CN102587659A - 一种以混凝土柱支顶后浇带两侧结构的施工方法 - Google Patents

一种以混凝土柱支顶后浇带两侧结构的施工方法 Download PDF

Info

Publication number
CN102587659A
CN102587659A CN2012100637129A CN201210063712A CN102587659A CN 102587659 A CN102587659 A CN 102587659A CN 2012100637129 A CN2012100637129 A CN 2012100637129A CN 201210063712 A CN201210063712 A CN 201210063712A CN 102587659 A CN102587659 A CN 102587659A
Authority
CN
China
Prior art keywords
sides
ater
concrete column
casting
steel pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100637129A
Other languages
English (en)
Inventor
李小玥
赵凡平
夏清准
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN2012100637129A priority Critical patent/CN102587659A/zh
Publication of CN102587659A publication Critical patent/CN102587659A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明提供了一种以混凝土柱支顶后浇带两侧结构的施工方法,包括以下步骤:步骤一:支设支撑后浇带两侧的梁板结构的混凝土柱的混凝土柱模板,浇筑混凝土柱至达到设计楼板的底标高并预留铺设楼板模板的位置;步骤二:混凝土柱浇筑好并达到强度后,搭设支撑后浇带两侧的梁板结构的第一钢管模板支架和楼板模板,然后进行梁板结构的浇筑;步骤三:待后浇带两侧梁板结构的混凝土强度等级达到要求时,拆除第一钢管模板支架,混凝土柱独立承受梁板结构的荷载;步骤四:支设后浇带部位的第二钢管模板支架,封闭后浇带;步骤五:待后浇带与后浇带两侧梁板结构连成一体且达到强度后拆除混凝土柱。本发明能在后浇带两侧钢管支架拆除后,支撑后浇带两侧结构,保证后浇带两侧结构在整个施工过程中的稳定性和安全性。

Description

一种以混凝土柱支顶后浇带两侧结构的施工方法
技术领域
本发明涉及建筑工程领域,具体涉及一种以混凝土柱支顶后浇带两侧结构的施工方法。
背景技术
建筑施工中为防止现浇钢筋混凝土结构由于温度、收缩不均可能产生的有害裂缝,建筑主体与裙房之间产生沉降差,按照设计或施工规范要求,在楼板、梁的相应位置留设后浇带,将结构暂时划分为若干部分,经过构件内部收缩,在若干时间后再浇捣后浇带混凝土,将结构连成整体。由于后浇带的设置使原结构的受力状态暂时改变,施工过程中后浇带两侧模板及其钢管支架原则上不拆除,但考虑到实际材料运输、钢管租赁费用等情况,部分后浇带两侧钢管支架需要拆除,在拆除的同时必须采取可靠的支撑措施以保证结构在施工阶段的稳定性和安全性。
发明内容
本发明所要解决的技术问题在于提供一种以混凝土柱支顶后浇带两侧结构的施工方法,在后浇带两侧钢管支架拆除后,支撑后浇带两侧结构,保证后浇带两侧结构在整个施工过程中的稳定性和安全性。
为解决上述现有的技术问题,本发明采用如下方案:一种以混凝土柱支顶后浇带两侧结构的施工方法,包括以下步骤:
步骤一:支设支撑后浇带两侧的梁板结构的混凝土柱的混凝土柱模板,浇筑混凝土柱至达到设计楼板的底标高并预留铺设楼板模板的位置;
步骤二:混凝土柱浇筑好并达到强度后,搭设支撑后浇带两侧的梁板结构的第一钢管模板支架和楼板模板,然后进行梁板结构的浇筑;
步骤三:待后浇带两侧梁板结构的混凝土强度等级达到要求时,拆除第一钢管模板支架,混凝土柱独立承受梁板结构的荷载;
步骤四:支设后浇带部位的第二钢管模板支架,封闭后浇带;
步骤五:待后浇带与后浇带两侧梁板结构连成一体且达到强度后拆除混凝土柱。
作为优选,所述步骤一中在支设混凝土柱模板之前,按照后浇带每侧所需支承荷载与混凝土柱等量的原则,确定混凝土柱的尺寸与间距。这样混凝土柱的结构和受力比较合理,既保证了工程质量又避免由于浇筑过量的混凝土柱造成浪费。
作为优选,所述步骤一中在支设混凝土柱模板之前,对混凝土柱的位置进行定位放线;所述步骤二中在搭设第一钢管模板支架之前,对第一钢管模板支架的位置进行定位放线;所述步骤四中在支设第二钢管模板支架之前,对第二钢管模板支架的位置进行定位放线。定位放线对混凝土柱以及钢管模板支架的位置定位更精确,工程质量较高,安全性好。
作为优选,所述步骤一中在支设混凝土柱模板之前,在混凝土柱对应位置的底部铺设第一保护层。保护层能避免或者减小混凝土柱拆除时对原结构造成破坏。
作为优选,所述步骤二中在支设第一钢管模板支架之前、所述步骤四中在支设第二钢管模板支架之前均在其对应位置的底部设置第二保护层。避免第一钢管模板支架和第二钢管模板支架对原结构造成破坏。
作为优选,所述步骤二中在第一钢管模板支架上设有竖向剪刀撑,所述步骤四中在第二钢管模板支架上设有竖向剪刀撑。剪刀撑使模板支架支撑更加稳固。
作为优选,所述步骤五中拆除混凝土柱时采用人工辅助小型机械设备拆除。人工辅助小型机械设备比如冲击钻等拆除施工比较安全。
有益效果:
本发明采用上述技术方案提供的一种以混凝土柱支顶后浇带两侧结构的施工方法,在后浇带两侧钢管支架拆除后,支撑后浇带两侧结构,保证后浇带两侧结构在整个施工过程中的稳定性和安全性。
附图说明
图1为本发明的混凝土柱浇筑示意图;
图2为本发明的后浇带两侧结构钢管模板支架搭设示意图;
图3为本发明的后浇带部位钢管模板支架搭设示意图;
图4为本发明的混凝土柱拆除示意图。
具体实施方式
如图1至4所示,一种以混凝土柱支顶后浇带两侧结构的施工方法,包括以下步骤:
步骤一:支设支撑后浇带31两侧的梁板结构32的混凝土柱1的混凝土柱模板,浇筑混凝土柱1至达到设计楼板的底标高并预留铺设楼板模板4的位置;
步骤二:混凝土柱1浇筑好并达到强度后,搭设支撑后浇带31两侧的梁板结构32的第一钢管模板支架21和楼板模板4,然后进行梁板结构32的浇筑;
步骤三:待后浇带31两侧梁板结构32的混凝土强度等级达到要求时,拆除第一钢管模板支架21,混凝土柱1独立承受梁板结构32的荷载;
步骤四:支设后浇带31部位的第二钢管模板支架22,封闭后浇带31;
步骤五:待后浇带31与后浇带31两侧梁板结构32连成一体且达到强度后拆除混凝土柱1。
所述步骤一中在支设混凝土柱模板1之前,按照后浇带每侧所需支承荷载与混凝土柱等量的原则,确定混凝土柱1的尺寸与间距。所述步骤一中在支设混凝土柱模板之前,对混凝土柱1的位置进行定位放线;所述步骤二中在搭设第一钢管模板支架21之前,对第一钢管模板支架21的位置进行定位放线;所述步骤四中在支设第二钢管模板支架22之前,对第二钢管模板支架22的位置进行定位放线。所述步骤一中在支设混凝土柱模板之前,在混凝土柱1对应位置的底部铺设第一保护层51。所述步骤二中在支设第一钢管模板支架21之前、所述步骤四中在支设第二钢管模板支架22之前均在其对应位置的底部设置第二保护层52。所述步骤二中在第一钢管模板支架21上设有竖向剪刀撑23,所述步骤四中在第二钢管模板支架22上设有竖向剪刀撑23。所述步骤五中拆除混凝土柱1时采用人工辅助小型机械设备拆除。
本发明中,也可以同时搭设第一钢管模板支架和混凝土柱的模板支架,混凝土柱与梁板结构一起进行浇筑。这样能够减少施工工序,节约施工时间,较适用于楼层高度较低时。本发明中,所述第一保护层51采用油毡,第二保护层52采用50mm厚的木垫板,模板4采用18mm厚的胶合板,模板4和第一钢管模板支架21、第二钢管模板支架22之间采用规格为60×80mm的木方支撑,以上材料均可以采用其它合适的具有同等作用的材料代替。在第一钢管模板支架21和第二钢管模板支架22上加设竖向剪刀撑23使模板支架更加稳固;一般在支架高度超过四米时按构造每隔两步加一道水平剪刀撑。当混凝土柱1高度不足时,可用水泥砂浆或其他合适的材料铺垫。本发明能够在后浇带两侧钢管支架拆除后,支撑后浇带两侧结构,保证后浇带两侧结构在整个施工过程中的稳定性和安全性。

Claims (7)

1.一种以混凝土柱支顶后浇带两侧结构的施工方法,其特征在于:包括以下步骤:
步骤一:支设支撑后浇带(31)两侧的梁板结构(32)的混凝土柱(1)的混凝土柱模板,浇筑混凝土柱(1)至达到设计楼板的底标高并预留铺设楼板模板(4)的位置;
步骤二:混凝土柱(1)浇筑好并达到强度后,搭设支撑后浇带(31)两侧的梁板结构(32)的第一钢管模板支架(21)和楼板模板(4),然后进行梁板结构(32)的浇筑;
步骤三:待后浇带(31)两侧梁板结构(32)的混凝土强度等级达到要求时,拆除第一钢管模板支架(21),混凝土柱(1)独立承受梁板结构(32)的荷载;
步骤四:支设后浇带(31)部位的第二钢管模板支架(22),封闭后浇带(31);
步骤五:待后浇带(31)与后浇带(31)两侧梁板结构(32)连成一体且达到强度后拆除混凝土柱(1)。
2.根据权利要求1所述的一种以混凝土柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤一中在支设混凝土柱模板之前,按照后浇带每侧所需支承荷载与混凝土柱等量的原则,确定混凝土柱(1)的尺寸与间距。
3.根据权利要求1所述的一种以混凝土柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤一中在支设混凝土柱模板之前,对混凝土柱(1)的位置进行定位放线;所述步骤二中在搭设第一钢管模板支架(21)之前,对第一钢管模板支架(21)的位置进行定位放线;所述步骤四中在支设第二钢管模板支架(22)之前,对第二钢管模板支架(22)的位置进行定位放线。
4.根据权利要求1所述的一种以混凝土柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤一中在支设混凝土柱模板之前,在混凝土柱(1)对应位置的底部铺设第一保护层(51)。
5.根据权利要求1所述的一种以混凝土柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤二中在支设第一钢管模板支架(21)之前、所述步骤四中在支设第二钢管模板支架(22)之前均在其对应位置的底部设置第二保护层(52)。
6.根据权利要求1所述的一种以混凝土柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤二中在第一钢管模板支架(21)上设有竖向剪刀撑(23),所述步骤四中在第二钢管模板支架(22)上设有竖向剪刀撑(23)。
7.根据权利要求1所述的一种以混凝土柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤五中拆除混凝土柱(1)时采用人工辅助小型机械设备拆除。
CN2012100637129A 2012-03-12 2012-03-12 一种以混凝土柱支顶后浇带两侧结构的施工方法 Pending CN102587659A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100637129A CN102587659A (zh) 2012-03-12 2012-03-12 一种以混凝土柱支顶后浇带两侧结构的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100637129A CN102587659A (zh) 2012-03-12 2012-03-12 一种以混凝土柱支顶后浇带两侧结构的施工方法

Publications (1)

Publication Number Publication Date
CN102587659A true CN102587659A (zh) 2012-07-18

Family

ID=46476843

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100637129A Pending CN102587659A (zh) 2012-03-12 2012-03-12 一种以混凝土柱支顶后浇带两侧结构的施工方法

Country Status (1)

Country Link
CN (1) CN102587659A (zh)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103397778A (zh) * 2013-04-27 2013-11-20 瑞华建设集团有限公司 高层商住楼结构转换层施工方法
CN103615053A (zh) * 2013-11-27 2014-03-05 温州宏源水电建设有限公司 现浇钢筋混凝土结构后浇带施工工法
CN104389430A (zh) * 2014-11-24 2015-03-04 中设建工集团有限公司 素砼柱在后浇带支撑中的应用
CN105003089A (zh) * 2015-07-21 2015-10-28 上海建工七建集团有限公司 沉降后浇带提前拆除临时支撑的施工方法
CN105089270A (zh) * 2015-08-20 2015-11-25 中建三局第二建设工程有限责任公司 一种混凝土梁板快拆木模装置支模体系的施工方法
CN105350719A (zh) * 2015-09-28 2016-02-24 黄坤坤 大跨度后浇带早拆模增设临时构造柱施工方法
CN106032704A (zh) * 2015-03-18 2016-10-19 中天建设集团有限公司 一种以混凝土柱支顶后浇带两侧结构的施工方法
CN106284845A (zh) * 2015-05-26 2017-01-04 五冶集团上海有限公司 一种后浇带钢筋混凝土构造柱独立支撑体系施工方法
CN106284428A (zh) * 2016-08-31 2017-01-04 云南省建设投资控股集团有限公司 一种建筑结构后浇带的混凝土立柱支撑方法
CN108442692A (zh) * 2018-05-21 2018-08-24 中建四局第六建筑工程有限公司 一种后浇带悬挑端独立支撑装置及其施工方法
CN110593311A (zh) * 2019-10-23 2019-12-20 中国建筑第七工程局有限公司 一种后浇带混凝土临时支撑柱
CN111058628A (zh) * 2020-01-14 2020-04-24 福建建工集团有限责任公司 一种后浇带模板支撑体系的施工方法
CN114541809A (zh) * 2022-02-15 2022-05-27 中国十七冶集团有限公司 一种建筑结构浇筑用的支护***及施工工艺
CN115387392A (zh) * 2022-08-23 2022-11-25 中国五冶集团有限公司 一种地下室后浇带施工结构及方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101144328A (zh) * 2007-10-17 2008-03-19 山东万鑫建设有限公司 后浇带梁板模板的施工方法
CN101560828A (zh) * 2008-10-27 2009-10-21 刘群 剪刀撑扣件式钢管脚手架模板支架
CN201972396U (zh) * 2011-01-28 2011-09-14 四川省建筑机械化工程公司 一种钢管模板支撑架
CN102345387A (zh) * 2010-07-30 2012-02-08 李国庆 楼板部位后浇带侧部模板支设方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101144328A (zh) * 2007-10-17 2008-03-19 山东万鑫建设有限公司 后浇带梁板模板的施工方法
CN101560828A (zh) * 2008-10-27 2009-10-21 刘群 剪刀撑扣件式钢管脚手架模板支架
CN102345387A (zh) * 2010-07-30 2012-02-08 李国庆 楼板部位后浇带侧部模板支设方法
CN201972396U (zh) * 2011-01-28 2011-09-14 四川省建筑机械化工程公司 一种钢管模板支撑架

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
周凤英: "后浇带梁板模板的施工", 《山西建筑》 *
陈竹丹 李理: "浅谈"后浇带"施工作业", 《四川建筑》 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103397778A (zh) * 2013-04-27 2013-11-20 瑞华建设集团有限公司 高层商住楼结构转换层施工方法
CN103615053A (zh) * 2013-11-27 2014-03-05 温州宏源水电建设有限公司 现浇钢筋混凝土结构后浇带施工工法
CN103615053B (zh) * 2013-11-27 2016-09-28 温州宏源水电建设有限公司 现浇钢筋混凝土结构后浇带施工工法
CN104389430A (zh) * 2014-11-24 2015-03-04 中设建工集团有限公司 素砼柱在后浇带支撑中的应用
CN104389430B (zh) * 2014-11-24 2016-07-13 中设建工集团有限公司 素砼柱在后浇带支撑中的应用
CN106032704A (zh) * 2015-03-18 2016-10-19 中天建设集团有限公司 一种以混凝土柱支顶后浇带两侧结构的施工方法
CN106284845A (zh) * 2015-05-26 2017-01-04 五冶集团上海有限公司 一种后浇带钢筋混凝土构造柱独立支撑体系施工方法
CN105003089A (zh) * 2015-07-21 2015-10-28 上海建工七建集团有限公司 沉降后浇带提前拆除临时支撑的施工方法
CN105089270A (zh) * 2015-08-20 2015-11-25 中建三局第二建设工程有限责任公司 一种混凝土梁板快拆木模装置支模体系的施工方法
CN105350719A (zh) * 2015-09-28 2016-02-24 黄坤坤 大跨度后浇带早拆模增设临时构造柱施工方法
CN106284428A (zh) * 2016-08-31 2017-01-04 云南省建设投资控股集团有限公司 一种建筑结构后浇带的混凝土立柱支撑方法
CN108442692A (zh) * 2018-05-21 2018-08-24 中建四局第六建筑工程有限公司 一种后浇带悬挑端独立支撑装置及其施工方法
CN110593311A (zh) * 2019-10-23 2019-12-20 中国建筑第七工程局有限公司 一种后浇带混凝土临时支撑柱
CN111058628A (zh) * 2020-01-14 2020-04-24 福建建工集团有限责任公司 一种后浇带模板支撑体系的施工方法
CN114541809A (zh) * 2022-02-15 2022-05-27 中国十七冶集团有限公司 一种建筑结构浇筑用的支护***及施工工艺
CN115387392A (zh) * 2022-08-23 2022-11-25 中国五冶集团有限公司 一种地下室后浇带施工结构及方法
CN115387392B (zh) * 2022-08-23 2023-12-15 中国五冶集团有限公司 一种地下室后浇带施工结构及方法

Similar Documents

Publication Publication Date Title
CN102587659A (zh) 一种以混凝土柱支顶后浇带两侧结构的施工方法
CN102561690A (zh) 一种以砖柱支顶后浇带两侧结构的施工方法
CN107090975B (zh) 一种超高大跨混凝土现浇梁贝雷架支模施工方法
CN103967277B (zh) 超高层核心筒倾斜剪力墙的施工方法
CN204098463U (zh) 悬挑脚手架
CN106223360A (zh) 采用桩撑支护体系的明挖装配整体式结构地铁站施工方法
CN105649360A (zh) 一种整体装配式建筑***及安装方法
CN102733606A (zh) 高空大悬挑结构的施工方法
CN103935911B (zh) 塔吊附墙支撑结构及其施工方法
CN105863253A (zh) 整体支模异步浇筑楼梯间墙柱支模体系及施工方法
CN103352428A (zh) 悬索桥索塔横梁无支架施工方法
CN110512719B (zh) 一种高层住宅大跨度间隔式连廊高空支模钢平台施工工法
CN105442839A (zh) 一种悬挑结构模板排架的搭设方法
CN106032704A (zh) 一种以混凝土柱支顶后浇带两侧结构的施工方法
CN102392536A (zh) 大跨度悬空通廊式模板支撑体系施工方法
CN103790423A (zh) 大型混凝土粮仓施工方法
CN105862602A (zh) 空心混凝土斜塔的翻转式模板***及其施工方法
CN105401679A (zh) 大坡度现浇混凝土斜屋面施工方法
CN107687254A (zh) 一种混凝土连体群仓滑模施工装置及施工方法
CN103061508A (zh) 一种三角形滑模装置及施工方法
CN109457814B (zh) 基于贝雷架结构的高耸及大直径建筑物顶盖施工方法
CN205636516U (zh) 空心混凝土斜塔的翻转式模板***
CN203834926U (zh) 清水混凝土地下室外墙模板支模结构
CN109881587B (zh) 一种大风环境下主塔上横梁支架整体安装方法
CN103485574A (zh) 一种造粒塔塔顶钢筋混凝土结构施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120718