CN102383433A - Design method for large deep foundation pit of super high-rise building - Google Patents

Design method for large deep foundation pit of super high-rise building Download PDF

Info

Publication number
CN102383433A
CN102383433A CN2011102419995A CN201110241999A CN102383433A CN 102383433 A CN102383433 A CN 102383433A CN 2011102419995 A CN2011102419995 A CN 2011102419995A CN 201110241999 A CN201110241999 A CN 201110241999A CN 102383433 A CN102383433 A CN 102383433A
Authority
CN
China
Prior art keywords
district
podium
foundation pit
construction
foundation ditch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011102419995A
Other languages
Chinese (zh)
Inventor
贾坚
谢小林
翟杰群
张羽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Architecture Design and Research Institute of Tongji University Group Co Ltd
Original Assignee
Architecture Design and Research Institute of Tongji University Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Architecture Design and Research Institute of Tongji University Group Co Ltd filed Critical Architecture Design and Research Institute of Tongji University Group Co Ltd
Priority to CN2011102419995A priority Critical patent/CN102383433A/en
Publication of CN102383433A publication Critical patent/CN102383433A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The invention provides a design method for a large deep foundation pit of a super high-rise building, which comprises the following steps of: dividing the large deep foundation pit of the super high-rise building into a tower community foundation pit and a podium community foundation pit; carrying out construction on envelope enclosures of a pile foundation and the foundation pit of the tower community foundation pit; carrying out down-top construction on the tower community foundation pit; carrying out construction on envelope enclosures of a pile foundation and the foundation pit of the podium community foundation pit; and after building a tower structure to finish a top plate of a basement, carrying out top-down construction on the podium community foundation pit. According to the design method for the large deep foundation pit of the super high-rise building which is provided by the invention, the construction period of the super high-rise building is accelerated by using coordinative designed construction of the tower community foundation pit and the podium community foundation pit, so that the whole construction period is positioned at an optimal time value; and meanwhile, the problem of insufficient construction site is solved and the influence of foundation pit construction on a surrounding environment is reduced.

