CN101634142A - 一种多重钢套管溶洞填充预处理施工方法 - Google Patents

一种多重钢套管溶洞填充预处理施工方法 Download PDF

Info

Publication number
CN101634142A
CN101634142A CN200910041839A CN200910041839A CN101634142A CN 101634142 A CN101634142 A CN 101634142A CN 200910041839 A CN200910041839 A CN 200910041839A CN 200910041839 A CN200910041839 A CN 200910041839A CN 101634142 A CN101634142 A CN 101634142A
Authority
CN
China
Prior art keywords
steel sleeve
karst cave
multilayer
solution cavity
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200910041839A
Other languages
English (en)
Inventor
彭少林
刘佰刚
陈亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG PROV FOUNDATION ENGINEERING Co
Original Assignee
GUANGDONG PROV FOUNDATION ENGINEERING Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG PROV FOUNDATION ENGINEERING Co filed Critical GUANGDONG PROV FOUNDATION ENGINEERING Co
Priority to CN200910041839A priority Critical patent/CN101634142A/zh
Publication of CN101634142A publication Critical patent/CN101634142A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种多重钢套管溶洞填充预处理施工方法,其方法步骤如下:(1):调查施工区域范围内溶洞情况,分析溶洞的大小、埋深、分布情况以及填充情况;(2):埋设钢套管;(3):埋设排气管:排气管采用地质钻机,钻孔至溶洞内,接着在孔内插一根管至溶洞中;(4):灌注填充料;(5):拔管:灌注完一层提升钢套管,分节分层进行回收;本方法简单方便,只需小型地质钻机,混凝土输送泵等设备,就能对多层溶洞(土洞)进行预处理,从而达到改良不良地质条件的目的,对后期桩基础施工提高了效率,增强了施工安全性,桩的承载能力也可以提高,溶洞填充后,可以考虑桩周摩阻力,建筑物的抗震性能也大大加强。

Description

一种多重钢套管溶洞填充预处理施工方法
技术领域
本发明涉及建筑施工领域,特别是涉及一种多重钢套管溶洞填充预处理施工方法。
背景技术
目前沿海地区,其地下以砂性土及淤泥表土为主,在这些地下土质的环境下,常常伴随有多层溶洞、串珠状溶洞(包括土洞等)等不良地质,如果不对溶洞进行填充预处理,就会造成钻孔灌注桩发生局部漏浆、断层、缩颈时令整桩承载力丧失,所以设计一种洞填充预处理施工方法已经提上了人们的研究日程。
发明内容
为了克服现有技术的不足,本发明提供一种有效改良了溶洞地质条件的预处理施工方法。
本发明解决上述技术问题所采用的技术方案是:
一种多重钢套管溶洞填充预处理施工方法,其方法步骤如下:
(1):调查施工区域范围内溶洞情况,分析溶洞的大小、埋深、分布情况以及填充情况;
(2):埋设钢套管:针对设计要求处理的多层溶洞、串珠状溶洞,先钻稍大钻孔到达第一层溶洞内,钢套管跟进,然后从钢套管内再用稍小的钻杆钻至第二层溶洞,稍小的钢套管跟进至第二层溶洞,依此施工;
(3):埋设排气管:排气管采用地质钻机,钻孔至溶洞内,接着在孔内插一根管至溶洞中;
(4):灌注填充料:采用混凝土输送泵进行填充料的灌注,填充料中以是水泥浆、水泥砂浆、砂、细石混凝土为主;
(5):拔管:灌注完一层提升钢套管,分节分层进行回收。
本发明的有益效果是:本方法简单方便,只需小型地质钻机,混凝土输送泵等设备,就能对多层溶洞(土洞)进行预处理,从而达到改良不良地质条件的目的,对后期桩基础施工提高了效率,增强了施工安全性,桩的承载能力也可以提高,溶洞填充后,可以考虑桩周摩阻力,建筑物的抗震性能也大大加强。
具体实施方式
一种多重钢套管溶洞填充预处理施工方法,其方法步骤如下:
(1):调查施工区域范围内溶洞情况,分析溶洞的大小、埋深、分布情况以及填充情况;
(2):埋设钢套管:针对设计要求处理的多层溶洞、串珠状溶洞,先钻稍大钻孔到达第一层溶洞内,钢套管跟进,然后从钢套管内再用稍小的钻杆钻至第二层溶洞,稍小的钢套管跟进至第二层溶洞,依此施工;埋设钢套管至要处理的多层溶洞内180~220mm。下层溶洞钢套管比上层溶洞内钢套管直径小2~3mm,如按180mm、150mm、130mm等规格布置多重钢套管。
(3):埋设排气管:排气管采用地质钻机(孔径110mm),钻孔至溶(土)洞底500mm左右,孔内插一根φ75PVC管至溶(土)洞,便于填充料灌注时,溶洞内水、气从管内排出。
(4):灌注填充料:采用混凝土输送泵进行填充料的灌注,填充料中以是水泥浆、水泥砂浆、砂、细石混凝土为主;当具有动水条件下,宜灌注C20细石混凝土,混凝土要有很好的流动性,坍落度为180~220mm。输送泵管与φ130钢套管接驳,在输送泵接驳安装等准备工作完成后,进行灌混凝土施工。按照由下往上逐层灌的顺序,即先灌底层溶洞,灌完后提升钢套管至上一层溶洞,逐层往上灌直至灌完顶层溶洞为止。当输送泵压力值达到25Mpa左右时,结束混凝土灌注施工。在灌注过程中对输送管适当加压,防止灌注过程中往上冲。
(5):拔管:灌注完一层提升钢套管,分节分层进行回收。
本施工方法简单方便,只需小型地质钻机,混凝土输送泵等设备,就能对多层溶洞(土洞)进行预处理,从而达到改良不良地质条件的目的,对后期桩基础施工提高了效率,增强了施工安全性,桩的承载能力也可以提高,溶洞填充后,可以考虑桩周摩阻力,建筑物的抗震性能也大大加强。

Claims (8)

1.一种多重钢套管溶洞填充预处理施工方法,其特征在于:该方法步骤如下:
(1):调查施工区域范围内溶洞情况,分析溶洞的大小、埋深、分布情况以及填充情况;
(2):埋设钢套管:针对设计要求处理的多层溶洞、串珠状溶洞,先钻稍大钻孔到达第一层溶洞内,钢套管跟进,然后从钢套管内再用稍小的钻杆钻至第二层溶洞,稍小的钢套管跟进至第二层溶洞,依此施工;
(3):埋设排气管:排气管采用地质钻机,钻孔至溶洞内,接着在孔内插一根管至溶洞中;
(4):灌注填充料:采用混凝土输送泵进行填充料的灌注,填充料中以是水泥浆、水泥砂浆、砂、细石混凝土为主;
(5):拔管:灌注完一层提升钢套管,分节分层进行回收。
2.根据权利要求1所述的一种多重钢套管溶洞填充预处理施工方法,其特征在于:步骤2)所述的埋设钢套管至要处理的多层溶洞内1 80~220mm。
3.根据权利要求1所述的一种多重钢套管溶洞填充预处理施工方法,其特征在于:步骤2)所述的下层溶洞钢套管比上层溶洞内钢套管直径小2~3mm。
4.根据权利要求1所述的一种多重钢套管溶洞填充预处理施工方法,其特征在于:步骤3)所述的钻机孔径为11 0mm。
5.根据权利要求1所述的一种多重钢套管溶洞填充预处理施工方法,其特征在于:步骤3)所述钻孔至溶洞内450~550mm。
6.根据权利要求1所述的一种多重钢套管溶洞填充预处理施工方法,其特征在于:步骤3)所述的管直径为75mm的PVC管。
7.根据权利要求1所述的一种多重钢套管溶洞填充预处理施工方法,其特征在于:步骤4)所述灌注时采用由下往上逐层灌的顺序。
8.根据权利要求1所述的一种多重钢套管溶洞填充预处理施工方法,其特征在于:步骤4)当输送泵压力值达到20~30Mpa时,结束混凝土灌注施工。
CN200910041839A 2009-08-13 2009-08-13 一种多重钢套管溶洞填充预处理施工方法 Pending CN101634142A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910041839A CN101634142A (zh) 2009-08-13 2009-08-13 一种多重钢套管溶洞填充预处理施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910041839A CN101634142A (zh) 2009-08-13 2009-08-13 一种多重钢套管溶洞填充预处理施工方法

Publications (1)

Publication Number Publication Date
CN101634142A true CN101634142A (zh) 2010-01-27

Family

ID=41593461

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910041839A Pending CN101634142A (zh) 2009-08-13 2009-08-13 一种多重钢套管溶洞填充预处理施工方法

Country Status (1)

Country Link
CN (1) CN101634142A (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101806059A (zh) * 2010-04-02 2010-08-18 中铁二局股份有限公司 高速公路下伏采空区地表钻孔注浆投沙工艺
CN101864763A (zh) * 2010-05-29 2010-10-20 中国二十二冶集团有限公司 覆盖型岩溶地区地基综合处理施工方法
CN102146672A (zh) * 2011-03-15 2011-08-10 中铁六局集团有限公司 一种在岩溶地区的桩基施工方法
CN102162249A (zh) * 2011-05-20 2011-08-24 大连宜华建设集团有限公司 预应力高强度混凝土管桩在深海回填区的施工工法
CN102852140A (zh) * 2012-10-10 2013-01-02 东华理工大学 一种帷幕式溶洞灌注桩施工方法及弹性网布
CN103031847A (zh) * 2012-12-20 2013-04-10 长江勘测规划设计研究有限责任公司 变径搭接组合式孔口管灌浆法
CN104278667A (zh) * 2013-07-02 2015-01-14 浙江国泰建设集团有限公司 一种地下溶洞的充填处理方法
CN104612143A (zh) * 2014-12-31 2015-05-13 云南建工基础工程有限责任公司 一种溶洞/土洞地质条件下的钻孔复合桩结构
CN104762970A (zh) * 2015-04-28 2015-07-08 中铁五局(集团)有限公司 一种深孔岩溶注浆辅助拔管装置及施工方法
CN110241671A (zh) * 2019-07-08 2019-09-17 郑州市交通规划勘察设计研究院 一种修复路基底部溶洞的施工方法
CN111691397A (zh) * 2020-06-22 2020-09-22 中铁二十四局集团南昌铁路工程有限公司 一种岩溶隧道底部充填串珠型溶洞钢管桩注浆成孔方法
WO2023178908A1 (zh) * 2022-03-21 2023-09-28 中交第四航务工程局有限公司 一种高压预填充溶洞桩基施工方法

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101806059A (zh) * 2010-04-02 2010-08-18 中铁二局股份有限公司 高速公路下伏采空区地表钻孔注浆投沙工艺
CN101864763A (zh) * 2010-05-29 2010-10-20 中国二十二冶集团有限公司 覆盖型岩溶地区地基综合处理施工方法
CN101864763B (zh) * 2010-05-29 2011-09-14 中国二十二冶集团有限公司 覆盖型岩溶地区地基综合处理施工方法
CN102146672A (zh) * 2011-03-15 2011-08-10 中铁六局集团有限公司 一种在岩溶地区的桩基施工方法
CN102146672B (zh) * 2011-03-15 2012-09-05 中铁六局集团有限公司 一种在岩溶地区的桩基施工方法
CN102162249A (zh) * 2011-05-20 2011-08-24 大连宜华建设集团有限公司 预应力高强度混凝土管桩在深海回填区的施工工法
CN102162249B (zh) * 2011-05-20 2013-01-23 大连宜华建设集团有限公司 预应力高强度混凝土管桩在深海回填区的施工工法
CN102852140B (zh) * 2012-10-10 2014-12-03 东华理工大学 一种帷幕式溶洞灌注桩施工方法及弹性网布
CN102852140A (zh) * 2012-10-10 2013-01-02 东华理工大学 一种帷幕式溶洞灌注桩施工方法及弹性网布
CN103031847A (zh) * 2012-12-20 2013-04-10 长江勘测规划设计研究有限责任公司 变径搭接组合式孔口管灌浆法
CN103031847B (zh) * 2012-12-20 2015-05-06 长江勘测规划设计研究有限责任公司 变径搭接组合式孔口管灌浆法
CN104278667A (zh) * 2013-07-02 2015-01-14 浙江国泰建设集团有限公司 一种地下溶洞的充填处理方法
CN104612143A (zh) * 2014-12-31 2015-05-13 云南建工基础工程有限责任公司 一种溶洞/土洞地质条件下的钻孔复合桩结构
CN104762970A (zh) * 2015-04-28 2015-07-08 中铁五局(集团)有限公司 一种深孔岩溶注浆辅助拔管装置及施工方法
CN104762970B (zh) * 2015-04-28 2016-08-17 中铁五局(集团)有限公司 一种深孔岩溶注浆辅助拔管装置及施工方法
CN110241671A (zh) * 2019-07-08 2019-09-17 郑州市交通规划勘察设计研究院 一种修复路基底部溶洞的施工方法
CN111691397A (zh) * 2020-06-22 2020-09-22 中铁二十四局集团南昌铁路工程有限公司 一种岩溶隧道底部充填串珠型溶洞钢管桩注浆成孔方法
WO2023178908A1 (zh) * 2022-03-21 2023-09-28 中交第四航务工程局有限公司 一种高压预填充溶洞桩基施工方法

Similar Documents

Publication Publication Date Title
CN101634142A (zh) 一种多重钢套管溶洞填充预处理施工方法
CN102444118A (zh) 袖阀管注浆加固施工方法
CN104631438B (zh) 长螺旋钻孔压灌混凝土抗拔桩施工方法
CN105178368B (zh) 微型桩桩孔取土建筑物纠倾法
CN112482364A (zh) 滨海地区强腐蚀性软弱地质条件下的旋挖灌注桩施工工艺
CN105239564A (zh) 全套管组合泥浆护壁的灌注桩施工方法
CN104818713A (zh) 一种适应于多种地层的型钢水泥土桩施工方法
CN101838988A (zh) 一种抽拔锚索的综合施工方法
CN103031847B (zh) 变径搭接组合式孔口管灌浆法
CN206204972U (zh) 一种兼作井点降水的预制管桩
CN201826302U (zh) 用于大直径现浇薄壁混凝土复合桩的成孔器
CN102345287B (zh) 大直径现浇薄壁混凝土复合桩的施工处理方法
CN101914915A (zh) 一种抗浮锚杆的施工方法及专用长螺旋钻机
CN105133641A (zh) 一种薄壁型连续墙式地基基础加固结构及方法
CN102995647B (zh) 一种桩孔注浆隔渗的地下水控制方法
CN104975611B (zh) 流质土层的井点降水管的沉设装置及沉设方法
CN201183950Y (zh) 无缝钢管自进式锚杆
CN1995689B (zh) 一种带有陀螺钻头的成桩机械的成桩方法
CN105040705A (zh) 多溶洞地质条件下地基基础处理施工工艺
CN204690767U (zh) 一种用于深基坑的新型集水套管和给排水装置
CN205804362U (zh) 可入岩的长螺旋钻孔灌注桩施工装置
CN102094419A (zh) 地基中存在粉质沙层的钻孔桩成型方法
CN207004431U (zh) 软土地基激振打井装置
CN103437360B (zh) 一种深基坑工程中的不换撑施工方法
CN102296597A (zh) 一种浅土层钢管桩的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Peng Xiaolin

Inventor after: Liu Baigang

Inventor after: Chen Liang

Inventor before: Peng Shaolin

Inventor before: Liu Baigang

Inventor before: Chen Liang

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: PENG SHAOLIN LIU BAIGANG CHEN LIANG TO: PENG XIAOLIN LIU BAIGANG CHEN LIANG

C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Open date: 20100127