CN102069336A - Combined integral fixture of construction elevator cage - Google Patents

Combined integral fixture of construction elevator cage Download PDF

Info

Publication number
CN102069336A
CN102069336A CN2010101891999A CN201010189199A CN102069336A CN 102069336 A CN102069336 A CN 102069336A CN 2010101891999 A CN2010101891999 A CN 2010101891999A CN 201010189199 A CN201010189199 A CN 201010189199A CN 102069336 A CN102069336 A CN 102069336A
Authority
CN
China
Prior art keywords
frock
facade
cage
vertical surface
fixture
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010101891999A
Other languages
Chinese (zh)
Inventor
刘传禄
黄书凯
陈吉川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING YINGFENGSHENG MACHINERY EQUIPMENT CO LTD
Original Assignee
CHONGQING YINGFENGSHENG MACHINERY EQUIPMENT CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING YINGFENGSHENG MACHINERY EQUIPMENT CO LTD filed Critical CHONGQING YINGFENGSHENG MACHINERY EQUIPMENT CO LTD
Priority to CN2010101891999A priority Critical patent/CN102069336A/en
Publication of CN102069336A publication Critical patent/CN102069336A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a combined integral fixture of a construction elevator cage, which comprises a bottom supporting platform and six plane combination fixtures of a cage, and is characterized in that the bottom supporting platform comprises a bottom plate of which the lower part is anchored in concrete, the bottom plate is fixedly connected with a front vertical surface fixture, the bottom plate is also movably connected with a rear vertical surface fixture, the upper surface of the bottom plate, which is exposed out of the concrete, is provided with a bottom surface fixture, and the front vertical surface fixture is movably connected with the rear vertical surface fixture to constitute a top surface fixture, a left vertical surface fixture and a right vertical surface fixture. With the technical scheme, the bottom plate of which the bottom is anchored in the concrete has sufficient strength and rigidity so as to ensure the main form tolerance and position tolerance of the bottom plate in welding to be controlled. The rear vertical surface fixture is movably connected with the bottom plate, so the rear vertical surface fixture is conveniently disassembled to take out the whole cage after the cage is integrally assembled and formed. The fixture structure ensures a good finished cage effect and high efficiency.

Description

A kind of building hoist cage composite entity frock
Technical field
The present invention relates to a kind of frock clamp of processing construction facility parts,, be specifically related to a kind of frock of cage combination of building hoist.
Background technology
Building hoist is the manned loading construction machinery that often uses in the building, because its unique body structure makes it take not only comfortable but also safety, is used widely at the realm of building construction.The casing that the manned loading of building hoist is used also is cage, in use bear complicated stress, the strength and stiffness that are easy to generate distortion or destruction so its structure are most important to construction safety, because it mainly adopts Welding Structure, when combination, must use frock clamp to guarantee the machining accuracy of cage.Prior art all is that each main facade Combination Welding is carried out overall package later on more basically, exists multiple welding to be out of shape when branch assembling and last overall package, causes finished product structural entity Deformation control poor effect.
Summary of the invention
The technical problem to be solved in the present invention provides a kind of once assembling, global formation, the building hoist cage composite entity frock of the little easy control of bulk deformation.
The technical scheme that technical solution problem of the present invention is adopted is: a kind of building hoist cage composite entity frock, six plane assembled tools that comprise bottom supporting platform and cage, it is characterized in that: the bottom supporting platform comprises that the bottom is anchored at the base plate in the concrete, base plate is fixedlyed connected with preceding facade frock, base plate also flexibly connects with back facade frock, base plate exposes concrete upper surface and is provided with the bottom surface frock, flexibly connect between preceding facade frock and the back facade frock, constitute end face frock and left and right facade frock.
Adopt the technical program, its technique effect is: the base plate of bottom anchor in concrete has enough strength and stiffness, the preceding facade of cage is the plane at main bearing member place, the frock that plays the location clamping action is fixedlyed connected with base plate, guarantees that its main form tolerance and position of related features can both be controlled when welding; Back facade frock and base plate flexibly connect, make things convenient for the moulding of cage overall package after, remove back facade frock, can take out cage is whole.This tool structure guarantees that the cage finished product is effective, the efficient height.
Further, the structure of preceding facade frock and back facade frock is limited, it is characterized in that: facade frock and back facade frock include one group of column parallel to each other before described, and column is provided with and is used for the anchor clamps that the shaped steel location clamps.This structure guarantees that the distortion of cage on whole face is restricted owing to clamping, and is convenient to install and regulate.
Further, the syndeton on back facade frock and ground is limited, the column bottom of described back facade frock is provided with connecting plate with holes, and described base plate is provided with the screwed hole of correspondence.This structure makes the flexible connection of column and bottom surface adorn, tear open rapidly, raises the efficiency.
Further, the syndeton of anchor clamps on the column of preceding facade frock and column is limited, it is characterized in that: the anchor clamps before described on the column of facade frock are threaded with column.The convenient mounting or dismounting of this structure are raised the efficiency.
Description of drawings
Below in conjunction with drawings and Examples technical solution of the present invention is further specified:
Fig. 1 is the stereogram of the object-cage that will process of a kind of building hoist cage of the present invention composite entity frock;
Fig. 2 is the stereogram of a kind of building hoist cage of the present invention composite entity frock.
The specific embodiment
As shown in Figure 1, cage comprise bottom surface 1, the facade 2 at actuating unit place is installed and be installed into bin gate facade 3, end face 4, the facade 5 of discharge door is installed and the facade 6 of driver's cabin is installed.Each face all is the plane that is formed by the rod member welding.Therefore each other position and size is exactly the problem that processing must be considered between the rod member.Such as channel-section steel 101 on its bottom surface 1 and angle steel 102, the channel-section steel 401 on the end face 4, channel-section steel 403 and angle steel 402, its depth of section is inconsistent, must consider accurate positioning man-hour adding, and will have corresponding clamping device to realize the accuracy of processing dimension in addition.
As shown in Figure 2, a kind of building hoist cage of the present invention composite entity frock, in order to satisfy above-mentioned processing request, its bottom surface is adopted steel plate and is anchored in the concrete, be welded with the column 7 that many channel-section steels constitute on the bottom surface, the top connects into integral body by backstay 702 between many root posts 7, strengthens its rigidity.Column 7 is provided with location channel-section steel 701 and location-plate 703.Opposite at the steel plate upper pillar stand 7 of bottom surface is provided with many active columns 8, active column 8 tops are connected to form one by backstay 804, the lower end employing bolt of active column 8 is connected with the Connection Block 801 on being welded on the bottom surface steel plate, the cage welding finishes, remove after the active column 8, easily cage integral body is taken out from frock.Also be provided with the channel-section steel 801 of location usefulness on the active column 8.Active column 8 and column 7 link into an integrated entity by backstay 802.The channel-section steel 101 on corresponding cage on the bottom surface and the position of angle steel 102 are provided with a plurality of positioning tubes 901, and are provided with the clamping device 902 that screw pair is formed.Adopt structure of the present invention, the base plate of its bottom anchor in concrete has enough strength and stiffness, the preceding facade of cage is the plane at main bearing member place, the frock that plays the location clamping action is fixedlyed connected with base plate, guarantees that its main form tolerance and position of related features can both be controlled when welding; Back facade frock and base plate flexibly connect, make things convenient for the moulding of cage overall package after, remove back facade frock, can take out cage is whole.This tool structure guarantees that the cage finished product is effective, the efficient height.
Above embodiment only illustrates embodiments of the present invention; can not be interpreted as qualification to protection scope of the present invention; so long as adopt technical scheme of the present invention, perhaps only make routine improvement or distortion that those of ordinary skill in the art can both expect, all fall into protection scope of the present invention.

Claims (4)

1. building hoist cage composite entity frock, six plane assembled tools that comprise bottom supporting platform and cage, it is characterized in that: the bottom supporting platform comprises that the bottom is anchored at the base plate in the concrete, base plate is fixedlyed connected with preceding facade frock, base plate also flexibly connects with back facade frock, base plate exposes concrete upper surface and is provided with the bottom surface frock, flexibly connects between preceding facade frock and the back facade frock, constitutes end face frock and left and right facade frock.
2. building hoist cage composite entity frock before as claimed in claim 1 is characterized in that: facade frock and back facade frock include one group of column parallel to each other before described, and column is provided with and is used for the anchor clamps that the shaped steel location clamps.
3. building hoist cage composite entity frock before as claimed in claim 2 is characterized in that: the column bottom of described back facade frock is provided with band connecting hole connecting plate, and described base plate is provided with corresponding screwed hole.
4. building hoist cage composite entity frock before as claimed in claim 2 is characterized in that: the anchor clamps before described on the column of facade frock are threaded with column.
CN2010101891999A 2010-06-01 2010-06-01 Combined integral fixture of construction elevator cage Pending CN102069336A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101891999A CN102069336A (en) 2010-06-01 2010-06-01 Combined integral fixture of construction elevator cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101891999A CN102069336A (en) 2010-06-01 2010-06-01 Combined integral fixture of construction elevator cage

Publications (1)

Publication Number Publication Date
CN102069336A true CN102069336A (en) 2011-05-25

Family

ID=44028207

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101891999A Pending CN102069336A (en) 2010-06-01 2010-06-01 Combined integral fixture of construction elevator cage

Country Status (1)

Country Link
CN (1) CN102069336A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103722337A (en) * 2014-01-09 2014-04-16 中山广都机电有限公司 Welding jig for elevator lift car bracket
CN104690500A (en) * 2015-01-12 2015-06-10 山东大汉建设机械有限公司 Processing technology for cage of construction hoist
CN106239005A (en) * 2016-08-31 2016-12-21 甘肃酒钢集团西部重工股份有限公司 A kind of magnetic medium box weld jig and welding procedure
CN114700676A (en) * 2022-05-18 2022-07-05 浙江杨明斯金属制品有限公司 Welding positioning tool for aerial work bucket

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2232819Y (en) * 1995-09-11 1996-08-14 昆明重工塔式起重机公司 Technical equipment of combined metal structure
CN101225706A (en) * 2007-01-19 2008-07-23 西北工业大学 Adhered self-lifting highrise operation platform
CN201309059Y (en) * 2008-12-15 2009-09-16 安徽鑫龙电器股份有限公司 Welding fixture
CN201807856U (en) * 2010-06-01 2011-04-27 重庆盈丰升机械设备有限公司 Too for combining and integrating suspension cage of construction lifter

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2232819Y (en) * 1995-09-11 1996-08-14 昆明重工塔式起重机公司 Technical equipment of combined metal structure
CN101225706A (en) * 2007-01-19 2008-07-23 西北工业大学 Adhered self-lifting highrise operation platform
CN201309059Y (en) * 2008-12-15 2009-09-16 安徽鑫龙电器股份有限公司 Welding fixture
CN201807856U (en) * 2010-06-01 2011-04-27 重庆盈丰升机械设备有限公司 Too for combining and integrating suspension cage of construction lifter

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103722337A (en) * 2014-01-09 2014-04-16 中山广都机电有限公司 Welding jig for elevator lift car bracket
CN104690500A (en) * 2015-01-12 2015-06-10 山东大汉建设机械有限公司 Processing technology for cage of construction hoist
CN104690500B (en) * 2015-01-12 2017-02-01 山东大汉建设机械股份有限公司 Processing technology for cage of construction hoist
CN104690500B8 (en) * 2015-01-12 2017-03-29 王智超 Construction elevator cage processing technique
CN106239005A (en) * 2016-08-31 2016-12-21 甘肃酒钢集团西部重工股份有限公司 A kind of magnetic medium box weld jig and welding procedure
CN106239005B (en) * 2016-08-31 2019-06-21 甘肃酒钢集团西部重工股份有限公司 A kind of magnetic medium box welding fixture and welding procedure
CN114700676A (en) * 2022-05-18 2022-07-05 浙江杨明斯金属制品有限公司 Welding positioning tool for aerial work bucket
CN114700676B (en) * 2022-05-18 2024-05-14 浙江杨明斯金属制品有限公司 Welding positioning tool for working bucket of high-altitude operation

Similar Documents

Publication Publication Date Title
CN103410353B (en) Garage steel framework and mounting process
CN102069336A (en) Combined integral fixture of construction elevator cage
CN105971272A (en) Fabricated type reinforced concrete constructional column adopting aluminum templates and block filling wall and construction method
CN102357816A (en) Fixture for fixing series parts
CN201807856U (en) Too for combining and integrating suspension cage of construction lifter
CN202517214U (en) Upper car platform welding fixture
CN201744985U (en) Automobile-used split assembly platform for ignition lock bracket and steering column
CN102380643A (en) Novel guide cover fixed collar drilling tooling of wind driven generator
JP3204250U (en) Damper unit and damping structure using the same
CN215889064U (en) Stand structure of steel construction installation
CN203635631U (en) High-rigidity portal frame type segmenting guide and guard fixing device
CN207402009U (en) Notebook computer shell punching positioning fixture
CN202123382U (en) Milling fixture capable of clamping rapidly
CN214446060U (en) Brake installation tool
CN213421059U (en) Steel structure fastening support suitable for boiler
CN113550518A (en) Stand structure of steel construction installation
CN211162942U (en) Clamp for machining mechanical parts
CN205476444U (en) Light -duty support post based on low level jacking die carrier system
CN210827164U (en) Novel road and bridge windshield
CN201702534U (en) Positioning module used for assembling and welding steel structure box type rod element
CN219411237U (en) Steel structure building frame structure
CN204197783U (en) Goods shelf support top connection structure
CN212773648U (en) Container module building integrated with plane conversion frame
CN220005506U (en) Bending device for tower crane guard ring
CN216531197U (en) Light and quick type photovoltaic frame easy to install

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20110525