CN102094534B - Method for mounting large-size discharging platform - Google Patents

Method for mounting large-size discharging platform Download PDF

Info

Publication number
CN102094534B
CN102094534B CN201110000986A CN201110000986A CN102094534B CN 102094534 B CN102094534 B CN 102094534B CN 201110000986 A CN201110000986 A CN 201110000986A CN 201110000986 A CN201110000986 A CN 201110000986A CN 102094534 B CN102094534 B CN 102094534B
Authority
CN
China
Prior art keywords
landing platform
chain block
mounting
tons
discharging platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201110000986A
Other languages
Chinese (zh)
Other versions
CN102094534A (en
Inventor
曹凯
张平
于海涛
张延年
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
COSCO (DALIAN) SHIPYARD Co Ltd
Original Assignee
COSCO (DALIAN) SHIPYARD Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by COSCO (DALIAN) SHIPYARD Co Ltd filed Critical COSCO (DALIAN) SHIPYARD Co Ltd
Priority to CN201110000986A priority Critical patent/CN102094534B/en
Publication of CN102094534A publication Critical patent/CN102094534A/en
Application granted granted Critical
Publication of CN102094534B publication Critical patent/CN102094534B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Jib Cranes (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a method for mounting a large-size discharging platform, comprising the following steps of: A. designing a tooling bracket and a bearing triangular bracket according to the self structure, the weight, the gravity center and the mounting position of the discharge platform, welding the tooling bracket at the designated position of a deck and mounting the bearing triangular bracket at the designated position of an outer board of a ship body at the bottom of the discharging platform; B. mounting a drawing and adjusting lifting lug at the designated position and arranging a hoisting lifting lug on the deck of the discharging platform; C. assembling a steel wire rope, a chain block and different shackles together; and D. hoisting a discharging platform structure to a mounting position, connecting the shackles connected with the chain block on the ship with the drawing and adjusting lifting lug on the discharging platform, tightening the chain block and releasing a hook of a hoist. According to the method for mounting the large-size discharging platform, the use time of hoisting on the sea is greatly shortened, the safety for the mounting process is improved, the time for using the hoist is shortened to 4-6 hours from 2-3 days, the cost is saved and the service efficiency of hoisting resources is improved.

Description

The installation method of large-scale landing platform
Technical field
The present invention relates to supertanker repacking Floating Production and store the emptying equipment field, relate in particular to a kind of installation method of large-scale landing platform.
Background technology
Along with oil field, deep-sea, the world is developed gradually; The world market stores emptying equipment (FPSO) for Floating Production and other maritime works's product consumptions constantly increase, and stores emptying equipment (FPSO) in operation 50-60% Floating Production at present and is converted by supertanker, in supertanker repacking (FPSO) process; Aboard ship to increase landing platform newly be one of Floating Production important engineering of storing emptying equipment (FPSO) repacking to stem deck extended spot all the time; The weight of general landing platform is the 150-230 ton, and the landing platform installation mainly is to lean on the large-scale floating crane handling to install in supertanker repacking Floating Production storage emptying equipment (FPSO) process in the past, owing to locate have line style to change from beginning to end; In needing very on a large scale, installation process repairs and adjustment; Can not carry out sealing at once, after sealing finishes, could allow crane pine hook, first landing platform installation process needs 2-3 days; So just increase the crane period of service greatly; Also carry out operation simultaneously night, this has just reduced safety of construction and has increased the quality control on construction difficulty, in order to reduce production costs; Enhance productivity and working security, a kind of science, reasonable, safe installation method design are absolutely necessary.
Summary of the invention
The purpose of this invention is to provide that a kind of installation method is simple, technology is succinct, the installation method of the large-scale landing platform of operating process safety.
The present invention for realizing the technical scheme that above-mentioned purpose adopted is: a kind of installation method of large-scale landing platform may further comprise the steps:
A, according to landing platform structure self structure; Weight, center of gravity, the installation site is through strength check design frock support and load-bearing spider; The frock support is welded on the deck assigned address, the load-bearing spider is installed in the ship hull plate assigned address of landing platform bottom;
B, according to frock support installation site, traction adjustment hanger is installed at assigned address, according to weight, center of gravity and landing platform constructional feature, the handling hanger is set on the landing platform deck;
C, according to frock backing positions, traction adjustment hanger position and landing platform structural weight, center of gravity, coupling steel rope, chain block, shackle and shackle fit together;
D, utilize the sea to hang the handling of landing platform structure to the installation site; Traction adjustment hanger on shackle of chain block bonded assembly and the landing platform on the ship is linked together, tighten up chain block, with crane pine hook; Through chain block landing platform is carried out leveling, centering, carry out the sealing welding then.
The frock support is two 5 meters frock supports in the said steps A, and said load-bearing spider is two.
Traction adjustment hanger is 4 among the said step B, and said handling hanger is 4.
Steel rope is that 2 diameters are that φ 80mm length is the steel rope of 7m among the said step C, and said chain block is 4 40 tons of chain blocks, and said shackle is 2 85 tons of shackles, and said shackle is 4 50 tons of shackles.
The installation method of the large-scale landing platform of the present invention; Greatly reduced large-scale sea and hung period of service and the safety that has improved installation process, will use the crane time to shorten to 4-6 hour, for company has practiced thrift cost and the service efficiency that has improved the lifting resource from 2-3 days; Production time can be controlled in and carries out daytime simultaneously; Heightened the safety and the construction quality of work progress greatly, and the landing platform structure installation method is simple, technology succinct, applied range, other and operating process safety.
The specific embodiment
The installation method of the large-scale landing platform of the present invention; Main through following steps completion: A, according to first landing platform structure self structure characteristics; Weight, center of gravity, the installation site, designing two height through strength check is frock support and 2 load-bearing spiders of 5 meters; The frock support is welded on stem deck assigned address, the load-bearing spider is installed in the ship hull plate assigned address of landing platform bottom; B, according to frock support installation site, 4 pieces of traction adjustment hangers are installed at assigned address, be provided with on the landing platform deck according to weight, center of gravity and landing platform constructional feature 4 pieces of handling hangers be installed; C, according to frock backing positions, traction hanger position and landing platform structural weight, center of gravity, be 7m steel rope, 4 40 tons of chain blocks, 2 pieces of 85 tons of shackles, 4 pieces of 50 tons of shackles through calculating 2 diameter phi 80mm length of coupling, it is fitted together; D, use the sea to hang the landing platform structure from the harbour handling to the installation site; Traction adjustment hanger on 4 pieces of 50 tons of shackles of the 30 chain block bonded assemblys of installation site preprepared on the ship and the landing platform is linked together; Tighten up 4 30 tons of chain blocks, can use 4 40 tons of chain blocks that landing platform is carried out leveling, centering on crane pine hook after tightening up; Carry out the sealing welding after finishing, withdraw from all facilities.
This installation method successfully uses; Compare with installation method in the past; Though the single-piece set-up time shortens seldom, greatly reduce large-scale sea and hung lease time and the safety that has improved installation process, practiced thrift cost; Also reach simultaneously the cost efficiency purpose and also be follow-up maritime works's product repacking establish a firm foundation, this field engineering achievement in research reaches leading domestic level.

Claims (4)

1. the installation method of a large-scale landing platform is characterized in that, may further comprise the steps:
A, according to landing platform structure self structure; Weight, center of gravity, installation site; Through strength check design frock support and load-bearing spider, the frock support is welded on the deck assigned address, the load-bearing spider is installed in the ship hull plate assigned address of landing platform bottom;
B, according to frock support installation site, traction adjustment hanger is installed at assigned address, according to weight, center of gravity and landing platform constructional feature, the handling hanger is set on the landing platform deck;
C, according to frock support installation site, traction adjustment hanger position and landing platform structural weight, center of gravity, steel rope, chain block, 85 tons of shackles and 50 tons of shackles are fitted together;
The installation site with landing platform structure handling to landing platform structure is hung in D, utilization sea; Traction adjustment hanger on shackle of chain block bonded assembly and the landing platform on the ship is linked together; Tighten up chain block; Loose hook is hung in the sea, landing platform is carried out leveling, centering, carry out the sealing welding then through chain block.
2. the installation method of a kind of large-scale landing platform according to claim 1, it is characterized in that: the frock support is two 5 meters frock supports in the said steps A, and said load-bearing spider is two.
3. the installation method of a kind of large-scale landing platform according to claim 1 is characterized in that: traction adjustment hanger is 4 among the said step B, and said handling hanger is 4.
4. the installation method of a kind of large-scale landing platform according to claim 1; It is characterized in that: steel rope is that 2 diameters are that φ 80mm length is the steel rope of 7m among the said step C; Said chain block is 4 40 tons of chain blocks; Said shackle is 2 85 tons of shackles, and said shackle is 4 50 tons of shackles.
CN201110000986A 2011-01-05 2011-01-05 Method for mounting large-size discharging platform Expired - Fee Related CN102094534B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110000986A CN102094534B (en) 2011-01-05 2011-01-05 Method for mounting large-size discharging platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110000986A CN102094534B (en) 2011-01-05 2011-01-05 Method for mounting large-size discharging platform

Publications (2)

Publication Number Publication Date
CN102094534A CN102094534A (en) 2011-06-15
CN102094534B true CN102094534B (en) 2012-10-10

Family

ID=44127781

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110000986A Expired - Fee Related CN102094534B (en) 2011-01-05 2011-01-05 Method for mounting large-size discharging platform

Country Status (1)

Country Link
CN (1) CN102094534B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3124537C1 (en) * 1981-06-23 1983-02-24 Willy 7715 Bräunlingen Küpper Wheeled road grit container transfer mechanism - has frame with wheel rails having two inclines to horizontal portions for transfer to truck or ground
EP0672598A1 (en) * 1994-03-18 1995-09-20 Kurt Alten Loading bridge for ramps
CN2515171Y (en) * 2001-09-30 2002-10-09 武汉市国裕物资贸易有限公司 Multifunctional port of transhipment
CN2871463Y (en) * 2005-12-14 2007-02-21 郭益村 Loading-unloading platform of double-arm-balancing push container

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3124537C1 (en) * 1981-06-23 1983-02-24 Willy 7715 Bräunlingen Küpper Wheeled road grit container transfer mechanism - has frame with wheel rails having two inclines to horizontal portions for transfer to truck or ground
EP0672598A1 (en) * 1994-03-18 1995-09-20 Kurt Alten Loading bridge for ramps
CN2515171Y (en) * 2001-09-30 2002-10-09 武汉市国裕物资贸易有限公司 Multifunctional port of transhipment
CN2871463Y (en) * 2005-12-14 2007-02-21 郭益村 Loading-unloading platform of double-arm-balancing push container

Also Published As

Publication number Publication date
CN102094534A (en) 2011-06-15

Similar Documents

Publication Publication Date Title
CN102261067A (en) Method for installing reinforcement cage of large-diameter ultra-long pile
CN108455451B (en) A kind of 600 tons of gantry cranes hold the method for hanging installation superelevation flare tower
CN214167082U (en) Special lifting device for pressure vessel
CN105151227B (en) A kind of structure arrangement of cylinder type FPSO hulls
CN105692468A (en) Large latticed shell type arch crown integral elevation hoisting mechanism and using method thereof
CN103072899B (en) Hoisting technology for ultra-large type cylinder block
CN201703776U (en) Inverted lifting device of storage tank
CN203372980U (en) Detachable top cover hanger applicable to pressurized water reactor
CN101109028A (en) Method of upside-down mounting hydraulic pressure lifting of converter shell
CN106567548A (en) Segmented mounting method for square raw coal hopper
CN102730544A (en) Radial gate fixing trunnion hoisting device and method
CN102094534B (en) Method for mounting large-size discharging platform
CN202542770U (en) Tube joint turning over device of pressure steel tube in hole chamber
CN102050377B (en) Method for installing combined hoist and oil production platform drilling equipment
CN107719583B (en) Equipment base and manhole cover combined device convenient to disassemble and examine
CN201686393U (en) Derrick mast hoisting tool
CN203452013U (en) Integrated unloading device for cantilever casting cradle template
CN106564819B (en) A kind of heavy loop wheel machine peculiar to vessel and underwater mounting process
CN105317031B (en) A kind of ship lift main equipment room bridge main beam hanging method
CN204899397U (en) A ring beam that is used for cable wire hydraulic lifting chimney steel inner tube
CN109368508B (en) The offshore lifting method of large size valve on floating production storage offloading's standpipe
CN202379586U (en) Hoisting system of assembly module used for hoisting large containers
CN202657829U (en) Hoisting in place device for fixing branch hinge of arc gate
CN102635732A (en) Process for mounting relatively long pipeline
CN102114897B (en) Method for installing large fair-lead structure on water

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121010

Termination date: 20180105