CN102561372B - Plugging method for downcomer for well-point dewatering of deep foundation pit - Google Patents

Plugging method for downcomer for well-point dewatering of deep foundation pit Download PDF

Info

Publication number
CN102561372B
CN102561372B CN201110436183.8A CN201110436183A CN102561372B CN 102561372 B CN102561372 B CN 102561372B CN 201110436183 A CN201110436183 A CN 201110436183A CN 102561372 B CN102561372 B CN 102561372B
Authority
CN
China
Prior art keywords
layer
downcomer
sand
water glass
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110436183.8A
Other languages
Chinese (zh)
Other versions
CN102561372A (en
Inventor
刘宝堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201110436183.8A priority Critical patent/CN102561372B/en
Publication of CN102561372A publication Critical patent/CN102561372A/en
Application granted granted Critical
Publication of CN102561372B publication Critical patent/CN102561372B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention provides a plugging method for a downcomer for the well-point dewatering of a deep foundation pit, and belongs to a falling water plugging method of civil engineering. The plugging method comprises the construction steps as follows: firstly, a filtering layer is disposed; secondly, a sand layer is filled; thirdly, a cotton batting layer is stuffed; fourthly, a soluble glass cement sand bed is poured; fifthly, a leaking stoppage agent layer is smeared; sixthly, a micro-expansive concrete layer is poured; and seventhly, a plugging steel plate is welded, wherein the filtering layer arranged at the lower part of an inner chamber of a conventional downcomer remains the same, and the sand layer is filled until the height of the sand layer reaches 1.5 meters below the top of the downcomer; the height of the cotton batting layer ranges from 0.7 to 1.0 m; the thickness of the soluble glass cement sand bed ranges from 50 to 80 mm, and the soluble glass cement sand bed is curdled when poured; the thickness of the leaking stoppage agent layer ranges from 40 to 60 mm; the micro-expansive concrete layer is poured until the height reaches the upper pipe orifice of the downcomer; and the round steel plate is utilized to plug an upper opening of the downcomer above the micro-expansive concrete layer in a full-length welding manner, wherein the thickness of the round steel plate ranges from 8 to 15 mm. The plugging method effectively solves the difficult problem that leakage is caused when the downcomer is plugged, is simple and convenient to operate, and has the advantages of quick construction progress, high construction quality and low cost.

