CN102285525B - Track transfer system for containers - Google Patents

Track transfer system for containers Download PDF

Info

Publication number
CN102285525B
CN102285525B CN2011102267634A CN201110226763A CN102285525B CN 102285525 B CN102285525 B CN 102285525B CN 2011102267634 A CN2011102267634 A CN 2011102267634A CN 201110226763 A CN201110226763 A CN 201110226763A CN 102285525 B CN102285525 B CN 102285525B
Authority
CN
China
Prior art keywords
track
container
destination
transhipment
freight container
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2011102267634A
Other languages
Chinese (zh)
Other versions
CN102285525A (en
Inventor
王纯政
张保军
张明华
谢波
李平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Leaddo Measuring and Control Co Ltd
Original Assignee
Wuhan Leaddo Measuring and Control Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Leaddo Measuring and Control Co Ltd filed Critical Wuhan Leaddo Measuring and Control Co Ltd
Priority to CN2011102267634A priority Critical patent/CN102285525B/en
Publication of CN102285525A publication Critical patent/CN102285525A/en
Priority to PCT/CN2012/079194 priority patent/WO2013020457A1/en
Application granted granted Critical
Publication of CN102285525B publication Critical patent/CN102285525B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Warehouses Or Storage Devices (AREA)
  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

The invention discloses a track transfer system for containers, which comprises a container transfer carriage, a track and lifting devices, wherein the lifting devices are respectively arranged on a container transfer station and a container destination, the container transfer station and the container destination are connected by the track, and the container transfer carriage is arranged on the track. In the invention, the container transfer station and the container destination are connected by the track, therefore, the container transfer with primary investment can be realized without a lot of workers, and the operation cost can be reduced; meanwhile, the track transfer system for containers is simple and practical in structure, difficult to have problems, and low in later maintenance cost; and the track transfer system for containers is implemented by using electric energy, therefore, the system is more energy-saving and environmentally-friendly, and in line with the needs of the development of our country. The track transfer system for containers disclosed by the invention has the advantages of simple structure, low cost, convenience in maintenance, energy conservation and environmental protection, and the like. The track transfer system for containers is suitable for container transfer.

Description

Freight container rail transfer system
Technical field
The present invention relates to the container transshipment system, particularly relate to a kind of freight container rail transfer system.
Background technology
China's economy is growing, and the transportation of goods is also increasing sharp.And a large amount of freight container specialized trucks of the general employing of the transhipment of cargo-type container at present (be commonly called as: there is following problem like this in haul back and forth truck):
1, owing to need to adopt a large amount of truck hauls, like this, each truck need be equipped with a chaufeur, has consumed a large amount of manpowers;
2, because the truck price is more expensive, so the initial stage input cost is higher, and the time long after, truck breaks down easily, have in addition need to change, cause later maintenance cost also high;
3, because present global fuel supply is nervous, cause the required fuel price of truck surging, further improved the container transshipment cost;
4, because truck must use fuel oil, so the operation of a large amount of trucks will inevitably be discharged a large amount of tail gas, the environment of pollution.
Summary of the invention
The objective of the invention is provides a kind of simple in structure in order to overcome the deficiency of above-mentioned background technology, and cost is low, the freight container rail transfer system of easy to maintenance and energy-conserving and environment-protective.
In order to realize above purpose; A kind of freight container rail transfer provided by the invention system; Comprise: container transshipment dolly, track and overhead hoist; Said overhead hoist is arranged in container transshipment station and freight container destination, and said container transshipment station is connected perforation through track with the freight container destination, and said container transshipment dolly is arranged in orbit.
In the such scheme; Said track comprises transhipment track and destination track; The junction of transhipment track and destination track is provided with the transition device that is used for freight container transition transportation, can let the container transshipment dolly move on another section track from track section smoothly like this, thereby reach the purpose that turns to; Can certainly the junction of transhipment track and destination track be designed to arc-shaped structure, so that the container transshipment dolly turns to smoothly.
In the such scheme, in the said track is double-deck track partly or entirely, and the two ends of double-deck track are respectively equipped with an elevator, and during practical implementation, individual layer track and double-deck track be collocation design arbitrarily.
In the such scheme, said transhipment track and destination track are the individual layer track, and the junction of transhipment track and destination track is provided with the transition device that is used for freight container transition transportation.
In the such scheme, said transhipment track is the individual layer track, and the destination track is double-deck track, and the two ends of this destination track are respectively equipped with an elevator, and the junction of transhipment track and destination track is provided with the transition device that is used for freight container transition transportation.
In the such scheme, said destination track is the individual layer track, and the transhipment track is double-deck track, and the two ends of this transhipment track are respectively equipped with an elevator, and the junction of transhipment track and destination track is provided with the transition device that is used for freight container transition transportation.
In the such scheme; Said transhipment track and destination track are double-deck track; The two ends of the track of being made up of transhipment track and destination track are respectively equipped with an elevator, and the junction of transhipment track and destination track is provided with and is used for the transition device that freight container is gone through transition and transported.
In the such scheme, said transhipment track and destination track are double-deck track, and the two ends of transhipment track and destination track are respectively equipped with an elevator, and the junction of transhipment track and destination track is provided with the transition device that is used for freight container transition transportation.
In the such scheme, the said transition device that is used for freight container transition transportation is a crane, certainly, also can adopt other transition devices.
In the such scheme; The said transition device that is used for freight container transition transportation comprises roller steering equipment that is arranged between container transshipment dolly bottom and the container transshipment trolley idler wheels and the telescopic supporting rod that is arranged on container transshipment dolly bottom; Certainly, also can adopt other transition devices.
In the such scheme, said overhead hoist is a gauntry crane, certainly, also can adopt other overhead hoist.
The present invention is connected perforation with the container transshipment station with the freight container destination through track, has realized the transhipment of freight container, and once investment need not a large amount of staff, has reduced operating cost; Simultaneously, this freight container rail transfer system architecture is simple and practical, is difficult for ging wrong, and later maintenance cost is low; And this freight container rail transfer system uses is electric energy, and more energy-conserving and environment-protective meet the needs of China's development.
The contrast of the present invention and prior art, show that fully its preceence is: simple in structure, cost is low, easy to maintenance and energy-conserving and environment-protective etc.
Description of drawings
Fig. 1 is the structural representation of embodiment 1;
Fig. 2 is the side-looking structural representation of Fig. 1;
Fig. 3 is the structural representation of embodiment 2;
Fig. 4 is the side-looking structural representation of Fig. 3;
Fig. 5 is the structural representation of embodiment 3;
Fig. 6 is the side-looking structural representation of Fig. 5;
Fig. 7 is the structural representation of embodiment 4;
Fig. 8 is the side-looking structural representation of Fig. 7;
Fig. 9 is the structural representation of embodiment 5;
Figure 10 is the side-looking structural representation of Fig. 9.
Among the figure: container transshipment dolly 1, track 2, transhipment track 2a, destination track 2b, overhead hoist 3, container transshipment station 4, freight container destination 5, transition device 6, elevator 7, freight container 8.
The specific embodiment
Below in conjunction with accompanying drawing and embodiment the present invention is made further detailed description, but following examples should not be construed as limitation of the present invention.
Embodiment 1:
A kind of freight container rail transfer system is provided; Comprise: container transshipment dolly 1, track 2 and overhead hoist 3; Said overhead hoist 3 is arranged in container transshipment station 4 and freight container destination 5; Said container transshipment station 4 is connected perforation through track 2 with freight container destination 5, and said container transshipment dolly 1 is arranged on the track 2.Said track 2 comprises transhipment track 2a and destination track 2b, and the junction of transhipment track 2a and destination track 2b is provided with the transition device 6 that is used for freight container 8 transition transportations.Said transhipment track 2a and destination track 2b are the individual layer track.Said transition device 6 comprises roller steering equipment that is arranged between container transshipment dolly 1 bottom and container transshipment dolly 1 roller and the telescopic supporting rod that is arranged on container transshipment dolly 1 bottom.Certainly, said transition device 6 also can be crane, or other transition mechanisms.Said overhead hoist 3 is a gauntry crane, certainly, also can adopt other overhead hoist.
Above-mentioned track 2 by transhipment track 2a and destination track 2b can be designed to semi-ring formula structure or loopful formula periodic structure.When track 2 is designed to semi-ring formula structure; Container transshipment dolly 1 is realized back and forth transfer container 8 through on track 2, walking back and forth, and when container transshipment dolly 1 is walked the junction of transhipment track 2a and destination track 2b, said crane will be transported on the container transshipment dolly 1 of freight container 8 handlings to the track 2b of destination on the container transshipment dolly 1 on the track 2a; At this moment; Container transshipment dolly 1 empty wagons on the transhipment track 2a is back walked, and the container transshipment dolly 1 on the track 2b of destination carries freight container 8 to be continued to the destination walking, behind the 1 arrival destination of the container transshipment dolly on the track 2b of destination; Only need gauntry crane that freight container 8 handlings are got final product to assigned address; At this moment, container transshipment dolly 1 empty wagons on the track 2b of destination is back walked, so circulation; When track 2 is designed to loopful formula periodic structure (promptly will transport track 2a, destination track 2b and transhipment track 2a through track 2 and connect into a closed ring structure); Transition device 6 adopts roller steering equipment; 1 need of container transshipment dolly just can be realized the transhipment of freight container 8 to a direction walking; And this texture ratio semi-ring formula structure efficiency is higher, particularly, and when container transshipment dolly 1 is walked the junction of transhipment track 2a and destination track 2b; The telescopic supporting rod of transition device 6 stretches out; Make the roller of container transshipment dolly 1 bottom be lifted away from track 2 container transshipment dolly 1 jack-up, the roller steering equipment of the device 6 of going through transition then is with the roller steering (roller is aimed at destination track 2b) of container transshipment dolly 1 bottom, and the telescopic supporting rod of the device 6 of going through transition is at last withdrawn; Container transshipment dolly 1 is fallen destination track 2b and is upward continued to walk to the destination; After container transshipment dolly 1 arrived at the destination, to assigned address, container transshipment dolly 1 continued walking forward and gets back to initial position said gauntry crane with 8 handlings of the freight container on the container transshipment dolly 1.
Embodiment 2:
A kind of freight container rail transfer system is provided; Comprise: container transshipment dolly 1, track 2 and overhead hoist 3; Said overhead hoist 3 is arranged in container transshipment station 4 and freight container destination 5; Said container transshipment station 4 is connected perforation through track 2 with freight container destination 5, and said container transshipment dolly 1 is arranged on the track 2.Said track 2 comprises transhipment track 2a and destination track 2b, and the junction of transhipment track 2a and destination track 2b is provided with the transition device 6 that is used for freight container 8 transition transportations.Said transhipment track 2a is the individual layer track, and destination track 2b is double-deck track, and the two ends of this destination track 2b are respectively equipped with an elevator 7.Said transition device 6 comprises roller steering equipment that is arranged between container transshipment dolly 1 bottom and container transshipment dolly 1 roller and the telescopic supporting rod that is arranged on container transshipment dolly 1 bottom.Certainly, said transition device 6 also can be crane, or other transition mechanisms.Said overhead hoist 3 is a gauntry crane, certainly, also can adopt other overhead hoist.
The present embodiment working process is following: said container transshipment dolly 1 walks back and forth on transhipment track 2a, is furnished with some container transshipment dollies 1 of walking of not stopping on the track 2b of destination.Container transshipment dolly 1 on transporting track 2a is walked to when transporting the junction of track 2a and destination track 2b; Said crane is with on the container transshipment dolly 1 of freight container 8 handlings on this container transshipment dolly 1 to the track 2b of destination; At this moment; Container transshipment dolly 1 on the transhipment track 2a is back walked, and the container transshipment dolly 1 on the track 2b of destination is walked on the track 2b of destination; When the container transshipment dolly 1 on the track 2b of destination was walked assigned address, said gauntry crane arrived the destination with 8 handlings of the freight container on the container transshipment dolly 1; When the container transshipment dolly 1 on the track 2b of destination is walked destination track 2b terminal point (arriving on the elevator 7); Container transshipment dolly 1 stops walking; Said elevator 7 work move to this empty container transport carriage 1 on another layer (being lower floor) track of destination track 2b; Empty container transport carriage 1 initial position of back walking again, so circulation.
Embodiment 3:
A kind of freight container rail transfer system is provided; Comprise: container transshipment dolly 1, track 2 and overhead hoist 3; Said overhead hoist 3 is arranged in container transshipment station 4 and freight container destination 5; Said container transshipment station 4 is connected perforation through track 2 with freight container destination 5, and said container transshipment dolly 1 is arranged on the track 2.Said track 2 comprises transhipment track 2a and destination track 2b, and the junction of transhipment track 2a and destination track 2b is provided with the transition device 6 that is used for freight container 8 transition transportations.Said destination track 2b is the individual layer track, and transhipment track 2a is double-deck track, and the two ends of this transhipment track 2a are respectively equipped with an elevator 7.Said transition device 6 comprises roller steering equipment that is arranged between container transshipment dolly 1 bottom and container transshipment dolly 1 roller and the telescopic supporting rod that is arranged on container transshipment dolly 1 bottom.Certainly, said transition device 6 also can be crane, or other transition mechanisms.Said overhead hoist 3 is a gauntry crane, certainly, also can adopt other overhead hoist.
The working process of present embodiment working process and embodiment 2 is similar, repeats no more at this.
Embodiment 4:
A kind of freight container rail transfer system is provided; Comprise: container transshipment dolly 1, track 2 and overhead hoist 3; Said overhead hoist 3 is arranged in container transshipment station 4 and freight container destination 5; Said container transshipment station 4 is connected perforation through track 2 with freight container destination 5, and said container transshipment dolly 1 is arranged on the track 2.Said track 2 comprises transhipment track 2a and destination track 2b, and the junction of transhipment track 2a and destination track 2b is provided with the transition device 6 that is used for freight container 8 transition transportations.Said transhipment track 2a and destination track 2b are double-deck track, and the two ends of the track of being made up of transhipment track 2a and destination track 2b are respectively equipped with an elevator 7.Said transition device 6 comprises roller steering equipment that is arranged between container transshipment dolly 1 bottom and container transshipment dolly 1 roller and the telescopic supporting rod that is arranged on container transshipment dolly 1 bottom.Certainly, said transition device 6 also can be crane, or other transition mechanisms.Said overhead hoist 3 is a gauntry crane, certainly, also can adopt other overhead hoist.
Present embodiment working process and embodiment 1 are similar with embodiment 2, repeat no more at this.
Embodiment 5:
A kind of freight container rail transfer system is provided; Comprise: container transshipment dolly 1, track 2 and overhead hoist 3; Said overhead hoist 3 is arranged in container transshipment station 4 and freight container destination 5; Said container transshipment station 4 is connected perforation through track 2 with freight container destination 5, and said container transshipment dolly 1 is arranged on the track 2.Said track 2 comprises transhipment track 2a and destination track 2b, and the junction of transhipment track 2a and destination track 2b is provided with the transition device 6 that is used for freight container 8 transition transportations.Said transhipment track 2a and destination track 2b are double-deck track, and the two ends of transhipment track 2a and destination track 2b are respectively equipped with an elevator 7.Said transition device 6 comprises roller steering equipment that is arranged between container transshipment dolly 1 bottom and container transshipment dolly 1 roller and the telescopic supporting rod that is arranged on container transshipment dolly 1 bottom.Certainly, said transition device 6 also can be crane, or other transition mechanisms.Said overhead hoist 3 is a gauntry crane, certainly, also can adopt other overhead hoist.
Present embodiment working process and embodiment 1 are similar with embodiment 2, repeat no more at this.
The present invention in the specific implementation, can be according to actual needs with being double-deck track partly or entirely in the track 2, individual layer track and double-deck track be collocation design arbitrarily; Simultaneously, also can according to actual needs track 2 be designed to semi-ring formula structure or loopful formula periodic structure.The present invention can realize freight container 8 is transported to the destination, freight container 8 is transported to second destination, directly freight container 8 is transported to from transfer point other transportation meanss (train etc.) are gone up and freight container 8 is transported to other transportation meanss from the destination first-class from first destination from transfer point through above design variation.

Claims (7)

1. freight container rail transfer system; Comprise: container transshipment dolly, track and overhead hoist; Said overhead hoist is arranged in container transshipment station and freight container destination; Said container transshipment station is connected perforation through track with the freight container destination, and said container transshipment dolly is arranged in orbit; Said track comprises transhipment track and destination track; The junction of transhipment track and destination track is provided with the transition device that is used for freight container transition transportation; It is characterized in that: in the said track is double-deck track partly or entirely, and the two ends of double-deck track are respectively equipped with an elevator.
2. freight container rail transfer as claimed in claim 1 system, it is characterized in that: said transhipment track is the individual layer track, and the destination track is double-deck track, and the two ends of this destination track are respectively equipped with an elevator.
3. freight container rail transfer as claimed in claim 1 system, it is characterized in that: said destination track is the individual layer track, and the transhipment track is double-deck track, and the two ends of this transhipment track are respectively equipped with an elevator.
4. freight container rail transfer as claimed in claim 1 system, it is characterized in that: said transhipment track and destination track are double-deck track, and the two ends of the track of being made up of transhipment track and destination track are respectively equipped with an elevator.
5. freight container rail transfer as claimed in claim 1 system, it is characterized in that: said transhipment track and destination track are double-deck track, and the two ends of transhipment track and destination track are respectively equipped with an elevator.
6. freight container rail transfer as claimed in claim 1 system is characterized in that: the said transition device that is used for freight container transition transportation is a crane.
7. freight container rail transfer as claimed in claim 1 system; It is characterized in that: the said transition device that is used for freight container transition transportation comprises: what be arranged on the roller steering equipment that is used for roller steering between container transshipment dolly bottom and the container transshipment trolley idler wheels and be arranged on container transshipment dolly bottom is used for the case telescopic supporting rod of transport carriage of support set.
CN2011102267634A 2011-08-09 2011-08-09 Track transfer system for containers Active CN102285525B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN2011102267634A CN102285525B (en) 2011-08-09 2011-08-09 Track transfer system for containers
PCT/CN2012/079194 WO2013020457A1 (en) 2011-08-09 2012-07-26 Container track-transfer system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011102267634A CN102285525B (en) 2011-08-09 2011-08-09 Track transfer system for containers

Publications (2)

Publication Number Publication Date
CN102285525A CN102285525A (en) 2011-12-21
CN102285525B true CN102285525B (en) 2012-11-28

Family

ID=45332326

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011102267634A Active CN102285525B (en) 2011-08-09 2011-08-09 Track transfer system for containers

Country Status (1)