Description

A kind of method for designing of super highrise building deep big foundation pit
Technical field
The present invention relates to the underground construction design field, relate in particular to a kind of method for designing of super highrise building deep big foundation pit.
Background technology
Along with the continuous development of urban construction, various types of underground constructions, deep-foundation pit engineering are more and more, and the construction method of deep foundation ditch of efficient, economy, energy-saving and environmental protection seems particularly important.At present, traditional construction method of deep foundation ditch is open type construction, and its method is to go along with sb. to guard him the back vertical cut or excavate with putting the slope greatly with supporting and protection structure.Dig to design elevation after-pouring steel bar concrete base plate, the basement structure of from bottom to top successively constructing is again treated to carry out the superstructure construction again after underground structure is accomplished, and this job practices is along practice construction.Opposite with suitable practice construction is contrary sequence method (Top-down method) construction; After space enclosing structure and engineering piles and stand column pile completion; Directly the construction underground structure top board; And then successively carry out the shoveling of each layer of below ground successively downwards, and successively carry out the construction of each layer basement floor downwards, all accomplish the excavation that just carries out lower floor's earthwork after this floor plate construction at every turn.
For the work items that comprises high building and multilayer podium in the super highrise building, high building district foundation ditch and podium district foundation ditch carry out along practice construction usually simultaneously, yet because high building district floor is a lot; The shared duration is long partially, accomplishes in the podium district when binding, and the high building district accomplishes also poor quite a lot of a period of time from construction; High building district and podium district are accomplished around; Prolonged the time of completion of whole construction project, in addition, high building district foundation ditch and podium district foundation ditch carry out causing the construction plant not enough along practice construction simultaneously; And the sedimentation relatively more easily of foundation ditch periphery, environment pollutions such as construction noise and airborne dust are serious; In addition, also have the part engineering to adopt and earlier the podium district carried out reverse construction, however the high building district duration that construction consumes in later stage delayed whole time of completion, make this foundation ditch design scheme also have drawback.
Summary of the invention
Technical problem to be solved by this invention has provided a kind of method for designing of super highrise building deep big foundation pit, how to plan as a whole to design the foundation ditch construction of high building district and the foundation ditch construction of podium district makes whole construction period be in best problem to solve.
In order to solve the problems of the technologies described above, technical scheme of the present invention is: the super highrise building deep big foundation pit is divided into high building district foundation ditch and podium district foundation ditch; Said high building district foundation ditch is carried out pile foundation and foundation pit enclosure structure construction; Said high building district foundation ditch is carried out suitable the construction, and said podium district foundation ditch is carried out pile foundation and foundation pit enclosure structure construction; Treat the high building structure return build accomplish basement roof after, said podium district foundation ditch is carried out adverse construction method.
Further, when said podium district foundation ditch carries out adverse construction method, utilize of the support of the structural beams plate body system of big rigidity as said podium district foundation ditch.
Further, when said podium district foundation ditch was carried out adverse construction method, said high building structure was carried out the above construction in ground.
Further, return to build in the high building structure and said podium district foundation ditch is carried out adverse construction method after accomplishing basement roof, said each floor plate of high building structure basement is docked with each floor plate of basement in said podium district.。
Further, the superstructure number of plies in said high building district is more than or equal to 50 layers.
Further, the superstructure number of plies in said podium district is less than or equal to 8 layers.
The method for designing of super highrise building deep big foundation pit provided by the invention and since the duration that the high building district builds than podium district build long in time limit, therefore; Earlier high building district foundation ditch is carried out along constructing; Can guarantee that high building binds as early as possible, plan as a whole the high building district foundation ditch of design and build and the construction of podium district foundation ditch, make whole construction period be in a best time value; Simultaneously; When high building district foundation ditch is carried out operation, can utilize the podium district that does not begin as yet to construct as the construction plant, the problem that the construction plant that possibly run into when having solved high building district excavation of foundation pit is not enough; Treat the high building structure return build accomplish basement roof after, said podium district foundation ditch is carried out adverse construction method, to reduce high building district and the interval of podium district deadline; Thereby make the time of accomplishing the duration plan as a whole to reach best, in addition, the podium district carries out adverse construction method; The top board in podium district that can utilize completion is as the construction plant in high building district and podium district; Simultaneously, podium district foundation ditch adverse construction method can reduce construction noise, airborne dust etc., to avoid that explosion takes place when making in the construction supporting removal; Reduced the influence of engineering construction, fully implemented the requirement of green building technology surrounding enviroment.
Further, when said podium district foundation ditch carries out adverse construction method, utilize of the support of the structural beams plate body system of big rigidity, help controlling the safety and stability of foundation pit enclosure structure structure as said podium district foundation ditch, thus the better protect surrounding enviroment.
Further, return to build in the high building structure and said podium district foundation ditch is carried out adverse construction method after accomplishing basement roof, said each floor plate of high building structure basement is docked with each floor plate of basement in said podium district., so that the structure level force transfer system is continuous between the zones of different, to guarantee the stable of whole building structure.
Description of drawings
Fig. 1 is the flow chart of steps of the method for designing of the super highrise building deep big foundation pit that provides of the embodiment of the invention;
Fig. 2 A~2D is a corresponding cross-sectional view in the method for designing of the super highrise building deep big foundation pit that provides of the embodiment of the invention.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the method for designing of the super highrise building deep big foundation pit of the present invention's proposition is done further explain.According to following explanation and claims, advantage of the present invention and characteristic will be clearer.What need explanation is, accompanying drawing all adopts the form of simplifying very much and all uses non-ratio accurately, only is used for conveniently, the purpose of the aid illustration embodiment of the invention lucidly.
Core concept of the present invention is, a kind of method for designing of super highrise building deep big foundation pit is provided and since the duration that the high building district builds than podium district build long in time limit; Therefore, earlier high building district foundation ditch is carried out can guaranteeing that along constructing high building binds as early as possible; Planning as a whole the high building district foundation ditch of design builds and the construction of podium district foundation ditch; Make whole construction period be in a best time value, simultaneously, when high building district foundation ditch is carried out operation; Can utilize the podium district that does not begin as yet to construct as the construction plant, the problem that the construction plant that possibly run into when having solved high building district excavation of foundation pit is not enough; Treat the high building structure return build accomplish basement roof after, said podium district foundation ditch is carried out adverse construction method, to reduce high building district and the interval of podium district deadline; Thereby make the time of accomplishing the duration plan as a whole to reach best, in addition, the podium district carries out adverse construction method; The top board in podium district that can utilize completion is as the construction plant in high building district and podium district; Simultaneously, podium district foundation ditch adverse construction method can reduce construction noise, airborne dust etc., to avoid that explosion takes place when making in the construction supporting removal; Reduced the influence of engineering construction, fully implemented the requirement of green building technology surrounding enviroment.
Fig. 1 is the flow chart of steps of the method for designing of the super highrise building deep big foundation pit that provides of the embodiment of the invention.With reference to Fig. 1, the embodiment of the invention provides a kind of method for designing of super highrise building deep big foundation pit, comprises the steps:
S11, the super highrise building deep big foundation pit is divided into high building district foundation ditch and podium district foundation ditch;
S12, said high building district foundation ditch is carried out the construction of pile foundation and foundation pit enclosure structure;
S13, said high building district foundation ditch is carried out along constructing, and said podium district foundation ditch is carried out pile foundation and foundation pit enclosure structure is constructed;
S14, treat the high building structure return build accomplish basement roof after, said podium district foundation ditch is carried out adverse construction method.
To combine generalized section being described in more detail below to the method for designing of the super highrise building deep big foundation pit of the embodiment of the invention.
Shown in Fig. 2 A; And integrating step S12; After carrying out step S11, said high building district foundation ditch 21 is carried out pile foundation and foundation pit enclosure structure construction, make and in high building district foundation ditch 21, form high building district's pile foundation 23 and high building district foundation pit enclosure structure 24; At this moment, podium district foundation ditch 22 is constructed.
Shown in Fig. 2 B, 2C; And integrating step S13; Said high building district foundation ditch 21 is carried out along constructing; The inwall of foundation ditch 21 is provided with a plurality of supports 25 along the high building district in along the process of doing construction, and carry out pile foundation and foundation pit enclosure structure construction to said podium district foundation ditch 22 this moment, makes and in podium district foundation ditch, forms podium district's pile foundation 26 and podium district foundation pit enclosure structure 27.Said high building district foundation ditch 21 carries out building construction along returning as basement structure, forms high building district each floor plate 28 of basement.
Shown in Fig. 2 D, and integrating step S14, treat the high building structure return build accomplish basement roof 28 ' after; Said podium district foundation ditch 22 is carried out adverse construction method; And, said high building district each floor plate 28 of basement dock with each floor plate 29 of basement in said podium district successively in the process that subinverse is done, high building district high building structure carries out constructing more than the ground in the time of podium district foundation ditch 22 adverse construction methods; Arrow is that high building district high building structure is carried out the direction of constructing more than the ground shown in Fig. 2 d; Also carry out the above construction in ground after foundation ditch 22 operations of podium district are accomplished, when said podium district foundation ditch 22 carries out adverse construction method, utilize of the support of the structural beams plate body system of big rigidity as said podium district foundation ditch 22; Help controlling the safety and stability of foundation pit enclosure structure structure, thus the better protect surrounding enviroment.
Particularly; Return to build in the high building structure and accomplish basement roof 28 ' back said podium district foundation ditch 22 is carried out adverse construction method; Said basement roof 28 ' is docked with the top board 29 ' in said podium district; So that the structure level force transfer system between the zones of different is continuous, to guarantee the stable of whole building structure.
Further, the superstructure number of plies in said high building district is more than or equal to 50 layers, and the superstructure number of plies in said podium district is less than or equal to 8 layers.In the present embodiment; The building height in said high building district is 600 meters, and the building height in podium district is 24 meters, according to the building storey in high building district and podium district; And, plan as a whole to design foundation ditch construction of high building district and the foundation ditch construction of podium district according to the foundation depth and the area of the excavation of needs separately.
The embodiment of the invention is planned as a whole the high building district foundation ditch 21 of design and is built and 22 construction of podium district foundation ditch, and said high building district 21 on-stream times of foundation ditch and high building top out time of completion in advance, thereby shorten total duration of engineering.Make whole construction period be in a best time value.
Obviously, those skilled in the art can carry out various changes and modification to invention and not break away from the spirit and scope of the present invention.Like this, belong within the scope of claim of the present invention and equivalent technologies thereof if of the present invention these are revised with modification, then the present invention also is intended to comprise these changes and modification interior.

Claims (6)

1. the method for designing of a super highrise building deep big foundation pit is divided into high building district foundation ditch and podium district foundation ditch with the super highrise building deep big foundation pit, it is characterized in that the method for designing of said super highrise building deep big foundation pit comprises:
The super highrise building deep big foundation pit is divided into high building district foundation ditch and podium district foundation ditch;
Said high building district foundation ditch is carried out pile foundation and foundation pit enclosure structure construction;
Said high building district foundation ditch is carried out suitable the construction, and said podium district foundation ditch is carried out pile foundation and foundation pit enclosure structure construction;
Treat the high building structure return build accomplish basement roof after, said podium district foundation ditch is carried out adverse construction method.
2. the method for designing of super highrise building deep big foundation pit according to claim 1 is characterized in that, when said podium district foundation ditch carries out adverse construction method, utilizes the support of the structural beams plate body system of big rigidity as said podium district foundation ditch.
3. the method for designing of super highrise building deep big foundation pit according to claim 1 is characterized in that, when said podium district foundation ditch was carried out adverse construction method, said high building structure was carried out the above construction in ground.
4. the method for designing of super highrise building deep big foundation pit according to claim 1; It is characterized in that; Return to build in the high building structure and said podium district foundation ditch is carried out adverse construction method after accomplishing basement roof, said each floor plate of high building structure basement is docked with each floor plate of basement in said podium district.
5. according to the method for designing of each super highrise building deep big foundation pit in the claim 1 to 4, it is characterized in that the superstructure number of plies in said high building district is more than or equal to 50 layers.
6. according to the method for designing of each super highrise building deep big foundation pit in the claim 1 to 4, it is characterized in that the superstructure number of plies in said podium district is less than or equal to 8 layers.
CN2011102419995A 2011-08-22 2011-08-22 Design method for large deep foundation pit of super high-rise building Pending CN102383433A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011102419995A CN102383433A (en) 2011-08-22 2011-08-22 Design method for large deep foundation pit of super high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011102419995A CN102383433A (en) 2011-08-22 2011-08-22 Design method for large deep foundation pit of super high-rise building

Publications (1)

Publication Number Publication Date
CN102383433A true CN102383433A (en) 2012-03-21

Family

ID=45823234

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011102419995A Pending CN102383433A (en) 2011-08-22 2011-08-22 Design method for large deep foundation pit of super high-rise building

Country Status (1)

Country Link
CN (1) CN102383433A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839673A (en) * 2012-09-19 2012-12-26 白福波 Design method of side wall depth of foundation pit
CN103195068A (en) * 2013-04-03 2013-07-10 哈尔滨工业大学 Method for determining foundation pit excavation depths through rock and soil constitutive broken lines
CN103711128A (en) * 2013-12-31 2014-04-09 上海建工七建集团有限公司 Construction method for shallow foundation structural beam slab
CN104514228A (en) * 2013-09-29 2015-04-15 浙江宝业建设集团有限公司 Large-chassis multi-tower building construction method and structure
CN104594358A (en) * 2015-01-07 2015-05-06 江苏中南建筑产业集团有限责任公司 Sequential construction and reversed construction Clockwise and counter-clockwise combined construction method of irregular planar deep foundation pit
CN105113514A (en) * 2015-08-31 2015-12-02 广东省建筑设计研究院 Foundation pit enclosure system using underground diaphragm wall as vertical cantilever supporting point and construction method
CN104878763B (en) * 2015-05-29 2016-08-24 朱奎 Main building basement supporting construction with annex
CN108203994A (en) * 2018-03-14 2018-06-26 中建四局第建筑工程有限公司 Along the method for subinverse construction technology on a kind of basement
CN112982484A (en) * 2021-03-04 2021-06-18 中国建筑第八工程局有限公司 Semi-synchronous sequential construction method for underground and overground structure
CN114197533A (en) * 2021-12-29 2022-03-18 中建四局第一建设有限公司 Method for constructing vertical shaft of ultra-high-rise deep foundation pit along straight edge in reverse direction
CN114519228A (en) * 2022-02-24 2022-05-20 四川省建筑设计研究院有限公司 Method for rapidly calculating anti-overturning stress of large-height-to-width-ratio double-tower-structure skirt house floor slab
CN115094912A (en) * 2022-08-01 2022-09-23 上海建工一建集团有限公司 Trans-partition forward and backward combined construction method for building on upper part of ultra-large soft soil foundation pit

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1804255A (en) * 2005-12-16 2006-07-19 张国梁 Reversed construction method for building
KR100625115B1 (en) * 2004-05-29 2006-09-20 (주)새길이엔시 downward reinforced-concrete underground structure using temporary assistant columns
CN1982546A (en) * 2005-12-12 2007-06-20 上海市第七建筑有限公司 Direct local skirt border reversing construction for central island
JP2009280957A (en) * 2008-05-19 2009-12-03 Shimizu Corp Prestressed foundation beam and introduction method of prestress into foundation beam
CN101736757A (en) * 2009-12-04 2010-06-16 上海市第二建筑有限公司 Two-way synchronous construction method of tube structure of high-rise building

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100625115B1 (en) * 2004-05-29 2006-09-20 (주)새길이엔시 downward reinforced-concrete underground structure using temporary assistant columns
CN1982546A (en) * 2005-12-12 2007-06-20 上海市第七建筑有限公司 Direct local skirt border reversing construction for central island
CN1804255A (en) * 2005-12-16 2006-07-19 张国梁 Reversed construction method for building
JP2009280957A (en) * 2008-05-19 2009-12-03 Shimizu Corp Prestressed foundation beam and introduction method of prestress into foundation beam
CN101736757A (en) * 2009-12-04 2010-06-16 上海市第二建筑有限公司 Two-way synchronous construction method of tube structure of high-rise building

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
戴斌: "基坑工程顺逆结合设计方法", 《地下空间与工程学报》 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839673A (en) * 2012-09-19 2012-12-26 白福波 Design method of side wall depth of foundation pit
CN102839673B (en) * 2012-09-19 2014-10-15 白福波 Design method of side wall depth of foundation pit
CN103195068A (en) * 2013-04-03 2013-07-10 哈尔滨工业大学 Method for determining foundation pit excavation depths through rock and soil constitutive broken lines
CN103195068B (en) * 2013-04-03 2015-05-13 哈尔滨工业大学 Method for determining foundation pit excavation depths through rock and soil constitutive broken lines
CN104514228A (en) * 2013-09-29 2015-04-15 浙江宝业建设集团有限公司 Large-chassis multi-tower building construction method and structure
CN103711128A (en) * 2013-12-31 2014-04-09 上海建工七建集团有限公司 Construction method for shallow foundation structural beam slab
CN104594358A (en) * 2015-01-07 2015-05-06 江苏中南建筑产业集团有限责任公司 Sequential construction and reversed construction Clockwise and counter-clockwise combined construction method of irregular planar deep foundation pit
CN104594358B (en) * 2015-01-07 2017-01-18 江苏中南建筑产业集团有限责任公司 Sequential construction and reversed construction Clockwise and counter-clockwise combined construction method of irregular planar deep foundation pit
CN104878763B (en) * 2015-05-29 2016-08-24 朱奎 Main building basement supporting construction with annex
CN105113514B (en) * 2015-08-31 2017-01-04 广东省建筑设计研究院 Foundation pit enclosure system with underground continuous wall as vertical cantilever fulcrum and construction method
CN105113514A (en) * 2015-08-31 2015-12-02 广东省建筑设计研究院 Foundation pit enclosure system using underground diaphragm wall as vertical cantilever supporting point and construction method
CN108203994A (en) * 2018-03-14 2018-06-26 中建四局第建筑工程有限公司 Along the method for subinverse construction technology on a kind of basement
CN112982484A (en) * 2021-03-04 2021-06-18 中国建筑第八工程局有限公司 Semi-synchronous sequential construction method for underground and overground structure
CN112982484B (en) * 2021-03-04 2022-07-12 中国建筑第八工程局有限公司 Semi-synchronous sequential construction method for underground and overground structure
CN114197533A (en) * 2021-12-29 2022-03-18 中建四局第一建设有限公司 Method for constructing vertical shaft of ultra-high-rise deep foundation pit along straight edge in reverse direction
CN114519228A (en) * 2022-02-24 2022-05-20 四川省建筑设计研究院有限公司 Method for rapidly calculating anti-overturning stress of large-height-to-width-ratio double-tower-structure skirt house floor slab
CN114519228B (en) * 2022-02-24 2023-09-22 四川省建筑设计研究院有限公司 Anti-overturning stress rapid calculation method for skirt house floor slab with large height-width ratio double-tower structure
CN115094912A (en) * 2022-08-01 2022-09-23 上海建工一建集团有限公司 Trans-partition forward and backward combined construction method for building on upper part of ultra-large soft soil foundation pit
CN115094912B (en) * 2022-08-01 2023-11-28 上海建工一建集团有限公司 Cross-partition forward and reverse combined construction method for super-large soft soil foundation pit upper building

Similar Documents

Publication Publication Date Title
CN102383433A (en) Design method for large deep foundation pit of super high-rise building
CN106522241B (en) The method for supporting deep foundation pit of the high basement structure of super large layer
CN203256761U (en) Tower crane foundation arranged on top plate of basement
CN101408025B (en) Pit construction method by using major structure as bearing point
CN203654294U (en) Foundation pit supporting structure used in reverse building method
CN106088148B (en) Pipe gallery template and its application
CN102127974A (en) Design and construction method of additional cellar under existing building
CN105113540A (en) Construction method for newly-built large deep foundation pit basements under protection building
CN201901879U (en) Nonstandard foundation used for fixing tower crane
CN204715366U (en) A kind of large-area deep foundation pit subregion is along the support system under inverse operating mode
CN104234082A (en) Jump-layer reversed construction method for deep foundation pit
CN209855277U (en) Conversion layer structure for underground added layer of existing building
CN101824825B (en) Deep foundation pit open cutting construction method
CN106065668B (en) A kind of construction techniques
CN102410031A (en) Underground space structure constructed by pile wall construction method
CN105926630B (en) A kind of annular support replacement and jump storehouse construction method for accelerating deep big Underground Construction
CN101498133B (en) Method and supporting construction for enlarging basement top-down method earth excavation space
CN202466597U (en) Semi-inverse annular plate support system oversized subway deep foundation ditch construction structure
CN202577313U (en) Supporting combined system for deep foundation pit
CN102493488A (en) Construction method for reverse beams and normal plates in foundation pit engineering
CN110616739B (en) Vertical construction method for underground space of existing building
CN105714851B (en) Assembled ground-connecting-wall or prefabricated pile are with cast-in-place underground station integrative construction device and using its construction method
CN106836230A (en) A kind of foundation ditch point hole construction method
KR101522300B1 (en) the self-positioning structure of column and the modular pile up construction method using the same
CN105625184A (en) Subway station building method using bridge and station combined building mode

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120321

WD01 Invention patent application deemed withdrawn after publication