CN102561690A - 一种以砖柱支顶后浇带两侧结构的施工方法 - Google Patents

一种以砖柱支顶后浇带两侧结构的施工方法 Download PDF

Info

Publication number
CN102561690A
CN102561690A CN2012100638210A CN201210063821A CN102561690A CN 102561690 A CN102561690 A CN 102561690A CN 2012100638210 A CN2012100638210 A CN 2012100638210A CN 201210063821 A CN201210063821 A CN 201210063821A CN 102561690 A CN102561690 A CN 102561690A
Authority
CN
China
Prior art keywords
sides
casting
ater
steel pipe
brick post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100638210A
Other languages
English (en)
Inventor
华学严
李小玥
竹永良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN2012100638210A priority Critical patent/CN102561690A/zh
Publication of CN102561690A publication Critical patent/CN102561690A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

本发明提供了一种以砖柱支顶后浇带两侧结构的施工方法,包括以下步骤:步骤一:砌筑支撑后浇带两侧的梁板结构的砖柱至达到设计楼板的底标高并预留铺设模板的位置;步骤二:砖柱砌筑好后,搭设支撑后浇带两侧的梁板结构的第一钢管模板支架和模板,然后进行梁板结构的浇筑;步骤三:待后浇带两侧梁板结构的混凝土强度等级达到要求时,拆除第一钢管模板支架,砖柱独立承受梁板结构的荷载;步骤四:支设后浇带部位的第二钢管模板支架,封闭后浇带;步骤五:待后浇带与后浇带两侧梁板结构连成一体且达到强度后拆除砖柱。本发明能在后浇带两侧钢管支架拆除后,支撑后浇带两侧结构,保证后浇带两侧结构在整个施工过程中的稳定性和安全性。

Description

一种以砖柱支顶后浇带两侧结构的施工方法
技术领域
本发明涉及建筑工程领域,具体涉及一种以砖柱支顶后浇带两侧结构的施工方法。
背景技术
建筑施工中为防止现浇钢筋混凝土结构由于温度、收缩不均可能产生的有害裂缝,建筑主体与裙房之间产生沉降差,按照设计或施工规范要求,在楼板、梁的相应位置留设后浇带,将结构暂时划分为若干部分,经过构件内部收缩,在若干时间后再浇捣后浇带混凝土,将结构连成整体。由于后浇带的设置使原结构的受力状态暂时改变,施工过程中后浇带两侧模板及其钢管支架原则上不拆除,但考虑到实际材料运输、钢管租赁费用等情况,部分后浇带两侧钢管支架需要拆除,在拆除的同时必须采取可靠的支撑措施以保证结构在施工阶段的稳定性和安全性。
发明内容
本发明所要解决的技术问题在于提供一种以砖柱支顶后浇带两侧结构的施工方法,能够在后浇带两侧钢管支架拆除后,支撑后浇带两侧结构,保证后浇带两侧结构在整个施工过程中的稳定性和安全性。
为解决上述现有的技术问题,本发明采用如下方案:一种以砖柱支顶后浇带两侧结构的施工方法,包括以下步骤:
步骤一:砌筑支撑后浇带两侧的梁板结构的砖柱至达到设计楼板的底标高并预留铺设模板的位置;
步骤二:砖柱砌筑好后,搭设支撑后浇带两侧的梁板结构的第一钢管模板支架和模板,然后进行梁板结构的浇筑;
步骤三:待后浇带两侧梁板结构的混凝土强度等级达到要求时,拆除第一钢管模板支架,砖柱独立承受梁板结构的荷载;
步骤四:支设后浇带部位的第二钢管模板支架,封闭后浇带;
步骤五:待后浇带与后浇带两侧梁板结构连成一体且达到强度后拆除砖柱。
作为优选,所述步骤一中在砌筑砖柱之前,按照后浇带每侧所需支承荷载与砖柱等量的原则,确定砖柱的尺寸与间距。这样砖柱的结构和受力会比较合理,既保证了工程质量又避免由于砌筑过量的砖柱造成浪费。
作为优选,所述步骤一中在砌筑砖柱之前,对砖柱的位置进行定位放线;所述步骤二中在搭设第一钢管模板支架之前,对第一钢管模板支架的位置进行定位放线;所述步骤四中在支设第二钢管模板支架之前,对第二钢管模板支架的位置进行定位放线。定位放线能更精确的对砖柱以及钢管模板支架的位置进行定位,保证安全和工程质量。
作为优选,所述步骤一中在砌筑砖柱之前,在砖柱对应位置的底部铺设第一保护层。避免砖柱拆除时对原结构造成破坏。
作为优选,所述步骤二中在支设第一钢管模板支架之前、所述步骤四中在支设第二钢管模板支架之前均在其对应位置的底部设置第二保护层。避免第一钢管模板支架和第二钢管模板支架对原结构造成破坏。
作为优选,所述步骤二中在第一钢管模板支架上设有竖向剪刀撑,所述步骤四中在第二钢管模板支架上设有竖向剪刀撑。使模板支架支撑更加稳固。
作为优选,所述步骤五中拆除砖柱时采用人工辅助小型机械设备拆除。人工辅助小型机械设备比如冲击钻等拆除施工比较安全。
有益效果:
本发明采用上述技术方案提供的一种以砖柱支顶后浇带两侧结构的施工方法,在后浇带两侧钢管支架拆除后,支撑后浇带两侧结构,保证了后浇带两侧结构在整个施工过程中的稳定性和安全性。
附图说明
图1为本发明的砖柱砌筑示意图;
图2为本发明的后浇带两侧结构钢管模板支架搭设示意图;
图3为本发明的后浇带部位钢管模板支架搭设示意图;
图4为本发明的砖柱拆除示意图。
具体实施方式
如图1至图4所示,一种以砖柱支顶后浇带两侧结构的施工方法,包括以下步骤:
步骤一:砌筑支撑后浇带31两侧的梁板结构32的砖柱1至达到设计楼板的底标高并预留铺设模板4的位置;
步骤二:砖柱1砌筑好后,搭设支撑后浇带31两侧的梁板结构32的第一钢管模板支架21和模板4,然后进行梁板结构32的浇筑;
步骤三:待后浇带31两侧梁板结构32的混凝土强度等级达到要求时,拆除第一钢管模板支架21,砖柱1独立承受梁板结构32的荷载;
步骤四:支设后浇带31部位的第二钢管模板支架22,封闭后浇带31;
步骤五:待后浇带31与后浇带31两侧梁板结构32连成一体且达到强度后拆除砖柱1。
所述步骤一中在砌筑砖柱1之前,按照后浇带每侧所需支承荷载与砖柱等量的原则,确定砖柱1的尺寸与间距。所述步骤一中在砌筑砖柱1之前,对砖柱1的位置进行定位放线;所述步骤二中在搭设第一钢管模板支架21之前,对第一钢管模板支架21的位置进行定位放线;所述步骤四中在支设第二钢管模板支架22之前,对第二钢管模板支架22的位置进行定位放线。所述步骤一中在砌筑砖柱1之前,在砖柱1对应位置的底部铺设第一保护层51。所述步骤二中在支设第一钢管模板支架21之前、所述步骤四中在支设第二钢管模板支架22之前均在其对应位置的底部设置第二保护层52。所述步骤二中在第一钢管模板支架21上设有竖向剪刀撑23,所述步骤四中在第二钢管模板支架22上设有竖向剪刀撑23。所述步骤五中拆除砖柱1时采用人工辅助小型机械设备拆除。
本发明中,所述第一保护层51采用油毡,第二保护层52采用50mm厚的木垫板,所述模板4采用18mm厚的胶合板,模板4和第一钢管模板支架21、第二钢管模板支架22之间采用规格为60×80mm的木方支撑,以上材料均可以采用其它合适的具有相同或相似功能的材料代替。在第一钢管模板支架21和第二钢管模板支架22上加设竖向剪刀撑23能使模板支架更加稳固;一般在支架高度超过四米时按构造每隔两步加一道水平剪刀撑。当砖柱1高度不足时,可用水泥砂浆或其他合适的材料铺垫。本发明能够在后浇带两侧钢管支架拆除后,支撑后浇带两侧结构,保证后浇带两侧结构在整个施工过程中的稳定性和安全性。

Claims (7)

1.一种以砖柱支顶后浇带两侧结构的施工方法,其特征在于:包括以下步骤:
步骤一:砌筑支撑后浇带(31)两侧的梁板结构(32)的砖柱(1)至达到设计楼板的底标高并预留铺设模板(4)的位置;
步骤二:砖柱(1)砌筑好后,搭设支撑后浇带(31)两侧的梁板结构(32)的第一钢管模板支架(21)和模板(4),然后进行梁板结构(32)的浇筑;
步骤三:待后浇带(31)两侧梁板结构(32)的混凝土强度等级达到要求时,拆除第一钢管模板支架(21),砖柱(1)独立承受梁板结构(32)的荷载;
步骤四:支设后浇带(31)部位的第二钢管模板支架(22),封闭后浇带(31);
步骤五:待后浇带(31)与后浇带(31)两侧梁板结构(32)连成一体且达到强度后拆除砖柱(1)。
2.根据权利要求1所述的一种以砖柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤一中在砌筑砖柱(1)之前,按照后浇带每侧所需支承荷载与砖柱等量的原则,确定砖柱(1)的尺寸与间距。
3.根据权利要求1所述的一种以砖柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤一中在砌筑砖柱(1)之前,对砖柱(1)的位置进行定位放线;所述步骤二中在搭设第一钢管模板支架(21)之前,对第一钢管模板支架(21)的位置进行定位放线;所述步骤四中在支设第二钢管模板支架(22)之前,对第二钢管模板支架(22)的位置进行定位放线。
4.根据权利要求1所述的一种以砖柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤一中在砌筑砖柱(1)之前,在砖柱(1)对应位置的底部铺设第一保护层(51)。
5.根据权利要求1所述的一种以砖柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤二中在支设第一钢管模板支架(21)之前、所述步骤四中在支设第二钢管模板支架(22)之前均在其对应位置的底部设置第二保护层(52)。
6.根据权利要求1所述的一种以砖柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤二中在第一钢管模板支架(21)上设有竖向剪刀撑(23),所述步骤四中在第二钢管模板支架(22)上设有竖向剪刀撑(23)。
7.根据权利要求1所述的一种以砖柱支顶后浇带两侧结构的施工方法,其特征在于:所述步骤五中拆除砖柱(1)时采用人工辅助小型机械设备拆除。
CN2012100638210A 2012-03-12 2012-03-12 一种以砖柱支顶后浇带两侧结构的施工方法 Pending CN102561690A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100638210A CN102561690A (zh) 2012-03-12 2012-03-12 一种以砖柱支顶后浇带两侧结构的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100638210A CN102561690A (zh) 2012-03-12 2012-03-12 一种以砖柱支顶后浇带两侧结构的施工方法

Publications (1)

Publication Number Publication Date
CN102561690A true CN102561690A (zh) 2012-07-11

Family

ID=46408157

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100638210A Pending CN102561690A (zh) 2012-03-12 2012-03-12 一种以砖柱支顶后浇带两侧结构的施工方法

Country Status (1)

Country Link
CN (1) CN102561690A (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102828616A (zh) * 2012-09-14 2012-12-19 中国建筑第八工程局有限公司 一种屋盖高支模体系
CN103147573A (zh) * 2013-03-19 2013-06-12 成军 游泳馆顶梁板高支模施工方法
CN103758347A (zh) * 2014-01-20 2014-04-30 常州第一建筑集团有限公司 大跨度钢筋混凝土梁板结构后浇带支撑托换施工方法
CN104131583A (zh) * 2014-07-30 2014-11-05 中建四局第五建筑工程有限公司 一种新型后浇带处支撑结构及其施工工艺
CN104153508A (zh) * 2014-09-02 2014-11-19 中国建筑第八工程局有限公司 楼板的施工结构及其施工方法
CN106284845A (zh) * 2015-05-26 2017-01-04 五冶集团上海有限公司 一种后浇带钢筋混凝土构造柱独立支撑体系施工方法
CN110043035A (zh) * 2019-02-25 2019-07-23 中天西北建设投资集团有限公司 一种新型的后浇带施工支撑方法
CN110565946A (zh) * 2019-07-31 2019-12-13 常州第一建筑集团有限公司 大型悬挑结构建筑物地下室后浇带支撑施工方法
CN111058628A (zh) * 2020-01-14 2020-04-24 福建建工集团有限责任公司 一种后浇带模板支撑体系的施工方法
CN114086737A (zh) * 2021-11-25 2022-02-25 中国水利水电第十工程局有限公司 一种隔震***悬挂电梯井道底部支撑的施工方法
CN114541809A (zh) * 2022-02-15 2022-05-27 中国十七冶集团有限公司 一种建筑结构浇筑用的支护***及施工工艺
CN114855884A (zh) * 2022-06-09 2022-08-05 安徽建工集团股份有限公司总承包分公司 一种便于地下基础结构后浇带提前回填土的施工方法

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101144328A (zh) * 2007-10-17 2008-03-19 山东万鑫建设有限公司 后浇带梁板模板的施工方法

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101144328A (zh) * 2007-10-17 2008-03-19 山东万鑫建设有限公司 后浇带梁板模板的施工方法

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
《施工技术》 20030228 陈竹丹等 浅谈"后浇带"施工作业 第23卷, 第1期 *
张敏红等: "梁式转换层后浇带支撑体系", 《河北建筑工程学院》 *
申玉林等: "后浇带施工小知识", 《建筑工人》 *
郑永明: "结合工程实例浅析建筑结构后浇带施工技术", 《建材与装饰》 *
陈竹丹等: "浅谈"后浇带"施工作业", 《施工技术》 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102828616A (zh) * 2012-09-14 2012-12-19 中国建筑第八工程局有限公司 一种屋盖高支模体系
CN102828616B (zh) * 2012-09-14 2015-03-18 中国建筑第八工程局有限公司 一种屋盖高支模体系
CN103147573A (zh) * 2013-03-19 2013-06-12 成军 游泳馆顶梁板高支模施工方法
CN103758347A (zh) * 2014-01-20 2014-04-30 常州第一建筑集团有限公司 大跨度钢筋混凝土梁板结构后浇带支撑托换施工方法
CN104131583A (zh) * 2014-07-30 2014-11-05 中建四局第五建筑工程有限公司 一种新型后浇带处支撑结构及其施工工艺
CN104153508A (zh) * 2014-09-02 2014-11-19 中国建筑第八工程局有限公司 楼板的施工结构及其施工方法
CN106284845A (zh) * 2015-05-26 2017-01-04 五冶集团上海有限公司 一种后浇带钢筋混凝土构造柱独立支撑体系施工方法
CN110043035A (zh) * 2019-02-25 2019-07-23 中天西北建设投资集团有限公司 一种新型的后浇带施工支撑方法
CN110043035B (zh) * 2019-02-25 2022-03-15 中天西北建设投资集团有限公司 一种后浇带施工支撑方法
CN110565946A (zh) * 2019-07-31 2019-12-13 常州第一建筑集团有限公司 大型悬挑结构建筑物地下室后浇带支撑施工方法
CN111058628A (zh) * 2020-01-14 2020-04-24 福建建工集团有限责任公司 一种后浇带模板支撑体系的施工方法
CN114086737A (zh) * 2021-11-25 2022-02-25 中国水利水电第十工程局有限公司 一种隔震***悬挂电梯井道底部支撑的施工方法
CN114541809A (zh) * 2022-02-15 2022-05-27 中国十七冶集团有限公司 一种建筑结构浇筑用的支护***及施工工艺
CN114855884A (zh) * 2022-06-09 2022-08-05 安徽建工集团股份有限公司总承包分公司 一种便于地下基础结构后浇带提前回填土的施工方法
CN114855884B (zh) * 2022-06-09 2024-03-29 安徽建工集团股份有限公司总承包分公司 一种便于地下基础结构后浇带提前回填土的施工方法

Similar Documents

Publication Publication Date Title
CN102561690A (zh) 一种以砖柱支顶后浇带两侧结构的施工方法
CN102587659A (zh) 一种以混凝土柱支顶后浇带两侧结构的施工方法
CN103967277B (zh) 超高层核心筒倾斜剪力墙的施工方法
CN107090975B (zh) 一种超高大跨混凝土现浇梁贝雷架支模施工方法
CN204098463U (zh) 悬挑脚手架
CN106223360A (zh) 采用桩撑支护体系的明挖装配整体式结构地铁站施工方法
CN102733606A (zh) 高空大悬挑结构的施工方法
CN103924525B (zh) 城市立交桥工业化短线预制拼装施工方法
CN103790423B (zh) 大型混凝土粮仓施工方法
CN110512719B (zh) 一种高层住宅大跨度间隔式连廊高空支模钢平台施工工法
CN106013781A (zh) 反吊模板的楼板支撑施工方法及施工装置
CN102392536A (zh) 大跨度悬空通廊式模板支撑体系施工方法
CN103935911A (zh) 塔吊附墙支撑结构及其施工方法
CN105401679A (zh) 大坡度现浇混凝土斜屋面施工方法
CN102337782A (zh) 一种高大空间顶部施工桁架平台提升***及其施工方法
CN106032704A (zh) 一种以混凝土柱支顶后浇带两侧结构的施工方法
CN105862602A (zh) 空心混凝土斜塔的翻转式模板***及其施工方法
CN107687254A (zh) 一种混凝土连体群仓滑模施工装置及施工方法
CN103061508A (zh) 一种三角形滑模装置及施工方法
CN101555709B (zh) 一种复合保温隔热混凝土剪力墙的安装工艺
CN109457814B (zh) 基于贝雷架结构的高耸及大直径建筑物顶盖施工方法
CN103952979B (zh) 一种钢砼叠合梁顶板无支架施工装置及施工方法
CN104962296A (zh) 焦炉基础烟道免支顶模快速施工方法
CN205636516U (zh) 空心混凝土斜塔的翻转式模板***
CN104234447A (zh) 深基坑用工具式吊挂楼梯

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120711