Country Link
CN (1) CN102285525B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013020457A1 (en) * 2011-08-09 2013-02-14 武汉利德测控技术股份有限公司 Container track-transfer system
CN103754653B (en) * 2013-12-13 2017-01-04 天津合纵电力设备有限公司 Circulating double-layer quick material conveyor line for ring main unit
CN105314408B (en) * 2015-11-06 2017-11-10 上海华兴数字科技有限公司 A kind of container terminal automation Orbital Transport Systems and operation method
CN106348036A (en) * 2016-11-17 2017-01-25 中冶华天工程技术有限公司 Bar transfer method and device
CN107499849A (en) * 2017-09-22 2017-12-22 王燏斌 A kind of container handling equipment and its carrying method
CN109160296B (en) * 2018-08-09 2020-11-17 中铁武汉勘察设计研究院有限公司 River and sea combined transport container transit transportation system and method based on rail truck
CN109160295B (en) * 2018-08-09 2020-10-23 中铁武汉勘察设计研究院有限公司 Container river-sea combined transportation transfer system and method based on rail truck
CN109160294B (en) * 2018-08-09 2020-10-23 中铁武汉勘察设计研究院有限公司 River and sea combined transport container transportation system and method based on rail collection truck
CN109160293B (en) * 2018-08-09 2020-10-23 中铁武汉勘察设计研究院有限公司 River and sea combined transport container transfer system and method based on rail truck
CN109319514B (en) * 2018-08-09 2020-10-23 中铁武汉勘察设计研究院有限公司 Container transportation system and method based on river and sea combined transportation

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2657643A (en) * 1950-02-17 1953-11-03 Globe Company Overhead switch
US4973219A (en) * 1986-04-30 1990-11-27 Sea-Land Corporation Grid rail container transport and storage system
CN2095787U (en) * 1990-11-24 1992-02-12 天津市第三棉纺织厂机械分厂 Small vehicle wheel
AT500088B1 (en) * 2002-09-11 2007-06-15 Rail Cargo Austria Ag METHOD OF LOADING AND UNLOADING
CN2623671Y (en) * 2003-05-21 2004-07-07 上海振华港口机械(集团)股份有限公司 Double carriage container crane
CN101070122A (en) * 2006-05-12 2007-11-14 上海明路绳网索具有限公司 Container loading-unloading automatic flow-line
CN101007590A (en) * 2006-12-31 2007-08-01 郑卫星 Double bearing track turnout
CN202208513U (en) * 2011-08-09 2012-05-02 武汉利德测控技术股份有限公司 Track transportation system for container

Also Published As

Publication number Publication date
CN102285525A (en) 2011-12-21

Similar Documents

Publication Publication Date Title
CN102285525B (en) Track transfer system for containers
CN102815546B (en) Vehicle goods bracket and vehicle goods bracket assembly
ATE474800T1 (en) LOADING/UNLOADING SYSTEM FOR A CONTAINER TERMINAL
CN103072902B (en) Double-crossbeam quayside container crane
CN106672856A (en) Double-shear fork container transferring trolley
CN203568720U (en) Integrally loading/unloading vehicle based on slippage arm-changing mechanism
CN202208513U (en) Track transportation system for container
CN203781102U (en) Self-loading-unloading device in container
CN204778506U (en) Container crane of two main dollies
CN203359826U (en) Bank crane with three sets of trolleys
CN203529772U (en) Container loading and unloading system with double-layer cross-sea trestle
CN106241594B (en) A kind of retractable sling for container
CN202671135U (en) Freight forklift
CN201092516Y (en) Novel container gantry crane
CN202296231U (en) Logistics trolley for engineering machinery production
CN203461541U (en) Ferry bridge with horizontal moving units
CN104401883A (en) Vertical turning equipment for container
CN208827682U (en) A kind of lifting charging crane for cargo
CN203331903U (en) Container site moving vehicle
CN204110827U (en) A kind of guide rail car
CN203740623U (en) Novel ferry crane for quayside container handling
CN202671149U (en) Forklift structure
CN102092411A (en) Manpower turnover vehicle
CN111142535A (en) Intelligent railway freight system and operation method
CN205855461U (en) A kind of container handlers

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant