法,使各项施工工序顺利衔接,作业进度加快。
2、挖土机械的安排和调配更为灵活,形成连续作业,减少了基坑开挖中出现的间歇性等待,节约了人力、物力,具备较好的经济性。
3、开挖速度的加快,减少了基坑的暴露时间,围护结构的变形和周边地表的沉降也相应减小,周边环境得到了有效控制。
附图说明
图1为本发明结构示意图;
附图标记如下:
1、上层环边土体    2、上层中部土体    3、下层环边土体
4、下层剩余土体    5、下层中部土体    6、放坡线
7、环形围檩        8、围护结构
具体实施方式
下面结合附图及实施例对本发明作进一步详述。
具体实施例,某工程大厦主楼121m直径圆形基坑顺作施工中,采用本发明顺作大直径圆形无内支撑深基坑土方开挖施工方法共分7层对基坑进行开挖。其中第一、二、七层以盆式挖土为主,第三~六层以岛式开挖为主。如图1所示,
(1)上层土体采用岛式开挖,先行施工上层环边土体1,及时施工该层环形围檩7,随后开挖上层中部土体2。
(2)待上层土体全部开挖完成后,受环形围檩7施工及养护进度制约,下层环边土体3不具备开挖条件,因此采用盆式开挖率先开挖下层中部土体5,并确保下层盆边留土量满足基坑变形控制要求,如监测数据反映围护结构变形超出正常范围或有异常波动时,应立即停止下层中部土方开挖。
(3)待上层环形围檩7达到设计强度后,停止下层中部土体5的开挖,转而开挖下层环边土体3,及时施工该层环形围檩,最后开挖该层剩余土体4。
本发明充分考虑环形围檩的施工及养护时间,灵活安排每层土方的施工方式,并根据其开挖方式合理分配每层土体的环边和中部土方量比例,争取上下层土方开挖时间上的无缝衔接,在确保基坑安全的前提下,尽早完成整个基坑的开挖工作。
以上所述仅为本发明的较佳实施方式,并非用来限制本发明的保护范围,凡是依照本发明权利要求所做的同等变换,均在本发明的保护范围之内。

Claims (1)

1.一种顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法,其特征在于,包括如下步骤:
(1)上层土体采用岛式开挖,先行施工上层环边土体,后开挖中部土体,及时施工该层环形围檩;
(2)如上层环形围檩已达到设计强度,应率先开挖下层环边土体,及时施工下道环形围檩,之后开挖下层中部土体;
(3)如上层环形围檩未形成或达到设计强度,可根据开挖深度预留一定的环边土体,在满足基坑变形控制要求的前提下,率先开挖下层中部土体,后开挖环边土体;如监测数据反映围护结构变形超出正常范围或有异常波动时,应立即停止中部土方开挖,待上层环形围檩达到设计强度后,转而开挖环边土体,及时施工下道环形围檩,最后开挖该层剩余土体。
CN201210225937XA 2012-07-02 2012-07-02 顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法 Pending CN102704495A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210225937XA CN102704495A (zh) 2012-07-02 2012-07-02 顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210225937XA CN102704495A (zh) 2012-07-02 2012-07-02 顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法

Publications (1)

Publication Number Publication Date
CN102704495A true CN102704495A (zh) 2012-10-03

Family

ID=46897527

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210225937XA Pending CN102704495A (zh) 2012-07-02 2012-07-02 顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法

Country Status (1)

Country Link
CN (1) CN102704495A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631465A (zh) * 2014-12-15 2015-05-20 上海市基础工程集团有限公司 卵石层红砂岩地质条件下的深基坑开挖施工方法
CN113882387A (zh) * 2021-09-01 2022-01-04 武汉市政工程设计研究院有限责任公司 一种无内支撑的大直径圆形超深基坑逆作结构及施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1191258A (zh) * 1997-02-21 1998-08-26 同济大学 基坑开挖的时空效应法
CN1982546A (zh) * 2005-12-12 2007-06-20 上海市第七建筑有限公司 中心岛顺作局部裙边逆作施工方法
CN101353896A (zh) * 2008-06-25 2009-01-28 江苏江都建设工程有限公司 超大直径、超埋深度调蓄池的半逆作施工方法
CN101408025A (zh) * 2008-11-11 2009-04-15 广州市设计院 利用主体结构作为支撑点的基坑施工方法
CN101705685A (zh) * 2009-11-06 2010-05-12 上海市第一建筑有限公司 地下结构周边梁板踏步式逆作施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1191258A (zh) * 1997-02-21 1998-08-26 同济大学 基坑开挖的时空效应法
CN1982546A (zh) * 2005-12-12 2007-06-20 上海市第七建筑有限公司 中心岛顺作局部裙边逆作施工方法
CN101353896A (zh) * 2008-06-25 2009-01-28 江苏江都建设工程有限公司 超大直径、超埋深度调蓄池的半逆作施工方法
CN101408025A (zh) * 2008-11-11 2009-04-15 广州市设计院 利用主体结构作为支撑点的基坑施工方法
CN101705685A (zh) * 2009-11-06 2010-05-12 上海市第一建筑有限公司 地下结构周边梁板踏步式逆作施工方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631465A (zh) * 2014-12-15 2015-05-20 上海市基础工程集团有限公司 卵石层红砂岩地质条件下的深基坑开挖施工方法
CN113882387A (zh) * 2021-09-01 2022-01-04 武汉市政工程设计研究院有限责任公司 一种无内支撑的大直径圆形超深基坑逆作结构及施工方法

Similar Documents

Publication Publication Date Title
CN107288653A (zh) 一种软弱围岩大断面隧道双侧壁导坑三台阶法开挖支护结构及施工方法
CN103174430B (zh) 一种浅埋大跨输水隧洞三台阶五步开挖方法
CN103590406A (zh) 一种超大型深基坑分区同步开挖的施工方法
CN108412509A (zh) 双护盾tbm防卡机方法
CN102787846A (zh) 海底隧道断层破碎带上堵下排的施工方法
CN102268993A (zh) 一种高液限土中隧道开挖方法
CN104164878B (zh) 一种超大型深基坑土方开挖的施工方法
CN105113514B (zh) 以地下连续墙作为竖向悬臂支点的基坑围护体系及施工方法
CN102797468B (zh) 盾构隧道浅覆土始发方法
CN109356593A (zh) 一种引水隧洞开挖施工方法
CN102704495A (zh) 顺作大直径圆形无内支撑深基坑岛盆结合土方开挖方法
CN106368176A (zh) 建于土料匮乏区深覆盖层上的高坝结构
CN101824825A (zh) 一种深基坑明挖施工方法
CN105545330A (zh) 一种冶金地下矿山溜破***施工中的防治水工艺
CN107524124A (zh) 一种抽水蓄能电站地下厂房岩壁吊车梁部位开挖施工方法
CN107288654A (zh) 地下核反应堆洞室超大跨度穹顶中空环向开挖结构及开挖方法
CN103132531A (zh) 基坑支护体系施工方法
CN103276706B (zh) 引水隧洞斜井段防渗结构的施工方法
CN101956395A (zh) 减少基坑周边变形的底板及其施工方法
CN104047607A (zh) 盾构机围护结构条件下吊出工法
CN103775094B (zh) 砂砾土地层中型断面输水隧洞两台阶三步开挖施工方法
CN202370539U (zh) 一种隧道的前掌子面开挖土体预加固结构
CN212742599U (zh) 一种灌浆帷幕与引水管道相交部位的防渗处理结构
CN104389609A (zh) 一种无***机械开挖法
CN102817364A (zh) 深基坑钢板桩加锚索支护体系施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C05 Deemed withdrawal (patent law before 1993)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121003