CN101666163B - 高空大跨度屋面管桁架安装方法 - Google Patents

高空大跨度屋面管桁架安装方法 Download PDF

Info

Publication number
CN101666163B
CN101666163B CN2009101908658A CN200910190865A CN101666163B CN 101666163 B CN101666163 B CN 101666163B CN 2009101908658 A CN2009101908658 A CN 2009101908658A CN 200910190865 A CN200910190865 A CN 200910190865A CN 101666163 B CN101666163 B CN 101666163B
Authority
CN
China
Prior art keywords
pipe truss
assembling
altitude
assembling support
tower crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009101908658A
Other languages
English (en)
Other versions
CN101666163A (zh
Inventor
徐国友
邱文波
周革文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Group Corp
Original Assignee
China Metallurgical Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Group Corp filed Critical China Metallurgical Group Corp
Priority to CN2009101908658A priority Critical patent/CN101666163B/zh
Publication of CN101666163A publication Critical patent/CN101666163A/zh
Application granted granted Critical
Publication of CN101666163B publication Critical patent/CN101666163B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种高空大跨度屋面管桁架安装方法,包括下述步骤:首先在地面组装管桁架;然后在高空组装管桁架处设置安装平台梁;采用移动式塔吊吊装管桁架,并把两段管桁架吊放在组装支架和钢筋混凝土立柱上;最后对管桁架进行高空碰头组装焊接;焊接检验合格后,移动组装支架到下一轴线处进行下一榀管桁架安装。本发明的高空大跨度屋面管桁架安装方法采用地面分段组装,移动式塔吊吊装,高空碰头焊接的方法,既提高施工质量、确保施工进度和施工安全,同时又降低施工成本。

Description

高空大跨度屋面管桁架安装方法
技术领域
本发明涉及一种屋面桁架安装方法,尤其涉及一种高空大跨度屋面管桁架安装方法。
背景技术
目前,安装低空小跨度的屋面管桁架大多直接采用吊车直接安装,但对于好几十米甚至上百米跨度的屋面,因吊车的回转半径小,工期要求紧,施工场地内较狭窄,无管桁架的整体组装场地,再采用超大型履带吊车安装就无法完成了,因此就必须借助移动式塔吊来完成。
针对安装管桁架重量大、截面大、跨度大、高度高达进百米的屋面,且施工场地狭窄,在狭窄的施工场地区间内采用大型履带吊吊车施工难度较大,而且成本高。若采用高空滑移施工方法进行管桁架安装,需在两根立柱上加设埋件,但滑移时易产生施工附加力,且耳房框架柱也需加设埋件,同样也会产生施工附加力,同时支承桁架安装、拆卸十分困难,施工周期长,吊车无法覆盖,桁架制作安装量较大。
发明内容
针对上述的不足之处,本发明提供了一种适用于施工场地狭窄,地形复杂的高空大跨度屋面管桁架安装方法,该方法既可提高施工质量、确保施工进度和施工安全,同时降低施工成本。
本发明提供的高空大跨度屋面管桁架安装方法,包括下述步骤:
a、地面分段组装管桁架;
b、在高空组装管桁架处设置左安装平台梁和右安装平台梁,左安装平台梁和右安装平台梁上分别设有相互平行的水平轨道,左侧的水平轨道上设有左组装支架,右侧的水平轨道上设有右组装支架,左组装支架和右组装支架分别通过底部安装的滚轮可在对应侧的水平轨道上滚动;
c、采用移动式塔吊吊装管桁架,左片管桁架的组装端吊放在左组装支架上,另一端吊放在左钢筋混凝土立柱上;右片管桁架的组装端吊放在右组装支架上并与左片管桁架的组装端对应,另一端安装在右钢筋混凝土立柱上;
d、高空碰头组装焊接;
e、焊接检验合格后,从管桁架上松开左组装支架和右组装支架,移动左组装支架和右组装支架到下一轴线安装处,移动式塔吊吊装管桁架也运行到下一轴线安装处进行下一榀安装。
进一步,在所述步骤d中,采取先焊接管桁架下弦主管,再对称焊接上弦主管,并采用反变形措施,监控管桁架的下绕度;
进一步,在所述步骤c中,利用千斤顶来进行矫正,调整两片管桁架之间的上下错位量和拱度值;
进一步,所述移动式塔吊选用吊装重量为单片管桁架重量的1.3~1.6倍,移动式塔吊的回转半径≥跨度的1/2;
进一步,所述水平轨道上设置有可防止左组装支架和右组装支架位移的阻挡器。
本发明的有益效果在于:本发明的高空大跨度屋面管桁架安装方法采用地面分段组装,移动式塔吊吊装,高空碰头焊接的方法,既提高施工质量、确保施工进度和施工安全,同时降低施工成本。
附图说明
附图为本发明的结构示意图。
具体实施方式
附图为本发明的结构示意图,如图所示:高空大跨度屋面管桁架安装方法包括下述步骤:
a、地面组装管桁架,管桁架的榀数主要根据屋面的长度确定,若间隔12m或间隔9m安装一榀管桁架;而每一榀管桁架由几段组成主要依据屋面的跨度以及移动式塔吊的平面位置和额定起重量,本实施例的管桁架跨度为左钢筋混凝土立柱1和右钢筋混凝土立柱2的距离(如96m),移动式塔吊10选用TQ1000/60移动式塔吊,移动式塔吊的回转半径为24m,故本实施例的管桁架由两片管桁架组成(即左片管桁架3和右片管桁架4)。
b、在高空组装管桁架处设置左安装平台梁5和右安装平台梁6,左安装平台梁5和右安装平台梁6上分别设有相互平行的水平轨道7,水平轨道7与管桁架的安装方向平行,左侧的水平轨道上设有左组装支架8,右侧的水平轨道上设有右组装支架9,左组装支架8和右组装支架9的标高分别根据左钢筋混泥土立柱1和右钢筋混泥土立柱2的标高确定,左组装支架8和右组装支架9分别通过底部安装的滚轮可在对应侧的水平轨道上滚动,以便随着管桁架安装位置的变化,可随时调整水平轨道上的左组装支架8和右组装支架9的位置并使其与管桁架的安装位置对应。水平轨道上设置有阻挡器,可利用阻挡器锁定左组装支架和右组装支架,以防止左组装支架和右组装支架位移。
c、采用移动式塔吊10吊装管桁架,移动式塔吊10首先吊装左片管桁架3,在正式吊运之前先试吊,采用钢扁担11和钢丝绳12吊装,确定吊点的合适位置,并用两个手拉葫芦调整左片管桁架3的斜度和安装位置角度,然后缓慢起升,检查左片管桁架3是否平衡及变形情况,在检查合格后才允许正式吊装;正式吊运时,需要在左片管桁架3的两端拉上溜绳,移动式塔吊行走要缓慢平稳行走,左片管桁架3要到位时先升到安装高度,然后移动式塔吊10将左片管桁架3运至安装位置,以左片管桁架3的支座为基准,将其支座与左钢筋混凝土立柱1顶上的支座对准,左片管桁架3的组装端与左组装支架8对准;安装左组装支架8内侧支撑左片管桁架3上弦的排架,并将调整到安装标高;移动式塔吊10的吊绳缓慢放松,在其吊绳不受力时停止松绳,检查所有左组装支架8的刚度和稳定性情况,在确定满足要求之后,在左片管桁架3的上弦两侧各拉两根缆绳进行稳定,以确保安全。用同样的方式吊装右片管桁架4,右片管桁架4的组装端吊放在右组装支架9上并与左片管桁架3的组装端对应,另一端吊放在右钢筋混凝土立柱2上。确定左片管桁架3和右片管桁架4之间距离,并在左组装支架8和右组装支架9上分别采用千斤顶进行矫正,调整两片管桁架之间的上下错位量和拱度值,以达到设计规范要求。
d、高空碰头组装焊接,采取先焊接管桁架下弦主管,再对称焊接上弦主管,以减少焊接变形,并采用反变形措施,监控管桁架的下绕度。
e、焊接检验合格后,从管桁架上松开左组装支架8和右组装支架9,移动左组装支架8和右组装支架9到下一跨安装处,移动式塔吊吊装管桁架也运行到下一跨安装处进行下一跨安装。
本实施例中,移动式塔吊选用吊装重量为单片管桁架重量的1.3~1.6倍,移动式塔吊的回转半径≥跨度的1/2。若移动式塔吊的幅度、最大幅度起重量和起升高度过大,移动式塔吊的租金和使用成本高;若移动式塔吊的幅度、最大幅度起重量和起升高度过小,吊车的幅度无法覆盖管桁架的安装中心线,而且施工危险性大,因此,移动式塔吊的正确选择关系到施工的安全和经济效益。
采用地面分段组装,移动式塔吊吊装和可移动的组装支架相结合,实现高空跨度大、重量大、截面大的管桁架高空碰头焊接,既提高施工质量、确保施工进度和施工安全,同时降低工程成本。
最后说明的是,以上实施例仅用以说明本发明的技术方案而非限制,尽管参照较佳实施例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,而不脱离本技术方案的宗旨和范围,其均应涵盖在本发明的权利要求范围当中。

Claims (5)

1.一种高空大跨度屋面管桁架安装方法,其特征在于:包括下述步骤:
a、地面分段组装管桁架;
b、在高空组装管桁架处设置左安装平台梁和右安装平台梁,左安装平台梁和右安装平台梁上分别设有相互平行的水平轨道,左侧的水平轨道上设有左组装支架,右侧的水平轨道上设有右组装支架,左组装支架和右组装支架分别通过底部安装的滚轮可在对应侧的水平轨道上移动;
c、采用移动式塔吊吊装管桁架,左片管桁架的组装端吊放在左组装支架上,另一端吊放在左钢筋混凝土立柱上;右片管桁架的组装端吊放在右组装支架上并与左片管桁架的组装端对应,另一端吊放在右钢筋混凝土立柱上;
d、高空碰头组装焊接;
e、焊接检验合格后,从管桁架上松开左组装支架和右组装支架,移动左组装支架和右组装支架到下一轴线安装处;移动式塔吊吊装管桁架运行到下一轴线安装处进行下一榀的安装。
2.根据权利要求1所述的高空大跨度屋面管桁架安装方法,其特征在于:在所述步骤d中,采取先焊接管桁架下弦主管,再对称焊接上弦主管的方法,并采用反变形措施,监控管桁架的下绕度。
3.根据权利要求1所述的高空大跨度屋面管桁架安装方法,其特征在于:在所述步骤c中,利用千斤顶来进行矫正,调整两片管桁架之间的上下错位量和拱度值。
4.根据权利要求1至3中任一项权利要求所述的高空大跨度屋面管桁架安装方法,其特征在于:所述移动式塔吊选用吊装重量为单片管桁架重量的1.3~1.6倍的塔吊,移动式塔吊的回转半径≥跨度的1/2。
5.根据权利要求4所述的高空大跨度屋面管桁架安装方法,其特征在于:所述水平轨道上设置有可防止左组装支架和右组装支架位移的阻挡器。
CN2009101908658A 2009-09-15 2009-09-15 高空大跨度屋面管桁架安装方法 Expired - Fee Related CN101666163B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101908658A CN101666163B (zh) 2009-09-15 2009-09-15 高空大跨度屋面管桁架安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101908658A CN101666163B (zh) 2009-09-15 2009-09-15 高空大跨度屋面管桁架安装方法

Publications (2)

Publication Number Publication Date
CN101666163A CN101666163A (zh) 2010-03-10
CN101666163B true CN101666163B (zh) 2010-12-01

Family

ID=41802928

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101908658A Expired - Fee Related CN101666163B (zh) 2009-09-15 2009-09-15 高空大跨度屋面管桁架安装方法

Country Status (1)

Country Link
CN (1) CN101666163B (zh)

Families Citing this family (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102003074B (zh) * 2010-10-15 2012-05-30 中国建筑第八工程局有限公司 室内大型钢连桥施工方法
CN102561788B (zh) * 2010-12-21 2014-09-17 国家电网公司直流建设分公司 用于直升机组立输电线路铁塔的系列导轨
CN102777047B (zh) * 2012-08-22 2014-08-20 河北二十冶工程技术有限公司 大跨度管桁架屋面梁的组拼安装方法
CN102953556B (zh) * 2012-11-14 2016-05-18 中冶天工集团有限公司 大跨度不对称矩形空间扭曲管桁架的吊装方法
CN103216109B (zh) * 2013-04-26 2015-02-25 江苏沪宁钢机股份有限公司 大跨度空间管桁架屋盖轨距变幅分块滑移的施工方法
CN103883129B (zh) * 2014-03-17 2016-06-22 中国华冶科工集团有限公司 一种钢结构屋面梁安装方法
CN104947955B (zh) * 2014-03-28 2017-04-19 上海宝冶集团有限公司 一种用于液压提升设备更换的荷载转换方法
CN103883131A (zh) * 2014-03-31 2014-06-25 中国建筑第八工程局有限公司 屋盖管桁架与钢管柱的连接结构及施工方法
CN104060843A (zh) * 2014-07-08 2014-09-24 七冶建设有限责任公司 一种超大型屋面***倒装施工方法
CN104389432A (zh) * 2014-10-21 2015-03-04 北京建工土木工程有限公司 钢桁架支撑的混凝土重屋盖体系整体提升设备及施工方法
CN105133841A (zh) * 2015-07-29 2015-12-09 五洋建设集团股份有限公司 空间曲面钢结构管桁架屋盖安装施工工法
CN105822066B (zh) * 2016-04-07 2017-11-24 中建六局第三建筑工程有限公司 地下大跨度大空间超高无柱钢结构管桁架施工工法
CN105888262B (zh) * 2016-04-14 2018-06-29 中国十七冶集团有限公司 一种大跨度管廊管道的施工方法
CN107524297B (zh) * 2016-06-22 2020-04-28 中国二十冶集团有限公司 锥台形屋架高空定位施工方法
CN106284668B (zh) * 2016-08-29 2019-08-13 江苏江中集团有限公司 一种大跨度大空间钢结构屋面桁架安装方法
CN110158833A (zh) * 2019-05-24 2019-08-23 中国二十二冶集团有限公司 轻钢结构屋架模块化安装方法
CN110863568B (zh) * 2019-11-22 2021-04-09 中国十七冶集团有限公司 一种复杂环境下大跨度钢结构屋盖吊装施工方法
CN111794529A (zh) * 2020-07-15 2020-10-20 沈阳科维润工程技术有限公司 一种模块化的拱式空间管桁架钢结构体系建筑吊装方法
CN111945891B (zh) * 2020-07-25 2022-01-18 北京城建二建设工程有限公司 一种环桁架高空原位散拼施工方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1584263A (zh) * 2004-06-03 2005-02-23 上海拜特钢结构设计有限公司 钢结构桁架高空弧线滑移安装方法
CN101200977A (zh) * 2007-11-29 2008-06-18 北京城建集团有限责任公司 屋面施工水平运输方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1584263A (zh) * 2004-06-03 2005-02-23 上海拜特钢结构设计有限公司 钢结构桁架高空弧线滑移安装方法
CN101200977A (zh) * 2007-11-29 2008-06-18 北京城建集团有限责任公司 屋面施工水平运输方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
JP平3-293447A 1991.12.25
JP特开平8-4302A 1996.01.09
鲍广鉴等.复杂空间钢结构测控技术.《施工技术》.2005,第34卷(第10期),第11-14页. *

Also Published As

Publication number Publication date
CN101666163A (zh) 2010-03-10

Similar Documents

Publication Publication Date Title
CN101666163B (zh) 高空大跨度屋面管桁架安装方法
CN102071644A (zh) 一种桥梁拱肋整体提升安装方法
CN106545172A (zh) 一种高空大跨度钢桁架的安装方法
CN107034791A (zh) 一种悬臂浇注施工用挂篮的拼装方法
CN102733615B (zh) 非对称整体提升施工方法
CN112081016A (zh) 一种桥梁拱肋的提升合拢装置
CN203296361U (zh) 大跨度钢结构跨外组对吊装平台
CN111719757B (zh) 不对称内环桁架和索穹顶整体提升方法及其***
CN113756501B (zh) 一种悬挑铝合金屋盖的施工方法
CN105256933B (zh) 一种开合屋盖***活动结构的施工方法
CN114215170A (zh) 一种超高空巨型吊挂多层连体结构提升方法
CN108894496A (zh) 一种大跨度张弦桁架梁场外施工方法
CN108842954A (zh) 一种翼型屋面巨型异截面蜂窝梁结构体系安装施工方法
CN103132702A (zh) 一种大跨度管桁架拔杆提升、空中施转就位施工方法
CN102877657B (zh) 大跨度h型钢平面组合结构张弦梁高空换索施工方法
JP3086101B2 (ja) 空中架構体の下面外装
CN202544423U (zh) 一种支撑钢柱的吊装结构
CN111576227A (zh) 双飞翼拱桥主副拱的施工方法及其所使用的吊具
CN110040632A (zh) 一种大跨度型钢梁的分段吊装施工方法
CN105386414A (zh) 下导式无主桁挂篮
CN212834992U (zh) 一种基于狭长山涧地形的悬索桥
CN110847616B (zh) 大体积钢架烟道安装方法
CN112575948A (zh) 一种张弦梁与悬挑桁架组合屋架及施工方法
CN113914225A (zh) 一种大吨位牵索挂篮主桁架纵向滑移竖向提升施工方法
CN108797350B (zh) 一种塔柱内外劲性骨架装置及其施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101201

Termination date: 20140915

EXPY Termination of patent right or utility model