Description

The downcomer method for blocking of Deep Foundation Pit Well-Point Dewatering
Technical field
The invention belongs to work China Democratic National Construction Association precipitation method for blocking, especially relate to a kind of method for blocking of Deep Foundation Pit Well-Point Dewatering.
Background technology
When high-building construction, because groundwater table is higher, excavation of foundation pit is darker, generally all need to adopt the construction of well-points dewatering method to carry out precipitation, so that the construction on excavation of foundation pit and basis, but when foundation construction finishes and remove well-points dewatering equipment, due to the effect of underground water hydraulic pressure, can cause downcomer shutoff difficulty, generally, in downcomer, fill rubble, then build high-grade concrete until below concrete roof 50mm, adopt again steel plate that 10mm is thick by downcomer sealing, but because of ground water pressure larger, stop after precipitation, underground water gushes on still can be in a large number, downcomer shutoff position easy to leak, not only cause difficulty of construction large, construction quality is difficult to control, and after construction, hidden danger is many, concrete of basement base plate infiltration in the future, leak stopping is difficulty very.
Summary of the invention
The downcomer method for blocking that the object of this invention is to provide a kind of Deep Foundation Pit Well-Point Dewatering, solves the difficult problem that downcomer shutoff produces seepage effectively, and not only easy and simple to handle, construction speed is fast, and improves construction quality, reduces construction cost.
The object of the present invention is achieved like this: a kind of downcomer method for blocking of Deep Foundation Pit Well-Point Dewatering, its construction sequence is:
One, the disposal of filtration beds, two, fill layer of sand, three, plug cotton layer, four, pouring water glass cement sand bed, five, smear and apply leak stopping king layer, six, build slightly expanded concrete layer, seven, the stifled steel plate of sealing;
Wherein:
One, the disposal of filtration beds:
After draining water pump being enhanced in downcomer, the filtration beds arranging in former downcomer inner chamber bottom maintains the original state constant, at the buried set strainer of task performance for impurity effect water pump in preventing dewatering well in the bottom of downcomer, maintain the original state constant, this strainer adopts finished product filter screen, and void content is not less than 20%.
[0005]two, fill layer of sand:
Above downcomer inner filtration layer, fill layer of sand, fine sand in employing, in this, fine sand granularity is that 0.25mm to 0.35mm is advisable, in this, fine sand is through 20 orders and the screening of 40 object sieves, must not contain impurity, the height of this layer of sand is filled to downward 1.5m depths, downcomer top; Layer of sand answers puddling real, and compactness is 90%, and layer of sand is filled and wanted layering filling, layering puddling reality, and take and fill middle fine sand that 50cm is thick tamping as good at every turn.
Three, plug cotton layer:
Fill after layer of sand, immediately the cotton-wool volume of wrapping is filled in to the top of layer of sand in downcomer, the diameter of this cotton-wool volume is than the large 15-30mm of downcomer internal diameter, and the diameter of this cotton-wool volume is good than the large 20mm of downcomer internal diameter, the height of this cotton layer is 0.7-1.0m, the height of this cotton layer be take 0.8m especially as good, playing water proof, prevent the object of gushing on underground water.
Four, pouring water glass cement sand bed:
In downcomer after jam-pack cotton layer, water glass cement sand bed is watered on top at cotton layer immediately, this water glass cement mortar bed thickness is 50mm-80mm, and this water glass cement mortar bed thickness be take 60mm as good, with filling with solidifying, 1), water glass water glass cement main material:: commercially available, modulus n=2.2,40 ° of Be of density, 2), cement: No. 32.5 Portland cements, 3), sand: river sand, fineness modulus uf=2.4; The proportioning of this water glass cement mortar is: cement: sand: water: water glass=565Kg:1380Kg:360Kg:113L: 1kg:2.44kg:1.57kg:200ml, water glass elder generation and water mix, be poured into again cement and become mortar with mixing in sand, while avoiding water glass directly to pour into, make partial water cement mortar produce rapid hardening, prevent from stirring inhomogeneous.
Five, smear and apply leak stopping king layer:
On the water glass cement sand bed condensing, smear and apply leak stopping king layer, the thickness of this leak stopping king layer is 40mm-60mm, and the thickness of this leak stopping king layer be take 50mm as good.
Six, build slightly expanded concrete layer:
After leak stopping king layer solidifies, on leak stopping king layer top, build slightly expanded concrete layer, the proportioning of this slightly expanded concrete is: (cement+expansion agent): sand: rubble: water: water reducing agent=(348Kg+36Kg): 744Kg:1071Kg:178Kg:3.5Kg, that is: (1Kg+0.10Kg): 2.14Kg:3.08Kg:0.51Kg:0.01Kg, concrete is No. 32.5 Portland cements; The vibration compacting while building, maintenance routinely, till this slightly expanded concrete layer is poured into the downcomer upper end mouth of pipe always, after building, concrete expansion and downcomer strong bonded, prevent that concrete is loosening, guarantees shutoff quality.
Seven, the stifled steel plate of sealing:
After treating that micro-expansion cement reaches design strength 75%, on the top of micro-expansion cement layer, with the thick round plate of 8-15mm, downcomer full weld suitable for reading is blocked.
The downcomer method for blocking of a kind of Deep Foundation Pit Well-Point Dewatering provided by the present invention, easy to operate, effectively solved the difficult problem that downcomer shutoff produces seepage, not only construction speed is fast, and improves construction quality, reduces construction cost.
The downcomer method for blocking of a kind of Deep Foundation Pit Well-Point Dewatering now in conjunction with the accompanying drawings and embodiments the present invention being proposed is described further.
Accompanying drawing explanation
Fig. 1 is that the downcomer method for blocking of Deep Foundation Pit Well-Point Dewatering proposed by the invention is implemented schematic diagram.
In Fig. 1: 1, filtration beds 2, back-up sand layer 3, cotton layer 4, water glass cement sand bed 5, leak stopping king layer 6, micro-expansion cement layer 7, round plate.
the specific embodiment
[0015]at lotus flower village, the Nanjing B project 8# building downcomer of forming a team, adopt the downcomer method for blocking of this Deep Foundation Pit Well-Point Dewatering, its construction sequence is: the filtration beds 1 of burying underground while retaining draining dewatering construction, fill layer of sand 2, middle fine sand is filled to downward 1.5m depths, downcomer top, then with thick be tight cotton layer 3 shutoff of 0.8m, then with thick, for the water glass cement paste layer 4(of 50mm seal, coagulate successively) and the thickness leak stopping king layer 5 that is 50mm, leak stopping king layer 5 top adopt C35 slightly expanded concrete layer 6 to be poured into the downcomer upper end mouth of pipe, last on micro-expansion cement layer 6, use again round plate 7 that 10mm is thick by downcomer full weld sealing, the top concreting of round plate 7 is also built concordant for 40mm pea gravel concreten with concrete floor with thick, through the careful conscientious inspection repeatedly of correlation engineering technician, do not find downcomer Seepage, successful, in follow-up 12#, 13# building downcomer shut-in well, continue to construct by this method, the step of going forward side by side has been demonstrate,proved the effect of its antiseep, effectively solved the technical barrier of downcomer shutoff moisture-proof and seepage-proof, and guaranteeing under the prerequisite of workmanship, make constructing operation easy, accelerate construction speed, reduced cost.

Claims (5)

1. a downcomer method for blocking for Deep Foundation Pit Well-Point Dewatering, its construction sequence is:
One, the disposal of filtration beds, two, fill layer of sand, three, plug cotton layer, four, pouring water glass cement sand bed, five, smear and apply leak stopping king layer, six, build slightly expanded concrete layer, seven, the stifled steel plate of sealing;
Wherein:
One, the disposal of filtration beds:
After draining water pump being enhanced in downcomer, the filtration beds arranging in former downcomer inner chamber bottom maintains the original state constant, at the buried set strainer of task performance for impurity effect water pump in preventing dewatering well in the bottom of downcomer, maintain the original state constant, this strainer adopts finished product filter screen, and void content is not less than 20%;
Two, fill layer of sand:
Above downcomer inner filtration layer, fill layer of sand, fine sand in employing, in this, fine sand granularity is 0.25mm to 0.35mm, and in this, fine sand, through 20 orders and the screening of 40 object sieves, must not contain impurity, and the height of this layer of sand is filled to downward 1.5m depths, downcomer top; Layer of sand answers puddling real, and compactness is 90%, and layer of sand is filled and wanted layering filling, layering puddling in fact;
Three, plug cotton layer:
Fill after layer of sand, immediately the cotton-wool volume of wrapping is filled in to the top of layer of sand in downcomer, the diameter of this cotton-wool volume is than the large 15-30mm of downcomer internal diameter, and the height of this cotton layer is 0.7-1.0m, playing water proof, prevent the object of gushing on underground water;
Four, pouring water glass cement sand bed:
In downcomer after jam-pack cotton layer, water glass cement sand bed is watered on top at cotton layer immediately, this water glass cement mortar bed thickness is 50mm-80mm, with filling with solidifying, 1), water glass water glass cement main material:: commercially available, modulus n=2.2,40 ° of Be of density, 2), cement: No. 32.5 Portland cements, 3), sand: river sand, fineness modulus u f=2.4; The proportioning of this water glass cement mortar is: cement: sand: water: water glass=565Kg:1380Kg:360Kg:113L: 1kg:2.44kg:1.57kg:200ml, water glass elder generation and water mix, be poured into again cement and become mortar with mixing in sand, while avoiding water glass directly to pour into, make partial water cement mortar produce rapid hardening, prevent from stirring inhomogeneous;
Five, smear and apply leak stopping king layer:
On the water glass cement sand bed condensing, smear and apply leak stopping king layer, the thickness of this leak stopping king layer is 40mm-60mm;
Six, build slightly expanded concrete layer:
After leak stopping king layer solidifies, on leak stopping king layer top, build slightly expanded concrete layer, the proportioning of this slightly expanded concrete is: (cement+expansion agent): sand: rubble: water: water reducing agent=(348Kg+36Kg): 744Kg:1071Kg:178Kg:3.5Kg, that is: (1Kg+0.10Kg): 2.14Kg:3.08Kg:0.51Kg:0.01Kg, concrete is No. 32.5 Portland cements; The vibration compacting while building, maintenance routinely, till this slightly expanded concrete layer is poured into the downcomer upper end mouth of pipe always, after building, concrete expansion and downcomer strong bonded, prevent that concrete is loosening, guarantees shutoff quality;
Seven, the stifled steel plate of sealing:
After treating that slightly expanded concrete reaches design strength 75%, on the top of micro-expansion cement layer, with the thick round plate of 8-15mm, downcomer full weld suitable for reading is blocked.
2. the downcomer method for blocking of Deep Foundation Pit Well-Point Dewatering according to claim 1, the diameter that it is characterized in that this cotton layer than the large 20mm of downcomer internal diameter, be highly 0.8m.
3. the downcomer method for blocking of Deep Foundation Pit Well-Point Dewatering according to claim 1, is characterized in that this water glass cement mortar bed thickness is 60mm.
4. the downcomer method for blocking of Deep Foundation Pit Well-Point Dewatering according to claim 1, is characterized in that the thickness of this leak stopping king layer is 50mm.
5. the downcomer method for blocking of Deep Foundation Pit Well-Point Dewatering according to claim 1, is characterized in that layer of sand is filled to thick middle fine sand the tamping of each filling 50cm.
CN201110436183.8A 2011-12-23 2011-12-23 Plugging method for downcomer for well-point dewatering of deep foundation pit Active CN102561372B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110436183.8A CN102561372B (en) 2011-12-23 2011-12-23 Plugging method for downcomer for well-point dewatering of deep foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110436183.8A CN102561372B (en) 2011-12-23 2011-12-23 Plugging method for downcomer for well-point dewatering of deep foundation pit

Publications (2)

Publication Number Publication Date
CN102561372A CN102561372A (en) 2012-07-11
CN102561372B true CN102561372B (en) 2014-04-09

Family

ID=46407852

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110436183.8A Active CN102561372B (en) 2011-12-23 2011-12-23 Plugging method for downcomer for well-point dewatering of deep foundation pit

Country Status (1)

Country Link
CN (1) CN102561372B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102797266B (en) * 2012-08-31 2014-12-17 天津住宅集团建设工程总承包有限公司 Well sealing waterproof construction method for dewatering well
CN103382722B (en) * 2013-07-15 2015-05-13 十一冶建设集团有限责任公司 Concrete foundation slab restoring method for preformed water collecting well for higher underground hydraulic pressure
CN103397651B (en) * 2013-07-15 2015-07-01 十一冶建设集团有限责任公司 Seal structure of concrete foundation slab of reserved water-collecting well
CN103485352A (en) * 2013-09-30 2014-01-01 上海建工七建集团有限公司 Construction method for blocking depressurization well by adopting accelerated cement
CN105625445B (en) * 2014-11-06 2017-11-28 五冶集团上海有限公司 A kind of Method on Dewatering of Foundation Pit of coastal sand soil area
CN105672336B (en) * 2015-03-13 2017-11-17 宁波恒进自动化技术有限公司 A kind of deformable filter assemblies of well-points dewatering
CN105133628B (en) * 2015-09-14 2017-05-24 中国建筑第二工程局有限公司 Under-pressure leaking stoppage structure and method for underground garage sump
CN107100181A (en) * 2017-05-09 2017-08-29 黄坤坤 " being cheated in hole " two grades of relay precipitation systems and its method for blocking
CN109869116B (en) * 2019-03-07 2021-11-23 东北大学 Dewatering well plugging structure and construction method thereof
CN114482105B (en) * 2022-03-18 2024-04-16 中铁一局集团有限公司 Precipitation well group plugging construction method with strong pressurized water after ultra-deep subway station is closed

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000352045A (en) * 1999-06-10 2000-12-19 Maeda Corp Spring water drain pipe cutoff construction method
JP2002206232A (en) * 2001-01-10 2002-07-26 Shimizu Corp Groundwater drainage well and execution method therefor
CN201172828Y (en) * 2008-03-19 2008-12-31 山西第六建筑有限公司 Well-covering device for dewatering well
CN101748742B (en) * 2008-12-04 2011-09-28 上海市基础工程有限公司 Dual-plugging construction method of concrete and flange for depressurization well
CN101713197A (en) * 2009-11-03 2010-05-26 上海建科建设监理咨询有限公司 Method for sealing foundation pit pressure reduction well
CN202047416U (en) * 2011-03-15 2011-11-23 北京中关村开发建设股份有限公司 Well sealing device of pressure-reducing and dewatering well at elevator well pit

Also Published As

Publication number Publication date
CN102561372A (en) 2012-07-11

Similar Documents

Publication Publication Date Title
CN102561372B (en) Plugging method for downcomer for well-point dewatering of deep foundation pit
CN101914917A (en) Anti-seepage and leak-blocking construction method for excavation of subway foundation pit in soft soil area
CN101581088B (en) Construction method for filling mortar combined stone dam
CN101525881A (en) Structure of karst strata pile holes protecting wall and method for constructing pile holes
CN112412496A (en) Full-section advanced curtain grouting construction method for water-rich broken geological zone tunnel
CN106894428A (en) Multi-channel waterproof plugging method for dewatering well of thick and large raft foundation
CN112144559A (en) Well construction method in high water-rich loess sandy gravel stratum transformer tube well
CN114808990A (en) High-pressure pre-filling karst cave pile foundation construction method
JP4628378B2 (en) Ground strengthening method
JP5390060B2 (en) Ground strengthening method
CN110159307A (en) A kind of tunnel multilayer grouting process
CN105178342B (en) Precipitation well casing and method for blocking reserved hole of foundation pit through precipitation well casing
CN103174135B (en) Repair method of unqualified post-grouting bored concrete pile
CN102174818A (en) Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system
CN214783811U (en) Grouting support and grouting system
CN111424695B (en) Seepage-proofing and leakage-stopping method for deep-buried karst pipeline
JP4689555B2 (en) Ground strengthening method
CN100355991C (en) Method for constructing composite foundation of piles and ground interactive slurry bonded dispersed body material
CN100523394C (en) Construction method for concrete shaft wall module masonry
JP2007040096A (en) Ground reinforcing method, managing method of pressure injection into ground, and managing device used for pressure injection
CN108193677A (en) High pressure mortar piled anchor method for processing foundation
CN110452671B (en) Plugging agent for foundation pit row pile enclosure wall and using method thereof
CN113832976A (en) Double-liquid grouting device for foundation pit engineering plugging and emergency rescue and construction method
CN204199324U (en) Connecting reinforcement cage i iron in construction of diaphragm wall
CN1250126A (en) Method of depositing fast solidifying material to eliminate piping and utilizing rotating spray to strength dykes

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant