CN102312430A CN201110104220A CN201110104220A CN102312430A CN 102312430 A CN102312430 A CN 102312430A CN 201110104220 A CN201110104220 A CN 201110104220A CN 201110104220 A CN201110104220 A CN 201110104220A CN 102312430 A CN102312430 A CN 102312430A
Authority
CN
China
Prior art keywords
pile
concrete
pipe
pile body
outer tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201110104220A
Other languages
Chinese (zh)
Inventor
王庆伟
王琢璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201110104220A priority Critical patent/CN102312430A/en
Publication of CN102312430A publication Critical patent/CN102312430A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention belongs to a building construction method, and in particular relates to a pipe sinking expansion pressure grouting pile forming method. The method comprises the following steps of: 1, sinking an outer pipe, the interior of which is provided with a core pipe and the front end of which is provided with a pointed valve, to the designed depth of a pile body by adopting a high-frequency hydraulic vibrating hammer; 2, when the outer pipe is uplifted and concrete is pumped to the height which is 1/5 to 3/5 of the pile at the same time, performing downward vibration and extrusion to form expansion on the concrete of the pile bottom and the pile body, repeating the operation for 2 to 3 times according to the requirement of bearing capacity, or omitting the step; 3, when the outer pipe is uplifted, continuously pumping concrete by using a high pressure pump, or lifting the pipe and continuously pumping and grouting the concrete while vibrating, so that the concrete of the pile body is more compact; and 4, if the pile foundation is constructed, forming the pile after a reinforcement cage is placed. By the pipe sinking expansion pressure grouting pile forming method, the bearing capacity of the pile body is greatly improved, noise and waste oil are not produced in construction, the civilization level of the construction environment is ensured, the production efficiency is high, and the engineering cost is reduced.

Description

The squeezed pressure of immersed tube is irritated into pile work method
Technical field
The invention belongs to construction techniques, the squeezed pressure of particularly a kind of immersed tube is irritated into pile work method.
Background technology
At present, in long-spiral-compacted-concrete pile, semi-screw pile, perfusion helical burr ram, all adopt the spiral drilling and forming hole, the high-pressure pump guncreting forms bored concrete pile technology; But in the castinplace pile of immersed tube class, also do not use the method pile that does not more utilize the high-pressure pump guncreting in the squeezed pile of technical method, particularly immersed tube of high-pressure pump guncreting, tube-sinking cast-in-situ pile is to sink to desired depth to pipe; Behind the descending reinforcing cage from top with hopper castinplace pile body concrete, vibrate tube pulling then, the flap valve valve of bottom is opened under gravity concrete; Because pressure is little, often the unlatching of flap valve valve is undesirable, causes broken pile sometimes; Undergauge, folder mud, reveal problems such as muscle, influence the bearing capacity of pile body, and speed of application is slow; Bearing capacity is low, and work efficiency is low; Existing several kinds of " the complex carrier compaction piles " invented in the pile work method are to utilize elongated hammer to ram pore-forming; Outer tube presses down thereupon and puts in place, fills out building waste and harsh concrete etc. from the sidewall mouth of outer tube again, is lowered to reinforcing cage; From sidewall mouth concrete placing; Dialled the outer tube pile, this technology efficiency of construction is low, presses pipe and pile water shutoff difficulty when stake is long; It also is to insert from the sidewall mouth that " static force top press poured piles " its filler is arranged in addition, owing to adopt the static pressure inner and outer pipes, often meets closely knit layer of sand and boulder bed and is difficult to penetrate; Also have " full pound type bottom-enlarging filling pile " and " interior rammer tube-sinking cast-in-situ pile "; The former whole pile body adopts low hammer compaction pile concrete, and the latter adopts weight impact pile end concrete, and the filler mode is the filler from the top; Shortcoming is that noise is big; Can't construct in the city, efficient is low, and the concrete of above-mentioned method for filling contact not as the high pressure pumping of concrete with hole wall soil, influences bearing capacity and brings into play.
Summary of the invention
The objective of the invention is to overcome above-mentioned technical deficiency, the squeezed pressure of immersed tube of a kind of single pile bearing height is provided, guarantee pile quality, construct noiselessness, raising the efficiency is irritated into pile work method.
The technical scheme that technical solution problem of the present invention adopts is: the characteristics that the squeezed pressure of immersed tube is irritated into pile work method are: 1, adopt the high frequency hydraulic vibration driver, have the core pipe to inside, the outer tube that front end has a pointed flap valve valve sinks to the projected depth of pile body; 2, carry outer tube simultaneous pumping concrete on and account for 1/5 ~ 3/5 when height of stake, vibrate extruding downwards, at the bottom of the stake and the concrete of pile body form squeezedly, according to requirement for bearing capacity, repeat this operation 2 ~ 3 times, also can omit this step; When carrying outer tube 3,, utilize high-pressure pump uninterrupted pumping concrete, but carry pipe while vibrating, uninterrupted pumping guncreting in limit makes pile concrete more closely knit; If 4 pile foundations, pile behind the placement reinforcing cage.
The invention has the beneficial effects as follows: the squeezed pressure of immersed tube is irritated into pile work method increases substantially the bearing capacity of pile body, the construction noiselessness, and no spoir, assurance construction environment civilization degree, production efficiency is high, reduces construction costs.
The specific embodiment
Below in conjunction with embodiment the present invention is specified.
Embodiment; It is the defective that overcomes long-spiral-compacted-concrete pile, semi-screw pile, tube-sinking cast-in-situ pile that the squeezed pressure of immersed tube is irritated into pile work method; Adopt the squeezed guncreting again of immersed tube pile-formation process, the pile body of formation carries greatly and improves, and adopts high frequency hydraulic vibration driver immersed tube; The high-pressure pump pumping of concrete, efficiency of construction significantly improves.Worker's method that it adopts is: 1, the drilling tool that adopted of the squeezed pile of immersed tube hole is that front end has pointed valve; The outer tube inboard is the core pipe, and the core pipe outside is an outer tube, and outer tube plays the retaining wall effect; Inner core tube be pumping of concrete passage, utilize the high frequency hydraulic vibration driver; Outer tube is sunk to the projected depth of pile body,, be convenient to sink to because the front end valve is pointed; 2, promote outer tube, in the stake hole, concrete is pumped into 1/5 ~ 3/5 high height of stake, the concrete that pumps into is vibrated extruding with high-pressure pump; To at the bottom of the stake and the concrete of pile body form squeezed; According to requirement for bearing capacity, can repeat this operation 2 ~ 3 times, also can omit this step; 3, Vibration on Start-up hammer promotes outer tube, on when dialling outer tube, utilize high-pressure pump uninterrupted pumping concrete, pipe is carried in limit continuous shaking, the continuous pump pressure concrete placing in limit makes the concrete of pile body more closely knit to a stake design height, and bearing capacity is increased substantially; If 4 pile foundations, pile behind the placement reinforcing cage in the stake hole.
It is the method combination pile with immersed tube hole forming method and high-pressure pump guncreting that this kind becomes pile work method; Adopt high frequency hydraulic vibration driver immersed tube pore-forming, make the speed of pile faster, noiselessness, and penetration capacity is stronger; Except that can not be in the decomposed rock stratum the pore-forming; Other stratum all can the pore-forming pile, and can the squeezed concrete of secondary, the bearing capacity of stake is higher, cost significantly reduces.

Claims (1)

1. the squeezed pressure of immersed tube is irritated into pile work method, it is characterized in that: 1, adopt the high frequency hydraulic vibration driver, have the core pipe to inside, the outer tube that front end has a pointed flap valve valve sinks to the projected depth of pile body; 2, carry outer tube simultaneous pumping concrete on and account for 1/5 ~ 3/5 when height of stake, vibrate extruding downwards, at the bottom of the stake and the concrete of pile body form squeezedly, according to requirement for bearing capacity, repeat this operation 2 ~ 3 times, also can omit this step; When carrying outer tube 3,, utilize high-pressure pump uninterrupted pumping concrete, but carry pipe while vibrating, uninterrupted pumping guncreting in limit makes pile concrete more closely knit; If 4 pile foundations, pile behind the placement reinforcing cage.
CN201110104220A 2011-04-26 2011-04-26 Pipe sinking expansion pressure grouting pile forming method Pending CN102312430A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110104220A CN102312430A (en) 2011-04-26 2011-04-26 Pipe sinking expansion pressure grouting pile forming method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110104220A CN102312430A (en) 2011-04-26 2011-04-26 Pipe sinking expansion pressure grouting pile forming method

Publications (1)

Publication Number Publication Date
CN102312430A true CN102312430A (en) 2012-01-11

Family

ID=45425968

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110104220A Pending CN102312430A (en) 2011-04-26 2011-04-26 Pipe sinking expansion pressure grouting pile forming method

Country Status (1)

Country Link
CN (1) CN102312430A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1928251A (en) * 2006-09-26 2007-03-14 徐东强 Pipe pile hole maker with concrete bottom sealing, pipe cover and wings and construction process thereof
CN101368385A (en) * 2007-08-14 2009-02-18 刘润郊 Pile forming method and device for static driven cast-in-place pile
CN201873991U (en) * 2010-10-23 2011-06-22 孔超 Device for forming cast-in-place pile through high frequency vibrating and compacting dry soil displacement
KR101125048B1 (en) * 2008-07-23 2012-03-21 이엑스티 주식회사 Steel pipe pile and phc pile with inner pipe for air injection and grouting

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1928251A (en) * 2006-09-26 2007-03-14 徐东强 Pipe pile hole maker with concrete bottom sealing, pipe cover and wings and construction process thereof
CN101368385A (en) * 2007-08-14 2009-02-18 刘润郊 Pile forming method and device for static driven cast-in-place pile
KR101125048B1 (en) * 2008-07-23 2012-03-21 이엑스티 주식회사 Steel pipe pile and phc pile with inner pipe for air injection and grouting
CN201873991U (en) * 2010-10-23 2011-06-22 孔超 Device for forming cast-in-place pile through high frequency vibrating and compacting dry soil displacement

Similar Documents

Publication Publication Date Title
CN104074186B (en) The casing device of pore-forming and construction method thereof in a kind of building lot
CN102733378B (en) Construction method of concrete pile
CN203403404U (en) High-efficiency cast-in-place pile device
CN105714773A (en) Foundation treatment method
CN101200893A (en) Construction method of pile with bearing base
CN105862861A (en) Rigid-pile embedding device and construction method
CN101575852A (en) Construction method of wall-retaining bottom-expanding sinking-pipe cast-in-situ piles
CN106192999A (en) The construction method of uplift pile
CN101024950A (en) Salinized-soil-strong tamping and water-discharging pile foundation processing method
CN104294818A (en) Construction method for concrete pile
CN102635110B (en) Construction method for concrete pile
CN1621626A (en) Construction method for concrete pile
CN205776216U (en) A kind of implantation equipment of rigid pile
CN111827247A (en) Method for reinforcing soft foundation
CN101298769A (en) Pile concrete filling method aiming at karst cave area
CN100513702C (en) Construction method of guarantying pile length of driven cast-in-place pile constructed in pebble layer and sand layer
CN1827924A (en) Foundation treatment method by static pressure replacement and multi-purpose press pipe thereof
CN204225100U (en) The construction equipment of concrete pile
CN204252120U (en) The construction equipment of concrete pile
CN101245597A (en) Breast wall type cast-in-situ bored pile construction method and pile machine
CN205776209U (en) The construction equipment of concrete-pile
CN107476295A (en) A kind of Concrete Grouting Pale technique
CN1148493C (en) Construction method of large-diameter fully-sleeved filled pile
CN108049401A (en) A kind of screw thread rammed bulb pile and its construction method
CN102312428A (en) Tooth pile and pile forming method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120111