CN102121385B - 一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法 - Google Patents

一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法 Download PDF

Info

Publication number
CN102121385B
CN102121385B CN 201110066010 CN201110066010A CN102121385B CN 102121385 B CN102121385 B CN 102121385B CN 201110066010 CN201110066010 CN 201110066010 CN 201110066010 A CN201110066010 A CN 201110066010A CN 102121385 B CN102121385 B CN 102121385B
Authority
CN
China
Prior art keywords
tunnel
excavation
hole
cavern
existing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201110066010
Other languages
English (en)
Other versions
CN102121385A (zh
Inventor
石景山
宫全美
周顺华
魏子龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN 201110066010 priority Critical patent/CN102121385B/zh
Publication of CN102121385A publication Critical patent/CN102121385A/zh
Application granted granted Critical
Publication of CN102121385B publication Critical patent/CN102121385B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明属于隧道工程领域,具体涉及一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法。在既有单洞隧道中多断面施作中隔墙,中墙施工完成后填筑既有隧道一侧空洞,然后在既有隧道另一侧开挖新建隧道的侧壁导洞,挖去中间土体,该侧隧道二衬施作完成后开挖另一侧洞室,开挖既有隧道内的填土同时开挖另一侧导洞,开挖完成拆除衬砌后施作二衬,两洞室错距开挖,错开距离由双联拱隧道的单洞洞径确定。新建洞室开挖顺序为先开挖侧壁导洞,施作临时支护然后开挖中间土体,拆除临时支护后隧道二衬。新建洞室开挖前先在与拟开挖洞室相对的既有隧道另一侧填土,填土部分再开挖该侧洞室时挖除。本发明考虑了开挖对围岩的扰动以及开挖的时间和空间效应,辅助以预支护措施可以适用于软弱土层、破碎带等不良地质条件下的隧道扩建,本发明具有实施简便,工序较少的优点,可以减少围岩扰动,节省工期。

Description

一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法
技术领域
本发明属于隧道工程领域,具体涉及一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法。
背景技术
目前,修建于上世纪70、80年代的单洞隧道大量面临“扩能”问题,以满***通需求。隧道“扩能”主要方式为原地改建、扩建既有隧道,一般采用原洞扩大,该方法会导致隧道空间利用不足(不改变隧道形状的情况下)或者出现大跨度扁平隧道,且单洞扩建没有解决双向交通干扰等问题。基于单洞隧道扩建双联拱隧道的可以减少交通干扰扩能能力较强,但其施工过程围岩主应力变化复杂,合理的施工顺序和支护措施对围岩扰动、隧道变形等影响较大。
单洞隧道扩建为双联拱隧道可以减少对向车流干扰,优化交通环境,但其施工技术难度相对较大。单洞隧道扩建为双联拱隧道主要问题有中隔墙的施作方式、道路线形匹配以及节约施工工期。既有隧道扩建为双联拱隧道的中隔墙的施工方式可以采用三种方式,一种为在既有隧道附近成洞施作中导洞,然后施工中隔墙,该方式可以多断面开挖施工中隔墙,但需要对原有隧道的线形进行调整,带来进出洞口线形、高程等变动较大;第二种为对既有隧道进行扩大然后在一侧施作中隔墙,该方法开挖增加了单洞隧道开挖的跨度,在易导致围岩不稳定等问题;第三种方式为在既有隧道中施作中隔墙,然后扩挖左右断面隧道。
发明内容
本发明的目的在于提供一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法,采用在既有隧道中多断面施工中隔墙,然后开挖左右导洞的既有隧道扩建为双联拱隧道的开挖方法。该方法在既有隧道中分断面施作中隔墙,中隔墙上部至隧道顶部采用注浆填筑处理,然后在开挖单侧隧道,最后开挖另一侧隧道。隧道开挖过程中为减少围岩应力集中,可采取填土、对称开挖等方式平衡土压力。
本发明提出的一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法,具体步骤如下:
既有单洞隧道用作双联拱隧道的中导洞,多断面施作中隔墙,错开距离开挖左右洞室,对中隔墙右侧进行既有隧道填土,填筑长度为1-2倍既有单洞洞径,接着对其左侧开挖新建隧道,新建隧道先开挖远离中导洞的侧壁导洞,施作临时支护,然后开挖新建洞室中间土体,中间土体的开挖采用上下台阶法,上台阶开挖后施工临时横撑,开挖完成后拆除临时支护,封闭隧道的初期支护,最后施作二衬;二衬施作一定距离后开挖右侧洞室,该侧洞室先开挖既有隧道填土,其余步骤和已建洞室相同,错开距离由双联拱隧道的单洞洞径确定。
本发明中,所述既有单洞隧道作为中导洞多断面施作中隔墙,然后错距开挖左右洞室,开挖前根据围岩等级新建洞室可采用管棚、注浆等预支护措施。当中隔墙高度小于既有单洞隧道净高时,中隔墙上部施作双联拱隧道初支结构,同时顶部空隙采用注浆填筑,使之密实。
本发明中,先开挖的新洞室开挖前在中导洞另一侧填土空洞部分填土,然后开挖远离中导洞的侧导洞,并施作临时支护和隧道初期支护,之后开挖中部土体并及时封闭隧道支护。后开挖洞室在先开挖隧道二衬施作完成后错距施工,先开挖既有隧道内部填土,然后开挖远离中导洞的侧壁导洞,其余过程与所述另一侧新建洞室顺序相同。
本发明中,所述隧道各部施工顺序在时间、空间上错开。中隔墙施工错开中隔墙顶部处理施工至少1.5倍既有单洞隧道洞径,中隔墙填土错开先开挖洞室侧壁导洞开挖1-2倍单洞洞径。先开挖洞室中部土体开挖滞后侧壁导坑开挖至少1倍单洞洞径,先于二衬施作滞后至少2倍洞径。后建隧道中导洞填土挖除滞后另一侧二衬施工至少1倍洞径,先于侧壁导洞开挖至少1倍单洞洞径。
本发明的优点在于双向交通干扰较少的同时还可以充分利用隧道空间以及扩建线形的匹配,在施工过程中利用既有隧道进行多断面中隔墙施工和错距开挖节约工期。
附图说明
图1为既有单洞隧道扩建为双联拱隧道结构示意图。
图2为中隔墙施工示意图。
图3为左侧隧道洞室开挖示意图。
图4为右侧洞室开挖示意图。
图中标号:1为既有单洞隧道,2为既有隧道初支和二衬,3为中隔墙,4为新建隧道支护结构,5为左侧隧道支护结构,6为左洞侧壁导洞临时支护,7为中隔墙上部注浆填筑,8为既有隧道填土,9为左洞中部临时横撑,10为右洞中部临时横撑,11为右洞侧壁导洞临时支护,12为右侧隧道支护结构。
具体实施方式
以下结合附图对本发明特征及应用流程进一步详细说明,以便于同行业技术人员的理解,为便于叙述以既有隧道洞室高度大于中隔墙洞室为前提,新建洞室采用双侧壁导洞法配合上下台阶法施工,具体内容如下:
附图1-3中标号1-12分别代表:1既有单洞隧道、2既有隧道初支和二衬、3中隔墙、4新建隧道支护结构、5左侧隧道支护结构、6左洞侧壁导洞临时支护、7中隔墙上部注浆填筑、8既有隧道填土、9左洞中部临时横撑、10右洞中部临时横撑、11右洞侧壁导洞临时支护、12右侧隧道支护结构。
图1所示为既有单洞隧道扩建为双联拱隧道结构示意图。新建隧道采用侧壁导洞开挖,隧道中部土体采用上下台阶法开挖。既有单洞隧道1用作双联拱隧道的中导洞,多断面施作中隔墙3,然后在中隔墙3左侧进行既有隧道填土8,在其右侧开挖新建隧道,新建隧道先开挖远离中导洞的侧壁导洞,施作临时支护6,然后开挖新建洞室中间土体,中间土体采用上下台阶法,施作临时横撑9,开挖完成后拆除临时横撑9,并封闭左侧隧道支护结构5;位于左侧的既有隧道初支和二衬2施作一定距离后开挖右侧洞室,右侧洞室先开挖既有隧道填土8,其余步骤和已建洞室相同,错开距离由双联拱隧道的单洞洞径确定。
图2所示为中隔墙施工示意图。在既有隧道1高于中隔墙3高度时,中隔墙3预留钢筋施作隧道支护结构,中隔墙上部空隙采用注浆填筑7,然后分别开挖作用两侧隧道。
图3所示为左侧隧道洞室开挖示意图。左侧隧道开挖前先将既有隧道填筑8,既有隧道填筑8长度为1-2倍单洞洞径,然后开挖侧左洞侧壁导洞临时支护6,隧道中间土体采用上下台阶法开挖,开挖错距为0.5-2.0倍单洞洞径,上台阶开挖后施工左洞中部临时横撑9,中间土体开挖完成后实现既有隧道初支和二衬2封闭。左洞侧壁导洞临时支护6和新建隧道轮廓范围内的既有隧道支护结构拆除后施作隧道二次衬砌。
图4所示为右侧洞室开挖示意图。右侧隧道开挖前先挖出既有隧道填筑8,然后开挖远离中隔墙一侧的隧道侧壁导洞并施作右洞侧壁导洞临时支护11,采用错距逐步开挖,既有隧道填土8挖除先于侧壁导洞开挖1-2倍单洞洞径。侧壁导洞开挖后,开挖右侧隧道中部土体,采用上下台阶法施工,上台阶开挖后施作拱部支护结构和中部临时横撑10,上下台阶错距施工,错距为0.5-2.0倍单洞洞径,上台阶开挖滞后侧壁导洞开挖至少1倍洞径,下台阶开挖完成后及时拆除既有隧道初支和二衬2和临时横撑10、临时支护11及时封闭支护结构12.
以上所述,仅是本发明的较佳实施例子而已,并非对本发明做任何形式上的限制,任何未脱离本发明技术方案内容,依据本发明的技术实质对以上实施例所做的任何简单修改、等同变化与修饰,均仍属于本发明技术方案的范围内。

Claims (4)

1.一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法,其特征在于具体步骤如下:既有单洞隧道用作双联拱隧道的中导洞,多断面施作中隔墙,错开距离开挖左右洞室,对中隔墙右侧进行既有隧道填土,填筑长度为1-2倍既有单洞洞径,接着对其左侧开挖新建隧道,新建隧道先开挖远离中导洞的侧壁导洞,施作临时支护,然后开挖新建洞室中间土体,中间土体的开挖采用上下台阶法,上台阶开挖后施工临时横撑,开挖完成后拆除临时支护,封闭隧道的初期支护,最后施作二衬;二衬施作一定距离后开挖右侧洞室,该侧洞室先开挖既有隧道填土,其余步骤和已建洞室相同,错开距离由双联拱隧道的单洞洞径确定。
2.根据权利要求1所述的一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法,其特征在于所述洞室开挖前针对Ⅳ级及以上围岩采用管棚或注浆预支护措施。
3.根据权利要求1所述的一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法,其特征是所述中隔墙高度小于既有单洞隧道净高时,中隔墙上部施作双联拱隧道初支结构,同时顶部空隙采用注浆填筑。
4.根据权利要求1所述的一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法,其特征在于各部开挖顺序在时间、空间上错开,中隔墙施工错开中隔墙顶部处理施工至少1.5倍既有隧道洞径,对中隔墙右侧进行既有隧道填土错开先开挖洞室侧壁导洞开挖1-2倍单洞洞径,先开挖洞室中部土体开挖滞后侧壁导坑开挖至少1倍单洞洞径,二衬施作滞后至少2倍洞径,后建隧道中导洞填土挖除滞后另一侧二衬施工至少1倍洞径,先于后开挖洞室侧壁导洞开挖至少1倍单洞洞径。
CN 201110066010 2011-03-18 2011-03-18 一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法 Expired - Fee Related CN102121385B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110066010 CN102121385B (zh) 2011-03-18 2011-03-18 一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110066010 CN102121385B (zh) 2011-03-18 2011-03-18 一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法

Publications (2)

Publication Number Publication Date
CN102121385A CN102121385A (zh) 2011-07-13
CN102121385B true CN102121385B (zh) 2012-12-05

Family

ID=44250033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110066010 Expired - Fee Related CN102121385B (zh) 2011-03-18 2011-03-18 一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法

Country Status (1)

Country Link
CN (1) CN102121385B (zh)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102650212B (zh) * 2012-05-04 2014-04-09 中国十七冶集团有限公司 一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法
CN102865084B (zh) * 2012-09-29 2014-09-03 中铁二局股份有限公司 从双线隧道断面到三线隧道超大断面的地下隧道扩挖方法
CN103114856B (zh) * 2013-03-05 2015-04-01 福州市规划设计研究院 既有连拱隧道原位拓宽改造的施工方法
CN103244127B (zh) * 2013-04-22 2016-07-06 中交路桥北方工程有限公司 一种加快连拱隧道施工速度的方法
CN103953366B (zh) * 2014-05-20 2016-03-23 长安大学 单洞隧道改为连拱时中隔墙顶部原衬砌空腔回填施工方法
CN104061000B (zh) * 2014-06-24 2016-08-31 中铁第四勘察设计院集团有限公司 触壁下沉通道式隧道中隔墙及其建造方法
CN104329095B (zh) * 2014-09-03 2016-09-21 福州市规划设计研究院 一种既有隧道拓宽施工方法
CN109190190A (zh) * 2018-08-13 2019-01-11 中国铁建大桥工程局集团有限公司 双侧壁导洞法施工对围岩应力和位移影响的数值分析方法
CN112329107B (zh) * 2020-11-05 2022-05-06 中铁二院工程集团有限责任公司 一种交叉隧道近接区域桥跨式承载结构及计算方法
CN113153308B (zh) * 2021-03-09 2023-12-08 中铁八局集团有限公司 双联拱隧道塌方段施工方法
CN113250705B (zh) * 2021-06-28 2023-10-20 重庆工程职业技术学院 一种连拱隧道施工方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0334262B1 (en) * 1988-03-24 1994-01-12 ING. GIOVANNI RODIO & C. IMPRESA COSTRUZIONI SPECIALI S.P.A. Method and apparatus for enlarging tunnels
JP3096652B2 (ja) * 1997-03-28 2000-10-10 稔 山本 拡幅トンネル及び非常駐車帯の構築方法
JP3677699B2 (ja) * 1997-04-04 2005-08-03 清水建設株式会社 トンネル合流部の施工方法
JP3796524B2 (ja) * 2002-03-25 2006-07-12 独立行政法人土木研究所 トンネルの拡幅方法およびトンネル
CN101196116A (zh) * 2007-12-28 2008-06-11 中铁十二局集团有限公司 软弱地质三联拱隧道双侧洞施工方法
CN101363322A (zh) * 2008-09-26 2009-02-11 中铁十二局集团第二工程有限公司 一种隧道单线改双线的施工方法
CN101545376A (zh) * 2009-05-07 2009-09-30 中铁四局集团第四工程有限公司 小断面隧道横向进入超大断面隧道的施工方法
CN101737061A (zh) * 2009-12-24 2010-06-16 中国水电顾问集团华东勘测设计研究院 既有单洞隧道改扩建为连拱隧道的施工方法

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0334262B1 (en) * 1988-03-24 1994-01-12 ING. GIOVANNI RODIO & C. IMPRESA COSTRUZIONI SPECIALI S.P.A. Method and apparatus for enlarging tunnels
JP3096652B2 (ja) * 1997-03-28 2000-10-10 稔 山本 拡幅トンネル及び非常駐車帯の構築方法
JP3677699B2 (ja) * 1997-04-04 2005-08-03 清水建設株式会社 トンネル合流部の施工方法
JP3796524B2 (ja) * 2002-03-25 2006-07-12 独立行政法人土木研究所 トンネルの拡幅方法およびトンネル
CN101196116A (zh) * 2007-12-28 2008-06-11 中铁十二局集团有限公司 软弱地质三联拱隧道双侧洞施工方法
CN101363322A (zh) * 2008-09-26 2009-02-11 中铁十二局集团第二工程有限公司 一种隧道单线改双线的施工方法
CN101545376A (zh) * 2009-05-07 2009-09-30 中铁四局集团第四工程有限公司 小断面隧道横向进入超大断面隧道的施工方法
CN101737061A (zh) * 2009-12-24 2010-06-16 中国水电顾问集团华东勘测设计研究院 既有单洞隧道改扩建为连拱隧道的施工方法

Also Published As

Publication number Publication date
CN102121385A (zh) 2011-07-13

Similar Documents

Publication Publication Date Title
CN102121385B (zh) 一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法
CN104612698B (zh) 一种浅埋暗挖隧道上台阶中隔壁施工方法
CN102996133B (zh) 适用于软弱围岩隧道斜井与正洞交汇处的施工方法
CN103775092B (zh) 隧道浅埋暗挖预留核心土改良crd施工工法
CN104047623B (zh) 一种大跨洞室开挖施工方法
CN104653197A (zh) 超大变断面隧道施工方法
CN102305077A (zh) 一种大断面连拱隧道的快速施工方法
CN103306680A (zh) 既有单线隧道扩建为多线隧道的施工方法
CN201412163Y (zh) 一种敞开式隧道掘进机施工的圆形隧道衬砌结构
CN108678771A (zh) 穿越断层破碎带隧道初期支护及中隔壁加强支护体系
CN109404005A (zh) 暗挖隧道小洞进大洞预加固体系及施工方法
CN109026020B (zh) 一种富水隧道溶洞处理与开挖方法
CN103362513A (zh) 暗挖区间既有洞体改造施工工法
CN104405411A (zh) 超大变断面隧道支护结构
CN105909263A (zh) 风积沙地层公路隧道结构及其施工方法
CN106917627A (zh) 一种富水地层暗挖施工下导洞的超前支护方法
CN107701193B (zh) 一种破碎围岩分离式隧道交叉口渐变段施工方法
CN205422752U (zh) 暗挖车站中隔壁法中导洞内顶纵梁与中拱二衬同步施工结构
CN112324442A (zh) 大断面隧道的挖掘方法
CN204851266U (zh) 一种暗挖车站正上方竖井结构
CN108915702B (zh) 一种圆形小断面隧道内盾构接收方法
CN108374674B (zh) 六导洞十二步地下空间开挖支护方法
CN111810165B (zh) 一种桥隧相连分岔隧道施工方法
CN107387092B (zh) 一种多个矩形顶管并联在复杂环境下形成地下空间的工法
CN202132053U (zh) Ⅵ级围岩双线隧道衬砌支护结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121205

Termination date: 20200318